Rate Analysis of reinforcing Steel (SAIL/TATA/RINL)
ANNEXURE - I
FORMAT - B
[Ref:- Page-43 of PWD(B) 2017 and 6th Corrigenda & Addenda dated 29.07.2019]
Rate as per Rate to be
Step Description
Schedule (Rs.) considered (Rs.)
Reinforcement for reinforced concrete work in all sorts of
structures including distribution bars, stirrups, binders etc
initial straightening and removal of loose rust (if necessary),
cutting to requisite length, hooking and bending to correct
shape, placing in proper position and binding with 16 gauge
black annealed wire at every intersection, complete as per ₹ 60,580.00 ₹ 60,580.00
drawing and direction.
Step - 1 :
(a) For works in foundation and upto roof of ground
floor/upto 4 m
(i) Tor steel/Mild Steel
I. SAIL/TATA/RINL
[Ref:- It. No. 40(a)(i)(I), Page-43 of PWD(B) 2017 and 10th Corrigenda &
Addenda dated 22.01.2020]
Deduct Issue Rate (per MT) of respective Quality Steel
including 10% contractor profit, 2% Sundries, water charges ₹ 43,140.00 -₹ 50,473.80
Step - 2 : & 5% wastage X 1.17
[Ref:- It. No. 2) ii), Table-1.1, Annexure-I, Page-304 of PWD(B) 2017 and 9th
Corrigenda & Addenda dated 01.11.2019]
Add Basic Price at outlet of Seel of respective quality of Steel
including 10% contractor profit, 2% Sundries, water charges ₹ 38,160.00 ₹ 44,647.20
Step - 3 : & 5% wastage X 1.17
[Ref:- It. No. 2) ii), Table-1.1, Annexure-I, Page-304 of PWD(B) 2017 and 9th
Corrigenda & Addenda dated 01.11.2019]
Add cost of Carriage from outlet to site with necessary
loading, unloading and stacking charges for 1.05 MT Steel
Carriage of Steel materials over pucca road.
₹ 82.00 ₹ 86.10
For a distance upto 5 Km.
[Ref:- It. No. 5, Table-1, Page-230 of PWD(R&B) 2018]
Loading, unloading and stacking by Manual Means.
Step - 4 : A. Loading in to trucks at the lifting point, unloading at
destination, stacking properly in go downs or yard etc. as
₹ 96.00
directed including carriage by head load up to a lead of 50.00
m at each of the two points.
(h) Steel
[Ref:- It. No. 1.03 A. (h), Chapter-1, Page-227 of PWD(R&B) 2018]
Considering Loading, unloading and non-stacking @ 75% of
₹ 72.00 ₹ 75.60
Cost = Rs. 96.00 X 0.75
Total Rate per MT of Reinforcing Steel = ₹ 54,915.10
Rate Analysis of reinforcing Steel
(JSW/JSPL/SHYAM/SRMB/BMASL/ELECTROSTEEL/SSL)
ANNEXURE - I
FORMAT - B
[Ref:- Page-43 of PWD(B) 2017 and 6th Corrigenda & Addenda dated 29.07.2019]
Rate as per
Step Description
Schedule (Rs.)
Reinforcement for reinforced concrete work in all sorts of
structures including distribution bars, stirrups, binders etc
initial straightening and removal of loose rust (if necessary),
cutting to requisite length, hooking and bending to correct
shape, placing in proper position and binding with 16 gauge
black annealed wire at every intersection, complete as per ₹ 60,150.00
drawing and direction.
Step - 1 :
(a) For works in foundation and upto roof of ground
floor/upto 4 m
(i) Tor steel/Mild Steel
II. JSW/JSPL/SHYAM/SRMB/BMASL/ELECTROSTEEL/SSL
[Ref:- It. No. 40(a)(i)(II), Page-43 of PWD(B) 2017 and 10th Corrigenda &
Addenda dated 22.01.2020]
Deduct Issue Rate (per MT) of respective Quality Steel
including 10% contractor profit, 2% Sundries, water charges ₹ 43,140.00
Step - 2 : & 5% wastage X 1.17
[Ref:- It. No. 2) ii), Table-1.1, Annexure-I, Page-304 of PWD(B) 2017 and 9th
Corrigenda & Addenda dated 01.11.2019]
Add Basic Price at outlet of Seel of respective quality of Steel
including 10% contractor profit, 2% Sundries, water charges ₹ 38,160.00
Step - 3 : & 5% wastage X 1.17
[Ref:- It. No. 2) ii), Table-1.1, Annexure-I, Page-304 of PWD(B) 2017 and 9th
Corrigenda & Addenda dated 01.11.2019]
Add cost of Carriage from outlet to site with necessary
loading, unloading and stacking charges for 1.05 MT Steel
Carriage of Steel materials over pucca road.
