OPSS - MUNI 909 - Nov 2021
OPSS - MUNI 909 - Nov 2021
TABLE OF CONTENTS
909.01 SCOPE
909.02 REFERENCES
909.03 DEFINITIONS
909.05 MATERIALS
909.06 EQUIPMENT
909.07 CONSTRUCTION
APPENDICES
909-A Commentary
909.01 SCOPE
This specification covers the construction requirements for fabrication, delivery, and installation of precast
prestressed concrete members with steel reinforcement.
This specification has been developed for use in municipal oriented Contracts. The administration,
testing, and payment policies, procedures, and practices reflected in this specification correspond to
those used by many municipalities in Ontario.
Use of this specification or any other specification shall be according to the Contract Documents.
Appendices are not for use in provincial contracts as they are developed for municipal use, and then, only
when invoked by the Owner.
Inclusion of an appendix as part of the Contract Documents is solely at the discretion of the Owner.
Appendices are not a mandatory part of this specification and only become part of the Contract
Documents as the Owner invokes them.
Invoking a particular appendix does not obligate an Owner to use all available appendices. Only invoked
appendices form part of the Contract Documents.
The decision to use any appendix is determined by an Owner after considering their contract
requirements and their administrative, payment, and testing procedures, policies, and practices.
Depending on these considerations, an Owner may not wish to invoke some or any of the available
appendices.
909.02 REFERENCES
When the Contract Documents indicate that municipal-oriented specifications are to be used and there is
a municipal-oriented specification of the same number as those listed below, references within this
specification to an OPSS shall be deemed to mean OPSS.MUNI, unless use of a provincial-oriented
specification is specified in the Contract Documents. When there is not a corresponding municipal-
oriented specification, the references below shall be considered to be the OPSS listed, unless use of a
provincial-oriented specification is specified in the Contract Documents.
CSA Standards
ASTM International
M182-05 (2017) Burlap Cloth made from Jute or Kenaf and Cotton Mats
909.03 DEFINITIONS
Bed means the assembly consisting of platform, forms and end blocks in which the members are cast.
Certificate of Conformance means a form issued by an Engineer confirming that the specified
components of the Work are in general conformance with the Contract Documents as shown in
OPSF 539-1.
Concrete Construction Report means a form used by the Contractor to report concrete test information as
shown in OPSF 909-1.
Design Proposal means a submission of proposed changes when engineering design is required.
Laitance means a layer of weak and nondurable material on the surface of the concrete containing
cement and fines from aggregates, brought by bleeding water to the top surface concrete.
Lot means all the members of the same member type, cast during 7 consecutive Days.
Manufacturer’s Certificate of Conformance means a letter issued by an Engineer confirming that the
fabrication and required testing has been carried out on a component or product in general conformance
with the Contract Documents as shown in OPSF 906-1.
Notice to Proceed means a form issued by the Contract Administrator notifying the Contractor to
proceed to the next operation as shown in OPSF 906-3.
Post-Tensioning means a method of prestressing in which tendons are tensioned after the concrete has
reached a predetermined strength.
Prestressed Concrete means reinforced concrete in which internal stresses have been initially introduced
so that subsequent stresses resulting from dead load and superimposed loads are counteracted to a
desired degree. This may be accomplished by pretensioning or post-tensioning.
Pretensioning means a method of prestressing in which tendons are tensioned before the concrete is
placed.
Repair Proposal means a submission when repairs to the members are required.
Request to Proceed means a form issued by the Contractor notifying the Contract Administrator that a
component or stage of the work has been completed in general conformance with the Contract
Documents. Form is OPSF 906-2.
Sweep means the lateral deviation from straightness of a member with respect to its design centre line.
Tendon means a high strength steel element consisting of one or more wires, strands or bars; used to
impart prestress to the concrete.
909.04.01.01 General
909.04.01.02.01 General
Changes from the Contract Drawings are permitted and may be implemented by the precaster, without
prior approval from the Owner, provided they meet the requirements of this specification.
