STRL Gts (Turnkey) Bhilai - r1 - Seq3
STRL Gts (Turnkey) Bhilai - r1 - Seq3
CONTENTS
AMENDMENT SHEET
1.1 The general specifications for structural works furnished herein are intended
as guidelines for execution of the works satisfying the Owner’s requirements
as also complying with all technical norms in totality. This specification is to
cover the design, preparation of design drawings and fabrication drawings,
supply of all labour as well as materials and construction of all structural
work on a turnkey basis for the Project / Works as described in the general
conditions of contract.
1.2 Description of various items of work under this specification and nature of
work in detail are given hereinafter. The complete work under this scope
is referred to as STRUCTURAL WORKS. The detailed scope of works
covered under Structural works is given in Section -2.
1.4 Supply of all materials including structural steel, roof cladding & side-
cladding sheets, fasteners, paints, consumables like gas, electrodes etc.
and all other materials as deemed necessary for proper completion of the
work, are included in the scope of the Contractor.
For all buildings and structures, necessary layout and details are to be
developed by the Contractor keeping in view the statutory & functional
requirements of the plant and facilities and providing enough space and
access for operation, use and maintenance. Certain minimum
requirements are indicated in this specification for guidance purpose
only. However, the Contractor’s offer shall cover the complete
requirements as per the best prevailing practices and to the complete
satisfaction of the Owner.
1.6 Contractor shall inspect the site, examine and obtain all information
required and satisfy himself regarding matters and things such as access
to site, communications, transport, right of way, the type and number of
equipment and facilities required for the work, availability of local labour,
materials and their rates, local working conditions, weather, tidal / flood
levels, subsoil conditions, natural drainage, etc. Ignorance of the site
conditions shall not be accepted by the Owner as basis for any claim for
compensation or extension of time. The submission of a bid by the
Contractor will be construed as evidence that such an examination was
made and any later claims / disputes in regard to price quoted shall not
be entertained or considered by the Owner on account of ignorance of
prevailing site conditions.
1.7. Contractor shall comply with all the applicable statutory rules pertaining
to Factory act, Fire safety rule of Loss prevention association, Water act
for Pollution control, Explosives act etc. Provisions of Safety, health and
welfare according to Factories act shall also be complied with. Statutory
clearances and norms of State Pollution Control Board shall be followed.
Statutory body /Act requirements shall be fulfilled by the Contractor and
in case any modifications /additions to the building /Structures are to be
made as per the above, shall be carried out by the Contractor at no extra
cost to the Owner.
2.0. The scope of work shall cover , but shall not be exclusively limited to,
the following :
- supply of all materials viz, raw steel, sheeting for roof and side
cladding, and paints
- supply of all loading data for RCC foundation, layout drawing, HD bolt
insert details and all other necessary information for requirement of
Foundation/ RCC work , where future expansion is envisaged , the
successful contractor shall furnish load data separately for present and
future construction.
- any other work deemed incidental for the completion of the overall
work but not included in the above detailed scope.
3.0 General
This specification shall apply to steel work in building and general structural steel
work. For technological structures, additional stipulations shall be considered
as per technical requirements.
3.1.0 General
3.1.01 Structures shall be designed such that they are economical and safe and meet
the functional and service requirement of the technological process for which
they are designed. The architectural planning of the building shall be based on
technological requirements.
3.1.02 The structures shall be designed conforming to the relevant safety regulations,
Factory Acts, Electricity Rules and stipulations of Statutory bodies as
applicable to the project.
3.1.03 Natural ventilation shall be provided ensuring that it does not permit rain water
entry into the building. Scope of natural lighting shall be used to the maximum
possible extent.
3.1.04 Mild steel gutters and down-pipes with gutter outlets having grating cover shall
be provided to carry rain water from roofs of buildings to the drainage system
at ground level. All gutters shall be designed as walkable with 600 mm sole
width.
3.1.05 Adequate facilities in the form of monorails, hoists, platforms etc. shall be
provided to facilitate repair and maintenance of overhead cranes, equipment,
etc. Access to these platforms shall be provided by stairs / ladders from the
nearest accessible floor or platform.
3.1.06 Access to all floors, gangways and landings shall be by staircases. Access to
platforms and landing of secondary importance or where such access is used
only rarely, shall be by vertical ladders with safety hoops.
3.1.07 Roofs with access shall be provided with safety handrails along the periphery
of the roof.
3.1.08 Edges of floors, gangways, stairs and landings shall be provided with safety
hand railings.
a) Gangways and landings shall have chequered plate with a minimum thickness
of 6mm o/p suitably stiffened to meet design load requirements.
b) Floors and operating platforms other than the above shall have chequered
plate flooring or hot dip galvanised open gratings , or RCC slab resting on
steel structural framework , to suit the technological requirements.
3.1.11 Protective metal heat shields shall be provided for steel structures exposed to
continuous heat radiation of temperature exceeding 150 °C and also where
hot metal splashing on structures is likely to occur.
3.1.12 All buildings and their foundations shall be designed so that it shall be possible
to extend them in the longitudinal direction at a later date without further
strengthening of gable structures. Provision for transverse extension ,if any ,
shall also be made at the initial stage.
3.1.13 Sheeting on sides and gables shall generally terminate 3.0 m above ground
floor level unless required to be otherwise. Sides below this level shall be
generally screened by brick walls allowing sufficient air inlet to achieve natural
ventilation, unless otherwise required from technological / ventilation
requirements.
3.1.15 For Analysis/ design of steel structural frame work STAAD PRO soft ware shall be
used . CD of input files shall be submitted to purchaser / consultant along with the
hard copy of the document.
3.2.01 Columns
b) Shear force at the column base shall be resisted either by shear keys
shop-welded to the underside of column base plates or by welding base plate
to inserts provided in foundation.
c) The level of underside of column base shall be so chosen such that the
complete anchor table lies below the finished floor level, thus keeping the
shop floor free from projections of anchor tables.
b) Top flange plate shall be welded to web plate with full penetration butt weld
with fully automatic submerged arc welding. Bottom flange plate shall be
welded to web plate by continuous fillet welds with automatic/semi-automatic
welding.
c) All intermediate stiffeners shall be fitted against top flange and welded to it by
fillet welds/partial penetration butt welds. These stiffeners shall terminate
short of bottom flange with at least 25 mm gap. The stiffeners shall be fillet
welded to web plate and corners shall be cut suitably to clear thermally
affected area of web to top flange connection.
d) End bearing stiffener plates of crane girder shall be capable of transmitting the
maximum reactions to the columns. The bearing surface of the bearing plate
shall be planed/machined to ensure full contact.
f) Generally for girders having span 12m and above, vertical auxiliary girder and
horizontal girder at crane girder bottom flange level shall be provided.
g) All crane girders shall be checked for fatigue as per IS: 1024 ( latest).
h)
i) At crane girder level, walkway shall be provided on both sides. Walkway at
column location s shall have minimum clear width of 500mm. Approach by
staircase to this level shall be near the maintenance bay.
j) All crane girders and their supporting structures shall be designed for loading
from loaded crane in worst position of crab and crane to create most
unfavorable loading condition of the girders. For increase of load due to impact
and crane load combination including lateral surge shall be taken as per
provision of IS 875 ( Part – 2) -1987.
k) Suitable approach to be provided for tightening of bolts of Crane Rail .
