CIGSP Phase I Report BRG 28june2023
CIGSP Phase I Report BRG 28june2023
i
TABLE OF CONTENTS
LIST OF FIGURES ........................................................................................................................................................... iii
LIST OF TABLES ............................................................................................................................................................. iii
LIST OF ABBREVIATIONS ............................................................................................................................................... iv
1 EXECUTIVE SUMMARY ..........................................................................................................................................1
1.1 BACKGROUND AND SCOPE .................................................................................................................................1
1.2 BRG CREDENTIALS ...........................................................................................................................................2
1.3 SUMMARY OF CONCLUSIONS .............................................................................................................................. 3
1.4 RECOMMENDATIONS ........................................................................................................................................4
1.5 STRUCTURE OF THE REPORT................................................................................................................................5
2 FORECAST OF UNMET GAS DEMAND NEED ......................................................................................................... 6
2.1 HISTORIC AND CURRENT DEMAND FOR NATURAL GAS BY THE WORKING GROUP UTILITIES............................................. 6
2.2 INCORPORATION OF RENEWABLE ENERGY SCENARIOS INTO POWER GENERATION UTILITIES’ FORECASTS ........................... 6
2.3 2022 COOK INLET GAS SUPPLY STUDY BY THE DEPARTMENT OF NATURAL RESOURCES ................................................. 9
2.4 UNMET GAS DEMAND FORECAST ...................................................................................................................... 10
2.5 UNCERTAINTIES OF THE UNMET GAS DEMAND FORECAST. ..................................................................................... 15
3 NEW SUPPLY OPTIONS CONSIDERED ................................................................................................................. 18
3.1 PROJECT OPTIONS ..........................................................................................................................................18
3.2 SUMMARY OF OPTION ANALYSIS ....................................................................................................................... 19
4 OPTION SELECTION.............................................................................................................................................39
4.1 OPTION SCORING METHODOLOGY ..................................................................................................................... 39
4.2 OPTION SCORING PROCESS .............................................................................................................................. 39
4.3 RESULTS OF OPTION SCORING EXERCISE ............................................................................................................. 42
5 MARKET, PRICE VOLATILITY, AND RISK ANALYSIS .............................................................................................. 45
5.1 LNG MARKET ENVIRONMENT AND CURRENT OUTLOOK ........................................................................................ 45
5.2 HISTORIC GAS AND LNG PRICE VOLATILITY ANALYSIS ............................................................................................ 46
5.3 LNG MARKET SOURCING STRATEGY .................................................................................................................. 49
5.4 STATISTICAL RISK ANALYSIS OF RECOMMENDED OPTIONS ...................................................................................... 50
6 RECOMMENDATIONS AND NEXT STEPS ............................................................................................................. 52
6.1 RECOMMENDED ACTIONS TO CONFIRM FEASIBILITY OF TOP SCORING OPTIONS.......................................................... 52
6.2 PROJECT MANAGEMENT NEXT STEPS ................................................................................................................. 52
ii
LIST OF FIGURES
Figure 1: Areas of Focus for Utility Clients..................................................................................................................... 2
Figure 2: Alaska Natural Gas Delivered to Consumers .................................................................................................. 6
Figure 3: Alaska Net Electricity Generation by Source (December 2022) ..................................................................... 7
Figure 4. Power Generation: Demand Planning Assumptions vs. Potential Bounds of Gas Requirements .................. 8
Figure 5: ADNR's 2022 Mean Truncated Annual Gas Supply Forecast ........................................................................ 10
Figure 6. Utilities’ Contracted and Uncontracted Demand vs Cook Inlet Supply ........................................................ 12
Figure 7: ADNR’s 2022 Mean Truncated Natural Gas Supply and Utilities’ Demand Forecasts .................................. 13
Figure 8: Unmet Gas Demand for Low, Medium, and High Demand Scenarios .......................................................... 14
Figure 9: Hilcorp’s Cook Inlet Gas Storage and Production Capacity .......................................................................... 16
Figure 10: 2018 ADNR Cook Inlet Gas Availability Curve ............................................................................................. 21
Figure 11: Incremental Regional Gas Supply Estimate ................................................................................................ 22
Figure 12: Estimated Project Costs and Greenhouse Gas Emissions ........................................................................... 32
Figure 13: Option Score Summary ............................................................................................................................... 42
Figure 14: Historical LNG Import Movements since January 2020 .............................................................................. 45
Figure 15: Potential LNG Price Indices: Historical Trends ............................................................................................ 47
Figure 16: Expected Volatility & Average Price (FOB) of Potential Supply Options (2024‐34) .................................... 49
LIST OF TABLES
Table 1: Unmet Gas Demand by Year (BCF) ................................................................................................................ 14
Table 2: Project Options Considered ........................................................................................................................... 18
Table 3: Summary of Project Option Analysis ............................................................................................................. 20
Table 4: Peak Day Demand for Alaska Consumers (MMcfd) ....................................................................................... 24
Table 5: Basis of Cost of Supply Assumptions.............................................................................................................. 35
Table 6: Private Project Options ..................................................................................................................................36
Table 7: State Participation Options ............................................................................................................................ 37
Table 8: Option Scoring Criteria Summary – Working Group Input and Final Results ................................................ 40
Table 9: Project Option Scores ‐ What Each Value Means .......................................................................................... 40
Table 10. Top Scoring Project Options in Phase I ........................................................................................................ 44
Table 11: Annualized Volatility of Potential LNG Price Indices .................................................................................... 48
Table 12: Average Historical Prices of Potential LNG Price Indices ............................................................................. 48
iii
LIST OF ABBREVIATIONS
ADNR State of Alaska Department of Natural Resources
EV Electric vehicle
HH Henry Hub
iv
KGFGS Kenai Gas Field Gas Storage
m3 Cubic meter
MW Megawatts
v
1 EXECUTIVE SUMMARY
1.1 Background and Scope
1. Southcentral Alaska, along with the Interior (the “Railbelt”), comprise the most densely
populated areas of the State. These regions have relied on natural gas produced in Cook Inlet to
various degrees to supply its heating and power generation needs since the 1950s. Gas
production in Cook Inlet field peaked in the mid‐2000s at around 200 BCF per year,1 and has
steadily declined to the current annual production of approximately 70 BCF per year.2 Formerly
active export facilities of Agrium Kenai Nitrogen Plant and Kenai LNG stopped operating in 20073
and 2015,4 respectively, due to the shortage and cost of gas produced in the region.
2. Over the last decade, Hilcorp Alaska, LLC (“Hilcorp”) has become the largest operator and gas
supplier in the state, maintaining and stabilizing Cook Inlet gas production after a period of
threatened shortages.5 Hilcorp has invested over $750 million in Cook Inlet drilling and capital
projects since 2012, and plans to continue the investment at around the same pace over the
next decade.6 In April 2022, Hilcorp first warned of uncertainty of future Cook Inlet natural gas
supplies, stating that “gas purchasers [were] not to rely on Hilcorp for gas beyond existing
contracts.”7
3. In May 2022, ENSTAR Natural Gas (“ENSTAR”), Chugach Electric Association, Inc. (“CEA”), Interior
Gas Utility (“IGU”), Matanuska Electric Association, Inc. (“MEA”), Homer Electric Association, Inc.
(“HEA”), and Golden Valley Electric Association, Inc. (“GVEA”), along with the State of Alaska
Department of Natural Resources (“ADNR”), and the Alaska Energy Authority (“AEA”)8 formed a
working group to assess future gas supply needs and energy security in Cook Inlet (“Working
Group”). The Working Group’s stated goal is to:
“[w]ork together for long‐term solutions. This requires better understanding of each
utility’s constraints and needs based on existing contracts and forecasting our
1State of Alaska Department of Natural Resources, Division of Oil & Gas, Cook Inlet Natural Gas Availability, March 2018, p. 19,
available at https://dog.dnr.alaska.gov/Documents/ResourceEvaluation/CI_Natural_Gas_Availability_Study_2018.pdf.
2 State of Alaska Department of Natural Resources, Division of Oil and Gas, 2022 Cook Inlet Gas Forecast, January 2023, pp. 10
alaska‐idUSWEN126820070925.
4EIA, Natural Gas Weekly Update, Alaska is a major natural gas producer, but little of the natural gas reaches market, May 27,
2021, https://www.eia.gov/naturalgas/weekly/archivenew_ngwu/2021/05_27/.
5 Bradner, Tim. Study says Inlet gas discoveries won’t stop shortage, Alaska Journal of Commerce, March 22, 2012.
6 Saugier, Luke, Presentation to Alaska State Legislature, House Energy Committee, p. 5, January 2023.
7DeMarban, Alex, Hilcorp Warms Alaska utilities about uncertain Cook Inlet natural gas supplies, Anchorage Daily News, May 17,
2022.
8ADNR and AEA participated in advisory capacity in order to provide information to the utilities, as well as remain aware of the
effort. These agencies did not fully participate in the deliberations or scoring of the options.
1
collective demand growth into the next decade as well as considering additional
options to meet the unique energy needs of our region.”9
4. In furtherance of these goals, the Working Group, through ENSTAR, engaged Berkeley Research
Group (“BRG”) to conduct a planning assessment to: (i) develop scalable options to fill the
natural gas supply gap anticipated to occur as Cook Inlet production declines, including Alaska‐
based options; (ii) develop and assess high‐level project scope, cost estimates, and time to
execute for each of the options; (iii) for options requiring LNG imports, analyze the available
sources for the required annual volumes of gas, potential contract structure and price ranges;
(iv) assess key risk and mitigations associated with each option; and (v) develop a ranking system,
ranked assessment of options, and recommendations, all of which comprises the advisory
engagement titled “Phase I Assessment.”
5. This report summarizes the outcomes and recommendations of the Phase I Assessment.
2
8. Appendix A.1. details BRG’s relevant engagements and experience in project analysis,
management, and design within the global oil and natural gas industry.