The prestressing strand pattern may be adjusted to suit production requirements provided all changes
meet the original design strength without adversely affecting other components of the structure. If the
centre of gravity of the strands at the interior hold down closest to mid-span is within 10 mm of the
original design, then one or more of the following adjustments shall be permitted provided that both the
serviceability and ultimate limit states capacities are not adversely affected:
a) Provide additional strands with a lower jacking stress provided the total prestress force is within
2% of the original design.
c) Addition of one hold-down per end is added towards the member end at the same spacing as the
original design.
d) One less hold-down per end when the hold-down closest to mid-span is deleted.
The stirrup projection may be adjusted from that shown on the original design, based on details such as
the predicted camber, provided it meets the deck embedment range indicated elsewhere in the Contract
Documents.
Spacing of stirrups around blockouts for diaphragms may be adjusted, as long as the minimum spacing
requirements of CAN/CSA S6 are satisfied, and up to two stirrups may be added in order to maintain the
total reinforcement requirements.
Details limited to those below may be adjusted to suit production requirements, provided all changes
meet the original design without adversely affecting other components of the structure:
a) Dowel holes and inserts may be adjusted vertically within 75 mm from the location shown on the
original design to avoid any conflict with tendons.
d) Additional temporary post-tensioning or pre-tensioning for shipping and handling may be added
provided they do not adversely affect the members at any stage.
The production length of the member may be adjusted to account for elastic shortening.
Temporary bracing for members shall be designed according to CAN/CSA S6 using a wind load specific
for the location and having a return period of 10 years if the members are to be permanently connected
within the same construction season. If the members are not to be permanently connected within the
same construction season, the return period to be used in the design shall be 25 years.
Three sets of Working Drawings, including supporting documentation, shall be submitted to the Contract
Administrator at least 7 Days prior to commencement of fabrication of the members, for information
purposes only. Prior to making a submission, the design Engineer and the design-checking Engineer
shall affix their seals and signatures on the Working Drawings verifying that the drawings are consistent
with the Contract Documents.
a) Member details.
b) Prestressing reinforcing steel size, grade, location, and jacking force as required by the design.
a) A letter signed and sealed by an Engineer listing all permitted changes made along with supporting
calculations. The letter shall state that the changes have not adversely affected the member
capacities.
b) Handling and installation procedures, including calculations and lifting point locations.
c) Details of bracing installed to provide adequate support and stability to the member during
construction.
The concrete mix design shall be according to OPSS 1350 and shall be submitted to the Contract
Administrator.
The precast concrete plant certificate verifying compliance with the certification requirements of the
Canadian Standards Association (CSA) under the category Precast Concrete Products-Structural,
Prestressed; or by the Canadian Precast Concrete Quality Assurance Certification Program (CPCQA),
Group B, Category D, shall be submitted to the Contract Administrator as part of the concrete mix design
submission.
Documentation verifying certification of the concrete production facility by the Ready-Mixed Concrete
Association of Ontario shall be submitted when concrete is supplied by an external concrete supplier.
One week prior to the commencement of fabricating the members, a description of the method for
monitoring and effectively controlling the temperature of the concrete shall be submitted to the Contract
Administrator, for information purposes only. The description shall include the method of controlling the
concrete temperature during the curing and protection period.
A Manufacturer’s Certificate of Conformance and a precast report shall be submitted to the Contract
Administrator for each shipment of members at least 5 Business Days prior to shipping from the
precasting plant.
b) The mill certificates for the strands, along with the elongation calculations based on the actual
material properties specified in the mill certificate of the strands used in the work.
c) Record of the jacking force, elongations, and corrections used for temperature variation.
e) Summary of material test results for plastic concrete: air content, slump, and concrete temperature.
f) Summary of material test results for hardened concrete: transfer strength, confirmation of the
projected 28-Day compressive strength, and air void system parameters. If test results are not
available at the time of shipping, they may be submitted within 4 Business Days following completion
of testing.
g) Summary of all measurements and inspections required herein, including the concrete cover, crack
measurement summary, tolerances, and surveys for geometric control.
h) Documentation that all repairable defects have been identified, evaluated, and corrected, as detailed
under the clause on Repair of Defects and Deficiencies Repairable by Standard Methods.
A Request to Proceed shall be submitted to the Contract Administrator before the delivery of each
shipment of members to the site.
The members shall not be delivered to the site until the Contract Administrator has received the
Manufacturer’s Certificate of Conformance, the precast report, Request to Proceed, and issued a Notice
to Proceed.