Approach for Crane Rail fixing shall be properly planned for all types of
sections of Crane Girders.
b) Connections between surge girder and the main columns shall be designed to
resist load due to lateral braking of crane trolley.
c) On the periphery of the building, full length handrails shall be provided along
the edge of the maintenance walkway at crane girder level.
d) Handrail and its clearance from crane end carriage shall conform to provisions
of relevant safety regulations.
a) Crane stops shall be provided at the ends of each crane girder system , or as
required to limit the movement of crane as per technological requirements.
h) The joints shall be free from kinks, twists etc, and shall be grinded properly after
welding to ensure smooth running of the crane.
i) Method of securing the crane rail to the crane gantry, alignment and expansion
joints , if any, shall be subject to Purchaser’ s approval. The crane rail clips shall
be preferably forged or pressed from steel plates.
a) The main supporting element for roof shall be roof trusses provided at uniform
spacing to suit shop layout. Roof shall be provided with adequately sized roof
monitor for natural ventilation, wherever required.
c) System of bracings shall be provided in the roof top chord and bottom chord
levels along with longitudinal ties to ensure stability and rigidity of the roof
structures. Vertical bracings between trusses shall also ve provided wherever
required.
d) Galvanised wind tie (45x6 mm flat) shall be provided at the free edge of roof
sheeting.
e) Suitable arrangement of anchors shall be provided at the ridge of roof sheeting
for holding lanyards of safety belts.
a) Full length roof lighting walkways, generally 600 mm wide, shall be provided in
each bay as required to match the number of rows of roof lights provided in
the shop as per technological requirement.
b) These walkways shall span between roof truss members and will be decked
with chequered plate floor. Walkways shall be provided with handrails on both
sides.
b) All valley and eaves gutters shall be of pressed plate construction with a
minimum sole width of 600 mm so as to function as walkways.
d) The gutters shall be laid to slope towards down-pipes with welded outlets and
having grills fitted flush with gutter sole. Slope of gutters and collector pipes shall
not be flatter than the following limits :
e) Poking holes with cover shall be provided in the down-pipes at suitable intervals
as well as at accessible levels, to clean the down-pipes.
h) When rain water falls from higher to lower roof, double layer of sheets shall be
provided for the portion of roof sheeting on which rain water falls, provided the
drop of roof is in the range of 3 m to 6 m. In case the drop is more than 6 m,
independent gutter shall be provided.
a) Wall runners with necessary sag rod arrangements shall be provided to support
wall and gable sheeting, including internal partition wall, wherever required.
b) Hanging wall posts shall generally terminate at 3.5 m above ground floor level
unless required to be otherwise ( Refer Clause 3.1.13 ).
c) Gables of buildings shall have wall post spaced at intervals to suit bay width.
b) Beams along-with framework, shall be provided with both horizontal and vertical
bracing (wherever permissible) to achieve overall rigidity.
a) Vertical bracings shall be provided on all column rows for each expansion
block.
b) Vertical bracings shall extend from ground level to roof level and shall be
designed to transmit longitudinal forces i.e wind forces, crane tractive forces,
seismic forces etc. to the foundation.
c) Below crane girder level, for two-legged columns, the bracings shall be of
twin system in the plane of each column leg, suitably tied or laced together.
b) All walkways and stairs leading to working platforms shall have minimum 1000
mm width of walkways/flight of stair.
c) All other walkways and stairs leading to areas for maintenance purpose, or due
to restriction of space, shall have a minimum width of 800 mm of
walkway/flight of stair, unless required otherwise.
d) Staircases shall be generally designed with slope of approximate 37.5° with the
horizontal. (in no case the slope shall exceed 40 ° with the horizontal).
Intermediate landings shall be provided wherever required such that vertical
rise of each flight does not exceed 3000 mm. Risers in one flight shall be
equally spaced.
e) Walkway floors and stair treads shall be designed with chequered plate ( or
non-slip type plates). Ribbed floor/treads may be provided wherever the
possibility of accumulation of dust exists, taking care that such provisions do
not crate a nuisance to the operating personnel on the shop floor.
i) Wherever the height of cat ladder exceeds 4.0 m, safety cage shall be provided.
Intermediate landing shall be provided to cat ladders such that vertical height
of single rise does not exceed 8.0 m.
iii) Minimum clearance from rung of ladder to back of cage (in case of caged
ladders) = 700 mm
iv) Minimum clearance from the centre of cage all round = 350 mm
v) Slope of cat-ladders :
I. For normal cat-ladders, slope shall be within the range of 75°-90° with the
horizontal.
II. For ship-type ladders (i.e cat-ladders with short side handrails) the slope shall
be within the range of 65°-75° with the horizontal.
k) All walkways, platforms and stairs shall be provided with safety handrails. All
handrails shall be constructed with steel tubes / angles for posts, top and middle
rail and plates/sheets for toe plates. In case of stairs, the toe guards need not
be provided.
m) Hand-railing along edge of roof and gutters shall have a minimum height of 600
mm over top edge of gutters/sheets. In such hand-railings toe guards need not
be provided. (only top handrail and mid-rail shall be provided).
3.3 Design
to 1.5.
For wind load calculation the following data may be considered
- Basic wind speed ( Vb) at 10 M ht = 39 m/ sec.
- Risk co- efficient ( K1) = 1.0
- Terrain ht and Structure size factor(K2) shall be calculated with Category 2.
- Topography co- efficient ( K3) = 1.0
Seismic load- Structure shall be designed as per IS- 1893-(Part1) 2002.
ii) Superimposed loads for roofs and floors plus any temporary machinery not
allowed within the general superimposed loads.
iv) Temperature loads from process requirements because of the position of the
structure relative to the heat source or from support of mains, pipes etc.
subject to heat.
vii) Dynamic loads from screens and other such reciprocating machinery.
x) Seismic loads
f) In absence of any suitable provision for design loads, any other recognised
code of practice may be followed subject to prior approval of the Owner.
Besides technological loads, all platforms, walkways, stairs etc. shall be designed
for the following live loads :
Vertical Deflection
Horizontal Deflection
Where H = Height of Column from bottom of base plate to crane rail level.
3.3.08 Camber
b) The diameter of structural bolts shall not be less than 16 mm except for those
securing roof and wall sheets, windows, doors and stitching of thin coverings.
For bolted joints, at least two bolts per joint shall be provided.
i) by welding
ii) by permanent bolts (for secondary members such as purlins, wall runners
etc.)
3.4.01 The general parameters for conveyor galleries shall conform to the provision
of IPSS:2-03-001-81 (Interplant Standards : Steel Industry - Design
parameters for galleries and tunnels for belt conveyors in steel plant), and
provisions of IS : 11592-1985 unless specified otherwise in Technical
Specifications. The structures shall be designed so as to meet functional
requirements and shall provide space for operation, maintenance and removal
of machinery and give the workers good and safe environment.
3.4.03 Steps shall be provided (rise not exceeding 130 mm) along the walkways if the
gallery slope exceeds 12°. In case the slope of gallery is between 6° to 12°,
suitable ribs shall be provided on floor (without any sharp edges) at 250 to
300 mm intervals.
3.4.04 Provisions shall be made for emergency exit from galleries to ground level and
also for cross-over above conveyor at 100 m intervals (maximum). The width
of cross over shall not be less than 600 mm.
