KSP-FSA-GMQ-EnG-ARC-RFI-0051 - 00 - Grand Mosque - Details of Rope Access System at Minaret-WSP

The document is a Request for Information (RFI) regarding the Rope Access System at the Grand Mosque in King Salman Park, seeking details on bracket fixation and layout plans. The contractor requests prompt clarification to ensure coordination and avoid delays, while responses from the PMCM and designer outline necessary adjustments and preparations for implementation. The document includes signatures and dates from various stakeholders involved in the project.

Uploaded by

Thabarak Shaikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views6 pages

KSP-FSA-GMQ-EnG-ARC-RFI-0051 - 00 - Grand Mosque - Details of Rope Access System at Minaret-WSP

The document is a Request for Information (RFI) regarding the Rope Access System at the Grand Mosque in King Salman Park, seeking details on bracket fixation and layout plans. The contractor requests prompt clarification to ensure coordination and avoid delays, while responses from the PMCM and designer outline necessary adjustments and preparations for implementation. The document includes signatures and dates from various stakeholders involved in the project.

Uploaded by

Thabarak Shaikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

REQUEST FOR INFORMATION – RFI – CONSTRUCTION PHASE

RFI Doc No. KSP-FSA-GMQ-ENG-ARC-RFI-0051 Date: 22-Mar-2025


Project King Salman Park Contract No. 20241014002
Client King Salman Park Foundation (KSF)
PMO Saudi Arabian Parsons Ltd (SAP) Contractor Freyssinet S.A
PMCM[1] Faithful+Gould (FGS) Other PMCM PMCM3-WSP

REQUEST DETAILS
Grand Mosque – Request for Details of Rope Access
Request Title Discipline ENG/ARC
System at Minaret
‫ ܈‬Cost Impact ‫ ܈‬Time Impact
DWG/Specs. Ref. KSP-MYA-P1-GMQ-IC-CGRM-DWG-LIG-33-4005-00
‫ ܈‬Designer Input
Question:
We are requesting details of Rope Access System bracket fixation and Layout plan showing brackets.
Please provide.

Document References: [KSP-MYA-P1-GMQ-IC-CGRM-DWG-LIG-33-4005-00]

Your prompt clarification on this matter would be helpful to ensure coordination and avoid potential delays.

Contractor’s PM
Name 4DLV$O$UDE Signature Date 22-Mar-2025

Request for Information – RFI – Construction Phase


KSP-FGS-GEN-PMC-PMT-TEM-0014 | 02 | 13-06-2021 Page 1 of 2
REQUEST FOR INFORMATION – RFI – CONSTRUCTION PHASE
PMCM RESPONSE
Please refer to the attached response. Any time or cost impact resulting from this must be
formally raised before implementation on site.

Name Ahmed Darwish Signature Date 14/05/25

DESIGNER RESPONSE
Add attachment(s) if necessary.

Prepare plan per attached information. Rails omitted and removable davit arm to be
provided complete with plinths / bases for mounting. One davit arm to be moved between
the three levels.

Name Jamie Smiley Signature Date 29 Apr 25

COST CONSULTANT *
Add attachment(s) if necessary

Name Signature Date

PMO RESPONSE
Add attachment(s) if necessary

Name Signature Date

CLIENT RESPONSE
Add attachment(s) if necessary

☐ Approved
KSPF* Name: Signature Date
☐ Rejected

Received by Contractor
Name Signature Date

* For cost and time impact.