₹ 82.00
For a distance upto 5 Km.
[Ref:- It. No. 5, Table-1, Page-230 of PWD(R&B) 2018]
Loading, unloading and stacking by Manual Means.
Step - 4 : A. Loading in to trucks at the lifting point, unloading at
destination, stacking properly in go downs or yard etc. as
₹ 96.00
directed including carriage by head load up to a lead of 50.00
m at each of the two points.
(h) Steel
[Ref:- It. No. 1.03 A. (h), Chapter-1, Page-227 of PWD(R&B) 2018]
Considering Loading, unloading and non-stacking @ 75% of
₹ 72.00
Cost = Rs. 96.00 X 0.75
Total Rate per MT of Reinforcing Steel =
EEL/SSL)
dated 29.07.2019]
Rate to be
considered (Rs.)
₹ 60,150.00
-₹ 50,473.80
₹ 44,647.20
₹ 86.10
₹ 75.60
₹ 54,485.10
Rate Analysis of reinforcing Steel
(OTHER MANUFACTURERS NOT SPECIFIED)
ANNEXURE - I
FORMAT - B
[Ref:- Page-43 of PWD(B) 2017 and 6th Corrigenda & Addenda dated 29.07.2019]
Rate as per
Step Description
Schedule (Rs.)
Reinforcement for reinforced concrete work in all sorts of
structures including distribution bars, stirrups, binders etc
initial straightening and removal of loose rust (if necessary),
cutting to requisite length, hooking and bending to correct
shape, placing in proper position and binding with 16 gauge
black annealed wire at every intersection, complete as per ₹ 58,662.00
drawing and direction.
Step - 1 :
(a) For works in foundation and upto roof of ground
floor/upto 4 m
(i) Tor steel/Mild Steel
I. SAIL/TATA/RINL
[Ref:- It. No. 40(a)(i)(I), Page-43 of PWD(B) 2017 and 10th Corrigenda &
Addenda dated 22.01.2020]
Deduct Issue Rate (per MT) of respective Quality Steel
including 10% contractor profit, 2% Sundries, water charges ₹ 43,140.00
Step - 2 : & 5% wastage X 1.17
[Ref:- It. No. 2) ii), Table-1.1, Annexure-I, Page-304 of PWD(B) 2017 and 9th
Corrigenda & Addenda dated 01.11.2019]
Add Basic Price at outlet of Seel of respective quality of Steel
including 10% contractor profit, 2% Sundries, water charges ₹ 38,160.00
Step - 3 : & 5% wastage X 1.17
[Ref:- It. No. 2) ii), Table-1.1, Annexure-I, Page-304 of PWD(B) 2017 and 9th
Corrigenda & Addenda dated 01.11.2019]
Add cost of Carriage from outlet to site with necessary
loading, unloading and stacking charges for 1.05 MT Steel
Carriage of Steel materials over pucca road.
₹ 82.00
For a distance upto 5 Km.
[Ref:- It. No. 5, Table-1, Page-230 of PWD(R&B) 2018]
Loading, unloading and stacking by Manual Means.
Step - 4 : A. Loading in to trucks at the lifting point, unloading at
destination, stacking properly in go downs or yard etc. as
₹ 96.00
directed including carriage by head load up to a lead of 50.00
m at each of the two points.
(h) Steel
[Ref:- It. No. 1.03 A. (h), Chapter-1, Page-227 of PWD(R&B) 2018]
Considering Loading, unloading and non-stacking @ 75% of
₹ 72.00
Cost = Rs. 96.00 X 0.75
Total Rate per MT of Reinforcing Steel =
ED)
dated 29.07.2019]
Rate to be
considered (Rs.)
₹ 58,662.00
-₹ 50,473.80
₹ 44,647.20
₹ 86.10
₹ 75.60
₹ 52,997.10