Five copies of the design proposal shall be submitted to the Contract Administrator for acceptance. The
design proposals shall bear the seal and signature of the design Engineer and the design checking
Engineer. The proposed changes shall not proceed until the design proposal has been accepted by the
Contract Administrator.
The Contract Administrator shall respond within ten Business Days of receiving the design proposal.
909.05 MATERIALS
The bearing plate shall be according to CSA G40.20/G40.21, Grade 300W or greater.
Anchor studs shall be a headed type and shall be according to CSA W59. Anchor studs shall be welded
to the bearing plates prior to galvanizing.
909.05.02 Burlap
Burlap shall be according to AASHTO M182, Class 4, and shall be free from substances that are
deleterious to concrete. The burlap shall have no tears or holes.
909.05.03 Concrete
Concrete materials and production shall be according to OPSS 1350 with the following exceptions and
amendments:
b) The air void system in hardened concrete when tested according to LS-432 shall be:
i. Air Content: 3.0% minimum
ii. Spacing Factor: 0.200 mm maximum
c) Rapid chloride permeability of concrete containing silica fume at 28 to 32 Days shall be equal to or
less than 1,000 coulombs and rapid chloride permeability of all other concrete at 28 Days shall be
equal to or less than 2,500 coulombs.
d) Aggregates shall be according to OPSS 1002 with the exception that the maximum nominal size of
coarse aggregate shall not exceed 19.0 mm.
f) Superplasticizer may be added to the mix at time of batching for all types of concrete.
909.05.06 Formwork
All formwork shall be according to OPSS 919 and CAN/CSA A23.4. Forms shall be fabricated to meet the
dimensional tolerances and finishes required herein.
909.05.07 Hardware
The hold down device may be black steel, however, the surfaces of the hold down device located within
40 mm of the concrete surface shall be chromate coated over an electrodeposited coating of zinc according
to ASTM B633.
The moisture vapour barrier shall be a white opaque polyethylene film according to ASTM C171 and shall
not be less than 100 μm thick.
Proprietary patching materials shall be from the Owner’s pre-qualified list of concrete patching materials.
The list of proprietary patching material shall be obtained from the Contract Administrator.
Steel reinforcement shall be according to OPSS 905, OPSS 1440, and OPSS 1442.
909.06 EQUIPMENT
Chipping hammers shall have a maximum weight of 9.0 kg and a maximum piston stroke of 102 mm. All
hammers shall have the manufacturer’s name and model number engraved on them by the manufacturer.
All information must be legible.
Pretensioning equipment shall be according to CSA A23.4. Post-tensioning equipment shall be according
to OPSS 910.
Thermocouples and associated instrumentation shall have an accuracy of 1.5 °C and shall be capable of
recording temperature and instantaneously displaying the temperature.
909.07 CONSTRUCTION
909.07.01 General
The Contract Administrator shall be notified in writing at least 7 Days prior to commencement of fabrication.
Each member shall be identified with a unique number and the date of casting. The information shall be
marked on the members and shall remain visible for the duration of construction. When the information is
stencilled, indelible ink or paint shall be used.
Members shall be fabricated by a plant certified by the Canadian Standards Association (CSA) under the
category Precast Concrete Products-Structural, Prestressed; or by the Canadian Precast Concrete Quality
Assurance Certification Program (CPCQA), Group B, Category D.
Tendons shall not be tensioned in the deflected position, unless the hold-down device used permits free
movement of the strand and the use of the device has been tested by its manufacturer to ensure that the
final stress along the full length of the tendon is uniform.
909.07.04 Welding
Welding of steel hardware including shear studs shall be according to CSA W59 and shall be performed
by a qualified welder working for a company certified by the Canadian Welding Bureau according to
CSA W47.1.
Welding of reinforcing steel bars shall be according to CSA W186 and performed by a qualified welder
working for a company certified by the Canadian Welding Bureau according to CSA W186.
The placement of steel reinforcement shall be according to OPSS 905, with the exception or addition or both
of the placing tolerances listed below:
909.07.06 Formwork
When members are to be post-tensioned, the sheaths and anchorages shall be placed according to
OPSS 905 except that the placing tolerances shall be 5 mm at splice points and 10 mm elsewhere.
