17 x11 Fin Man e
17 x11 Fin Man e
Financial Management
(E. Quantitative Methods)
714
Financial Management
(E. Quantitative Methods)
Sun, Inc. manufactures product X and product Y, which are processed as follows: B. Activity BC 2 weeks
Type A machine Type B machine C. Activity DE 1 week and activity BC 1 week
Product X 6 hours 4 hours D. Activity DE 1 week and activity EF 1 week
Product Y 9 hours 5 hours
Learning Curve
The contribution margin is P12 for product X and P7 for product Y. The available time daily for
1
. Contratista, Inc. is considering a three-phase research project. The time estimates for
processing the two products is 120 hours for machine Type A and 80 hours for machine Type B. completion of Phase 2 of the project are:
Pessimistic 24 weeks
10. How would the constraint for machine Type A be expressed? Most likely 20 weeks
A. 4X + 5Y C. 4X + 5Y ≤ 80 Optimistic 10 weeks
B. 6X + 9Y ≤ 120 D. 12X + 7Y Using the program evaluation and review technique (PERT), the expected time for
completion of Phase 2 should be
11. How would the constraint for machine Type B be expressed? A. 20 weeks C. 18 weeks
A. 4X + 5Y C. 4X + 5Y ≤ 80 B. 19 weeks D. 24 weeks
B. 6X + 9Y ≤ 120 D. 12X + 7Y
.
2
Wind Company expects an 85% learning curve. The first batch of a new product required 500
12. How would the objective function be expressed? hours. The first four batches should take an average of
A. 4X + 5Y C. 4X + 5Y ≤ 80 A. 361.25 hours C. 500.0 hours
B. 6X + 9Y ≤ 120 D. 12X + 7Y B. 425.0 hours D. 322.4 hours
3
. A learning curve of 80% assumes that production unit costs are reduced by 20% for each
PROBLEMS: doubling of output. What is the cost of the sixteenth unit produced as an approximate
PERT-CPM percent of the first unit produced?
A. 30 percent C. 41 percent
2. Castle Building Company uses the critical path method to monitor
B. 51 percent D. 64 percent
construction jobs. The company is currently 2 weeks behind schedule on Job
WW, which is subject to a P10,500-per-week completion penalty. Path A-B- 4
. Soft Inc. has a target total labor cost of P3,600 for the first four batches of a product. Labor
C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D- is paid P10 an hour. If Soft expects an 80% learning curve, how many hours should the first
E-F-G-H-I has a normal completion time of 22 weeks. The following batch take?
activities can be crashed. A. 360 hours C. 57.6 hours
Activities Cost to Crash 1 Week Cost to Crash 2 Weeks B. 140.63 hours D. 230.4 hours
BC P 8,000 P15,000
DE 10,000 19,600 .
5
Havenot has estimated the first batch of product will take 40 hours to complete. A 90%
EF 8,800 19,500 learning curve is expected. If labor is paid P15 per hour, the target labor cost for four batches
Castle desires to reduce the normal completion time of Job WW and, at the same time, report of product is
the highest possible income for the year. Castle should crash A. P600 C. P1,944
A. Activity BC 1 week and activity EF 1 week B. P2,160 D. P2,400
715
Financial Management
(E. Quantitative Methods)
A. 640 C. 1,600 boxes. A box of muffins costs P2 and sells for P3 through regular stores. Any
B. 960 D. 2,560 boxes not sold through regular stores are sold through Dough’s thrift store for
P1. Dough assigns the following probabilities to selling additional boxes:
.
8
A construction company has just completed a bridge over the Visayan area. This the first
Additional sales Probability
bridge the company ever built and it required 100 weeks to complete. Now having hired a
60 0.6
bridge construction crew with some experience, the company would like to continue building
100 0.4
bridges. Because of the investment in heavy machinery needed continuously by this crew, the
company believes it would have to bring the average construction time to less than one year What is the expected value of Dough’s decision to buy 100 additional boxes of muffins?
