MPP Installation Manual For Battery C Version

The document is an installation and configuration manual for the Pytes Lithium Battery E-BOX Series with the Voltronic Axpert King Inverter. It includes detailed steps for installation, power and communication cable connections, setting the DIP switch, and starting up the system. Additionally, it provides a BOM list and cautions users to refer to the inverter user manual for more settings.

Uploaded by

Teodor Markov
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views11 pages

MPP Installation Manual For Battery C Version

The document is an installation and configuration manual for the Pytes Lithium Battery E-BOX Series with the Voltronic Axpert King Inverter. It includes detailed steps for installation, power and communication cable connections, setting the DIP switch, and starting up the system. Additionally, it provides a BOM list and cautions users to refer to the inverter user manual for more settings.

Uploaded by

Teodor Markov
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Installation and configuration manual

With Voltronic

Pytes Lithium Battery

E-BOX Series

With Voltronic Axpert King Inverter


CONTENTS
1.BOM List ................................................................................ 3

2.Communication Cable ........................................................... 4

3.How to Install ......................................................................... 5

4.Power Cable Connection ........................................................ 6

Step.1 ..................................................................................................... 6

Step.2 ..................................................................................................... 6

Step.3 ..................................................................................................... 6

5.Communication Cable Connection ........................................ 7

Step.1 ..................................................................................................... 7

Step.2 ..................................................................................................... 8

6.Set the DIP Switch................................................................. 9

7.Start Up the System ............................................................ 10

8.Change the Battery Setting of The Inverter ...................... 10

9.Warning Message 61. How to Reset It ................................ 11

2
1.BOM List

Before installation, you should prepare following items as shown in

Graph 1.

Item Remarks Quantity

Conductor cross-section: 50 mm²to


95 mm²
Cable diameters: 14 mm to 25 mm Depends on the number of
Power Cable
Only copper cables may be used. batteries and the
(DC)
The DC cables must be sized for the connection method
maximum battery voltage and the
maximum battery current.
RS485 communicationTerminal
RJ45 Cable (RJ45 port) follow RS485 protocol, to 1
output batteries information.

PC (Personal
Self-Provide. 1
Computer)

Depends on the number of


Battery 48100R / 48100C / 4850 batteries and the
connection method

Inverter Voltronic Axpert King 1

Graph 1.

3
2. Communication Cable

RJ45 Port cable configuration for BMS and Inverter is shown in Pic 2.1.

and Pic 2.2.

Pic 2.1

Pic 2.2

4
3. How to Install

Install the system as shown in Flow Chart 1.

Communication cable
Power cable connection
connection

Start up the system Set the DIP switch

change the battery


Check the battery SOC
setting of the inverter

System monitoring

Flow Chart 1.

CAUTION: If you want to get more inverter-related settings, please refer to


the inverter user manual first.

5
4. Power Cable Connection

Step.1

Before connecting all wirings, please take off bottom cover by

removing two screws as shown Pic 4.1.

Pic 4.1

Step.2

Connect the red and black cables to the inverter DC connector as

shown in Pic 4.2.


BATTERY+
BATTERY-

Pic 4.2

Step.3

At the other end of the cable, connect to the battery as shown Pic 4.3.
6
(Ensure that the battery power switch is off)

Pic 4.3

5. Communication Cable Connection

Step.1: Wire Set Up

a): Prepare one cable, one clamp and one scissor as shown in Pic

5.1.1.

Pic 5.1.1

b): Cut the cable skin at both ends to expose the wires as shown in Pic

5.1.2.

Pic 5.1.2
7
c): Arrange wires sequence according to the Appendix C V1.0.4.

d): Check the battery wire sequence

e): Insert battery wire lines and inverter wire lines respectively into

crystal heads.

f): Clamp two crystal heads tightly and take them out as shown in Pic

5.1.3.

Pic 5.1.3

Step.2: Cable Connection

Connect one end of the cable to the inverter communication port as

shown in Pic 5.2.1. Make sure which communication port to use.

8
RS485

Pic 5.2.1

Connect the other end of the cable to the battery communication port

as shown in Pic 5.2.2 (Ensure the correct sequence of wires inside the

communication cable).

Pic 5.2.2

6. Set the DIP Switch

Set the 1st dip-switch up and the rest of the switches down. Only the

master battery requires the dip switches adjusted (Up, Down, Down, Down)

as shown in Pic 6.1

9
Pic 6.1

7. Start Up the System

Start up the inverters and batteries.

8. Change the Battery Setting of The Inverter

※CAUTION: If you want more details about the batteries settings,

please check the operating manual of inverters.

You have to navigate to menu 05 (press enter button for 3 seconds to

enter the menu) of the off grid inverter and select the option PYL. When

you find PYL press enter and then return to the main menu (press return

button to top left corner of the LCD) as shown in Pic 8.1 and Pic 8.2

10
Pic 8.1

Pic 8.2

END