Oee351 Ia2 Iiicse Even Sem

The document outlines the details for an internal assessment test for B.E CSE students at A.R. Engineering College, focusing on renewable energy systems. It includes the test structure, marking scheme, and a series of questions categorized into three parts, covering topics such as hydrogen energy, wind turbines, tidal energy, and fuel cells. The test is scheduled for a duration of 2 hours with a maximum score of 100 marks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views2 pages

Oee351 Ia2 Iiicse Even Sem

The document outlines the details for an internal assessment test for B.E CSE students at A.R. Engineering College, focusing on renewable energy systems. It includes the test structure, marking scheme, and a series of questions categorized into three parts, covering topics such as hydrogen energy, wind turbines, tidal energy, and fuel cells. The test is scheduled for a duration of 2 hours with a maximum score of 100 marks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

REG No:

A.R. ENGINEERING COLLEGE


CS
Approved by AICTE,New delhi,Affiliated to Anna
University, Chennai E&
vadakuchipalayam,kappiyampuliyur(post),Villupuram
-605601 AI
[email protected]/www.arenggc.com
DS
INTERNAL ASSESMENT TEST -2
Program B.E CSE AND Se VI
me B.TECH AIDS mes
&Branch ter
Course OEE 351- Dat 24.
code & RENEWABLE e 4.2
Name ENERGY SYSTEM 02
5
Maximu 100 Duratio 2 HOURS &
9.45am-
m Marks n and 11.45am
Time

PART-A(Answer ALL questions) (10 X 2 = 20 Marks)

Q.No Questions Blooms CO Mark


Level
1 Why hydrogen is considered as a secondary energy source? BL-3 1 2
2 List the classification of OTEC based on location. BL-2 1 2
3 Compare the fuel cell and battery BL-1 1 2
4 List any four benefits of OTEC BL-5 1 2
5 List any four advantages of wind turbine BL-2 1 2
6 List the various components of wind energy system.
7 Define geothermal gradient.
8 What is biogas? Give the advantages.
9 What is a Draft tube?
10 Define surge tank:

PART-B(Answer ALL questions) (5X13 = 65 Marks)

Q.NO Questions Blooms CO Mark


Level
Explain with the neat sketchMagneto Hydro Dynamic
11 a generation (MHD). BL-3 1 13

(or)
11 b
Compare vertical and horizontal axis wind turbine.
BL-1 1 13
Generalized the factor to be considered for the sitting to
install the wind power plant.

12 a BL-6 1 13
Draw the line diagram of various types of wind mill blades
and write their advantagesand disadvantages.

(or)

BL-3 1 13
12 b What is tidal energy? Explain the working of a tidal power plant
with a neat sketch.

Describe the various components and working of


13 a hydroelectric system.

13 b List some turbines used in hydro electric power plant?


List the classification of dams? BL-1 1 13

14 a Explain any one type of gasifier with neat line


diagram. Mention the merits and demerits of the BL-6 1 13
same.

14 b With the help of neat sketch, explain the


BL-1 1 13
working of floating drum type biogas plant..
15 a What is geothermal energy? Explain the working
principle of a geothermal power plant with the BL-6 1 13
help of a neat sketch.

15 b Elaborate the site selection process for Micro


hydro power plant erection.
BL-1 1 13

PART-C(Answer ALL questions) (1X14 =14 Marks)

Q.NO Questions Blooms CO Mark


Level
16 a Explain the construction and working of fuel cell also
BL-6 1 14
mention its merits and demerits.
(or)
16 b Write on the factors that should be consider while selecting a
BL-3 1 14
site for a hydroelectric plant.