BOQ FOR THE CONSTRUCTION OF REB ROOM, BHDP
Sl. TOTAL
DESCRIPTION OF WORK QTY. UNIT UNIT RATE
No. AMOUNT
PRELIMINARIES
MOBILIZATION,
1 DEMOLITION,CLEANING SITE, 1.00 LS 30000.00 30000
SAFETY AND LAYOUT ETC.
TOTAL COST FOR PRELIMINARIES 30000
CIVIL CONSTRUCTION MATERIALS COST
2
TOTAL COST FOR CONSTRUCTION MATERIALS 347981.19
CONSTRUCTION LABOR WORKS
EARTH EXCAVATION 240.00 Cft 9.50 2280
BACK FILLING 202.31 Cft 8.00 1619
CC WORKS 13.20 Sft 15.00 198
3 SHUTTERING WORK 761.42 Sft 25.00 19035
REBAR FABRICATION 1493.18 Kg 12.00 17918
CONCRETING 367.66 Cft 40.00 14706
PLASTERING 1229.66 Sft 20.00 24593
TOTAL COST FOR CONSTRUCTION LABOR WORKS 80350
PLUMBING AND ELECTRICAL WORKS WITH MATERIAL COST
PLUMBING LINE WORK TO
DRAIN OUT WATER FROM 1 LS 12000 12000
4 ROOF
ELECTRICAL WORKS (TUBE 10000
1 LS 10000
LIGHT,SWITCH,SOCKET ETC)
TOTAL COST FOR PLUMBING WORKS 22000
FINISHING WORKS WITH MATERIAL COST
PAINTING WORKS WITH 43038
1229.66 Sft 35.00
MATERIAL COST
MOSAIC WORKS 187 Sft 300.00 56100
5
GLASS & THAI WORKS 30 Sft 500.00 15000
GRILL WORKS 30 Sft 350.00 10500
DOOR WORKS 28 Sft 480.00 13440
TOTAL COST FOR FINISHING WORKS 138078
TOTAL COST 618409.12
CONTRACTOR PROFIT 10% 61840.91
OFFICE OVERHEAD 5% 30920.46
GRAND TOTAL 711170.48
QUANTITY ANALYSIS F
SL Sub-
NO DESCRIPTION OF WORKS Description Unit Quantity
1 Footing RCC work Cft 66.00
2 CC Casting Cft 13.20
3 RCC Short Column upto G.L Cft 18.38
4 RCC for Grade Beam Cft 63.18
5 RCC for Beam Cft 36.74
6 RCC Column Cft 30.50
7 RCC for SLAB AND LINTEL Cft 152.86
9 Sand Filling work Cft 202.31
10 Rebar Kg 1493.18
BFS Sft 313.57
11 Bricks 5" Brick Wall Sft 404.81
10" Brick Wall Cft
12 Plaster Cft 47.96
13 Polythene Sft
TOTAL
RATE (AS PER MARKET RATE)
TOTAL
UANTITY ANALYSIS FOR CONSTRUCTION OF REB SUB STATION
MATERIALS
CEMENT BRICKS REBAR STONE SYLHET SANDMYMENSIN VITI SAND
CHIPS G SAND
14.40 54.00 13.50 13.50
2.26 11.22 5.68
4.01 15.03 3.76 3.76
13.79 51.70 12.92 12.92
8.01 30.06 7.51 7.51
6.66 24.96 6.24 6.24
33.35 125.07 31.27 31.27
202.31
1493.18
940.71
10.12 2024.06 44.53
0.00 0.00 0.00
11.51 47.96
104.11 2964.77 1493 312.03 75.20 173.37 202.31
510.00 12 90.00 220.00 105.00 40 15
53095.76 35577.225 134386.4693 68647.029 7896.313688 6934.608 3034.6875
ON
ALS
CHEMICAL SHUTTER Polythene
4.80 70.00
0.75
1.34 65.00
4.60 145.00
2.67 130.65
2.22 128.10
TOTAL
11.12 222.67 MATERIALS
COST
3.84
12.00
31.33 761.42 12.00
250 40 10
7832.418179 30456.6847 120 347981.19
0
Approximate quantities & Cost estimates FOR CONSTRUCTION OF
REB SUB STATION
A. Sub-Structure
1. Schedule for Earth excavation work
Item Description No. of footing Length Width Depth Volume Sub-Total
No. CFT
of work
1 Earh excavate-F1 4 3 4 5 60 240
Total Amount in CFT= 240
2. Schedule for CC Work
Item No. of Length Width Thickness Volume Sub-Total
No. Description of work column CFT
1 Fooing-F1 4 3 4 0.25 3 13.2
Total Amount in CFT= 13.2
3. Schedule for Brick Flat Soliing work
Item No. of Length Width Volume Sub-Total Sft
No. Description of work Footing
1 Fooing-F1 4 3 4 12 158.4
Total Amount in SFT= 158.4
4. Schedule for Footing work
Item Description No. of footing Length Width Depth Volume Sub-Total
No. of work CFT
1 Casting-F1 4 3 4 1.25 15.00 66.00
Total Amount in CFT= 66
5. Schedule for Short Column upto G.L
Item Description No. of Length (FT) Width (ft) Height Volume Sub-Total
No. CFT
of work Column
All units are in Feet
1 Casting-C1 4 1.167 1 3.75 4.375 18.375
Total Amount in CFT= 18.375