(52 weeks) per bridge to earn a sufficient return on investment. The average construction time A. P28 C. P52
will follow an 80% learning curve. To bring the average construction time (over all bridges B. P40 D. P68
constructed) below one year per bridge, the crew would have to build approximately
A. 2 additional bridges. C. 3 additional bridges.
11
. Karen Company has three sales departments. Department A processes about 50 percent of
B. 7 additional bridges. D. 8 additional bridges. sales, Department B about 30 percent, and Department C about 20 percent. In the past,
Departments A, B, and C had error rates of about 2 percent, 5 percent, and 2.5 percent,
9
. Moss Point Manufacturing recently completed and sold an order of 50 units that had the respectively. A random audit of the sales records yields a recording error of sufficient
following costs: magnitude to distort the company’s results. The probability that Department A is responsible
Direct materials P 1,500 for this error is
Direct labor (1,000 hours @ P8.50) 8,500 A. 0.50 C. 0.20
Variable overhead (1,000 hours at P4.00) 4,000 B. 0.33 D. 0.25
Fixed overhead 1,400
P15,400
12
. A beverage stand can sell either softdrinks or coffee on any given day. If the stand sells
softdrinks and the weather is hot, it will make P2,500; if the weather is cold, the profit will be
7
. Answer: B P1,000. If the stand sells coffee and the weather is hot, it will make P1,900; if the weather is
Cumulative average DLH after 4 units: (1,000 x 0.8 x 0.8) 640 cold, the profit will be P2,000. The probability of cold weather on a given day at this time is
Total DLH after 4 units: 4 x 640 2,560 60%. The expected payoff if the vendor has perfect information is
Less Total DLH used after 2 units (1,000 x 0.8 x 2) 1,600 A. P3,900 C. P2,200
Total DLH used by 3rd and 4th units 960 B. P1,360 D. P1,960
716
Financial Management
(E. Quantitative Methods)
13
. The Teeners’ Club sells fresh hot cider at Recto football games. The A. 191 C. 234
frequency distribution of the demand for cups of hot cider per game is B. 225 D. 250
presented below:
Unit sales volume Probability Question Nos. 17 and 18 are based on the following:
Sampaguita Company makes corsages that it sells through salespeople on the streets. Each
10,000 0.10
sells for P2 and has variable production costs of P0.80. The salespeople receive a P0.50
20,000 0.15
commission on each corsage they sell, and the company must spend P0.05 to get rid of each
30,000 0.15
unsold corsage. The corsages last for only one week and cannot be carried in inventory.
40,000 0.40
50,000 0.20
The manager of the firm had estimated demand per week and associated
The hot cider is sold for P35.00 a cup and the cost per cup is P20.00. Any unsold hot cider
is discarded because it will spoil before the next game. probabilities as follows:
What is the estimated demand for hot cider at the next football game if a deterministic Demand Probability
approach based on the most likely outcome is used? 100,000 0.20
A. 34,500 C. 16,000 120,000 0.20
B. 40,000 D. 50,000 140,000 0.30
160,000 0.30
14
. Green Co. is considering the sale of banners in an exhibit fair. Green Co. could purchase
these banners for P7.50 each. Unsold banners would be unreturnable and worthless after 16
. The optimal weekly production of the corsage is
the exhibit. Green would have to rent a booth at the stadium for P4,000. Green estimates A. 120,000 C. 134,000
sales of 2,000 banners at P20.00 each. If Green’s prediction proves to be incorrect and only B. 140,000 D. 145,000
1,500 banners were sold, the cost of this prediction error would be:
A. P 6,250 C. P 4,750 17
. The value of perfect information is
B. P10,000 D. P 3,750 A. P14,400 C. P23,800
B. P16,000 D. P22,100
15
. The manager of Batanes Company has developed the following probability
distribution of dairy sales of a highly perishable product. The company Question Nos. 21 through 24 re based on the following information:
restocks the product each morning: Glassco, Inc. has two products, a frozen dessert and ready-to-bake breakfast rolls,
X (Units Sold P (Sales =X) ready for introduction. However, plant capacity is limited, and only one product
150 0.20 can be introduced at present. Therefore, Glassco has conducted a market study, at
175 0.40 a cost of P26,000, to determine which product will be more profitable. The
200 0.15 results of the study show the following sales patterns.