The temperature of formwork, steel reinforcement, or the material on which the concrete is to be placed
shall not exceed 30 °C.
The placing of concrete shall be according to OPSS 904, with the exception that the temperature of the
formwork, steel reinforcement, or the material on which the concrete is to be placed shall be at a minimum
temperature of 5 °C, prior to the placing operation. After discharging of concrete has started, one addition
of superplasticizer shall be allowed, provided there is sufficient remaining time for mixing and testing.
The slump and air content shall be re-tested if the mix is re-dosed.
During the placing operation, all exposed concrete surfaces shall be covered with water saturated burlap,
within 2 to 4 m of the concrete reaching the top of the forms.
The top surface of prestressed members, against which new concrete is to be placed, shall be
intentionally roughened while it is sufficiently plastic so that the depth of the indentations is at least 5 mm
and the spacing is not greater than 15 mm.
All concrete surfaces against which new concrete is to be placed shall be clean, sound, and free from any
loose particles and laitance.
The following surfaces shall be abrasive blast cleaned according to OPSS 929, prior to shipping the
members:
b) The portion of the sides and end of the member against which new concrete is to be placed.
During production and during moist curing, moisture retention, and protection periods, the following
temperature requirements shall be met:
b) The concrete temperature shall not fall below 10 °C before the concrete has reached 75% of the
specified 28-Day compressive strength.
c) The temperature difference between the concrete temperature of the member, and the conditions to
which it is to be exposed shall not exceed 20 °C along any part of the member.
Thermocouples, data loggers, handhelds units, and associated hardware shall be used to monitor the
temperature of the member and the ambient conditions to which the member is exposed.
A sufficient number of thermocouples and thermocouple wires shall be installed to ensure compliance
with the standard. As a minimum, thermocouples shall be installed to measure the following:
For I-members
i. In the middle of the web, 1 m from each end of the member.
ii. In the middle of the web at mid-span.
iii. In the middle of the bottom flange at mid-span.
For box-members
i. In the middle of the solid section at each end of the member.
ii. In the middle of the bottom slab at mid-span.
Recording of the concrete temperatures shall begin at the start of the placing operation and continue until
the moist curing, moisture retention, and protection periods are complete. For each member, the listed
temperatures shall be recorded at intervals of 30 minutes or less.
Moist curing shall be applied for 48 hours followed by a 48-hour moisture retention period.
Concrete containing silica fume shall be moist cured for 7 Days, regardless of the ambient conditions.
During the moist curing and moisture retention period, the members may be exposed to ambient
conditions for no more than a cumulative total of 3 hours for the purposes of form removal, release of
strands at transfer strength, filling of bug holes, inspection, removal from the bed, and storage.
During the first 48 hours after concrete placement, exposed surfaces shall be moist cured by any of the
methods described below.
a) Saturated burlap.
c) Steam.
d) Other means of maintaining 100% relative humidity next to the concrete surface.
Surfaces covered by the forms are not considered exposed. If forms are removed within the first
48 hours, all concrete surfaces shall be immediately moist cured by the positive addition of moisture for
the duration of the 48 hours, according to the methods noted above.
Spray or steam to raise the ambient temperature above 30 °C, shall not be applied until after the concrete
has attained its initial set. Steam, heat, or forced air shall not be directed on the concrete, forms, reinforcing
steel or tendons. There shall be free circulation of steam, heat, and forced air around the top, sides, and
ends of the members. The members shall be heated evenly. Concrete surfaces shall not be exposed to
combustion gases.
All water shall be removed from and precautions taken to prevent the re-entrance of water into the
sheaths or any internal voids.
After the initial moist curing has been completed, member surfaces shall be completely covered by
moisture vapour barrier to protect members from moisture loss for a period of 48 hours. Alternatively,
moist curing methods may be continued during this period.
Prior to full exposure and after the moist curing and moisture retention periods, members that are to be
exposed to temperatures less than 5 °C shall be protected from moisture loss for a minimum of an
additional 3 Days. The protection period shall be extended beyond 3 Days, if required to meet the
Control of Temperature clause.
All members must be dry prior to exposing them to temperatures below 0 °C.
The prestressing force shall not be transferred to the members until the transfer strength specified in the
Contract Documents has been reached. The prestressing force shall be transferred gradually and in a
sequence that ensures eccentricities are kept to a minimum.