6. Schedule for Grade Beam
Item Description No. of Length Width 12'' Height Volume Sub-Total
No. 18'' CFT
of work GB
1 Casting 1 58 0.83 1.25 60.175 63.18375
Total Amount in CFT= 63.18375
7. Schedule for Sand Filling work
Item Description Nos. Excavate Volume casting Rest Volume Sub-Total
No. of work volume (cft) (cft) CFT
1 Sand Filling 1 240 84.375 155.625 202.3125
Total Amount in CFT= 202.3125
8. Schedule for Ground Floor Slab
Item Description Thick volume Sub-Total
No. Area CFT
of work
1 4'' Thick Casting 185 0.333 64.750 67.988
Total Amount in CFT= 67.988
9. Schedule for Polythene Laying
Item Description Area Sub-Total
No. of work SFT
1 Polythene 3 4 12
Total Amount in SFT= 12
B. Super-Structure
1. Schedule for Column
Item Description No. of Length Width Height Volume Sub-Total
No. Column CFT
of work
1 Casting -C1 4 1 0.83 8.75 7.26 30.50
Total Amount in CFT= 30.5025
2. Schedule for Floor Beam
Item Description No. of Length Width Depth Volume Sub-Total
No. Story minus 6'' slab
of work
1 FB 1 56 0.833 0.75 34.99 36.74
Total Amount in CFT= 36.7353
3. Schedule for Floor Slab
Item Description No. of Area Thick volume Sub-Total
No. of work Story
1 5'' Thick Casting 1 185 0.417 77.08 80.94
Total Amount in CFT= 80.94
5. Schedule for BFS
Item Description No. of wall Length Height Thick Area
No. SFT
of work
1 BFS 1 15.25 9.25 155.17
4. Schedule for Brick Work
Item Description No. of wall Length Height Thick Area
No. SFT
of work
1 5'' Brick wall 2 14.917 8.75 287.1458333
2 5'' Brick wall 2 9.333 8.75 179.6666667
3 Deduct Door 1 6.000 5 -30
4 Deduct Door 1 2.000 2 -4
5 Deduct Door 1 4 7 -28
Total Amount in SFT= 404.813
5. Schedule for Plastering
Item Description No. of Story/ Wall Height Area Surface Sub-Total
No. of work wall Length
1 1/2'' wall plaster 1 809.625 1 890.5875
2 1/2'' Ceiling plaster 1 185 1 203.5
3 1/2'' Column Plaster 4 1.250 10 50 1 55
4 1/2'' Beam Plaster 1 58.600 1.25 73.25 1 80.575
Total Amount in SFT= 1229.6625
6. Schedule for Lintel
Item No. of No. Door/ Width Depth Length Sub-Total
No. Description of work Story Window 6''
1 Casting 1 1 0.500 0.5 15 3.9375
Total Amount in CFT= 3.9375
Total Shutter in SFT=
Shutter
70
65
145
128.1
130.648
207.669
15
761.417
Fo
FOOTING SPACING (in) ROD DIA(mm)
FOOTING ID COVER(in)
L(ft) B(ft) long short L Direction
F1 4.00 3.00 2.00 6.00 6.00 12
Short Column Reinforcement (Longitudinal reinforcement)
Column
Column 16mm Total Total 16mm
Column ID rebar 20 mm bar
Quantity bar 20mm bar bar
length
C1 4.00 6.00 0.00 6.00 0.00 24.00
Short Column Reinforcement (Shear Reinforce
Column Dimension (in) The
perimete Hook One stirrup
Column ID Clear Cover
r of lentgh Length (ft)
W D stirrup
S-C 1 14.00 12.00 2.50 32.00 3.00 3.17
L 1-C 1 14.00 12.00 2.50 14.00 3.00 1.67
Column Reinforcement (Longitudinal reinforcement)
Column
Column 16mm Total Total 16mm
Column ID rebar 20 mm bar
Quantity bar 20mm bar bar
length
C1 4.00 11.50 0.00 6.00 0.00 24.00
Column Reinforcement (Shear Reinforceme
Column Dimension (in) The
perimete Hook One stirrup
Column ID Clear Cover
r of lentgh Length (ft)
stirrup
The
perimete Hook One stirrup
Column ID Clear Cover
r of lentgh Length (ft)
W D stirrup
S-C 1 12.00 10.00 1.50 32.00 3.00 3.17
L 1-C 1 12.00 10.00 1.50 14.00 3.00 1.67
Grade Beam Reinforcement (Longitudinal Reinforcem
NUMBER OF Beam 20mm 25mm Rod
Beam type 25mm Rod 16mm Rod
BEAM Length (ft) Rod length
2 17.17 0.00 0.00 6.00 0.00
GB 1
2 11.33 0.00 0.00 6.00 0.00
GB 1