1.2.1 Project Leadership
9. The following key experts from BRG and Cornerstone Energy Services, a subcontractor engaged
by BRG, led the Phase I Assessment.
10. In addition, the team included BRG and Cornerstone staff with deep experience in LNG systems
engineering, siting, and processing, pipeline engineering and materials, worldwide gas and LNG
market analysis and contracting, energy macroeconomic, investment analysis, financial
modeling, and market research.
10 Demand projections are based on the utilities Working Group’s estimates, as described below in this report.
11 The cost, design, or potential location(s) of this storage expansion have not been taken into account in Phase I Assessment.
3
16. In order to meet the expected supply shortfall, one or more options need to be selected to
progress to an active engineering effort by the end of 2023. In order to meet the expected gas
shortfall in 2027‐2028, there is a limited set of options that can deliver, namely LNG imports in
various forms, and all of them are still at a stage where uncertainties and risks related to design
and feasibility need to be resolved before choosing a specific design configuration. Other
options, such as a gas pipeline from the North Slope, can meet long‐term demand most
economically, but are not expected to be online by 2027‐2028 or even reach a construction
decision in the timeframe where alternatives would need to be sanctioned.12 This drives the
potential need to make progress on multiple fronts. Several viable options to supplement Cook
Inlet gas supply need to be progressed further in the next phase of this project (“Phase II”) to
enable a sanction decision on at least one option by the end of 2023.
1.4 Recommendations
17. BRG recommend the following scope of work as part of “Phase II”, estimated to take 4‐6 months:
a. Utilities individually continue to work with Cook Inlet producers and the State to
promote and secure additional contracted supply and promote alternative
development.
b. The Working Group should continue to pursue top‐scoring options to further define
scope, schedule, and commercial viability; specifically: 1) Modification of existing
Kenai LNG facilities (via commercial discussions with owner); 2) Scope definition and
planning for FSRU option; 3) Greenfield site selection and feasibility assessment for
LNG imports if retrofit options become unavailable; 4) Market survey to further define
availability and cost of LNG; and 5) Optimization and feasibility assessment of the In‐
State Pipeline option with AGDC and State of Alaska in areas of permitting critical path
and financing structure.
c. Complete permitting due diligence of all top‐scoring options and identify key
bottlenecks and showstoppers.
d. For all top‐scoring options, develop draft venture model, project finance structure
and plan of engagement with capital markets.
e. Refine cost of supply estimates for the top‐scoring options, including greenfield LNG
import, if existing infrastructure in Nikiski becomes non‐feasible or excessively risky.
f. Select one permanent solution or multiple short and long‐term options to pursue by
the end of 2023 with target date for first delivery of gas in 2027‐2028. Phase II
12 The timeline of feasible start dates and cost of supply ranges for various options are presented in Appendix D, which was
assembled by CEA as a collaborative work product between BRG and BV based on each company’s separate analyses, and
illustrates a multitude of considered options with their feasible start dates.
4
refinement of scope and schedule will enable a more accurate estimate of feasible
start dates for the options under consideration.
5
2 FORECAST OF UNMET GAS DEMAND NEED
2.1 Historic and Current Demand for Natural Gas by the Working Group Utilities
19. After the end of fertilizer production and export, Alaska natural gas consumption in the Railbelt
area decreased to around 70 billion cubic feet per year (“BCF”) over the last decade, divided
between residential and commercial heating, power generation, and the rest for small industrial
users, such as Kenai Refinery owned by Marathon Petroleum Corporation (“Marathon”). The
chart below breaks down the various consumer uses of natural gas.
Figure 2: Alaska Natural Gas Delivered to Consumers
100
90
80
70
60
BCF
50
40
30
20
10
0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Natural Gas Deliveries to Electric Power Consumers (BCF)
Natural Gas Industrial Consumption (BCF)
Natural Gas Deliveries to Commercial Consumers (BCF)
Natural Gas Residential Consumption (BCF)
Natural Gas Vehicle Fuel Consumption (BCF) - Negligible Quantity
2.2 Incorporation of Renewable Energy Scenarios into Power Generation Utilities’ Forecasts
20. Renewable energy has been a part of Alaska’s power generation portfolio for decades, with
hydropower supplying more than 20 percent of the state’s electrical energy in an average year.
The integrated Railbelt system is powered by approximately 85% fossil fuels and 15%
renewables.13 The largest renewable energy project supplying the Working Group of utilities is
Bradley Lake, at 120 megawatts (“MW”) installed capacity. The project supplies about 10% of
13 Bettina Chastain (CEA Board President) and Arthur Miller (CEA CEO), Opinion: Anchorage’s electric utility is making progress on
its clean‐energy goals, Anchorage Daily News (April 13, 2023).
6
the Railbelt’s electricity demand.14 Several new projects, some of them very large, are in various
stages of development.15
21. Solar and wind generation has gained footing in the state as well, starting to supply a significant
part of electric generation produced in the entire state, as shown in the chart below.
22. All electric utilities in the working group have incorporated plans for integration of renewables
into their generation portfolio as part of their strategic and near‐term plans. For example, CEA
is currently evaluating two proposed utility‐scale projects (one wind, one solar), that could
provide up to 400,000 MWh, or 20% of their annual energy needs, provided that the ongoing
feasibility studies can show no negative impact on electricity rates.16 GVEA’s plan to incorporate
more natural gas generated electricity into its system would offset the decrease in natural gas
demand from using more renewable power generation in the Railbelt. Also, Alaska’s currently
14 Kirong, N., Alaska utilities plan $200M Railbelt transmission system upgrades, S&P Global, May 30, 2022.
15Corri A. Feige (ADNR Commissioner) and Lucinda Mahoney (Alaska Department of Revenue Commissioner), Investing in
Alaska Beyond ESG, January 2022, available at
https://dog.dnr.alaska.gov/Documents/ResourceEvaluation/Alaska_ESG_Jan_2022.pdf.
16 Bettina Chastain (CEA Board President) and Arthur Miller (CEA CEO), Opinion: Anchorage’s electric utility is making progress on
its clean‐energy goals, Anchorage Daily News (April 13, 2023).
7
relatively low (0.2%) penetration of electric vehicles (“EV”), heat pumps, and induction cooking
will likely grow over time and increase combined‐cycle natural gas power generation demand
overall. 17
23. Figure 4 below provides a breakout of the projected electric utility18 natural gas requirements.
These requirements (represented by dotted lines) are based on planning scenarios to provide a
range for strategic planning. As can be seen, there is a substantial range of projected gas
requirements for the electric utilities attributed to potential varying degrees of clean energy
uptake along with beneficial electrification such as EVs and heat pumps. For the purposes of
project requirements, the three demand lines between the Lower and Upper Bounds of Gas
Requirements were utilized since they best represent reasonable expectations and timelines.
Figure 4. Power Generation: Demand Planning Assumptions vs. Potential Bounds of Gas Requirements
17Alaska Energy Authority, State of Alaska Electric Vehicle Infrastructure Implementation Plan (approved by USDOT FHWA on
September 27, 2022), pp. 25‐26.
18 CEA, MEA, HEA, and GVEA.
8
2.3 2022 Cook Inlet Gas Supply Study by the Department of Natural Resources
24. In the 2022 Cook Inlet Gas Forecast,19 ADNR evaluates 90 oil and gas pools in the Cook Inlet Basin
within 38 different fields and developed probabilistic forecasts for proved developed and proved
undeveloped dry and associated natural gas reserves for each pool.20 The study assesses
reserves based on “present conditions and assumptions”21, and “does not estimate future
natural gas prices”.22 Undeveloped reserves are assumed to be developed at a drilling pace of
15 wells per year from 2023 until 2030, with no additional drilling assumed thereafter.23 ADNR’s
assumed annual gas demand is 70 BCF; it is a “steady demand profile” assumption24 and thus
does not make judgments regarding any potential changes in future natural gas demand.
25. ADNR truncates forecasts of the technically recoverable gas to account for the economic limit of
the various pools. The economic limit ensures that the production forecasts are limited to only
economically feasible production. This is typically determined as the difference between
revenues and variable costs borne by the producer.25 Since ADNR does not forecast future prices
in this study, it is implied that production for various pools will be truncated based on the
economic limits determined under the prevalent price conditions. ADNR estimates that under
the mean truncated (“ADNR’s 2022 Mean Truncated”) production scenario there are currently
803 BCF of dry natural gas and 17 BCF of associated natural gas remaining in Cook Inlet.26
19 State of Alaska Department of Natural Resources, Division of Oil and Gas, 2022 Cook Inlet Gas Forecast, January 2023, (“2022
Cook Inlet Gas Supply Study”).
20 2022 Cook Inlet Gas Supply Study, p. 4.
9
Figure 5: ADNR's 2022 Mean Truncated Annual Gas Supply Forecast
27IGU Board of Directors Special Board Meeting, January 17, 2023, IGU Board Memorandum 2023‐01, p. 8. IGU’s current gas
contract with Hilcorp provides sufficient gas through 2032, however in the event of the gas supply source switching to Harvest,
the Cook Inlet contract will end earlier, as shown in Figure 6.
10
a. Lower‐risk uncontracted demand compares consumer demand forecasts to firm
contract quantities committed to Alaskan utilities with access to the Cook Inlet gas
market; or
b. Higher‐risk uncontracted demand compares consumer demand forecasts with ADNR
truncated production, which assumes that utilities are able extend or execute new
agreements up to the proved reserves production profile provided by ADNR.
28. BRG used the second definition as the planning assumption in this assessment to determine
Unmet Gas Demand, since ADNR’s 2022 Mean Truncated forecast is based on reserves of high
degree of confidence (1P) that can be delivered at current prices. In other words, this assessment
assumes that additional Cook Inlet gas will be contracted and re‐contracted up to ADNR’s 2022
Mean Truncated production profile. ADNR’s 2022 Mean Truncated production profile28 along
with demand forecasts provided by utilities are depicted in Figure 6.