The prestressing tendons at ends of members that are to be encased in concrete shall be cut off 25 mm
beyond the ends of the beams. The prestressing tendons at the end of members that are not to be encased
in concrete shall be cut back to recess the cable 25 mm from the end of member. The recess shall be
cleaned, filled with a proprietary patching material, and the ends of the members coated with elastomeric
coating.
909.07.14.01 General
Sufficient quality control testing and inspection shall be carried out to ensure that the concrete meets the
requirements of the Contract Documents.
All aspects of sampling and testing of the plastic concrete for slump, air content, and temperature shall be
according to OPSS 1350. The results of these tests shall be recorded. The minimum frequency of testing
shall be at least once for each load of concrete delivered by a truck mixer, or once for every 7 m3 of
concrete for non-truck mixers until satisfactory control is established.
Satisfactory control is established when three consecutive tests of concrete are within the specified
requirements, without field adjustments. If any field adjustments are required, testing shall continue until
three consecutive tests meet the requirements with no field adjustments.
After satisfactory control has been established, testing shall be carried out on every third load delivered
by a truck mixer, or at a delivery frequency of 21 m3 of concrete for non-truck mixers.
Sampling and testing of slump, air content, and temperature of plastic concrete, and casting of cylinders
for determination of hardened concrete properties shall be carried out by a person holding either of the
following certifications:
The person shall have a valid original card issued by the certifying agency in their possession at all times.
It shall be demonstrated that the transfer strength specified in the Contract Documents has been achieved
prior to transfer of prestressing force.
Standard cylinder correlation strength testing programs shall be conducted by the Ministry of
Transportation when requested by the Owner.
A cover meter survey on all members shall be carried out at the precaster’s facility until satisfactory
control is established. For each lot, satisfactory control shall be established when three consecutive
members of the same design are within the specified tolerances. After satisfactory control has been
established, testing shall be carried out on every fifth member. If testing indicates that cover
measurements for a member do not meet the tolerances specified in Table 1, testing shall resume on
each member until satisfactory control is re-established.
Readings shall be taken at locations 300 mm from both ends, at mid-span, and at intervals not exceeding
5 metres along the length of the member.
For box members, readings shall be taken at each location, as detailed below:
Measurements shall be carried out on each member to determine compliance with tolerance requirements.
Members shall meet the tolerances specified in Table 1.
909.07.15.01 General
Cylinders shall be 100 mm in diameter and 200 mm long. Samples shall be taken after all field
adjustments have been made to the load of concrete.
Concrete cylinders shall be cast, cured, handled and transported according to CSA A23.2-3C. The
specimens shall be delivered to a CCIL-approved laboratory as designated by the Contract Administrator.
Moulds shall be according to CSA A23.2-1D, with a lid. The lids shall be chemically and physically
compatible with the concrete and shall provide a watertight seal for the moulds.
One set shall be cast for acceptance and one set of referee cylinders may be cast for each lot. Both sets of
cylinders shall be cast from the same batch of concrete.
One cylinder shall be cast from each lot for determination of air void system parameters of hardened
concrete and two cylinders from each lot for determination of rapid chloride permeability. Each cylinder
shall be cast from concrete from a different member in the lot.
Samplings of steel reinforcement shall be provided to the Owner according to OPSS 905 when
requested.
Electrical power, scaffolding, protection from the weather, and unhindered access shall be provided to
Owner’s representatives for inspection and testing of all fabrication, delivery, and installation of prestressed
concrete precast members.
For the purposes of cover meter and dimensional measurements, all debris and obstructions shall be
cleared and the Owner’s representative shall be provided access.
909.07.17 Delivery
The Contract Administrator shall be notified in writing 3 Days prior to delivery of the members.
Delivery shall include transportation and storage of the members. Transportation and storage shall be
according to CAN/CSA A23.4. The work shall consist of loading of the members, delivery, unloading, and
storage at the storage site and shall include temporary works for access.
Members shall be loaded for shipping in such a manner that they can be transported and unloaded at
their destination without being damaged or exposed to stresses for which they were not designed.
