The Government of Andhra Pradesh has issued an order allowing monthly price adjustments for steel and cement in ongoing and future civil works, superseding previous regulations. This decision follows recommendations from the Board of Chief Engineers and addresses concerns from the Builders' Association regarding financial losses due to rising material costs. The new adjustment scheme will apply to all government contracts and is effective from March 1, 2008.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
0 ratings0% found this document useful (0 votes)
37 views3 pages
01 G.O 94, 16.04.2008
The Government of Andhra Pradesh has issued an order allowing monthly price adjustments for steel and cement in ongoing and future civil works, superseding previous regulations. This decision follows recommendations from the Board of Chief Engineers and addresses concerns from the Builders' Association regarding financial losses due to rising material costs. The new adjustment scheme will apply to all government contracts and is effective from March 1, 2008.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 3
GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
Roads & Buildings - Adoption of Price Adjustment for Steel and Cement for
all ongoing works of Bridges, Roads and Buildings and other Civil Works of
all Departments ~ Further Orders ~ Issued.
TRANSPORT, ROADS & BUILDINGS (R.I) DEPARTMENT
G.0.Ms.No.94 Dated: 16.04.2008.
Read the following
G.0.Ms.No.35, T.R & B(R.1) Dept., Dt:28.02.2006.
G.0.Ms.No.73, T.R & B(R.I) Dept., Dt:24.04.2006.
G.0.Ms.No.123, T.R & B(R.I) Dept., Dt:06.07.2006.
G.0.Ms.No.233, T.R & B(R.I) Dept., Dt:20.11.2006.
G.0.Ms.No.175, T.R & B(R.I) Dept., Dt:19.02.2007.
Builders’ Association of India representation dated: 11-04-2006.
Minutes of the Board of Chief Engineers, Dt:02.01.2008.
Minutes of the meeting held in the Chambers of Hon’ble CM on
09.04.2008 at 11.am.
ORDER:
Inthe G.Os 1*to 5 read above, orders were issued according Price
Adjustment to all the works under the control of Roads & Buildings
Department viz. Roads, Bridges, Buildings and Civil Works for all ongoing
and future works for the items Steel, Cement, Bitumen, POL and other
items duly following the Price index rates and following the formula
mentioned therein.
ee
2. The Builders’ Association of India, A.P.Centre have made
representation that, hike in steel and cement etc, are causing heavy losses
to them, hence it is not possible to take up the works and have requested
to issue orders allowing difference in estimate rate to monthly rates
instead of adopting Price Index Formula issued in G.O.Ms.No.35, T.R & B
Dept., Dt:28.02.2006, in respect of items Steel and Cement. |
3. The I & CAD Dept. have placed the matter before the Board of Chief
Engineers. The Board of Chief Engineers have recommended for allowing
monthly price adjustment based on rates fixed by the Board of Chief
Engineers, provided that the agencies furnish monthly work done quantity
and measures/check measures by the concerned Departmental
Officers/EPC Agencies.4. In the minutes of the meeting held on 09.04.2008 in the chambers of
Hon’ble Chief Minister, it has been decided to allow monthly Price
adjustment for Stee! and cement. With regard to Bitumen and POL prices it
is not included in this scheme, as these are being corrected by the PSU Oil
companies every fortnight and being adopted by the Roads & Buildings
Dept.
5. Government after careful examination of the matter accept the
recommendations of the Board of Chief Engineers and minutes of meeting
held on 9-04-08 and hereby allow to adopt Price adjustment for steel and
cement every month in supersession of the orders issued in G.O.Ms.No.35,
T.R & B Dept., Dated: 28.02.2006 and formula used for adjustment based
‘on whole sale price index and co-efficient of 0.85 is now replaced by the
absolute variation between the estimated rate and the rate approved by
the Government based on the recommendation of Board of Chief Engineers
for the month starting from the 1% March 2008 subject to the following
conditions:~
i) The Board of Chief Engineers shall meet on the 5" of every month
and will recommend the new price to the Principal Secretary, R&B on
the next day of the review for approval starting from 5‘ May,2008.
ii) The Principal Secretary, R&B in consultation with the Secretary,
Finance (W&P) shall issue a Order on the settled new price every
month based on the Board of Chief Engineers recommendation.
iii) The BOCE shall collect quotations from ISI approved producers for all
categories of Steel including TMT and arrive at an average admissible
price to be applied for the month.
lv) The Board of Chief Engineers shall collect quotations from ISI
standards cement manufacturers and similarly average rates should be
adopted for the month.
v) For Indiramma housing programme, the required increase will be
RS.3,000 per unit for rural and urban individual housing. For G +,
Housing Board houses taken up by the A.P.State Housing Corporation
and Rajiv Swagruha programme the adjustment scheme will be
applicable to meet the price contingency.
vi) The Price adjustment shall not be limited to Rs.50.00 Lakhs and above
estimated projects and a time period of 6 months and above, but shall
be applied irrespective of cost estimates and time period.
vii) For the works taken up in externally aided projects, the guidelines
specified thereon are to be followed.viii)
Ix)
6.
The price adjustment shall be applicable for all ongoing and future
works. ane_price adjustment shall be applicable within original
contract period or period extended on gi the departmental
Gelays and valid fall not be applicable to the extensions
nted on account of the contractors fault as envisaged in G.0.94 of
(CAD. The price adjustment shall be applicable from the date of
agreement for all those ongoing works where final bills are not taken
by the contractors as on the date of issue of these orders. Price.
adjustment shall _be applicable for actual components. of _items_of
works actually carried out during the period of the bill. The above
orders are applicable for all contracted works of the Government of
Andhra Pradesh and Corporations, local bodies and Government
Undertakings, Tirumala Tirupathi Devasthanam, etc.
The adjustment scheme will be applied in all cases where the
variation between the estimated rates and Board of Chief Engineers
approved rates (increase or decrease) is more than 5% for the
month.
All the Heads of Department/Corporations, Universities dealing with
PWD Works shall take action accordingly.
7
8
UO.
To:
The
The’
The
The
The
The
The
The above orders will come into effect from 01.03.2008.
This order issues with the concurrence of Finance Dept. vide their
.No.11746-B/524/A2/Expr.PW/08, Dated: 16.04.2008.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
Dr.T.CHATTERJEE,
PRINCIPAL SECRETARY TO GOVERNMENT
all HODs connected with Engineering works...
Housing, I & CAD, Panchayat Raj, Home, Higher Education,
School Education, Social Welfare, Tribal Welfare, Revenue,
M.A & U.D and H.M & F.W. Depts.
ENC (AW) I&CAD, ENC(R&B) Admn. & NH,
Builder’s Association of India,
A.P.Centre, Hyd.
P.S to Pri, Secy. to Govt. (TC)
T.R & B Dept.
Advisor, QC for R&B, Hyd.
Technical Advisor,
Housing Dept. & School Education Dept.
//forwarded by order//
SECTION OFFICER