28
This is the Base Case for the gas supply forecast that is based on ADNR’s 2022 Mean Truncated Annual Gas Supply Forecast
which BRG digitized with the values rounded and truncated after 2040.
11
Figure 6. Utilities’ Contracted and Uncontracted Demand vs Cook Inlet Supply
29. The difference between these assumed supply and demand forecasts is the Unmet Gas Demand
assumed by BRG for the purposes of sizing a potential natural gas replacement project and
calculating the costs of supply per Mcf, as depicted in Figure 7. The assumed demand stays
relatively flat for each of the High, Medium, and Low scenarios after 2040 as a planning
assumption for the purpose of sizing a project that is capable of delivering up to each respective
demand assumption and for calculating 20‐year levelized costs of supply per Mcf.
12
Figure 7: ADNR’s 2022 Mean Truncated Natural Gas Supply and Utilities’ Demand Forecasts
80
70
60
Unmet Gas Demand
50 Low: 355 BCF
BCF/year
30
20
10
30. Subject to the risks described below in Section 2.5, and in order to evaluate the project options
on a comparable basis, the Working Group and BRG adopted the following range of Unmet Gas
Demand as part of this assessment, presented graphically in Figure 8 and in Table 1 below.
13
Figure 8: Unmet Gas Demand for Low, Medium, and High Demand Scenarios
60
50
40
BCF/year
30
20
10
0
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
Low Demand Medium Demand High Demand
14
Low Medium High
Demand Demand Demand
2037 40 46 50
2038 43 49 53
2039 44 50 54
2040 44 52 55
15
annual basis; however, adequate storage capacity and deliverability needs to be in place to
ensure the demand is met on the coldest days of the year. The Cook Inlet Natural Gas Storage
Alaska (“CINGSA”) facility has a current design capacity of 11 BCF. Additionally, Cook Inlet gas
storage capacity held by Hilcorp is depicted in Figure 9 below as part of all storage and producing
fields. Hilcorp‐owned storage fields are Swanson River Gas Storage (“SRGS”), Pretty Creek Gas
Storage (“PCGS”), and Kenai Gas Field Gas Storage (“KGFGS”).30
Figure 9: Hilcorp’s Cook Inlet Gas Storage and Production Capacity31
33. The timing of when Cook Inlet will first require additional sources of gas and the Unmet Gas
Demand profile have significant implications on the schedule and the cost of meeting this
30 All storage assets are depicted as white boxes with red borders and text on the map below.
31 Hilcorp Presentation to the House Energy Committee – Luke Saugier, Senior Vice President, Alaska, January 2023.
16
shortfall. Some of the long lead‐time options which are described in subsequent chapters have
longer development timeframes than what is necessary to meet the Unmet Gas Demand in 2027
and 2028. Furthermore, the Unmet Gas Demand increases from less than 10 BCF in the medium
demand case in 2028 to over 50 BCF in 2040. Large scale developments could be underutilized
in early years leading to higher overall cost of supplying the gas.
34. Continued close coordination within the Working Group and with the project management team
as project options are developed further is essential to ensure the most efficient timely
implementation of solutions to fill the Unmet Gas Demand during this generational energy
system transition.
17
3 NEW SUPPLY OPTIONS CONSIDERED
35. In this chapter, we review the scope of the project options considered by BRG to fill the Unmet
Gas Demand need starting at first occurrence and continuing to 2050 and beyond.
18
3.2 Summary of Option Analysis
38. BRG and Cornerstone analyzed each project option at a sufficiently detailed screening level to
enable the prioritization and scoring of the options. The summary of this analysis in the table
below highlights the main outcomes of the analysis:
39. Year Available. The year that each option is estimated to deliver first gas, assuming that a
decision is made in 2023 to progress the option to the next necessary development step. For
most project options, the next step is preliminary engineering design, and in some cases Front
End Engineering Design (“FEED”), which precedes a Final Investment Decision (“FID”).
40. Max Annual Supply and Demand Met Through [Year]. The Unmet Gas Demand assumed in
Phase I Assessment (using High Demand case from the Working Group) begins in 2027 and
increases to approximately 20 BCF annually by 2030, and to approximately 55 BCF by 2040.
Assuming ADNR’s case of mean truncated supply, all Cook Inlet Gas is offline by 2041,
necessitating the new supply project to provide up to approximately 70 BCF of gas annually.
Some of the options, such as the North Slope gas pipeline projects, have plentiful capacity to
meet this demand; LNG Import options are expandable beyond listed initial capacity. All other
project options have unique capacity limitations that make them unsuitable for long‐term supply
reliance, although it is our understanding that utilities with contracts expiring in the short term
are considering other short‐term options, as detailed in Appendices C and D.
41. Total CAPEX, $MM. Total estimated capital investment made by utilities and/or third parties
expressed in 2023 prices (“$2023”).
42. Direct Investment, $MM. Estimated portion of Total CAPEX shouldered by the utilities
individually or as part of a joint venture. This figure is subject to change and commercial
structure negotiations. The estimate reflects the industry standard or status‐quo assumption for
each type of project, in $2023.
43. Indicative Cost of Supply, $2023/Mcf. For all options, the estimated indicative cost of supply
carries an inherent uncertainty at this stage of evaluation, whether or not stated in the table
below or further in this report. This is due to the early stage of development of all the options.
For some options such as Cook Inlet Gas or North Slope Gas Supply, once in service, costs of
supply are likely to stay relatively flat. For projects involving LNG Import, prevailing market will
create ongoing volatility in the cost of supply during operations that could be smoothed out with
hedging. BRG used the Working Group’s high demand case to estimate the cost of supply
presented below. This indicative cost of supply compares to the current contract price of Cook
Inlet Gas of about $8 per Mcf. Current estimates of the cost of supply do not include potential
additional underground storage.
19
Table 3: Summary of Project Option Analysis
# Title Year Max Annual Demand Total Direct Gas Transport TOTAL
Available In‐State Met CAPEX, Investment, and
Supply, BCF Through $MM $MM Processing
1 Cook Inlet Gas 2027 23 2032 $1,500 ‐ NA $9.3 ‐ Included $9.3 ‐ $25.5
$2,000 $25.5
2 (a) In‐state Pipeline (Privately 2030 142 After $8,750 $10 $1.3 $26.8 $28.1
owned) 2050
2(b), In‐State Pipeline (Subsidized 2030 142 After $8,750 $10 $1.3 $7.8 $9.1
(c) or State‐Owned) 2050
4 Greenfield Port and Regas 2030 55 2040 $877 $877 $8.6 $4.0 $12.6
5 FSRU (Own/Lease) 2027‐2029 55 2040 $698 $607 / $201 $8.6 $3.6 $12.2
6 Barge / Small LNG Carrier 2027‐2029 25 NA $563 $158 $8.6 $13.3 $21.9
7 Alaska LNG 2030 182 After $43,000 $140 $1.3 $3.1 $4.4
2050
8 LNG Truck and/or Rail 2026 10 2028 $796 $346 $2.5 $25.0 $32.0
20
3.2.1 Scope Descriptions
44. In this section, we describe the high‐level scope of each of the project options considered in
Phase I. BRG and Cornerstone provided corresponding supporting cost and high‐level project
schedules (to be refined in Phase II) to ENSTAR in support of the summary assumptions.
3.2.1.1 Option 1 ‐ Cook Inlet Gas
45. The Cook Inlet Gas option is the estimated quantity of gas that may be available for future
contracting in Cook Inlet above and beyond ADNR’s 2022 Mean Truncated case.
46. Information on available reserves is generally confidential, and thus we relied on the previous
2018 ADNR Cook Inlet Natural Gas Availability study (“2018 ADNR Study”) to estimate the
quantifies of gas that may be available beyond the 2022 Cook Inlet Gas Forecast mean truncated
supply, and thus also likely above the level of current contract prices. Figure 10 below from the
2018 ADNR study32 shows total gas supply available at a 15% hurdle rate assumption, including
proved reserves. The amount of gas incremental to the rough equivalent of ADNR’s 2022 Mean
Truncated case is only the portion of the supply above the $8/Mcf price threshold in Figure 10,
i.e. around 220 Bcf at the 50th percentile measurement.
Figure 10: 2018 ADNR Cook Inlet Gas Availability Curve
21
47. Due to the vintage of the 2018 ADNR study and the intervening factors such as the stability of
remaining proved reserves and prices between the two ADNR assessments, as well as the recent
inflationary market signals, we perceive and acknowledge a significant amount of uncertainty in
both the quantity of additional gas available, and its potential price. However, after review of
the available public information and a consultation with ADNR’s technical staff, the estimate of
220 BCF available33 additional reserves beyond ADNR’s 2022 Mean Truncated forecast appears
to be a reasonable working assumption using public data.
48. The chart below represents the estimated potential of incremental regional gas supply beyond
the ADNR’s 2022 Mean Truncated case.
80 $9‐19/Mcf
70
60
50
BCF
40 $15‐26/Mcf
30
20
10
0
49. The gas supply estimate depicted in Figure 11 consists of reserves and resources with different
degrees of commercial and technical confidence. Approximately 466 BCF of already contracted
capacity is included as part of the Base profile that represents ADNR’s Mean Truncated case.35
Approximately 287 BCF of uncontracted capacity would also fall within the ADNR’s 2022 Mean
Truncated case.36
22
50. Approximately 188 BCF of 220 BCF incremental production might be developed by 2040.37
Depending on location, investments by ENSTAR and Harvest Midstream in new pipeline
connections may be necessary.
