Daily Plan

The document outlines the daily maintenance schedule for various mining equipment on May 5, 2025, detailing tasks, locations, and statuses for each unit. It includes completed, rescheduled, and upcoming maintenance activities, along with specific remarks regarding issues and follow-up actions. Additionally, it lists washing, greasing, and inspection tasks planned for the same day.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views2 pages

Daily Plan

The document outlines the daily maintenance schedule for various mining equipment on May 5, 2025, detailing tasks, locations, and statuses for each unit. It includes completed, rescheduled, and upcoming maintenance activities, along with specific remarks regarding issues and follow-up actions. Additionally, it lists washing, greasing, and inspection tasks planned for the same day.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

DAILY SCHEDULE MAINTENANCE SERVICE WHEEL MINING

KEMARIN 04/05/2025 KAI-PLT-TMP01-001A Rev 01


MAINTENANCE Total
NO KODE UNIT MODEL HM HM + - LOKASI TIRE START TIME FINISH Status REMARK
TIPE SERVICE DUR BACKLOG DUR FOLLOW UP PAP DUR Σ DUR

Wheel R10

1 KDT052 FMX 400 10769 -231 WS KM11 PS1 2 0 0 02 7.00 AM 9.00 AM DONE

2 KDT087 FMX 400 6550 50 KM23 PS2 2 0 0 02 9.00 AM 11.00 AM RESCHEDULE PROGRES SHIFT 2

F/U PAP RATING C ENGINE - VISCOSITY - 001017-


3 KDT070 FMX 400 8538 38 KM23 PS2 2 0 1 03 11.00 AM 2.00 PM RESCHEDULE PROGRES SHIFT 3
GAM-SKL-11915

4 KDT037 P360 17542 -208 WS KM11 PS2 2 0 0 02 9.30 AM 11.30 AM DONE

5 KDT044 P360 B6X4HZ 8512 -238 WS KM11 PS2 2 P1-V-BELT BROKEN PART KDT044 BELT TENSIONER 250404141 1 0 03 11.30 AM 2.30 PM DONE

Wheel A2B

P2 - PILLOW BLOCK BROKEN (KCP-006) PILLOW BLOCK ,HEXAGONAL NUT 1.F/U PAP RATING C RIGHT VIBRATION BEARING -
240402248 WEAR METAL - 001017-GAM-SKL-11838
1 KCP-006 BW211-D40 16582 82 KM23 PS2 2 1 1 04 9.30 AM 1.30 PM DONE
P2 - STEERING CYLINDER LEAK (KCP-006) KIT, SEAL 240402250 2.F/U PAP RATING C LEFT VIBRATION BEARING -
P2 - SPHERICAL PLAIN BEARING BROKEN (KCP-006) GASKET 240402251 WEAR METAL - 001017-GAM-SKL-11839

HARI INI 05/05/2025


MAINTENANCE Total
NO KODE UNIT MODEL HM (+/-) HM LOKASI TIRE START TIME FINISH Status REMARK
TIPE SERVICE DUR BACKLOG DUR FOLLOW UP PAP DUR Σ DUR

Wheel R10

1 KDT049 FMX 400 9984 -16 WS KM11 PS4 2 REPLACE RUBBER BOOGIE 1 0 03 6.00 AM 9.00 AM SCHEDULE

UNIT WARRANTY
2 KDT081 FMX 400 7269 19 KM23 PS1 2 0 0 02 9.00 AM 11.00 AM SCHEDULE
COMPONEN

3 KDT053 FMX 400 10262 12 KM23 PS1 2 0 0 02 11.00 AM 1.00 PM SCHEDULE

Wheel A2B

1 KCP-005 BW211-D40 15522 22 KM23 PS2 2 0 0 02 6.00 AM 8.00 AM SCHEDULE

2 GDKM021 GD755-5R 11111 -60 KM23 PS1 2 0 0 02 8.00 AM 10.00 AM SCHEDULE

(+/-)HM BERTANDA WARNA MERAH UNIT WAJIB DI TARIK SERVICE > 50 JAM = UNIT OVERDUO HM 50 JAM / LEBIH 50 JAM
NOTE :
(+/-)HM BERTANDA WARNA KUNING UNIT AKAN DI TARIK SERVICE < 50 JAM = OVERDUO BELUM HM 50 JAM

BESOK 06/05/2025
MAINTENANCE Total
NO KODE UNIT MODEL HM (+/-) HM LOKASI TIRE START TIME FINISH Status REMARK
TIPE SERVICE DUR BACKLOG DUR FOLLOW UP PAP DUR Σ DUR

Wheel R10

F/U PAP RATING C ENGINE - VISCOSITY - 001017-


1 KDT070 FMX 400 8538 38 KM23 PS2 2 0 1 03 6.00 AM 9.00 AM SCHEDULE
GAM-SKL-11915

UNIT WARRANTY
2 KDT084 FMX 400 6509 9 KM23 PS2 2 0 0 02 9.00 AM 11.00 AM SCHEDULE
COMPONEN
P2 - PROGRAM MIDLIFE KOMPONEN COOLING SYSTEM (KDT-
3 KDT036 P360 18246 -4 KM23 PS1 2 1 0 03 11.00 AM 2.00 PM SCHEDULE
036)RADIATOR,IDLER ROLLER240415246
UNIT WARRANTY
4 KDT091 FMX 400 6744 -6 KM23 PS1 2 0 0 02 2.00 PM 4.00 PM SCHEDULE
COMPONEN
(+/-)HM BERTANDA WARNA MERAH UNIT WAJIB DI TARIK SERVICE > 50 JAM = UNIT OVERDUO HM 50 JAM / LEBIH 50 JAM
NOTE :
(+/-)HM BERTANDA WARNA KUNING UNIT AKAN DI TARIK SERVICE < 50 JAM = OVERDUO BELUM HM 50 JAM

PREPARED BY, APPROVED BY, ACKNOWLEDGED BY, ACKNOWLEDGED BY,


REVIEW BY,

PUTRA DEDY HENDRI C ENDANG BUDIONO KUKUH YUDIANTO


MACHFUZH A
(SITE PLANNER) (PLANT DEPT HEAD) (PRODUCTION DEPT HEAD) (PROJECT MANAGER)
(SITE SECTION HEAD PLANNING)
PT. Karunia Armada Indonesia
Ganda Alam Makmur – Sangkulirang
Member of Karunia Group

DAILY SCHEDULE WASHING, GREASING & INSPECTION


Date :05 May 2025
CODE TIME HM
NO MODEL UNIT UNIT JOBDESC REMARK
SITE START STOP PLAN ACTUAL

1 FMX 400 KDT073 (WASHING, GREASING & INSPECTION)

2 FMX 400 KDT049 (WASHING, GREASING & INSPECTION)

3 FMX 400 KDT054 (WASHING, GREASING & INSPECTION)

4 FMX 400 KDT067 (WASHING, GREASING & INSPECTION)

5 FMX 400 KDT068 (WASHING, GREASING & INSPECTION)

6 FMX 400 KDT069 (WASHING, GREASING & INSPECTION)

7 FMX 400 KDT072 (WASHING, GREASING & INSPECTION)

8 FMX 400 KDT081 (WASHING, GREASING & INSPECTION)

1.

NAME MECHANIC EKSEKUTOR : 2.

3.

NAME PIC ( GROUP LEADER )

Created By, Diketahui Oleh,

Muhammad zacky hasbullah


Group Leader/Section Head