3.4.05 Roof and side walls of conveyor galleries shall be covered with GCS/ Aluminium
sheets. with a provision of gap of 300 mm below roof and 150 mm from top of
floor level on the side wall for ventilation.
3.4.06 Adequate provision for natural light inside conveyor gallery shall be made
through side walls by providing translucent sheets (FRP sheets as per IS:
12866-1989). Every sixth sheet on side wall shall be FRP sheet and shall be
staggered on opposite wall.
3.4.08 The level of underside of the base plate of gallery supporting trestles shall be
300 mm above the average ground level of the surrounding area.
3.4.09 Protective hand railing shall be provided along gallery walkways, open
platform, stairways, landings, edges of walkways when the gallery is not
enclosed, and around erection openings, if any, to ensure safety of operating
personnel.
3.4.10 Conveyor galleries longer than 150 m shall be provided with expansion joints
with twin trestles/supports. Each expansion block shall have fixed
support/rigid trestle with adequate arrangement (provision of top chord and
bottom chord bracing to gallery girder etc.) for transferring the transverse and
longitudinal forces to the foundation.
3.4.11 Gallery girders near junction house shall be preferably supported on trestle
located as close to the junction house as possible, with part of gallery girder
between junction house and trestle cantilevered from the trestle. Supporting
gallery girders on junction house shall be generally avoided.
3.4.12 The underside of the belt conveyor shall be fully covered with 3 mm sheet in
case of conveyor is located within the boundaries of the plant. Wherever such
covering is not provided (as in case of the mines area or cross country), the
covering must be provided where the gallery crosses roads, railway lines or
areas of public gatherings.
When underside of gallery is at less than 12m height from track level, heat
shield shall be provided below gallery as well as on sides for a width of track
8 m ( i.e. 4 m on either side of center line of the track ).
3.4.14 When conveyor gallery crosses above or below H.T cables, a minimum clear
distance of 1.0 m between the structural elements/cladding and HT cables
shall be maintained.
3.4.15 When the conveyor bridge passes over plant roads, clearance between the
road surface and the lowest points of the bridges shall not be less than 4.5 m
or the height needed for the passage of the largest individual components of
the plant equipment, whichever is the larger.
3.4.16 The junction house shall be designed to suit the technological requirements.
Number of floors, height of building etc. shall be decided accordingly.
3.4.17 In general the junction house shall be designed as framed structures on shorter
span side and vertically braced on longer side to achieve stability.
3.4.18 Floor of junction houses shall be of RCC slab supported on steel beams, unless
required otherwise from technological consideration. The RCC slab will be
connected to steel beams through suitable lugs.
3.4.19 Roof and side covering of junction houses shall be with GCS/Aluminium sheets
/ troughed colour coated sheets as specified. Roof slope shall be 1 : 5 ( 1
Vertical : 5 Horizontal).
3.4.20 Suitable access staircase and safety hand railing shall be provided to all floors
of junction houses.
3.4.21 When hydro-washing of floor of junction house is envisaged , the floor beam
supporting RCC slab shall be laid to a suitable slope to achieve the same,
wherever the same is not practicable to achieve through screed concrete.
(Minimum slope of floor shall be 1.5%).
3.4.22 Wall sheeting shall generally start from the lowest working floor and extend up
to roof level with louvres at each floor level to ensure adequate natural
ventilation.
3.4.23 Monorails for maintenance hoists shall be provided for maintenance and repair
of various equipments located on the floors.
Components of structures
a) Gallery truss shall be of latticed type construction and shall support roof (for
covered galleries) as well as floor deck supporting conveyor system.
b) The trusses shall be adequately braced at top and bottom chord level to transfer
the horizontal wind forces to end portals.
These beams shall be suitably spaced to support the conveyor stringer post and
shall deliver load to gallery trusses. Walkways on either side of the conveyor shall
also be supported on these stringer beams.
Intermediate trestles shall be two legged and shall deliver loads from gallery
trusses to the foundations. In addition, four legged trestles shall be provided which
will act as fixed support to transmit all longitudinal forces between expansion block,
in addition to other forces.
a) Floors - Floor beam layout shall be arranged to suit equipment layout as well as
equipment anchoring system.
b) Columns - In addition to loads from floor and roof, columns shall be designed to
transmit horizontal load due to belt tension/snapping of belts to the foundation.
a) Wall runners with necessary sag rods shall be provided to support wall sheeting
in conveyor galleries and junction houses.
3.4.30 Access stairs, walkways, platforms, ladders, hand railing etc. - These shall be
provided in accordance with clause 3.2.11 of this specification.
b) In absence of specified dynamic factor to be considered for the load from the belt
conveyor, a dynamic factor of not less than 1.3 shall be considered for the design
of floor beams and gallery girders.
c) Gallery trusses and stringers as well as floor beams of junction house shall be
checked for obviating occurrence of resonance and shall be designed in
accordance with clause 3.3.01(c).
d) For wind load consideration the following may be considered :
- Basic wind speed (vb) at 10 M ht = 39 m/ s.
- Risk co-efficient ( K1) = 1.0
- Terrain ht and structure size factor ( K2) shall be calculated with category 2.
- Topography co- efficient (K3 ) = 1.0
e) Seismic load – structure shall be designed as per IS 1893 ( Part 1) 2002. site is
located in zone II.
3.5.1 Description of loads and loading codes
3.5.01 Unless specified otherwise hereinafter, all the live loads shall be considered in
accordance with IS:875 (Part-2)-1987.
3.5.04 Live loads from conveyor on the gallery floor shall be as per conveyor suppliers
load data.
3.5.05 While designing the fixed support/rigid trestles in an expansion block of conveyor
gallery the following loads (in addition to wind load) shall be considered.
a) Forces due to difference in frictional resistance of top and return idle rollers of
conveyor.
c) Break down load caused by snapping of belt (in case of multiple conveyors,
snapping of one belt at a time) shall be considered.
3.5.06 Gallery girders and floor shall be designed for the following live loads, inclusive
of spillage loads on floors.
3.5.07 Dust load on roof of junction house and conveyor galleries shall be considered
as follows :
a) For building and structures located at a distance of 300 m from the dust
producing units - 0.5 KN/m²
b) At a distance of 300 m to 800 m from the dust producing unit - 0.25 KN/m²
a) Ventilation duct.
3.5.09 Junction house floors shall be designed for the following loads :
The various loads specified shall be combined in accordance with clause 8.0 of
IS:875 (Part-5)-1987 to give the most severe loading condition for design of
structures.
3.6.01 Bridges shall be provided to support pipelines of smaller diameters for which
maximum permissible span is less than the distance between supporting
trestles.
3.6.02 Trestles which are designed to transmit longitudinal loads (along the length of
pipeline) to the foundation, shall be four legged construction. Other trestles
which transmit only the vertical load to the foundation shall be two-legged
construction.
3.6.03 Access stair and platforms shall be provided for maintenance of equipment
installed in the pipeline (eg. valves etc.). Maintenance walkways with hand-
railing shall also be provided along the pipeline, wherever required. Provision
of access stairs, walkways platforms, hand-railing etc. shall conform to clause
3.2.11 of this specification.