51. This additional supply could come online in Cook Inlet to fill in Unmet Gas Demand beyond
proved reserves, starting around 2027. These reserves could be comprised of a mix of onshore,
near‐shore developments, including installation of new platforms and longer economic life of
existing fields. Regional gas supply is provided in the form of contracted agreements where the
utility customers incur minimal direct investment. However, the new capital needed to invest in
the development of these new reserves is difficult to secure for Cook Inlet operators for various
reasons. Based on the interviews conducted by BRG and on public information presented by
certain operators during the 2023 Alaska State Legislative session, these reasons include the high
cost of securing an offshore or even a new land rig for only a few prospects, overall high
operating costs and low availability of service providers, difficulty securing capital for Alaska oil
and gas activities based on climate change concerns as well as past fiscal instability, and the
overall concentration of the Alaska market under a large owner and operator in Hilcorp. The
relatively small and closed gas market generally leads to the dilemma of operators being
unmotivated to take substantial risks without a gas contract, utilities unwilling to sign firm gas
contracts for unproven reserves, and both parties finding it difficult to land on mutually
agreeable prices for new developments with significant cost uncertainty. Recent federal offshore
lease sales attracted no new interested producers to Cook Inlet,38 accentuating the challenge of
securing new capital for the region.
52. Working Group utility customers continue to be best positioned to gauge the availability and
pricing of incremental Cook Inlet gas supply, as they have access to confidential producer
information that is not available to this Phase I Assessment. However, based on the review of
public information and in consultation with the Working Group, it is our opinion that it would be
risky and unadvisable under current market conditions to count on sufficient Cook Inlet or other
regional gas supply to fill the Unmet Gas Demand beyond 2026 without developing alternative
supplies.
3.2.1.2 Option 2 ‐ In‐State Pipeline
53. The In‐State Pipeline option is a variant of the Alaskan Gasline Development Corporation’s
(AGDC) proposed Alaska Standalone Pipeline (ASAP). The pipeline would run 733 miles to supply
natural gas from Prudhoe Bay to ENSTAR’s system in Anchorage. AGDC has previously sized this
pipeline with a 36‐inch diameter to meet a demand of 500 MMcfd to Anchorage and the
37 See Appendix B.2 for production profile and price assumption methodology.
38Anchorage Daily News, Hotly debated federal Cook Inlet oil and gas lease sale draws only 1 bid, Dec. 30, 2022,
https://www.adn.com/business‐economy/energy/2022/12/30/hotly‐debated‐federal‐cook‐inlet‐oil‐and‐gas‐lease‐sale‐draws‐
only‐1‐bid/.
23
surrounding utilities together with an industrial export customer. The design has a ~30 mile,
lateral to supply the Fairbanks region.39
54. For the purposes of Phase I Assessment, BRG and its sub‐contractor, Cornerstone Energy
Services, Inc., have assumed that the intent of this In‐State Pipeline is to meet only local utility
and refinery natural gas needs with no initial intent to provide exporting capabilities like that of
the Alaska LNG project. Operating under that assumption, BRG has determined that the current
36‐inch diameter ASAP pipeline is over‐designed and could be optimized to better fit the needs
of the state of Alaska. Assumptions made in a preliminary sizing of the ASAP line are outlined in
the following section.
Mainline Size
55. The Gas Supply model developed by ENSTAR, in conjunction with the Working Group and
Marathon, indicates projected peak‐day demand of around 404 MMcfd.
Table 4: Peak Day Demand for Alaska Consumers (MMcfd)40
39 Davis, Carolyn, Natural Gas Intel, Alaska Gasline Secures Final EIS for Pipeline Project, June 22, 2018,
https://www.naturalgasintel.com/alaska‐gasline‐secures‐final‐eis‐for‐pipeline‐project/.
40 Working Group input, November 2022.
24
56. Sized at 36 inches, the 733 miles ASAP pipeline can free‐flow 390 MMcfd from Prudhoe Bay to
Anchorage while experiencing a pressure drop of < 300 psig. A 36‐inch pipeline can handle nearly
100% of Alaska natural gas needs on a peak demand day from first day of operation, and requires
no compression or storage to do so. This design is the basis for the project cost estimate used in
this report for the In‐State Pipeline option. BRG adapted the estimate from the 2014 AGDC FEED
results by removing the gas processing plant on the North slope (which also included
compression), adding a pipeline from Pt Thomson to Prudhoe Bay, and adjusting for inflation up
to $2023.
57. A more economical solution would be to utilize a smaller diameter pipeline and add compression
along the mainline as the gas demand increases. Cornerstone has performed some preliminary
modeling using GasCalc 5.041 that indicates that a 24‐inch steel pipeline could accomplish this
goal. The 24‐inch pipeline provides enough capacity to free‐flow gas from Prudhoe Bay to
Anchorage at 105 MMcfd, thus supplying average annual Unmet Gas Demand until at least 2034.
Compression
58. Adding compression at key points in the line would provide capacity for the 24‐inch ASAP
pipeline to flow 390 MMcfd to Anchorage in addition to 60 MMcfd to Fairbanks.42 This volume,
according to the gas supply model, would eliminate the need for any Cook Inlet supply, and thus
would likely be subject to a phase‐in period of time as Cook Inlet declines.
Infrastructure Requirements
59. The infrastructure requirements and supply sources and strategy are as follows:
Approx. 800 miles 24‐inch steel pipeline from Pt Thomson to Anchorage Beluga Pipeline
interconnect
30 miles 12‐inch steel pipeline to Fairbanks
~38 mainline valve sites (for both mainline and Fairbanks lateral)
Up to 7 mainline compressor stations, as needed
Supply Sources and Strategy
60. Gas to the pipeline would be supplied via a gas purchase agreement with Pt. Thomson gas
owners, including potentially State of Alaska as a Royalty‐In‐Kind gas owner. Placing the pipeline
origin at Pt. Thomson, rather than Prudhoe Bay, allows deliver of utility‐quality gas with minimal
conditioning requirements, 43 thus avoiding a multi‐billion expenditure for this In‐State Pipeline
project.
25
Financing and Ownership
61. Even the smaller 24‐inch pipeline dedicated solely to filling the Unmet Gas Demand for the
Working Group is oversized and expensive compared to other feasible options, such as LNG
imports. Current natural gas demand in Alaska simply does not support a pipeline project of
about 800 mi in length, if compared strictly on cost to the LNG import option. However, the
Working Group recognizes that such a project may still have significant generational benefits
due to the ability of the In‐State Pipeline project to:
Supply natural gas to areas of the state currently relying on coal, biomass, or diesel for power
generation and heating, and thus experiencing the negative effects of pollution, intense
carbon emitting generation, high and volatile costs, or both;
Generate significant in‐state construction and operations jobs;
Create the ability to supply natural gas to new industrial customers along and nearby the
pipeline route, such as mine projects;
Generate gas royalty revenue to the State of Alaska;
Aid in extending the life of the North Slope oil and gas production base by creating a new
revenue stream in large‐scale gas sales; and
Provide a stable and reliable energy source for many years that will benefit economic
development of the region.
62. In recognition of these unique characteristics of an In‐State Pipeline option, ENSTAR requested
that BRG evaluate alternative ownership and financing structures of this pipeline option. BRG
developed three example ownership structures:
a. Option 2(a). Traditionally financed, privately owned pipeline.
b. Option 2(b). Public‐Private Partnership structure, with a private pipeline owner and
operator, and a percentage of the project construction costs shouldered by a
government sponsor. This is effectively a subsidized structure that can be arranged
so that upside economic gains go to the public partner. The level of public investment
can vary; BRG modeled an 80% “subsidy” investment.
c. Option 2(c). Fully state‐owned structure that substitutes a 2% annual return on
investment back to the state for State of Alaska and does not carry Ad Valorem tax
or a traditional return structure.
3.2.1.3 Option 3 ‐ Kenai LNG
63. Kenai LNG in the context of this study, refers to the concept of retrofitting the Kenai LNG export
facility located in Nikiski (owned by Marathon) to be utilized as an LNG import and regasification
facility for a broader group of customers than the Kenai refinery as currently proposed by
26
Marathon.44 The project would utilize as much of the existing infrastructure as possible,
including the pier and the storage tanks, at project initiation. LNG would be imported via an LNG
tanker,45 offloaded, stored in the existing storage tanks, and then vaporized and injected into
the Kenai Beluga Pipeline system (“KBPL”).
Infrastructure Requirements
64. When the Kenai LNG facility was in active operation, its storage capacity consisted of three tanks
with total capacity around 2 BCF. The tanks would be modified as required to fit the new facility
arrangement. Since the existing tanks are now more than 50 years old, we suggest that the long‐
term solution is to site a new storage tank on the facility to replace these aging vessels, with a
target date of 2032.
65. Pier upgrades are not expected to be required, however top‐side mechanical work on the liquid
and vapor lines would be required.
66. New vaporizers (capable of 150 MMcfd sendout capacity) would be installed in the Kenai facility
to meet daily send out demands. The design of the plant would allow vaporization scalability.
Initial vaporization sendout rates would be discussed and finalized with the Working Group
during sequential design phases such that capital deployment is phased responsibly.
67. A custody transfer meter station equipped with gas measurement, and any necessary upgrades
to the pipeline connecting the Kenai LNG terminal to KBPL.
68. We note that the infrastructure assumptions are not taking into account the maximum extent
of potential investments necessary to bring the facilities to current FERC standards for long‐term
use, should that be required. These assumptions need to be further examined and developed
with participation of the facility owner.
Supply Source and Contracting Strategy
69. Since the current facility owner has filed and gained FERC approval to import LNG for its own gas
usage, the contracting strategy for this project has become more complicated than in years past
when this project was considered. BRG sees four methods of executing this project:
a. Joint venture with Marathon for joint investment and LNG sourcing.
b. Contract with Marathon to provide dry gas supply to utilities.
c. Purchase the Kenai LNG facility from Marathon with agreement to supply the volumes
the Kenai refinery requires.
27
d. Limited use of the facility with floating storage, as suggested by an independent study
conducted by CEA and BV, thus only contracting with Marathon for the use of the
dock and sufficient land area for regasification.