Members shall be handled and transported with their webs in a vertical plane, and the points of support
during lifting, storing, and transporting shall be according to the Working Drawings. When stored, members
shall be stored in such a manner to avoid excessive stress or other damage.
Advertising by means of removable signing is permitted on elements only while in transit to the storage
site. Any permanent markings on a surface that would be visible after installation shall not be permitted.
909.07.18 Installation
The Contract Administrator shall be notified in writing of the installation date at least 3 Days prior to the
commencement of field installation operations. Installation shall be according to CAN/CSA A23.4.
The work shall consist of installation and stabilization of the members during construction. Members shall
be lifted and placed in a manner to ensure they are not overstressed, unstable, or unsafe at any time.
A copy of the Working Drawings shall be kept on the site and accessible to the Contract Administrator
during installation of the members.
The installation tolerance of members shall be 15 mm on the bearing in both the longitudinal and
transverse directions.
The forces resulting from the lifting devices acting on the members shall not be inclined to the vertical at an
angle greater than 30 degrees. All lifting devices for members shall be removed prior to the deck being
poured.
CPCI members and other members that may experience stability problems during construction shall be
braced individually by attaching each end to the respective substructure element, immediately upon
installation.
Any individual member having one or more of the defects and deficiencies identified in Table 2, shall be
repaired according to the repair method specified. Such repairs do not require proposals or owner
approval. Where more than one of the defects or deficiencies listed in Table 2 are located in the same
area in the member, a repair proposal shall be submitted. All causes, preventative actions, and corrective
actions, including repair methods and materials used shall be documented.
When defects or deficiencies occur, at the discretion of the design Engineer, a visual inspection may be
conducted or other measures required, such as cores to be taken to assess the effectiveness of the
repairs.
A Certificate of Conformance shall be submitted to the Contract Administrator within 5 Business Days of
installing all the members within a stage. The Certificate of Conformance shall identify the members and
state that the Work has been carried out in general conformance with the signed and sealed documents,
which include the Working Drawings, supporting documents, and Contract Documents.
909.08.01 General
The acceptance of members shall be according to the requirements of this specification, including
satisfactory completion of all repairs, if applicable. Members not meeting the requirements of the Contract
Documents shall be deemed unacceptable and shall not be included in the Work.
A 28-Day concrete compressive strength of a lot shall be considered acceptable when it meets all of the
following:
a) The average of the three individual compressive strength tests shall be equal to or greater than the
specified strength.
Compressive strength shall be determined according LS-426 for concrete with silica fume and high
strength concrete and according to LS-407 for all other concrete.
The compressive strength result of the lot shall be the average of the set of three acceptance cylinders
rounded to one decimal place.
The individual test results shall be forwarded to the Contractor as they become available.
If the Contractor has submitted a set of referee cylinders, an individual test result may be questioned by
the Contractor within 4 Business Days of receiving the test result. The Owner shall be notified of the
intention to referee test.
The lot shall be re-evaluated as based on the test result from the referee compressive strength cylinders
representing the lot and the referee test result shall replace the original test result. The referee test result
shall be binding.
One half of a cylinder shall be tested to determine the acceptability of the lot. The cylinder shall be tested
according to LS-432. The other half of the cylinder shall be retained by the Owner for audit purposes.
Individual test results shall be forwarded to the Contractor, as they become available.
For a lot to be considered acceptable, the cylinder shall have an air content of 3.0% or more and a
spacing factor of 0.200 mm or less. Acceptable lots shall be subject to full payment.
Lots with a spacing factor between 0.200 mm and 0.250 mm shall be repaired as identified in Table 2.
Lots with a spacing factor exceeding 0.250 mm shall be rejected and replaced at the Contractor’s
expense.
Referee testing of air void system parameters shall be according to OPSS 1350.
Rapid chloride permeability testing shall be according to LS-433. Acceptance of rapid chloride
permeability shall be based on the result obtained on the cylinders representing the lot. Lots with rapid
chloride permeability less than 2,500 coulombs are considered acceptable. Lots with a rapid chloride
permeability result greater than 2,500 coulombs and less than or equal to 3,500 coulombs shall be
considered unacceptable and shall be repaired as identified in Table 2. Lots with rapid chloride
permeability results exceeding 3,500 coulombs shall be rejected and replaced.