3.7.01 Unless otherwise specified hereinafter, all live loads shall be considered in
accordance with IS:875 (Part-2) 1987.
3.7.04 In addition, pipeline, bridge and supporting trestle shall be designed for the
following loads :
The various loads specified shall be combined in accordance with clause 8.0 of
IS:875 (Part-5)-1987 to give the most severe loading condition for design of
structures.
3.8.0 General
This specification shall apply to design of self supporting steel chimneys.
e) Chimneys shall be fitted with helical strakes of three rail system, and shall be
strong enough to withstand the additional wind load from the strakes.
3.8.2 Design
b) Elements like platforms, hand-rails, ladders, anchor bolts etc. shall be designed
in accordance with IS:800-1984.
c) For wind and seismic refer clause 3.3.01 (d) and (e) .
3.8.3 Limiting Deflection
The maximum deflection at the top due to the action of wind, without considering
the dynamic factor shall not be greater than h/200, where h is the unsupported
height of the chimney.
3.9.0 General
a) Uniform layout module shall be adopted to the extent possible consistent with
economy. It is suggested to adopt a basic module of 3 m for building width
and 6 m for column spacing along building length.
4.1 Drawings
4.1.2 The fabrication drawings shall show full length layout with all connecting
members and connections marked thereon. The fabrication drawings
shall include all the necessary blown-up details required for the correct
fabrication of the structures to meet the design requirements. These
drawings shall be made in conformity with the best modern practices and
with due regard to speed and economy in fabrication and erection. Each
erection piece shall be clearly identified by an erection mark in these
drawings.
4.1.5 For bolted connections subjected to dynamic loading, lock nuts or spring
washers shall be used in addition to plain washers.
4.1.6 Erection drawings shall consist of line diagrams showing every detailed
member in position with the respective erection mark. Erection marks
shall appear on the left end of the members as detailed. All steel
members shall be erected with marks in the same relative position as
shown in plan or elevation. All loose members shall either be given part
marks or wired on to the main erection mark for despatch.
4.2.1 All steel and other materials used for steelwork and in association with
steelwork shall conform to appropriate Indian standards. Only tested
materials shall be used unless written authority is obtained for the use of
untested materials for certain secondary structural members.
4.2.3 Steel tubes for structural purpose shall conform to IS : 1161 (of Grade Yst 240)
4.2.4 Corrugated Galvanised Sheets shall conform to IS:277 with appropriate Zinc
coating for the selected thickness of sheet on roof and sides.
4.2.7 Colour coated sheets shall be as per appropriate standard. All roof
,monitor roof galvanised / zinc aluminium colour coated sheets of total
coated thickness (TCT) of 0.65 mm with base metal yield strength of
240 MPa or alternately sheets having TCT of 0.5mm with base metal
yield strength of 550 MPa.
All side sheets , monitor sides colour coated sheets of total thickness
(TCT) of 0.6 mm with base metal yield strength of 240 MPa or alternately
sheets having TCT of 0.5mm with base metal yield strength of 550 MPa.
Ridging/ Flushing : colour coated sheets TCT of 0.8 mm with base
metal yield strength of 240 MPa or alternately sheets having TCT of 0.5
mm with base metal yield strength of 550 MPa. For all above, minimum
zinc deposition shall be 150 gms per sq.m.
4.2.8 Gutters shall be of copper bearing steel conforming to Grade "A" as per
IS :2062
4.2.10 All black bolts, nuts and locknuts shall conform to IS : 1363 and IS :
1364 (for precision and semi precision hexagonal bolts) of property
class 6.4 unless otherwise specified. Washers shall conform to IS : 6610
4.2.11 All tapered washer shall be as per IS:5372 for channels, and IS:5374 for
Joists. Spring washers shall conform to IS:3063.
4.2.12 All HSFG bolts shall conform to IS : 3757. Assembly of joints using
HSFG bolts shall conform to IS : 4000. Nuts and washers for HSFG bolts
shall be as per IS:6623 & IS:6649 respectively.
4.2.13 Covered electrodes for arc welding shall conform to IS: 814. Coding of
electrodes shall be as follows :
a) ER421 ‘C’ X for mild steel of Grade 'A’ and Grade 'B’ as per IS :
2062
b) EB 542 ‘C' H3X for Mild steel of Grade 'B’ as per IS 2062 for
dynamically loaded structures (arising out of crane, vibratory
screen, equipments etc.) ‘C' is the value of the current as
recommended by the electrode manufacturer.
4.2.14 Certified mill test reports of materials used in the work shall be made
available for inspection by the Owner / Consultant upon request.
4.2.15 All materials shall be straight and if necessary before being worked shall
be straightened and / or flattened by pressure including de-coiling of
plates unless required to be of curvilinear form and shall be free from
twists.
4.4.1 Drilling and punching of holes for bolts shall be done as per clause
no.11.4.4 of IS:800:1984, unless otherwise specified by the Owner.
4.4.2 Drifting of holes for bolts during assembly shall not cause enlargement of
holes beyond permissible limit or damage the metal.
4.4.3 Holes for bolted connection should match well to permit easy entry of
bolts. Gross mismatch of holes shall be avoided.
4.4.4 Permissible deviation in holes for mild steel bolts of normal accuracy and
high strength bolts are given in the ANNEXURE-A.
4.5.3 All erection units shall bear erection mark no. and reference drg no. at a
prominent location on the structures for easy identification at site.
4.5.5 All the components of structures shall be free from twist, bend, damage
etc,
4.5.6 Assembly of structures shall be carried out by using suitable jigs and
fixtures in order to obviate distortion during welding.
4.5.7 Cutting of items specially for truss, bracing, bunker, hopper, galleries
surge girder, portal etc, shall be done only after checking of sizes as per
Layout.
4.5.13 The threaded portion of each bolt shall project through the nut at least
by one thread.
4.6.2 Bolt diameter shall not be less than 16mm. except for bolts securing
roof and wall sheeting, windows, doors and stitching of thin coverings.
For bolted joints, min. two bolts shall be used.
4.6.3 The size of fillet welds shall not be less than 5mm for load-bearing
joints.
4.6.7 Roof and wall sheets shall be fixed to purlins and wall girts by stainless
steel top speed screws/galvanized J- hook bolts, each complete with
neoprene and stainless steel /galvanized washers. The connections
shall ensure water-tightness into the buildings. The spacing of these
screws/bolts shall be sufficient to prevent uplift of sheets by suction. The
roof and wall sheets shall be stitched together at their edges by using
studs, rivets or screws. The end and side overlaps of sheeting shall be
sufficient to prevent ingress of rainwater. End lap shall not be less than
75mm and side lap shall not be less than one and half corrugation for
4.7.1 The Contractor shall be responsible for the design and the detailing of all
connections. The design of connections shall provide for adequate
strength for the transfer of force in the structural elements indicated on
the design drawings. For purposes of detailing of connections, the
allowable stresses in material, bolts and welds shall be as per IS:800
and IS:816 or as specified in the design drawings.
4.7.2 For all full strength butt welding of plates and sections thicker than or
equal to 10 mm, edge preparation shall be done and got approved by
the Owner / Consultant.
4.7.3 Two numbers of washers shall be used for all bolted connections, one
washer bearing against the head and other bearing against the nut.