3.2.1.4 Option 4 ‐Greenfield Port and Regas
70. A greenfield LNG import terminal is another possible solution to meet the gas needs for the
region. This import terminal would contain a pier capable of docking a 3.5‐4 BCF LNG tanker
which would offload LNG year‐round. LNG would be offloaded, stored, and then vaporized when
system demand calls for it. Since the Alaska LNG project has been able to site a pier and above
ground storage for export purposes, the proposed site for this greenfield import terminal is the
same site as that of the Alaska LNG project until further siting search and analysis is performed.
Infrastructure Requirements
71. The proposed pier would be of similar size of the one proposed by the Alaska LNG project,
designed to handle LNG cargo ships up to 180,000 m3 in capacity. The final vessel size will be
determined in later phases as scope is narrowed. The chosen vessel will be designed to provide
volumes on a year‐round basis to the port in the long term. Seasonal deliveries may be
appropriate in the near term when shortages between Cook Inlet production and utility
demands are not significant.
72. The terminal itself would require approximately 60 acres of land suitable to site a 3.5 BCF storage
tank (size to be finalized in further siting and design efforts) along with the necessary spill
containment and vaporization equipment.
73. Vaporization capacity for this facility will have capacity finalized in later phases of design efforts
but is proposed to scale up to 150 MMcfd at full build out, as currently estimated.
74. A custody transfer meter station equipped with gas measurement, as well as an interconnecting
pipeline will be required to deliver volumes from the LNG import terminal to KBPL.
Supply Source and Contracting Strategy
75. The freedom to design the new pier and a new storage tank provides flexibility and opens up
additional market possibilities based on acceptable LNG cargo vessel sizes. There are developing
projects in British Columbia and Mexico which could provide the contracted LNG volumes for
this project. Pricing structure on a $/Mcf basis assumes multi‐year contracts using a North
American gas index, pipeline toll, liquefaction toll, and marketing premiums.
3.2.1.5 Option 5 – FSRU
76. A Floating Storage and Regasification Unit (FSRU) is a viable LNG import solution to meet gas
needs for the region. This option would require the use of a new pier, or an existing dock
(“Agrium Pier,” currently owned by Nutrien, or other) with modifications to support the year‐
round docking of large LNG vessels, 140,000 m3 or larger in size. This solution provides a scalable,
but not totally permanent asset to be utilized to supply gas to the region.
Infrastructure Requirements
28
77. A single large FSRU vessel would be required (3.5 – 4 BCF) for the long‐term needs of the region.
The vessel would be designed and constructed to be moored permanently at a selected pier that
could handle the docking of such a vessel. Onboard the vessel, it is proposed there be enough
room to provide a scalable vaporizer arrangement, allowing the flexibility to add necessary
equipment to meet increased sendout demands in later years.
78. The pier that is selected for this option must be designed to handle a moored vessel year‐round,
as even the most efficient seasonal operation can only deliver up to about 37 BCF per year.46
Seasonal deliveries by an existing FSRU vessel in the market could meet demands in the near
term, but would not be a permanent solution as Cook Inlet production continues to decline.
Agrium Pier would require substantial work to upgrade the structure to not only handle larger
vessels, but reach deeper water at lower risk of freezing. As a result, later stages of analysis
should consider siting a new pier for this solution.
79. A high‐pressure gas pipeline is required to transport gas from the FSRU vessel, across the pier,
and to a custody transfer meter station equipped with gas measurement. Once measured for
volume and heat content, an interconnect to KBPL may be required to deliver the volumes to
CINGSA or other gas storage. The length of this interconnecting pipeline will be a factor in siting
a potential new pier for an FSRU solution.
Supply Source and Contracting Strategy
80. Pending selected or newly installed pier, existing market vessels could be contracted in the near‐
term and have the potential to be utilized to provide seasonal deliveries, and leave port during
the winter months. The new build of an FSRU vessel can be optimized for available supply source
and demand profile, and provide the capability to be docked 365‐days a year as the demand for
LNG volumes grows. British Columbia and Mexico are developing projects that could supply
contracted volumes, in addition to spot market volumes. Pricing for this LNG would be based on
the NA gas index, pipeline toll, liquefaction toll, and a marketing premium.
3.2.1.6 Option 6 ‐Barge/Small LNG Carrier
81. Small scale LNG has gained popularity in recent years with companies like Norgas out of
Norway47 supplying single or fleet solutions for LNG transportation and regas needs. A small‐
scale FSRU would be moored at the end of a pier, take deliveries from vessels smaller than typical
LNG carriers (“LNGC”), vaporize the gas on‐board, and inject it into a high‐pressure gas pipeline
where it is transported to a meter station for odorization, gas quality and volume measurement,
and then injected into the ENSTAR system. This LNG import option would have sendout
scalability as sendout demand grows, but due to smaller on‐vessel liquid storage, would also
involve increasing the frequency of LNG deliveries to the vessel as the LNG demand grows to
cover Cook Inlet shortfalls.
46With an LNGC of 145,000 cubic meters in size, delivering and off‐loading to a moored FSRU with re‐gas capacity of 300 MMcfd,
a seasonal operation from Vancouver may supply the Unmet Gas Demand through 2034.
47 https://norgascarriers.com/
29
Infrastructure Requirements
82. A single small scale FSRU vessel would be needed to be moored at the selected site to provide
the storage and regas. LNG deliveries would be taken onto the FSRU, stored, and vaporized as
needed. These deliveries would quickly scale up as the LNG demand is increased to counteract
the Cook Inlet decline in production.
83. A pier, Agrium Pier with modifications or otherwise, will be required to permanently moor the
small‐scale FSRU vessel. Because these vessels are not as large as a typical LNGC, there is more
flexibility in selecting, or constructing, a pier to meet this project’s needs.
84. A high‐pressure gas pipeline is required to transport gas from the FSRU vessel, across the pier,
and to a custody transfer meter station equipped with gas measurement. Once measured for
volume and heat content, an interconnect to KBPL may be required to deliver the volumes to
CINGSA or other gas storage. The length of this interconnecting pipeline will be a factor in siting
a potential new pier for an FSRU solution.
Supply Source and Contracting Strategy
85. British Columbia (Kitimat or Tilbury) are the likely source of this LNG supply and would be long‐
term contracts due to the limited number of suppliers. Spot market options are likely limited,
and would involve re‐selling LNG delivered to Asia, or shipping long distances such as from an
FSRU on the coast of Peru.
3.2.1.7 Option 7 ‐Alaska LNG
86. AGDC is advancing the 807 miles, 42‐inch pipeline project from the North Slope to Nikiski that is
designed to transport about 3.5 BCF/D of natural gas, and export LNG from a new terminal sized
at 20 Mtpa (together, the “Alaska LNG” project). This strategic project has reserved more than
sufficient capacity for local gas demand and has included local offtakes in its design basis,
however there is no lateral pipeline connecting the mainline to Fairbanks in its scope.48
Therefore, BRG has included a provision for this pipeline in the direct investment portion of the
estimate (see Table 3).
87. Alaska LNG has been approved by FERC under Section 3 of the Natural Gas Act as an integrated
gas processing, pipeline, and LNG export project. The Biden administration recently re‐affirmed
its LNG export permit to non‐Free Trade Agreement nations.49 While in possession of significant
government and local support, this large project nevertheless faces the challenge of marshalling
a ~$43 billion investment and debt package that will require long‐term firm LNG supply
agreements to secure. Currently in 2023, AGDC is working to secure an initial at‐risk FEED
30
investment of around $150 million for a FEED study.50 Despite being the lowest‐cost alternative
if sanctioned at full capacity, Alaska LNG Alaska LNG does not currently have a target FID date
and requires multiple years to construct after FID, requiring progress on other alternatives from
the Working Group.
3.2.1.8 Option 8 ‐ LNG Truck and/or Rail
88. As another source of LNG, Trucking and Rail transportation from the North Slope was analyzed.
Due the lack of established technology, rules, and regulations, in addition to the added layer of
logistical barriers, LNG transport by rail was disregarded early on in the evaluation process, and
this option became purely trucking from the North Slope. LNG would be produced in Deadhorse,
and then trucked by teams of drivers down to the Matanuska‐Susitna Valley area where it would
be unloaded, stored, and vaporized as demand required.
Infrastructure Requirements
89. Harvest Midstream, an LNG supplier on the North Slope, could expand its planned facility from
150,000 gal/day to 450,000 gal/day by adding two (2) additional trains of LNG production.51 This
production could meet ~13 BCF/yr of total system demand, meaning there would need to be
additional sources of gas to meet volume demands very quickly after 2029. As a result, trucking
is best looked at as a bridge or partial solution and not a long‐term solution to address the
declining Cook Inlet production. Understanding this, a virtual pipeline of LNG between the North
Slope would involve the following major investments:
Expanding Harvest Midstream’s LNG production facility from initial 150,000 gal/day to
450,000 gal/day.52
A fleet of LNG trucks/trailers to scale with trucking demand, ultimately requiring between 28
and 35 truck deliveries (depending on size of the trailer) on a daily basis to keep up with
450,000 gal/day production.53
A service garage near Fairbanks to act as both a depot to store and repair trucks, as well as a
location to switch truck drivers heading north and south.
this number of trucks on the Dalton and Parks highways appear quite challenging. The operational risks and potential for supply
interruptions also must be considered. BRG used 450,000 gal/day as the maximum potential due to these considerations, as well
as the cost and contracting information available for this specific option from IGU and Harvest Midstream.
31
An LNG Trucking Depot with a 1 BCF storage tank, vaporizers, and gas measurement. Storage
tank size and vaporization system sizing is to be finalized in later stages of design to
accommodate ENSTAR sendout needs and functional capacity of the operation.
Supply Source and Contracting Strategy
90. Due to the nature of this project requiring extensive investments both on the liquefaction side
to produce the LNG, and the LNG trucking depot in Anchorage to store and regas, there would
be long‐term ~20‐year volume commitments on the part of the utilities. Contracts for the
volumes would be based on the cost of gas, cost of liquefaction, cost of transportation, and the
capital costs associated with the necessary infrastructure investments.