Grade Beam Reinforcement (Shear Reinforcem
Beam Dimension
The
Clear
Beam ID perimeter Hook lentgh
W D Cover
of stirrup
GB1 10.00 15.00 1.50 56.00 3.00
Beam Reinforcement (Longitudinal Reinforcemen
NUMBER OF Beam 20mm 25mm Rod
Beam type 25mm Rod 16mm Rod
BEAM Length (ft) Rod length
2 17.17 0.00 0.00 6.00 0.00
FB 1
2 11.33 0.00 0.00 6.00 0.00
FB 1
Beam Reinforcement (Shear Reinforcemen
Beam Dimension
The
Clear
Beam ID perimeter Hook lentgh
W D Cover
of stirrup
FB1 10.00 15.00 1.50 56.00 3.00
Ground FLOOR Slab Reinforcement
Spacing
Dia of Reinforcement Bar length Number of
Reinforce type Direction
Bar(mm) Spacing(inch) (ft) bar
length (ft)
X Direction top bar Main Bar 10 8.00 11.00 16.83 18
Y Direction bar Binder 10 8.00 16.83 11.00 26
Ground FLOOR Top Slab Reinforcement
Spacing
Dia of Reinforcement Bar length Number of
Reinforce type Direction
Bar(mm) Spacing(inch) (ft) bar
length (ft)
X Direction top bar Main Bar 10 6.00 16.83 11.00 35
Y Direction top bar Main Bar 10 6.00 11.00 16.83 23
X Direction extra
EXTRA Bar 10 6.00 16.83 6.33 35
top bar
Y Direction extra
EXTRA Bar 10 6.00 11.00 9.33 23
top bar
Footing Reinforcement
ROD DIA(mm) ROD UNIT WEIGHT(kg) HOOK LENTGH(ft) ROD NUMBER ROD LENTGH(ft)
B L-
B Direction L Direction B Direction L Direction B Direction L Direction
Direction direction
12 0.271 0.271 0.50 0.50 9 7 3.83
ongitudinal reinforcement)
Total 20mm Total16mm Total 20mm Total 16mm
Total weight
length length Weight Weight
0.00 144.00 0.00 72.58 72.58
SUM 72.58
forcement (Shear Reinforcement)
Unit weight
Column Total COLUMN Total
Spacing (in) Total length of 10 mm
length(ft) Stirrups NUMBER Weight
bar(kg/ft)
5.00 5.00 13.00 41.17 0.19 4.00 32.33
5.00 5.00 13.00 21.67 0.19 4.00 17.02
SUM 49
gitudinal reinforcement)
Total 20mm Total16mm Total 20mm Total 16mm
Total weight
length length Weight Weight
0.00 276.00 0.00 139.10 139.10
SUM 139.10
cement (Shear Reinforcement)
Unit weight
Column Total COLUMN Total
Spacing(in) Total length of 10 mm
length(ft) Stirrups NUMBER Weight
bar(kg/ft)
Unit weight
Column Total COLUMN Total
Spacing(in) Total length of 10 mm
length(ft) Stirrups NUMBER Weight
bar(kg/ft)
5.00 11.50 28.60 90.57 0.19 4.00 71.13
5.00 11.50 28.60 47.67 0.19 4.00 37.44
SUM 109
nt (Longitudinal Reinforcement)
20mm Rod 16mm Rod 25mm bar 20mm bar 16mm bar
Total Weight
length length weight (kg) weight (kg) weight (kg)
0.00 103.02 0.00 0.00 49.45 103.84
0.00 67.98 0.00 0.00 32.63 68.52
SUM 172
orcement (Shear Reinforcement)
Unit weight
One stirrup Total
Spacing(in) Beam length Total Stirrups Total length of 10 mm
Length (ft) Weight
bar(kg/ft)
5.17 5.50 86.50 189.73 980.26 0.19 192.47
SUM 192
Longitudinal Reinforcement)
20mm Rod 16mm Rod 25mm bar 20mm bar 16mm bar
Total Weight
length length weight (kg) weight (kg) weight (kg)
0.00 103.02 0.00 0.00 49.45 103.84
0.00 67.98 0.00 0.00 32.63 68.52
SUM 172
ement (Shear Reinforcement)
Unit weight
One stirrup Total
Spacing(in) Beam length Total Stirrups Total length of 10 mm
Length (ft) Weight
bar(kg/ft)
5.17 5.50 70.08 153.90 795.16 0.19 156.13
SUM 156
ment
Total Length Bar weight Total Weight
of bar (ft) (kg) (kg)
294.53 0.19 58.14
288.70 0.19 56.99
Total 115.13
ement
Total Length Bar weight Total Weight
of bar (ft) (kg) (kg)
381.26 0.19 75.26
387.09 0.19 76.41
219.40 0.19 43.31
214.59 0.19 42.36
Total 237.34
TOTAL 1493.18
ROD LENTGH(ft) WEIGHT(kg)
B- L- B- Factor Footing
Total
direction direction direction (5%) quantity
4.83 9 9 0.93 4 78 KG
SUM 78 KG