4.7.5 If extra joints are to be provided in column, crane girder etc, prior
approval on the same shall be obtained from the Owner / Consultant
However , as general guidance, the following is suggested :
- Splice joint on column and crane girder shall be of full strength
butt weld, and, wherever possible, shall be located at the section
of minimum or substantially lesser stress.
- Splice joints of web and flange should be sufficiently staggered
in position.
4.7.6 All penetration for piping, conduit, cable trays, etc., through grating or
plate flooring shall be cut and suitably banded in the field, except when
such penetrations are dimensioned in the drawings in which case they
shall be shop cut and banded.
4.8 Fabrication
4.8.3 All pieces shall be properly identified and bundled for transportation to
work site. Care shall be exercised in the delivery, handling and storage
of material to ensure that material is not damaged in any manner.
Materials shall be kept free of dirt, grease and foreign matter and shall
be protected from corrosion. All materials shall be stored properly on
skids above the ground which shall be kept clean and properly
drained. Girders and beams shall be placed upright and stored. Long
members such as columns and chord members shall be supported on
skids spaced near enough to prevent damage due to deflection.
4.8.4 Bolts shall be furnished according to bolt lists showing the location of their
use and additional bolts shall be supplied to cover wastage.
4.8.5 All fabricated pieces shall bear erection mark numbers painted/punched
according to appropriate erection and shop drawings at a prominent
location on the structure for easy identification.
4.8.6 All workmanship shall be in accordance with the best practice in modern
structural shops. Greatest accuracy shall be achieved in the
manufacture of every part of the work and all identical parts shall be
strictly interchangeable.
4.8.8 Unless clean square and true to shape all flame cut edges shall be
planed/cleaned by chipping or grinding. Where machine flame cutting is
permitted for high tensile steel, special care shall be taken to leave
sufficient margin and all flame hardened material shall be removed by
machining/edge grinding.
4.8.9 Wherever shearing is used for cutting to size, sheared members shall be
free from distortions at sheared edge.
4.8.10 The ends of all girder stiffeners shall be in contact with the compression
flange and shall be planed or ground to fit tightly against flange plates
unless otherwise stated on the drawings. Care shall be taken to ensure
full bearing of the stiffeners at the supports by machining the contact
surfaces of both bearing stiffeners and bearing plates. The ends shall
not be drawn or caulked.
4.8.12 In column cap and bases, the ends of shafts, should be accurately
machined so that the parts connected butt over the entire surface of
contact. Care should be taken so that these connecting members are
fixed with such accuracy that they are not reduced in thickness by
machining by more than 1.0 mm. On secondary members, where
sufficient gussets and welds are provided to transmit the entire loading,
the column ends may not be machined subject to the approval of the
Owner / Consultant.
4.8.13 Holes for permanent black bolts shall not be more than 1. 5 mm larger
than the nominal diameter of the black bolts unless specified otherwise.
All holes for turned and fitted bolts shall be sub punched or drilled and
reamed at site under assembly of connected parts to a tolerance of +0.3
mm unless specified otherwise.
Holes in purlins, side-sheeting runners, packing plates and lacing bars
may be punched full size. Holes in light framing with the exception of
joint holes, may be punched full size. All punching and sub-punching
shall be clean and accurate and all drilling free from burrs. In
block/batch drilling, parts shall be separated after drilling and the burrs
removed. No hole shall be made by gas cutting process.
4.8.14 The component parts shall be so assembled that they are neither twisted
nor otherwise damaged and specified cambers, if any, shall be provided.
No drifting of hole shall be permitted except to draw the parts together.
Drifts used shall not be larger than the nominal diameter of the bolt.
Drifting done during assembling shall not distort the metal or enlarge the
holes. Sufficient trial assembly shall be carried out in the fabrication
works to prove the accuracy of workmanship of the and the number of
such trials required shall be at inspector's discretion.
4.8.16 In all cases where the full bearing area of the bolt is to be developed, the
bolt shall be provided with a washer of sufficient thickness, under the nut
so as to avoid any threaded portion of the bolt being within the thickness
of the parts bolted together. Column bases and caps, shall be in one
solid piece, and except when cut from plates with true surfaces, shall be
accurately machined over the bearing surfaces, and shall be in effective
contact over the whole area of the machine end of the stanchion.
4.8.17 Each piece shall be distinctly marked before delivery, in accordance with
an approved marking diagram and shall bear such other marks as
well to facilitate erection. For easy identification at site a small
distinguishing mark for each building shall be painted at each end of
every member before despatch from fabrication shop. The fabricated
steel work shall be despatched in sequence as per agreed programme
and for such portion as may be found convenient for erection or as
ordered by the Owner / Consultant.
4.8.19 The tolerances for fabrication of steel structures shall generally conform
to IS:7215 and to suit the technological requirements as specified by the
equipment supplier.
4.8.20 Any fabrication work which is considered not to be in keeping with the
Technical Specification forming the Contract, or in absence of Technical
Specification with recognized good practice, shall be rectified /replaced
/corrected at the Contractor's expense as directed by the Owner /
Consultant. Site fabrication work shall also conform to all specifications,
stipulations, terms and conditions applicable for shop-welded structures
as mentioned above.
4.8.21 Fabrication of steel structures shall not be allowed inside the plant
premises.
4.9.1 For the purpose of accounting of materials where the same is supplied by
the Owner, free or on cost recoverable basis, the following wastage
including rolling margin, invisible wastage and cut pieces of less than
one metre length and plates with lesser dimension less than 300 mm
shall be allowed.
For all cut pieces ( plates & sections ) invisible wastage (cutting and
burning losses) of maximum 0.5% will be admissible.
4.9.2 Owner reserves the right to take back such sections or quantity of steel
issued in excess of quantity as per fabrication drawings plus permissible
wastage where raw steel is issued free of cost by Owner. The contractor
shall return to the Owner all such steel supplied in good and acceptable
condition. In case of failure of the Contractor to return such surplus steel
on demand by the Owner , Owner reserves the right to recover the cost of
such steel at a penal rate of twice the SAIL- Stockyard rate of that
particular section of steel as on the date of accountability.
4.9.3 If the Contractor fails to return scrap / wastage generated as per the
percentage mentioned at 4.9.1. recovery on account of such scrap /
wastage shall be made by the owner at prevailing rate of steel+ 20 pc per
tonne.
4.10.1 Each despatchable structure shall bear mark no. along with reference
drawing number at two prominent locations (e.g. on flange and bottom of
base plate of a column).
4.10.3 Control assembly of important structures shall be done in the shop floor
before despatch to avoid mismatching. For all such important structures,
match marking shall be given at the control assembly stage in the shop
floor and such match markings shall be made clearly visible while
assembling the structures at site.
4.10.4 Centre lines of column flanges and both sides of web shall be punched,
preferably at top and bottom to facilitate alignment after erection.
5.1 Scope
iii) Reaming for use of next higher size bolt for holes which do not
register or which are damaged.
iv) Welding of connections in place of bolting for which holes are
either not drilled at all or wrongly drilled during fabrication.
5.2.1 The erection drawings prepared by the Contractor and any approved
arrangement drawings, specifications or instructions accompanying them
shall be followed in erection of structures and miscellaneous connected
items throughout the project.
5.5.2 The fabricated materials shall be verified with respect to markings on the
marking plan or shipping list which shall be supplied by the Contractor.