Request for Information – RFI – Construction Phase


KSP-FGS-GEN-PMC-PMT-TEM-0014 | 02 | 13-06-2021 Page 2 of 2
roof hatch at highest
level

hatch in wall
for access to lower
roof

hatch in wall
for access to lower
roof
provide shop drawings
of all davit arm bases
for approval
Project

Key Plan

REQUEST FOR BRACKET


LAYOUT PLAN & details

WALL BRACKET FOR


550 LIGHT FIXTURE

details for lighting provided on Drawing Orientation

KSP-FSA-GMQ-ENG-ARC-RFI-0049
Keyplan Legend:
137 ROPE ACCESS SYSTEM Plot Boundary
Transition Boundary
Parking Boundary
Royal Terminal

79
HSA-M12x120/25/45

General Notes
107 47 1. ALL LEVELS SHOWN ON THIS DRAWING ARE INDICATED IN METRES
2. ALL DIMSIONS SHOWN ARE IN MILLIMETERS
3. THIS DRAWING SHALL BE READ IN CONJUNCTION WITH ALL RELATED ARCHITECTURAL,

REF J1 STRUCTURAL, CIVIL AND SERVICES DRAWINGS


4. ALL CONTRACT DRAWINGS ARE TO BE READ IN CONJUNCTION WITH THE
ACCOMPANYING SPECIFCATIONS

SURFACE MOUNTED LINEAR GRAZE LIGHT


5. ALL DIMENSIONS, LEVELS AND QUANTITIES SHOWN ON THIS DRAWING ARE INDICATIVE
ONLY. BEFORE STARTING ANY SITE WORKS,
ALL FINISHED FLOOR LEVELS AND DIMENSIONS HAVE TO BE VERIFIED BY THE
CONTRACTOR. ANY DISCREPANCIES MUST BE REPORTED TO THE SUPERVISING
LANDSCAPE ARCHITECT BEFORE EXECUTION
6. DISCREPANCIES BETWEEN DRAWN AND EXISTING SITE CONDITIONS TO BE ADJUSTED
AND RESOLVED BY SUPERVISING LANDSCAPE ARCHITECT
7. TREE LOCATIONS SHOWN ARE INDICATIVE ONLY. ALL LOCATIONS TO BE VERIFIED BY
SUPERVISING LANDSCAPE ARCHITECT:

refer notes on above


pages, top rail omitted and
provide bases for
demountable davit arm

00 Issued For Construction IC BE 30/08/2024


DRAW
REV DESCRIPTION CODE DATE
BY

REVISIONS

Client

plinths per BMS design drawings


attached above to mount davit arm

Project Title

REMOTE LED DRIVER TO BE LOCATED KSP GRAND MOSQUE, HUB 3


WITHIN THE MINARET INTERIOR. MUST BE AND ARABIC GARDENS
ACCESSIBLE FOR MAINTENANCE. TO BE Drawing Title
EITHER IP RATED OR INSTALLED WITHIN Grand Mosque
AN IP RATED HOUSING.
TX DETAILS

Mosque Details 01
N.T.S. At A0

Drawing Purpose ISSUED FOR CONSTRUCTION

MINARET LIGHTING DETAIL Drawn By Checked By


BK
Approved By
PN
1 SCALE 1:4
BE

Project Org. Phase Project Stage Facility Doc. Func. Catg. Serial Rev.
Code Pack Code / Bldg. Type no.

KSP MYA P1 GMQ IC CGRM DWG LIG 33 4005 00


Project

LEGEND:

TUCKER POLE
FFL 677.500 m
CGRM 12º FLOOR LEVEL MEWP Key Plan

DEMOUNTABLE DAVIT ARM


WITH ABSEILER

FFL 655.500 m
CGRM 8º Floor FFL (Platform) N
Drawing Orientation

FFL 644.500 m
CGRM 6º FLOOR LEVEL

General Notes

FFL 634.000 m
CGRM 4º FLOOR (ROOF PLAN)

FFL 628.000 m
CGRM 3º Floor FFL

FFL 622.500 m
CGRM 2º Floor FFL

FFL 617.000 m
CGRM 1º FLOOR

FFL 611.500 m
GGRM Ground Floor FFL

01 WEST ELEVATION
0102 SCALE 1:200

FFL 677.500 m
CGRM 12º FLOOR LEVEL

00 Issued For Construction JR 30/08/2024


DRAW
REV DESCRIPTION CODE DATE
BY
FFL 655.500 m REVISIONS
CGRM 8º Floor FFL (Platform)

