0% found this document useful (0 votes)
51 views1 page

1.ZS Itp El 0004

Zs itp

Uploaded by

rohan dsouza
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views1 page

1.ZS Itp El 0004

Zs itp

Uploaded by

rohan dsouza
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

CLIENT MAN CONTRACTOR

Project PROPOSED G+4+20+ROOF


CONSULTANT MEP CONSULTANT MEP CONTRACTOR Name: RESIDENTIAL BUILDING ON
PLOT NO.JVC14AHRG001
AT JUMEIRAH VILLAGE
CIRCLE
AL BARSHA SOUTH
681,DUBAI-U.A.E

ITP No.: NAQ -MEP-ELEC-ITP-006


INSPECTION AND TEST PLAN Rev: 0
WORK ITEM:LV PANELS,SMDB'S,DB'S,CAPACITOR BANKS AND ATS PANEL Page: 1 OF 1
Item Inspection Authority & Codes

Activity Responsible Person Controlling Documents Acceptance Criteria DAR PROLEED Verifying Document
No. AL NAQEEB CONSTRUCTION CONSULTANT

Project Specification &


Ensure that all materials are
1 Project Engineer (Electrical) Approved Manufacturers list Approved Material Submittal A1 H,R H,R Material Submittal
according to project specification.
of client

Project Specification & Free from physical damage,


Project Engineer (Electrical) Material Inspection Request,
2 Material receiving inspection. Approved Material Submittal equipments are of approved size A1 A1 A1
& Store Keeper Delivery Note or Purchase Order
and Sample & type as per approved submittal

Ensure that all shop drawings to be


used for installation of LV cables & Shop Drawing Submittal Approved Drawing issued for
3 Project Engineer (Electrical) A1 H,R H,R Drawing Submittal Schedule
Earth, LV Switchboards are Schedule construction
approved.

Inspection for the installation of LV Approved Shop Drawing & Position,location and type of
4 panels,SMDB'S , DB's,Capacito Electrical Site Engineer Project Specification, Method mounting,alignment ofjoint and A1 A1 A1 Work Inspection Request
banks and ATS panel Statement other parameters
Inspection for installation of Project Engineer Approved Shop Drawing & Position,location and type of
5 capacitor bank and detuned reactor (Electrical),Electrical site Project Specification, Method mounting,alignment ofjoint and A1 A1 A1 Work Inspection Request
as per approved drawing engineer Statement other parameters

Size and no:of cable/containment of


Inspection for installation of Project Engineer Approved Shop Drawing &
cable,physical damage,proper
6 automatic transfer switch cables as (Electrical),Electrical site Project Specification, Method A1 A1 A1 Work Inspection Request
engineer Statement circuit,proper termination and
per approved drawing
glanding and other parameters

PROLEED
AL NAQEEB CONTRACTING LLC DAR CONSTRUCTION CO.LLC
CONSULTANT
Name Project Manager Project Engineer Consulting Engineer
Position
Signature
Date

LEGEND
A1 100 % Inspection H Holdpoint N/A Not Applicable

A2 Random Inspection W1 100 % Witnessed


R Review W2 Random Witnessed