5.5.4 The handling and storing of the component parts of a structure shall
involve the use of methods and appliances not likely to produce injury
by twisting, bending or otherwise deforming the structures. No member
slightly bent or twisted shall be put in place until the defects are
corrected. Members seriously damaged in handling shall be rejected.
5.4.2 During assembly and during erection of the units to position, the
Contractor shall compare the structures with the drawings to ensure that
there are no fabrication omissions or errors. Should any omission or
defect be found the same shall be brought to the notice of the Owner /
Consultant who will issue necessary instructions for the rectification.
5.5.1 The Contractor shall prepare geodetic survey scheme of all embedded
parts and holding down bolts and submit the same to Owner /
Consultant. The Contractor shall inform the Owner / Consultant about
any discrepancy with approved design drawings well in advance of
erection and if necessary shall make necessary adjustments at site or
during fabrication of structures.
5.5.2 The Contractor shall assume, full responsibility for the free and correct
setting out of all steel work and erection correctly in accordance with
position, alignment, dimensions and levels shown on the approved
drawings and plumbing vertical members. Particular care shall be taken
to ensure free expansion and contraction wherever provided.
Notwithstanding any assistance rendered to the Contractor by the Owner
/ Consultant, if at any time during the progress of the work, any error
should appear or arise therein, on being required to do so, the
Contractor at his own cost shall remove and amend the work to the
satisfaction of the Owner / Consultant.
5.6.1 Before starting erection, the Contractor shall submit to the Owner /
Consultant for his approval the method he proposes to follow and the
number of types of equipments and temporary, works he proposes to
use for the erection.
5.6.2 The approval of drawings by the Owner / Consultant will not relieve the
Contractor from the basic approach to design as regards the loads
which the erection equipment and temporary work shall be called upon
to .carry and support. Adequate allowance and provision shall be made
for lateral forces and wind loads.
5.6.3 If in the opinion of the Owner / Consultant, the tools, tackles plant and
equipment instruments, apparatus, etc. arranged by the Contractor are
not sufficient or are inadequate for the fulfilment of the contractual
obligations of the Contractor within the stipulated period, the Owner /
Consultant will have the right to order the Contractor and the Contractor
shall comply with the order to bring/arrange such additional tools,
tackles, plant and equipment instruments, apparatus, etc. to the site and
employ the same to complete the work in time. All charges in connection
thereof shall be borne by the Contractor.
5.6.5 Erection shall be carried out according to the best modern practices and
as laid down in the IS : 800-1984 and other relevant standards referred
5.6.6 The Contractor shall design, manufacture, erect and provide false work;
staging, temporary supports, etc. required for safe and accurate erection
of structural steelwork and shall be fully responsible for the adequacy of
the same.
5.6.7 The Contractor shall, if so required by the Owner Consultant, get his
drawings, erection schemes and designs for such false work, staging,
etc. approved by the Owner / Consultant, but such approval by the
Owner / Consultant shall not relieve the Contractor of any of his
responsibilities for the safety of such works. As far as possible,
assemblies of structures shall be made on the ground itself.
5.6.8 The Contractor shall provide adequate supervision at all stages of the
work and examine each portion of the work for accuracy before
commencing the erection of the next structural member. The Contractor
shall also provide facilities such as adequate temporary access ladders,
tools and tackles, instruments, etc. satisfactory to Owner Consultant
for his inspection at any stage during erection.
5.6.10 All structural members shall be erected with erection marks in the same
relative position as shown' in the appropriate erection and shop
drawings.
5.7.1 The holes of erection joints required to be machine bolted shall be filled
with temporary bolts and plugs after mounting the structures. The
number of bolts and plugs shall be determined by design but it shall not
be less than 50% of the total number of holes. In joints where the
number of holes is equal to 5 or less, not less than 3 holes shall be filled.
The number of plugs shall be about 20% of the holes filled.
5.7.2 The number of washers on permanent bolts shall not be more than two
(and not less than one) for nut and one for the bolt head. Wooden rams
or mallet shall be used in forcing members into position, in order to
protect the metal from injury and shocks. Chipping of edges of plates
shall be done without breaking parent metal. Chipped edges shall be
finished with a file and all short corner and hammered rough faces shall
be rounded off. Chipping with the use of sledge hammer shall only be
permitted in exceptional cases and shall be done without resulting in
fractured edges.
5.7.3 Where bolting is specified on the drawings, the bolts shall be tightened
to the specified limit. The threaded portion of each bolt shall project
through the nut by at least one thread. Tapered washers shall be
provided for all heads and nuts having bearing on bevelled surfaces.
Use of special bolts, such as high strength friction grip bolts, shall be
according to the relevant Indian or other recognized standards and shall
be subject to the prior approval of the Owner / Consultant before use.
5.7.5 Erection bolts shall be retained in position permanently even after site
welding
5.8.1 The mating surfaces shall be absolutely free from grease, lubricant, dust,
rust, etc. and shall be thoroughly cleaned before assembly. The
preparation of the mating surfaces shall be done as specified in the
design drawings.
5.8.2 Nuts shall be tightened up to the specified torque with the help of torque
wrench or by half turn method with the help of pneumatic wrench lever.
Torque value has to be specified in design / fabrication drawings itself.
The direction of tightening of the nuts shall be from the middle towards
the periphery of the joint. The bolt head, nuts and edges of the mating
surfaces shall be sealed with a coat of paint to obviate entry of
5.9.1 Base plates shall be set to elevations shown in the drawings, supported
and aligned using steel wedges and shims or any other approved
method. The supply of wedges, shims and any other material for
alignment shall be the responsibility of the Contractor as part of his
work. Plates shall be levelled, properly positioned and the anchor bolts
properly tightened. The bedding/grouting shall not be carried out until a
sufficient number of columns have been properly aligned, levelled and
plumbed, and sufficient girders, beams, trusses and bracings are in
position to the satisfaction of the Owner / Consultant.
5.9.2 Grouting shall be done before casting of elevated RCC floors , if any,
and before equipments contributing to the loading on columns are
placed in position. No moving equipment shall be tested and no trial run
of any equipment conducted, before grouting has been done and cured
to the satisfaction of the Owner / Consultant.
5.9.3 Grouting shall be minimum M25 grade or one grade higher than the
grade of base concrete with 10 mm and below graded coarse aggregate.
Ready-mix, non-shrink, free-flow grout from recognised manufacturer as
approved by the Owner / Consultant shall be used with pressure
grouting technique to ensure proper filling-up of all void spaces
underneath the base plate. Manufacturer’s recommendations /
instructions shall be followed for proper application of grout material.
5.9.4 The Contractor shall inform the Owner / Consultant when the base
plates are ready for grouting for their verification. The Contractor shall
be responsible for final vertical and horizontal alignment of all the base
plates.
6.1 General
6.1.1 The welding and welded work shall conform to IS:816 and other relevant
codes unless otherwise specified. Electrodes shall conform to IS:814
and shall be approved by the Owner / consultant.
6.1.2 Welding shall be done by Electrical Arc Process. Automatic welding shall
be employed for important structures as specified in the drawings.
Generally, submersed arc, Automatic & Semi-automatic welding shall be
6.1.3 Welding shall not be done under such weather conditions which might
adversely affect the efficiency of the welding and where necessary,
effective protection and other safeguards shall be provided.