225 0.10 Sales of Desserts at P1.80 per unit Sales of Rolls at P1.20 per unit
250 0.10 Volume Probability Volume Probability
275 0.05 250,000 .30 200,000 .20
If the company desires an 85% service level in satisfying sales demand, what should the 300,000 .40 250,000 .50
initial balance be for each day? 350,000 .20 300,000 .20
717
Financial Management
(E. Quantitative Methods)
400,000 .10 350,000 .10 netting P4 per bottle will result. Without rain (probability 0.5), there will still be a full 100,000-
The costs associated with the two products have been estimated by Glassco’s cost bottle yield, but the net will be only P3 per bottle.
accounting department and are shown below: The optimal expected value is
Dessert Rolls A. P200,000 C. P350,000
B. P310,000 D. P400,000
Ingredients per unit P 0.40 P 0.25
Direct labor per unit 0.35 0.30
Theory of Constraints
Variable overhead per unit 0.40 0.20
Production tooling* 48,000.00 25,000.00 . Happy Holidays produces three products: X, Y, and Z. Two machines are
23
Advertising 30,000.00 20,000.00 used to produce the products. The contribution margins, sales demands, and
time on each machine (in minutes) is as follows:
*Glassco treats production tooling as a current operating expense rather than capitalizing it as a Demand CM Time on M1 Time on M2
fixed asset. X 100 P10 5 10
Y 80 18 10 5
. According to Glassco’s market study, the expected value of the sales volume of the breakfast
18 Z 100 25 15 5
rolls is There are 2,400 minutes available on each machine during the week. How
A. 125,000 units C. 260,000 units many units should be produced and sold maximize the weekly contribution?
B. 275,000 units D. 250,000 units X Y Z
A. 100 80 100
. Applying a deterministic approach, Glassco’s revenue from sales of frozen desserts would be
19
B. 20 80 100
A. P549,000 C. P540,000 C. 100 40 100
B. P195,000 D. P216,000 D. 100 80 73
. The expected value of Glassco’s operating profit directly traceable to the sale of frozen
20
Inventory Management
desserts is
EOQ, Safety Stock, Reorder Point
A. P198,250 C. P471,000 Question Nos. 25 through 30 are based on the following:
B. P150,250 D. P120,250
KMU Company uses a small casting in one of its finished products. The castings are purchased
from a foundry located in another Asian country. In total, KMU Company purchases 54,000
. In order to recover the costs of production tooling and advertising for the breakfast rolls,
21
castings per year at a cost of P8 per casting.
Glassco’s sales of the breakfast rolls would have to be The castings are used evenly throughout the year in the production process on a 360-day-per-year
A. 37,500 units C. 100,000 units
basis. The company estimates that it costs P90 to place a single purchase order and about P3 to
B. 60,000 units D. 54,000 units carry one casting in inventory for a year. The high carrying costs result from the need to keep the
castings in carefully controlled temperature and humidity conditions, and from the high cot of
Decision Tree insurance.
22
. A wine maker must decide whether to harvest grapes now or in four weeks. Harvesting now
Delivery from the foundry generally takes 6 days, but it can take as much as 10 days. The days of
will yield 100,000 bottles of wine netting P2 per bottle. If the wine maker waits and the delivery time and the percentage of their occurrence are shown in the following tabulation:
weather turns cold (probability 0.2), the yield will be cut in half but net P3 per bottle. If the
weather does not turn cold, the yield will depend on rain. With rain (probability 0.5), a full yield
718
Financial Management
(E. Quantitative Methods)
719
Financial Management
(E. Quantitative Methods)
ANSWER EXPLANATIONS
8
. Answer: B
No. of BridgesCumulative Average WeeksComputation1100.00280.00(0.8 x
100.0)464.00(0.8 x 80.00)851.20(0.8 x 64.00) It will take 8 bridges to complete them with
cumulative average time in weeks of below 52. The company needs to complete additional 7
bridges to have an average completion time of less than 52 weeks.