3.2.1.9 Option 9 ‐ RNG
91. Renewable natural gas can be produced by upgrading biogas generated from landfills,
wastewater sludge, animal manure, municipal solid waste and other sources. Cost of producing
natural gas can vary significantly by source and project as depicted below in Figure 12.54
Figure 12: Estimated Project Costs and Greenhouse Gas Emissions
92. BRG identified Landfill and Wastewater biogas as the main potential sources of RNG that could
be delivered to the Alaska utilities. The largest landfill55 in Alaska is the Anchorage Regional
Landfill which already collects 4 MMcfd56 of non‐upgraded natural gas, about 2.3 MMcfd57 flows
from Anchorage Landfill Gas to Energy Project that supplies power to Joint Base Elmendorf‐
54 World Resources Institute, Renewable Natural Gas as a Climate Strategy: Guidance for State Policymakers, December 17, 2020,
https://www.wri.org/research/renewable‐natural‐gas‐climate‐strategy‐guidance‐state‐policymakers.
55 US EPA, Project and Landfill Data by State‐ Alaska (March 2023), https://www.epa.gov/lmop/project‐and‐landfill‐data‐state.
56 US EPA, Project and Landfill Data by State‐ Alaska (March 2023), https://www.epa.gov/lmop/project‐and‐landfill‐data‐state.
57 US EPA, Project and Landfill Data by State‐ Alaska (March 2023), https://www.epa.gov/lmop/project‐and‐landfill‐data‐state.
32
Richardson (“JBER”),58 and about 2 MMcfd is flared. If the flared gas could be re‐used, or if an
additional resource in a comparable amount is available at Anchorage Regional Landfill, 2 MMcfd
could support production and upgrade to 0.3 BCF/year of pipeline quality natural gas, assuming
50% of the gas is methane and the processing facility runs with 90% efficiency. Palmer Central
Landfill currently collects around 0.174 MMcfd59 of biogas and should also be considered as an
additional source but for much smaller quantities.
93. John M. Asplund Wastewater Treatment facility is Alaska’s largest wastewater treatment plant
with plant capacity of up to 58 million of gallons per day (“MMgal/d”). The process of extracting
methane from wastewater requires construction of an anaerobic digestor.60 Assuming
approximately 60 gallons of wastewater per cubic foot of natural gas,61 John M. Asplund
Wastewater Treatment facility could produce up to 0.35 BCF/year of methane. The majority of
the remaining treatment facilities in the region treat less than 2.5 MMgal/d of wastewater,
making the economics of producing RNG from such facilities unfavorable.
94. It is likely that up to around 1 BCF/year of renewable natural gas could be produced in Alaska
from various across Southcentral Alaska and the Railbelt. There is significant heterogeneity in
the cost of supply across different projects and sources of renewable natural gas. Further
detailed assessment is needed to quantify the cost of producing natural gas from specific source
in Alaska. The higher end of the cost ranges provided in Figure 12 for wastewater and landfill
derived RNG development are likely in Alaska due to the length of supply chain and generally
higher construction costs.
3.2.1.10 Hydrogen
95. Hydrogen can be produced from multiple sources including natural gas, renewable power
sources, nuclear power, coal, as well as biomass. Hydrogen produced from renewable power
sources is generally referred to as green hydrogen. BRG assessed potential for wind based green
hydrogen development in Cook Inlet. BRG did not estimate the cost of supplying hydrogen from
natural gas because natural gas can be used directly in the ENSTAR natural gas system.
Furthermore, production of natural gas‐based hydrogen would require sufficient and
inexpensive gas supply which is unlikely to be available in Cook Inlet unless a viable alternative
to Cook Inlet sourced gas is found.
96. Cost of power is the main cost input associated with green hydrogen production. On October
10, 2011 RCA approved a 25‐year PPA between Chugach Electric Association and CIRI to supply
power from Fire Island Wind facility located in Cook Inlet. Under the supply agreement Chugach
33
electric pays a fixed price of $97 per megawatt hour.62 In 2023 electric power rates for large
customers ranged between $90 to $137 per megawatt.63 However, future clean power rates for
generation of hydrogen are expected to fall, as the costs of technology for both new solar and
wind power generation have decreased globally by 88% and 68% respectively in the past
decade.64 In Alaska, this is evidenced by a more recent small (6 MW) solar power contract held
by MEA at $67/MWh,65 although the project is not anywhere near the size necessary for utility‐
scale hydrogen generation.
97. Other major cost items include capital expenditures to acquire an electrolyzer facility, cost of
acquiring or leasing land parcel of sufficient size to accommodate electrolyzer infrastructure,
access to and processing costs of fresh water required for hydrogen generation, operating and
maintenance costs as well as onsite and offsite costs that include hydrogen distribution and
storage costs, and potential upgrades to the ENSTAR system to accommodate hydrogen
development.
98. The Inflation Reduction Act of 2022 introduced tax credits for qualified clean hydrogen
facilities.66 Facilities that begin construction before January 1, 2033, produce less than 0.45
kilograms of CO2 equivalent lifecycle emissions, and meet prevailing wage and apprenticeship
requirements can qualify for a tax credit of up to $3/kg for a period of 10 years. The tax credit is
viewed as a significant subsidy by industry participants.67
99. To assess the viability of hydrogen development in Southcentral Alaska, BRG assumed that the
tax credit, if efficiently monetized, could be sufficient to cover both capital and operating costs
of an electrolyzer facility and all associated infrastructure costs, other than the cost of power.
Assuming power price in the range of $70‐80/MW, a high efficiency electrolyzer facility that
requires 53 kWh68 per kg of hydrogen, and a lower heating value of 51,585 btu per pound of
hydrogen the cost of delivered hydrogen would exceed $32/MMBtu.
34
100. It is important to keep in mind that additional clean power generation capacity is more efficiently
used first to replace thermal power generation, before expending additional resources to turn it
into a gas in a market that is already experiencing a power fuel shortage. However, there may
be synergistic systems of hydrogen production during times of low power demand, once
sufficient renewable generation capacity exists.
3.2.2 Cost of Supply Assumptions
101. Due to the screening level of this Phase I Assessment, the costs of each project option were
evaluated at a very preliminary level, frequently without the ability to examine physical
characteristics of existing infrastructure. Where possible, available, and of a higher quality than
would be reasonable to estimate for this assessment, third‐party estimates were used, such as
those developed by specific project sponsors. However, the estimates were evaluated for
reasonableness and completeness with similar projects, and brought to the same $2023 basis at
a high level.69 Table 5 below summarizes the sources of each major cost assumption for the
evaluated options.
Table 5: Basis of Cost of Supply Assumptions
35
102. In order to develop consistent cost of supply assumptions for all options, we assumed that the
costs of investing in each project would be amortized over consistent Unmet Gas Demand,
levelized using common midstream capital structure and discount rate assumptions for a 20‐
year period, and then converted back to $2023 values using inflation assumptions.
103. The capital structure assumptions used for all midstream and shipping infrastructure
investments were 60% debt, 40% equity, with 4.6% after‐tax cost of debt (BBB rating), and 12%
cost of equity. We applied inflation using historic 10‐year CPI for All Urban Consumers, PPI for
Oil and Gas Extraction, and PPI for Oil and Gas Field Machinery and Equipment Manufacturing
indices, as appropriate, to adjust historical estimates. For long‐term inflation, we assumed 2%
average.70
104. The resulting cost of supply estimate range, using High and Low Working Group demand forecast
as a variable of the range for midstream costs are presented in Table 6 (for private project
options) and Table 7 (for government participation options) below.
Table 6: Private Project Options
Cost of Supply
Timeline from
Capital Supply
Option decision Gas Midstream Total
Investment Volume
YE2023
years $ mm BCF/year $/Mcf $/Mcf $/Mcf
up to $1500
1 Cook Inlet Gas 3‐4 up to ~23 $9.3 ‐ $25.5 Included $9.3 ‐ $25.5
‐ $2000
In‐State
2 (a) Pipeline 6‐7 ~ $8,790 up to 105 $1.3 – $2.6 $26.8 – $34.2 $28.1 ‐ $37.0
(Private)
3 Kenai LNG 4‐5 $768 up to 55 $8.6 ‐ $8.9 $3.4 ‐ $4.7 $12.0 ‐ $13.6
Greenfield Port
4 6‐7 $876 up to 55 $8.6 ‐ $8.9 $4.0 ‐ $5.3 $12.6 ‐ $14.2
and Regas
FSRU ‐
5 4‐6 $698 up to 55 $8.6 ‐ $8.9 $3.6 ‐ $5.0 $12.2 ‐ $13.9
Own/Lease
Barge / Small
6 4‐5 $563 up to 25 $8.6 ‐ $8.9 $13 ‐ $14 $21.6 ‐ $23.0
LNG Carrier
7 Alaska LNG 7‐8 ~$43,000 up to 183 $1.3 – $2.6 $3.1 $4.4 ‐ $5.8
LNG Truck
8 3‐4 $321 ~9 $2.50 $22.5 ‐ $29.5 $25 ‐ $32
and/or Rail
70Long‐term inflation is used to estimate future annual capital and operating costs of each project, as well as for adjusting future
expected tariffs and prices to $2023. Since the valuation period of all projects is about 27 years, the use of standard long‐term
inflation factor is appropriate. All Capex and Cost of Supply estimates are expressed in $2023 for consistency, and actual project
metrics such as capital investment at the time of expenditure, or contract gas prices, will be impacted by actual inflation to the
extent it differs from this assumption.