6.1.4 Only qualified welders suitable for the job shall be employed. The Owner
/ Consultant at his discretion can order periodic tests in accordance with
IS:817 of the welders and / or of the welds produced by them at no extra
cost. Welding shall be done using requisite jigs and fixtures to avoid
distortions or damage to members during / after welding. Welds on
exposed work shall be finished uniformly smooth to present a neat
appearance.
6.2.2 The welding procedure shall be arranged to suit the details of the joints
as indicated in the drawings and the positions in which the welding is to
be carried out. The welds shall meet the requirements of quality
specified.
6.2.3 All electrodes for use in the work to which the specification relates
shall be kept under dry conditions. Electrodes which are damaged
by moisture shall not be used unless it is certified by the manufacturer
that when it is properly dried there shall be no detrimental effect. Any
electrode which has part of its flux coating broken away or is otherwise
damaged shall be discarded.
6.2.4 Low hydrogen electrodes and flux for submerged arc welding shall be
dried at 250- 300 deg. C for one hour in drying oven before use.
6.2.3 At site, the electrodes shall be kept in proper coves while using them for
welding
6.2.5 Submerged arc welding of mild steel and low alloy steel shall be as per
IS : 4353
6.2.6 For multi-run weld deposit the succeeding run shall be done only after the
preceding run is cleaned of all slag and flux deposits.
6.2.8 The welding surfaces shall be smooth, uniform and free from fins, tears,
notches or any other defect, which may adversely affect welding.
6.2.10 After completing each run of weld, all slag shall be thoroughly removed,
and the surface cleaned before starting the next run of weld. The weld
metal, as deposited (including tack welds if to be incorporated) shall be
free from cracks, slag, inclusions, gross porosity, cavities and other
deposition faults. The weld metal shall be properly fused with the
parent metal without serious undercutting or overlapping at the toes
of the weld. The surfaces of the weld shall have a uniform and consistent
contour and uniform appearance.
6.2.11 All weld runs found defective shall be cut by using either chipping
hammer, gouging torch, or suitable grinding wheel in such a manner
that adjacent material is not injured in any way. Peeling of the welds
involving deformation of the weld surface either during de- slagging or
thereafter shall not be allowed.
6.3.1 The extent of quality control in respect of welds for structural elements
for both statically and dynamically loaded structures shall be as follows
and shall be conducted by the contractor at his own cost:-
i) Presence of undercuts
b) Dye Penetration Test (DPT) - This shall be carried out for all
important fillet welds and groove welds for both statically and
dynamically loaded structures to check the following
i) Surface cracks
ii) Surface porosities
i) Cracks
ii) Lack of fusion
iii) Slag inclusions
iv) Gas porosity
i) gas porosity
ii) slag inclusions
iii) lack of penetration
iv) lack of fusion
v) cracks
6.3.2 The Contractor shall provide testing equipment for conducting non-
destructive tests for confirming the integrity of welding wherever
necessary as directed by the Owner / consultant.
i) All craters in the weld and breaks in the weld run shall be
thoroughly filled with weld.
ii) Undercuts, beyond acceptable limits, shall be repaired with
dressing so as to provide smooth transition of weld to parent metal.
iii) Welds with cracks and also welds with incomplete penetration,
porosity, slag inclusion etc. exceeding permissible limits shall be
rectified by removing the length of weld at the location of such
defects plus 10 mm from both ends of defective weld, and shall be
re-welded. Defective weld shall be removed by chipping hammer
gouging torch or grinding wheel. Care shall be taken not to damage
the adjacent material.
7.2.2 In the event of conflict between this General Specification for painting
and the paint manufacturer's specification, this conflict shall be
immediately brought to the notice of the Owner / Consultant. Generally
in cases of such conflicts, manufacturer's
Specification/recommendation shall prevail.
7.2.4 Control areas shall serve as specimen of painted surfaces, for observing
and recording quality and performance of paint.
7.2.5 In case of any doubts, the Contractor shall send samples of paint to
recognized testing laboratories to establish quality of paint with respect
to:
i) Viscosity
ii) Adhesion/bond of paint to steel surfaces
iii) Adhesion/simulated salt spray test
iv) Chemical analysis/percentage of solid by weight
v) Normal wear resistance as encountered during handling and
erection
vi) Resistance against exposure to acid fumes, and such other tests as
considered necessary by the Owner / Consultant.
7.2.6 Guarantee period on paints and painting shall commence from the date
of completion of finishing coat of paint on entire structures. The
guarantee period shall be indicated depending on the type of surface
preparation and system of painting. To fulfil this obligations, the
Contractor may obtain from the painting manufacturer, guarantee for the
performance of paint/painted surfaces.
7.2.9 All field welded areas on shop painted items shall be mechanically
cleaned including the weld area proper, adjacent areas contaminated by
7.2.12 The inside surfaces of gutter which come in contact with rain water shall
be provided with 2 finishing coats of water resistant, bitumastic paint of
minimum DFT 75 microns, in addition to the primer coats of red oxide
zinc phosphate in phenolic alkyde medium or 2 primer coats of epoxy
based red oxide zinc chromate/epoxy based zinc phosphate of minimum
DFT 25 microns per coat, as given in Specification and drawings. Other
structures shall be painted as per painting system mentioned .
7.2.13 All structures shall receive one coat of primer paint at shop after
fabrication before despatch after surface preparation has been done as
per requirements. Unless otherwise specified all structures after erection
shall be given one coat of primer and two coats of finishing paint of
approved colour and quality. The under coat shall have different tint to
distinguish the same from the finishing coat. Edges, corners, crevices,
depressions, joints and welds shall receive special attention to ensure
that they receive painting coats of required thickness.
7.2.14 Machine-finished surface shall be coated with white lead and tallow
before shipment or before being put out into the open air. Part of steel
structures to be embedded in concrete, shall be given a protective coat
of Portland cement slurry immediately after fabrication after this part is
thoroughly cleaned from grease, rust, mill scales etc. No paint shall be
applied on such parts.
7.2.15 Zinc-rich primer paints, which have been exposed several months before
finishing coat is applied, shall be washed down thoroughly to remove
soluble zinc salt deposits. In similar circumstances, the surface of paint
based on epoxy resin should be abraded or lightly blast cleaned to
ensure adhesion of next coat.
7.2.16 Paints selection shall be based on Preferred make list of BSP. Type of
paint ( heat resistant/high corrosion resistant) required to be applied for a
structure shall be approved by BSP and prior permission shall be taken
before application of paint.
8.1 Programme
8.2 Drawings
8.2.5 The Contractor shall assume full responsibility for the correct setting out
of all steel works and erecting correctly in accordance with alignment
and levels shown on the approved drawings and plumbing of vertical
members. Notwithstanding any assistance rendered to the
Contractor by the Owner / Consultant, if at any time during the progress
of the work, any error should appear or arise therein, on being required
to do so, the Contractor at his own cost shall remove and amend the
work to the satisfaction of the Owner/Consultant.
8.2.6 The Contractor shall provide his own measuring instruments for
setting out, levelling and aligning work at his own expense.
8.4 Staging
Any staging necessary for the pre assembly work of structures shall be
provided by the Contractor.
The Contractor shall at all times comply with such rules and regulations
as stipulated in relevant factory acts, electricity rules, safety regulations,
etc.