Client

FFL 644.500 m 54/52/021x21M-ASH

CGRM 6º FLOOR LEVEL

FFL 634.000 m
CGRM 4º FLOOR (ROOF PLAN)

Project Title

FFL 628.000 m
CGRM 3º Floor FFL
KSP GRAND MOSQUE, HUB 3
AND ARABIC GARDENS
Drawing Title
FFL 622.500 m
CGRM 2º Floor FFL GRAND MOSQUE
BMU
WEST AND EAST ELAVATION
FFL 617.000 m
CGRM 1º FLOOR

1:200 At A0

0 2 4 6 8 10[m]
FFL 611.500 m Scale: 1:200
GGRM Ground Floor FFL
Drawing Purpose ISSUED FOR CONSTRUCTION

02 EAST ELEVATION Drawn By


JR
Checked By
AG
Approved By
SC
0102 SCALE 1:200
Project Org. Phase Project Stage Facility Doc. Func. Catg. Serial Rev.
Code Pack Code / Bldg. Type no.

KSP MYA P1 GMQ IC CGRM DWG BMU 03 0102 00


Project
18 17 16 15 14 13 12 11 10 09 08 07 06 05 04 03 01
FFL 676.500 m
CGRM 12º FLOOR LEVEL 54/52/021x21M-ASH HSA-M12x120/25/45

02
-

Key Plan

FFL 654.500 m
CGRM 8º Floor FFL (Platform)
Drawing Orientation

FFL 643.500 m General Notes


CGRM 6º FLOOR LEVEL

FFL 634.000 m
CGRM 4º FLOOR (ROOF PLAN) 3 3
26-4015 26-4015

04.136+ OT 52.136+ LFF

00.136+ LSS

GNICARB DEDLEW
TESSUG

,TEEHS LEETS SSELNIATS DEWERCS


TROPPUS TLUAV CRG

411
ERAUQS LEETS YRADNOCES
TEKCARB )mm5X021X021(

,TEEHS LEETS SSELNIATS DEWERCS


TROPPUS LLAW CRG

FFL 628.000 m

3971
CGRM 3º Floor FFL 957
002

0001
926

00.726+ COT
00.726+ COT

01

3841

0001
041

023 009 023

FFL 622.500 m
CGRM 2º Floor FFL

4
26-4015

FFL 617.000 m
00.816+ WOT

CGRM 1º FLOOR 00.716+ LFF

58.516+ LSS

51.516+ LCF

5704
FFL 611.500 m
GGRM Ground Floor FFL

01 SECTION
0103 SCALE 1:150
30

28 00 Issued For Construction JR 30/08/2024


DRAW
REV DESCRIPTION CODE DATE
BY
26 REVISIONS

24 Client
ACCESS HATCH AT
DEMOUNTABLE DAVIT ARM
OPEN POSITION
22

20

18
RETRACTABLE STILE

16

14

140 kg
300 kg
400 kg
12

10
1

8
Project Title
6
KSP GRAND MOSQUE, HUB 3
Inside outside 5 AND ARABIC GARDENS
OUTSIDE INSIDE
4 Drawing Title
ABSEILER

2
GRAND MOSQUE
BMU SECTION
0

-2
At A0
-2 0 2 4 6 8 10 12 14 16 18
0 2 4 6 8 10[m]

Scale: As Shown

Drawing Purpose ISSUED FOR CONSTRUCTION


03 MEWP Drawn By Checked By Approved By

- SCALE N.T.S. JR AG SC

02 BLOW UP Project Org. Phase Project Stage Facility Doc. Func. Catg. Serial Rev.
Code Pack Code / Bldg. Type no.
- SCALE N.T.S.
KSP MYA P1 GMQ IC CGRM DWG BMU 04 3500 00