36
Cost of Supply
Timeline from
Capital Supply
Option decision Gas Midstream Total
Investment Volume
YE2023
years $ mm BCF/year $/Mcf $/Mcf $/Mcf
Renewable
9 Unknown n/a ~1 ~$25 Included ~$25
Natural Gas
Hydrogen
10 12+ unknown n/a n/a n/a $>32
(green)
In‐State Pipeline
2 (b) 6‐7 ~ $8,790 up to 105 $1.3 – $2.6 $7.8 ‐ $9.9 $9.2 ‐ $12.6
(Subsidized 80%)
In‐State Pipeline
2 (c) 6‐7 ~ $8,790 up to 105 $1.3 – $2.6 $5.9 – $7.4 $7.3 ‐ $10.0
(State Owned)
Greenfield Port
4 (b) and Regas 6‐7 $876 up to 55 $8.6 ‐ $8.9 $2.3 ‐ $3.3 $10.9 ‐ $12.2
(Subsidized 80%)
Greenfield Port
4 (c) and Regas (State 6‐7 $876 up to 55 $8.6 ‐ $8.9 $2.2 ‐ $3.1 $10.8 ‐ $12.0
Owned)
7146 CFR 154.176(b)(1)(iii)(A), Longitudinal contiguous hull structure, up to date as of May 19, 2023; 46 CFR 154.172(c),
Contiguous steel hull structure, up to date as of May 19, 2023; 46 CFR 154.32(c), Equivalents, up to date as of May 19, 2023; US
Department of Energy, LNG Annual Report 2015, Office of Fossil Energy; US Department of Energy, LNG Annual Report 2014,
Office of Fossil Energy.
37
106. Among other requirements, this design temperature leads to the requirement for “low‐
temperature” carbon steel for vessels designed to temperature of ‐25 °C (‐ 13 °F). In order to
comply with 46 CFR 154.172 (b), vessels need to be constructed using “type E” steel. 72 Given
that the Coast Guard regulations do not apply in other commonly visited cold‐weather LNG
ports, most vessel owners do not select to employ this type of steel in the manufacturing of their
ships. There are only two bespoke 89,900 m3 carriers in the market that were built for
ConocoPhillips in 1992‐1993. 73 These vessels, Seapeak Polar and Seapeak Arctic, are now owned
by Seascape, with one of them offered for demolition sale earlier in 2023.74
107. A regular LNGC could be considered compliant with the regulation on an “equivalency
argument,” as per 46 CFR 154.32 “equivalent or greater protection for the purpose of safety.”75
For example, ConocoPhillips brought LNGC Excel to the Kenai LNG plant in the past for summer
cargo shipping between April and October.76
108. Based on these standards and history, we are making the assumption that a standard LNGC or
FSRU in good condition could be approved to operate in Alaska approximately during the
summer months, but a newbuild LNGC or FSRU would be required to operate year‐round, given
the advanced age and scarcity of the two existing tankers that were constructed specifically for
Alaska operations.
109. Even though chartering an LNGC or FSRU for seasonal use is a possible option, BRG has not
evaluated availability of specific vessels. Based on BRG’s research, there are currently 17 active
FSRUs which are under 150,000 m3.77 Charter rates for FSRUs and LNGCs have experienced
significant recent volatility.78 This option needs to be approached with the FSRU owners and
suppliers at the opportune time when the Working Group is ready to commit to this path.
38
4 OPTION SELECTION
110. In this chapter we review the process that BRG and Working Group undertook to select the most
viable options among the alternatives that should progress through the next phase of the
project.
79ADNR and AEA did not submit individual priority rankings, as they participated in an advisory and informational capacity and
thus did not participate in the ranking or scoring. See Roszkowska, E., Rank Ordering Criteria Weighting Methods – A Comparative
Overview, Optimum. Studia Ekonomiczne, Nr 5 (65), 2013, available at
https://pdfs.semanticscholar.org/f983/e8c4eb7d7c30694dd72c5849dd6fee8a5c79.pdf.
80Roszkowska, Ewa, Rank Ordering Criteria Weighting Methods – A Comparative Overview, Optimum Studia Ekonomiczne, Issue
65, No. 5, p. 7, 2013, section 4.2.
39
Table 8: Option Scoring Criteria Summary – Working Group Input and Final Results
Priority Scoring Criteria ENSTAR Chugach MEA GVEA HEA IGU BRG Recommendation Ratio Method
(10 = Highest Weight) Score
Multiplier
1 Schedule Risk
10 9 10 6 10 9 10 0.18
4 Flexibility
7 5 7 7 7 7 7 0.12
6 Permitting
6 3 4 1 6 3 5 0.09
7 Environmental Impact
4 6 2 3 6 2 4 0.07
114. For each Scoring Criteria, BRG in consultation with the Working Group developed a scale of one
(1) or zero (0) to 5, and a description of what each score represented in valuing the options, to
ensure consistent results. The summary of the scores is presented below in Table 9.
Table 9: Project Option Scores ‐ What Each Value Means
1 Schedule Risk 5 = Meets contract shortfall by 2026 and volume shortfall by 2029
4 = Meets contract shortfall by 2026 but provides no long-term solution
3 = Meets volume shortfall by 2029 with other options to supplement
2 = Meets volume shortfall by 2029 but precludes other options
1 = May not meet volume shortfall by 2029 and precludes other options
0 = Provides immaterial supply, or utility demand has no ability to affect the
sanction of this option
40
Priority Scoring Criteria Score
2 Reliability of supply 5 = Project uses proven technology, experienced providers, and is local to
during operations the service area
4 = Project uses proven technology but requires investment remote from
service area
3 = Project uses mostly proven technology and relies on new market
entrants
2 = Project uses novel technology deployed by experienced suppliers local
to the area
1 = Project relies on new technology, providers, and geographic challenges
4 Flexibility 5 = Storage and gas supply can be increased yearly with no cost or
efficiency penalties
4 = Storage and gas supply can be increased in multi-year phases
3 = Storage and gas supply can be ramped up according to a plan but
requires substantial upfront investment
2 = Project can be implemented in two (2) phases
1 = Firm daily supply commitment, infrequently adjusted.
41
Priority Scoring Criteria Score
9 Local economic 5 = > 80% jobs and revenues created are in Alaska
impact (jobs and 4 = >60 - 80% jobs and revenues created are in Alaska
revenues) 3 = >40 - 60% jobs and revenues created are in Alaska
2 = >20 - 40% jobs and revenues created are in Alaska
1 = < 20% jobs and revenues created are in Alaska
42
117. Based on the scoring results, the Working Group is further evaluating the following options in
addition to Cook Inlet Gas Supply81:
118. In‐State Pipeline. In order to achieve the benefits of this option, a decision to subsidize this
project needs to be made in an expeditious manner. Given the projected time required to
construct a long‐distance pipeline across Alaska, it is likely that alternative supply is still
necessary to bridge the time to when the pipeline gas becomes available. While an In‐State
Pipeline project has many benefits, including development of North slope gas with many years
of supply security, state royalties, and ability to provide gas to communities along the pipeline
route, In‐State Pipeline carries prohibitive costs if developed solely for the Working Group utility
demand. Reconfiguring the project so that state ownership or an investment decision can be
made on the merits of the project for Alaska demand and its economic benefits, rather than
depending on large export LNG buyer commitments, would be a change in the strategy of the
project and its current owner, Alaska Gasline Development Corporation (“AGDC”). We recognize
this as a policy decision outside the scope of this report.
119. Kenai LNG. Retrofitting the former Nikiski LNG export facility currently owned by Marathon
presents an opportunity to use a brownfield facility with existing pipeline connections to the
main ENSTAR system, existing dock, and potentially existing LNG storage tanks. This option
provides important advantages of shortening the time to project start‐up and potentially
lowering costs of LNG import. However, the old age of the facility and the size and condition of
the dock and tanks (currently in warm status) present their own risks and challenges related to
permitting and potential costs. In addition, Marathon’s stated goal to employ the site as a small
import facility for Kenai Refinery’s own gas needs presents a potential regulatory and
operational conflict. This option should not be discounted at this stage due to its timing
advantages, provided that good‐faith negotiations with the facility owner begin expeditiously.
120. FSRU. Importing LNG using an FSRU as storage and regas provides a significant project schedule
advantage. To the extent a suitable chartered FSRU vessel can be secured in the short term, this
option has the shortest lead time and lowest risk of securing necessary supply of all options
reviewed. The key risks to the schedule of this option are availability of cold climate appropriate
FSRUs of the right capacity (i.e. small enough to utilize existing docks), and the availability and
suitability of either the Agrium Pier (owned by Nutrien) or Marathon dock.
121. These top options, with scores by individual prioritized criteria, are presented in Table 10 below.
81 See recommendations on Cook Inlet Gas Supply option in Sections 1.3, 16, and 3.2.1.1.
43
Table 10. Top Scoring Project Options in Phase I
1 = Low Score, 5 = High Score
PrioriScoring Criteria 2(B). In-State 2 (c). In-State 3. Kenai LNG 5. FSRU
Pipeline (80/20 Pipeline (State-
Subsidized) (1)
Owned)
1 Schedule Risk 1 1 3 3
2 Reliability of supply during operations 5 5 4 4
3 Delivered cost per Mcf/MMBtu 5 5 4 4
4 Flexibility 3 3 2 3
5 Project Complexity and Integration 2 2 2 3
6 Permitting 4 4 2 1
7 Environmental Impact 3 3 4 2
Size of direct investment required by the
8 5 5 3 4
utilities (CAPEX)
9 Local economic impact (jobs and revenues) 4 4 2 1
44
5 MARKET, PRICE VOLATILITY, AND RISK ANALYSIS
122. In this chapter, we review the current LNG market conditions and outlook, including the global
and North American liquefaction capacities. We also analyze the volatility of energy commodity
markets to which new LNG supply to Alaska could be indexed.