For concrete lots containing silica fume, rapid chloride permeability less than 1,000 coulombs are
considered acceptable. Lots containing silica fume with a rapid chloride permeability result greater than
1,000 coulombs and less than or equal to 2,000 coulombs shall be considered unacceptable and shall be
repaired as identified in Table 2. Lots containing silica fume with rapid chloride permeability results
exceeding 2,000 coulombs shall be rejected and replaced.
Referee testing of rapid chloride permeability testing for all concrete shall be carried out according to the
high performance concrete requirements of the OPSS 1350 Acceptance of Rapid Chloride Permeability
for Silica Fume Overlays and High Performance Concrete clause. The reference to cores in OPSS 1350
shall be interpreted to mean cylinders.
The cost of rapid chloride permeability testing for all concrete shall be according to OPSS 1350
Acceptance of Rapid Chloride Permeability for Silica Fume Overlays and High Performance Concrete
clause.
The Contract Administrator shall carry out measurements to confirm compliance with tolerance
requirements of Table 1. Members exceeding the tolerances specified in Table 1 shall be rejected and not
incorporated into the Work.
909.08.06.01 General
Any individual member having one or more of the defects and deficiencies listed in Table 2 shall be
deemed unacceptable and the member shall be repaired according to Table 2. When more than one of
the defects or deficiencies listed in Table 2 is located in the same area in the member, a proposal for
repair shall be submitted to the Contract Administrator for acceptance according to the All Other Defects
and Deficiencies clause.
A member having any one of the following defects and deficiencies shall be rejected and shall not be
incorporated into the Work:
b) For I-members, if there is honeycombing, voids, cavities, spalls, delaminations, or cracks, in the
concrete within a bearing surface area defined by the contact area of the bearing plus 30 mm on all
sides, except when member ends are encased in concrete.
c) For box members, if there is honeycombing, voids, cavities, spalls or delaminations in the concrete
within a bearing surface area defined by the contact area of the bearing plus 30 mm on all sides,
except when member ends are encased in concrete.
d) If there is a crack in the bottom flange that extends through to the opposite face.
f) If the sweep of the member on site and in position without any intermediate bracing is in excess of
1.5 mm/m length of member.
For members with defects or deficiencies that are not identified as rejectable or included in the list of
defects and deficiencies repairable by standards methods in Table 2, or when more than one of the
defects or deficiencies listed in Table 2 are located in the same area in the member, a proposal for repair
shall be submitted to the Contract Administrator for acceptance.
If the repair proposal is deemed acceptable, the members shall be repaired according to the proposal.
No repairs shall be carried out without the acceptance of the proposal. If the repair proposal is deemed
unacceptable, the members shall be rejected and shall not be incorporated into the Work.
The repair proposal, signed and sealed by an Engineer, shall include as a minimum:
b) Detailed sketches, width, length, depths, location, and nature and frequency of any defects.
c) Assessment of any impact of the repaired defects on durability, structural adequacy, and integrity of
the member or on the structure.
e) Verification that the repair plan complies with the applicable standards for the type of work.
f) All relevant supporting information, including material test results, field measurements and
observations, production records, photographs, and structural analysis calculations used for
determining that the performance and function originally expected from the member shall be met.
g) Causes of the defect and corrective action to be taken to prevent recurrence of the defect in future
production, delivery, or installation.
Payment at the Contract price for the above tender items shall be full compensation for all labour,
Equipment, and Material to do the work.
For concrete members containing silica fume, lots of members with an average value of rapid chloride
permeability exceeding 1,500 Coulombs and less than or equal to 2,000 Coulombs shall be accepted with
a payment reduction in addition to the repair method required in Table 2. The payment reduction shall be
calculated and applied as follows:
a) The price for the fabrication items in the Contract shall be converted to an equivalent price per metre
length for each member type in the lot.
c) For each member type in the lot, the payment reduction = (Pf) x (Equivalent price per metre length) x
(Length of Members).
d) Total payment reduction for each lot is the sum of the individual payment reductions for each member
type calculated in ‘c’.
Payment at the Contract price for the above tender item shall be full compensation for all labour,
Equipment, and Material to do the work.
Payment at the Contract price for the above tender item shall be full compensation for all labour,
Equipment, and Material to do the work.