9
. Answer: A
Cumulative Ave. DHL50 units20.0100 units16.0( 20 x 80% )200 units12.80( 16 x
80% )Total hrs required by 200 units 128.80 x 2,000 2,560
Less Hours used by first 50 units 1,000
Additional Hours 1,560
Costs
Direct materials (1,500 x 3) P 4,500
Direct labor 1,560 x 8.50 13,260
Variable OH 1,560 x 4 6,240
Total variable Costs 24,000
Fixed OH 10% x 24,000 2,400
Total Cost P26,400
720
Financial Management
(E. Quantitative Methods)
22
. Answer: B
Expected value if immediately harvested: (100,000 x P2) P200,000
10
. Answer: C
SalesConditional Profit (Loss) 60(60 x P3) + (40 x P1) – P200 = P 20 100(100 x P3) – P200 = 100Expected Value: (P20 x 0.6) + (P100 x 0.4) = P52
11
. Answer: B
Dept.ErrorWeightProbabilityA0.020.010.01/.03 = 33.00%B0.050.015.015/03= 50.00% C0.0250.05.005/03= 16.67%0.03
12
. Answer: C
Expected payoff:
Sale of coffee during cold weather 2,000 x 0.6 1,200
Sale of soft drinks during hot weather 2,500 x 0.4 1,000
Total 2,200
13
. Answer: B
The expected sales based on the most likely outcome are 40,000. This is based on the concept that which one with the highest probability is the most likely to happen.
14
. Answer: D
The cost of prediction error = unsold units x purchase price
500 x 7.50 = P3,750
15
. Answer: B
At the service level of 85%, there is 15% risk that the company runs out of stock. To achieve 85% level, 225 units must be purchased at the start of day. (0.20 + 0.40 + 0.15 + 0.10 = 85%); 225
units corresponds to 85%.
16
. Answer: B
PurchasesProbabilityDemand100,000120,000140,000160,000 20%100,00070,00053,00036,000 19,00020%120,00070,00084,00067,000 50,00030%140,00070,00084,00098,000
81,00030%160,00070,00084,00098,000112,000Expected Value 70,000 77,800 79,400 71,700Optimal Production is 140,000 because it gives the highest pay off, which is 79,400
17
. Answer: A
Perfect Information:
721
Financial Management
(E. Quantitative Methods)
722
Financial Management
(E. Quantitative Methods)
Second step is to determine the order of profitability of the product lines per minute of machine 1.
Product X: P10 ÷ 5 min. P2.00
Product Y: P18 ÷ 10 min. 1.80
Product Z: P25 ÷ 15 min. 1.67
The company should produce product Z last because it is the least profitable per minute of usage of Machine 1. It is apparent that Choice D is the only possible correct response.
24
. Answer: A
EOQ = the square root of 2 x annual units required x ordering cost ÷ carrying cost per unit
EOQ = the square root of 2 x 54,000 x 90,000 ÷ 3 = 1,800
25
. Answer: C
Annual ordering cost: 54,000/1800 x 90 2,700
Annual carrying cost: 1,800/2 x 3 2,700
Total cost 5,400
26
. Answer: B
A 15% risk of out-of-stock means a 85% assurance that order will be received on time. Without having a safety stock, the company will use a lead time of 6 days (75%). Therefore, 7-day lead time has
85% assurance or a 15% risk of stockout. The safety stock level is for 1 day (7 – 6) or 150 units.
Daily requirements: 54,000/360 = 150
27
. Answer: D
723
Financial Management
(E. Quantitative Methods)
A 5% risk of out-of-stock means a 95% assurance that order will be received on time. This is
estimated to have a lead time of 9 days (the total of probability for 9 days is 95%).
Reorder point without safety stock 6 days x 150 900
Safety stock (9 – 6) 150 450
Reorder point 1,350
28
. Answer: D
Ordering cost (unchanged) 2,700
Carrying cost
Average inventory (1800/2) + 450 = 1,350
1,350 x 3 4,050
Total 6,750
29
. Answer: A
Safety unitsStock out costCarrying CostTotal 00.25 x 2,400 = 600 0 6001500.15
x 2,400 = 360150 x 3 = 450 8103000.10 x 2,400 = 240300 x 3 = 9001,1404500.05 x
2,400 = 120450 x 3 = ,3501,470Annual stockout cost (100% probability) based 30 orders
(54,000/1800):
30 x 800 = 2,400
The probability of stockout is the inverse of assurance, say at zero safety stock, 6 days, its
75% probable that ordered goods will arrive, therefore, its 25% probable that it won’t.
30
. Answer: C
Defective Units ÷ Actual Units Produced (20 ÷ 3,800) = 0.526%
724