45
5.1.2 LNG Market Demand and Supply Outlook
126. The Global LNG market is expected to remain tight in the next few years. Europe is continuing
to shift its reliance from Russian gas to LNG following the energy crisis in the second half of 2021
and Russia’s invasion of Ukraine. Global LNG demand could reach up to 444 million tonnes83 in
2026, an increase of 18% from 2021.84
127. The favorable market conditions of 2022 did not translate into FIDs on LNG liquefaction projects,
with just under 5 trillion cubic feet per year of new capacity globally (excluding North America)
that is under construction.
128. Based on BNEF LNG outlook, China, South Asia and Southeast Asia could see LNG imports climb,
especially as coal‐to‐gas switching initiatives continue in China, but growth may be restricted by
increased spot LNG prices. Northwest Europe and Italy are slated to see the largest jump in LNG
imports, as their LNG demand increases by 36 million tonnes by 2026 compared to 2021. Japan,
Korea, Taiwan (JKT) region is the only major market forecast to see a dip in LNG demand due to
higher nuclear, renewables and coal generation in Japan and a lower gas demand for power in
South Korea.85
129. New supply projects are expected to ramp up in the coming years, particularly in the US. Global
supply is forecasted to increase to 460 million tonnes in 2026,86 an almost 20% rise from 2021.87
130. With the tight supply expected until 2026, prices are expected to maintain at elevated levels
compared to their pre‐Covid levels.88
8321.3 trillion cubic feet, using a conversion factor of 1 million tonnes of LNG to 48.028 billion cubic feet of gas from BP Statistical
Review of World Energy, Approximate conversion factors, July 2021, p. 2.
84 Bloomberg, Global LNG market outlook 2022‐26, June 29, 2022, Global LNG balance‐ slide 3,
https://www.bloomberg.com/professional/blog/global‐lng‐outlook‐overview‐tight‐supply‐expected‐until‐2026/.
85Bloomberg, Global LNG market outlook 2022‐26, June 29, 2022, Global LNG balance‐ slides 3‐4,
https://www.bloomberg.com/professional/blog/global‐lng‐outlook‐overview‐tight‐supply‐expected‐until‐2026/.
8622.1 trillion cubic feet, using a conversion factor of 1 million tonnes of LNG to 48.028 billion cubic feet of gas from BP Statistical
Review of World Energy, Approximate conversion factors, July 2021, p. 2.
87Bloomberg, Global LNG market outlook 2022‐26, June 29, 2022, Outlook overview‐ slide 1,
https://www.bloomberg.com/professional/blog/global‐lng‐outlook‐overview‐tight‐supply‐expected‐until‐2026/. Note that
supply generally exceeds demand due to average utilization of less than 100% of installed capacity.
88Bloomberg, Global LNG market outlook 2022‐26, June 29, 2022, Outlook overview‐ slide 1,
https://www.bloomberg.com/professional/blog/global‐lng‐outlook‐overview‐tight‐supply‐expected‐until‐2026/.
46
commodity markets to which LNG supply to the Alaskan project could feasibly be indexed is
illustrated in Figure 15 below.89
Figure 15: Potential LNG Price Indices: Historical Trends90
132. Prices at North American hubs also increased – albeit to a lesser extent – partly due to surging
LNG export demand. Average monthly prices at Henry Hub, Waha, and AECO reached their
highest levels in over a decade last year. However, prices at North American hubs have since
moderated substantially, and there is little to suggest that the multi‐year highs of 2022 are likely
to recur with any frequency.
133. Nevertheless, LNG and gas price volatility remains elevated by historical standards. This is
demonstrated in Table 11, which presents annualized volatility, a measure of how LNG prices
fluctuate over a given period, in each of the markets in Figure 15 since 2013. Uncertainty in
market conditions or events that affect natural gas supply and demand tend to result in higher
price volatility.
89 Unlike AECO, Henry Hub (“HH”), and Brent crude oil prices, Platts’ JKM does not represent a traded market or hub. Rather, it
is a price assessment, which is compiled daily on the basis of voluntary reporting of transactions by market participants
90 Price data from Platts’ and S&P Global Capital IQ.
47
Table 11: Annualized Volatility of Potential LNG Price Indices91
134. JKM price volatility has spiked since late 2021 due to disruption to and then full cessation of
Russian supply to Europe, prompting intense global competition for spot LNG cargoes.
Competition has moderated in recent months, and JKM prices have stabilized, but volatility
remains high. In contrast to JKM, volatility at AECO and Waha is in large part a function of low
prices in recent years – resulting from constraints on takeaway capacity and local pipeline
bottlenecks – rather than demand spikes and reduced global gas availability. The average price
of each indexation option since 2013 is presented in Table 12. 92
Table 12: Average Historical Prices of Potential LNG Price Indices
Average Price Average Price
Average Price ($/MMBtu)
Index/Hub ($/MMBtu) ($/MMBtu)
2013-2016
2017-2020 2021-2023
Brent Crude Oil 14.55 10.90 14.76
JKM 12.29 7.38 26.14
Henry Hub 3.55 2.88 5.09
Waha Hub 3.43 1.77 5.45
AECO 3.05 1.42 3.51
91BRG analysis of Platts’ and S&P Global Capital IQ price data. Annualized volatility is calculated by taking the standard
deviation of the daily price changes over the course of each year and multiplying the result by the square root of the number of
trading days in each year.
92Note that Waha, HH, and AECO represent only a portion of LNG FOB contract price, as those indices are paired with additional
gas transportation and liquefaction fees before shipping, on the order of $4‐6 per MMBtu in addition to the index price. JKM Spot
Price generally includes full LNG price including shipping to the market hub, and Brent‐based LNG prices may or may not include
shipping, depending on contract.
48
annualized volatility (displayed on the x‐axis) between 2024–2034. The least volatile potential
price index considered is Brent crude oil, with an annualized volatility of 35% since 2013. The
results of this analysis are displayed in Figure 16.
Figure 16: Expected Volatility & Average Price (FOB) of Potential Supply Options (2024‐34)93
136. Assuming a slope of 14% (expressed as a percentage of crude oil prices in $/bbl), an LNG import
portfolio fully indexed to Brent crude – the least volatile potential index – is expected to cost
just under $9.80/MMBtu over the 2024‐2034 time period. This is approximately $1/MMBtu
higher than an equivalent portfolio indexed entirely to AECO hub (after accounting for estimated
liquefaction costs and marketing fees). Perhaps unsurprisingly, JKM is likely to present the
highest potential risks by both metrics, and does not feature in the optimal indexation mix.
93BRG analysis using price projections developed for the Cook Inlet Gas Supply Project options analysis. Historical annualized
volatility calculated based on price data from Platts’ and S&P Global Capital IQ. Projected prices include assumed liquefaction &
marketing costs.
49
138. As we reviewed above, Alaska’s best matches in the LNG market for suppliers are the projects
on West Coast of Mexico and Canada that are currently under construction or in pre‐FID stages.
Capacity associated with those projects has largely been sold through 2026, however there is
some still potentially available in 2026‐2028 FID projects. Additionally, spot cargos will likely be
available from these projects while in operation in the late 2020s. A global LNG supplier may
offer a contract for a number of cargos annually that are supplied from one of the North
American West Coast projects or other sources in the Pacific, provided both the vessel and LNG
specifications are appropriate for Alaska. Those spot cargos will most likely be priced using JKM
indexation. Once this project reaches a stage where an FID commitment is imminent, it would
be appropriate to seek a multi‐year contract for FOB or DES LNG supply from several of the
developing projects and worldwide LNG suppliers, using a structured expression of interest and
bidding process.
139. However, even at this early stage, and given the bespoke characteristics of the Alaska regulatory
and market environment, we advise conducting an informal outreach to suppliers as early as
Phase II of this project, even as non‐LNG import options are still under consideration.
Confidential discussions with willing suppliers would provide valuable information on the need
for this project to procure its own vessels or shipping arrangements, exact LNG chemical
composition available from each suppliers, potential indexation and price structures available,
and flexibility of seasonal and annual contract volumes. This information would greatly inform
technical and commercial planning of the project.
50
@Risk94 or Crystal Ball95. These inputs are then used in a cash flow model that combines these
inputs by sampling the input distributions to calculate a median economic output and a
confidence range indicating the likelihood that the economic parameter would be lower or
higher than a certain value. For example, a Monte Carlo could quantify a mean cost of alternative
gas supply of $15/mmbtu with a 95% chance that the ultimate cost of supply will not exceed
$20/mmbtu and a 5% chance that the ultimate cost of supply will be less than $12/mmbtu.
51
6 RECOMMENDATIONS AND NEXT STEPS
6.1 Recommended Actions to Confirm Feasibility of Top Scoring Options
142. BRG recommend the following scope of work as part of Phase II, estimated to take 4‐6 months:
a. Utilities individually continue to work with Cook Inlet producers and the State to
promote and secure additional contracted supply and promote alternative
development.
b. The utilities’ Working Group should pursue several top‐scoring options in order to
further define scope, schedule and commercial viability, specifically, 1) Modification
of existing Kenai LNG facility (via commercial discussions with owner); 2) Scope
definition and planning for FSRU option; 3) Greenfield Port and Regas site selection
and feasibility assessment for LNG imports if retrofit options become unavailable; 4)
Market survey to further define availability and cost of LNG; and 5) Optimization and
feasibility assessment of the In‐State Pipeline option with AGDC and State of Alaska
in areas of permitting critical path and financing structure.
c. Complete permitting due diligence of all top‐scoring options and identify key
bottlenecks and showstoppers.
d. For all top‐scoring options, develop draft venture model, project finance structure
and plan of engagement with capital markets.
e. Refine cost of supply estimates for the top‐scoring options, including Greenfield Port
and Regas, if existing infrastructure in Nikiski becomes non‐feasible or excessively
risky.
f. Select one permanent solution or multiple short‐term and long‐term options to
pursue by the end of 2023.
52
f. Develop an implementation roadmap.
g. Conduct an alternates analysis.
h. Provide a recommendation for contract/procurement strategy.
i. Assist the Working Group in establishing a project management office.
53