Item Tolerances
Length:
Straight-line measurement taken horizontally at the mid- 1.0 mm/m; not to exceed 25 mm maximum
height of member
Overall Depth 8 mm for depths up to 600 mm
12 mm for depths over 600 mm
Flange Depth and Web Width for Members Without Flange depth 5 mm
Voids Web width -5/+10 mm
Flange Depth and Web Width for Members With Voids Flange depth 10 mm
Web width 10 mm
Width:
Flanges and box members 10 mm
Sweep:
I-members, spaced box members and spaced hollow 1 mm/m length of member.
slab members
Camber Difference:
Between adjacent members spaced apart 25 mm
Between adjacent members placed side-by-side 15 mm
Hold-Down Position Along Length 300 mm
Concrete Cover Over Reinforcing Steel Unless otherwise specified in the Contract
Documents, the tolerance for concrete cover
over reinforcing steel shall be -5/+15 mm
Stirrup Projection -10/+15 mm
Contractor: …………………………………………………………………………………………….……
………………………………………………………………………………………………………………..
………………………………………………………………………………………………………….…….
Date__________________________________
DISTRIBUTION: 1) Contractor
2) Contract Administrator or Project Manager File
Contractor: ………………………………………………………………………………….……
(Attach documents per Contract Documents (examples: test results, production records) outside of form)
Date
DISTRIBUTION: 1) Contractor
2) Contract Administrator or Project Manager File
Request to Proceed
Contract Number:
Number:
Consultant
Contractor Name:
Name:
Applicable specification(s)
/special provision(s):
This is to confirm that the above stage of work, component or product has been completed according to
the general requirements of the Contract Documents.
DISTRIBUTION: 1) Contractor
2) Contract Administrator or Project Manager File
Request to Proceed
Contract Number:
Number:
Consultant
Contractor Name:
Name:
Applicable specification(s)
/special provision(s):
The Contractor may proceed to the next operation as of the date of this notice.
Any Notice to Proceed by the Owner or its Contract Administrator or Project manager of the Work and
Materials of the Contractor does not relieve the Contractor from any responsibility or obligation for the
proper performance of the Work in general conformity with the requirements of the Contract Documents.
As well, the Notice to Proceed imposes no liability upon the Owner or its Contract Administrator or Project
Manager and is not to be interpreted as an approval or acceptance of the Work or the Materials by the
Owner that the Work and Materials was completed or supplied in general conformance with the Contract
Documents.
DISTRIBUTION: 1) Contractor
2) Contract Administrator or Project Manager File
Designer Action/Considerations
Several revisions have been made to the technical information of OPSS 909. It is recommended that the
designer and the users read the specification in its entirety to become familiar with the differences and
necessary requirements for municipal use.
Clause 909.07.20 requires the use of a Certificate of Conformance as shown on form OPSF 539-1. If a
form other than OPSF 539-1 is to be used for submission purposes, the alternate form should be invoked
by reference in the Contract Documents and the specification should be amended to remove reference to
OPSF 539-1.
Clause 909.04.02.05 requires the use of a Manufacturer’s Certificate of Conformance as shown on form
OPSF 906-1. If a form other than OPSF 906-1 is to be used for submission purposes, the alternate form
should be invoked by reference in the Contract Documents and the specification should be amended to
remove reference to OPSF 906-1.
Clause 909.04.02.05 requires the use of a Request to Proceed as shown on form OPSF 906-2. If a form
other than OPSF 906-2 is to be used for submission purposes, the alternate form should be invoked by
reference in the Contract Documents and the specification should be amended to remove reference to
OPSF 906-2.
Clause 909.04.02.05 requires the use of a Notice to Proceed as shown on form OPSF 906-3. If a form
other than OPSF 906-3 is to be used for submission purposes, the alternate form should be invoked by
reference in the Contract Documents and the specification should be amended to remove reference to
OPSF 906-3.
Clause 909.07.15.02 requires the use OPSF 909-1 for reporting concrete test information. If a form other
than OPSF 909-1 is to be used for submission purposes, the alternate form should be invoked by
reference in the Contract Documents and a special provision should be written to remove reference to
OPSF 909-1.
The designer should ensure that the General Conditions of Contract and the 100 Series General
Specifications are included in the Contract Documents.