8.6 Deviations
9. INSPECTION OF STRUCTURES
The Owner / Owner’s Inspector shall have free access at all times to
those parts of Contractor's or his Sub- Contractor's works which are
concerned with the fabrication of steel works and shall be afforded all
reasonable facilities at all stages of preparation, fabrication and trial
assemblies for satisfying himself that the fabrication is being undertaken
in accordance with the provisions of relevant specification.
9.2 All gauges and templates, tools, apparatus, labour and assistance for
checking shall be supplied by the contractor free of charge. The Owner /
Inspector may at his discretion, check the test results obtained at the
Contractor's works, by independent test at the Government Test House
or elsewhere, and should the material so tested be found to be
unsatisfactory, the cost of such test shall be borne by the Contractor.
9.3 Contractor shall make all necessary arrangements for stage inspection by
Owner/Inspector during the fabrication at shop and incorporate all
on-the-spot instructions / changes conveyed in writing to the Contractor.
a) To declare, before any structure is submitted for inspection, that the same
is not in accordance with the contract, owing to the adoption of any
unsatisfactory method of fabrication and the same will be rejected.
9.5.2 The Owner / Inspector's decision regarding rejection shall be final and
binding on the Contractor.
10.1 GENERAL
The Contractor must recognise the importance of quality and follow the
defined quality programme in all manufacturing and quality control
activities of the product. The Contractor shall define and implement the
tasks and controls that shall provide needed assurance in case
manufacturing of product is sub-contracted either partly or fully and / or
for the procured components of the product. All bought-out components,
if any, shall be procured from approved list of vendors issued by the
Project Authority.
Owner reserves the right to verify the quality programme and entire
product characteristics to assure the intended and specified quality of the
product.
10.3.1 The Contractor shall furnish the Quality Assurance Plan (QAP) for the
respective structural unit / component after finalisation of billing schedule
for Owner's approval at least two months prior to start of manufacturing.
10.3.2 The Contractor shall indicate the procurement source and furnish to
Owner during discussions on QAP, copies of Owner Order, Sub-Owner
Order, and data sheets as backup reference materials for scrutiny &
finalisation of QAP.
10.3.3 QAP shall be prepared & furnished by the Contractor in the prescribed
format (enclosed as Annexure- B) for structural components, in four sets.
10.3.4 Inspection and test requirements shall be decided with due consideration
of factors like safety, duty cycle, operating conditions, equipment life,
environmental conditions, place of installation and statutory regulations,
as applicable, for a particular component. Any, additional type or special
test or routine tests if found necessary to establish the intended quality,
shall be incorporated in the QAP on mutual agreement without any
commercial implication.
10.3.5 Detailed QAP shall be prepared by the Contractor based on the general
plan given by Owner and shall be approved by Owner to avoid any
complication later.
10.3.6 QAP shall clearly indicate the followings through use of codes in the
appropriate columns:
10.3.7 Sampling method for lot inspection of similar bulk items, if any, shall be
indicated under column 16 of QAP with linkage to applicable standard.
10.3.8 While submitting the QAP, the Contractor shall indicate the acceptance
criteria under column 15 of QAP form regarding check parameters of each
- Dimensional checking
10.5.1 All the measuring equipment used for inspection & testing shall be
calibrated and appropriate accuracy class of measuring equipment shall
be used. Calibration standards used for calibration of measuring
10.6.1 For each of the items being fabricated, the following test certificates and
documents, as applicable, in requisite copies including original shall be
submitted to Inspection Agency. All test certificates must be endorsed by
the Contractor with linkage to project, purchase order and acceptance
criteria.
xi) Certificates from competent authority for the items coming under
statutory regulations.
10.6.2 The Inspection Agency shall have the right to be present and witness all
tests being carried out by the Contractor at their own laboratory or
approved laboratories. Also, the Inspection Agency shall reserve the right
to call for confirmatory test on samples, at his discretion.
The Contractor shall submit the schedule for fabrication and inspection
indicating components/ assembly / sub-assembly, date of approval of
drawings / data sheets, address of Fabricator with contact person and
scheduled date of inspection. Such reports shall be submitted to Owner
with a copy to Inspection Coordinating Office once in a month. These
monthly reports shall state the planning for next three months.
Submission of first report must commence one month prior to
commencement of fabrication activities of the component.
10.8.2 The Contractor shall carry out their internal inspection & obtain clearance
from statutory bodies e.g. IBR, CCE, TAC, Weights & Measures, safety,
IE rules etc. as and where applicable, prior to offering any component for
Owner's inspection in accordance with approved QAP.
10.8.4 The Contractor shall identify all the inspected component / raw materials
& shall maintain the record of status of inspection viz. inspected & found
acceptable, require rectification / rework, rejected etc.
10.8.5 The Contractor shall establish and maintain procedures to ensure that
product that does not conform to specified requirements, is prevented
from inadvertent use or installation. The description of non-conformity
that has been accepted subsequently by Owner by concession and / or
of repairs shall be recorded.
10.8.6 The Contractor shall not despatch any equipment till receipt of despatch
clearance from Owner.
(ii) Inspection call shall be floated to Owner with ten days clear
margin, enclosing all documents like test Certificates, Internal Inspection
Reports, Purchase Order, Sub-Purchase Order, T.S., Approved QAP,
approved GA drawings/ data sheets and fabrication drawings with a copy
of call letter to Inspection Co-ordinating Office. Inspection calls without
above documents shall be ignored.
10.10.1 The Contractor shall provide all facilities and ensure full and free
access of the Inspection Engineer of Owner to the Contractor's or their
Sub-Contractor's premises at any time during contract period, to
facilitate him to carry out inspection & testing of the product during or
after manufacture of the same.
10.10.6 The Contractor shall ensure that the assembly / component of the plant
and equipment required to be inspected, are not dismantled or
despatched before inspection.
10.10.7 The Contractor shall not offer equipment for inspection in painted
condition unless otherwise agreed in writing by Owner / Consultant.
10.10.8 The Contractor shall ensure that the equipment and materials once
rejected by the Inspection Engineer are not re-used in the manufacture
of the plant and equipment. Where parts rejected by the Inspection
Engineer have been rectified, as per agreed procedures laid down in
advance, such parts shall be segregated for separate inspection and
approval, before being used in the work.
Inspection Memo: -
For stage inspection & for rejected items / items which do not conform
to Technical Specification in one or more quality characteristics
requiring rectification / rework, Inspection Memo shall be issued in
Inspection Certificate: -
10.12.1 Inspection & tests carried out by Owner / Third Party Inspector shall
not absolve the responsibility of the Contractor to provide acceptable
product nor shall it preclude subsequent rejection.
10.12.2 Owner / Third Party Inspector reserves the right to inspect any product
at any stage of manufacturing without prior notice to Contractor beyond
pre-identified stages & hold points of approved QAP.
A) SQUARE BUTT-JOINT
C) LAP JOINT
TABLE – 1
Description Tolerance in mm
TABLE – 2
DESCRIPTION DEVIATION IN mm
Caving in or bulging of 5
joints
measured by gauge over
a length of 200 mm.
TABLE – 3
Portions of the
BF Shell 100 3 2.0 welded joint found
defective by
ultrasonic testing
Dust catcher,
Junction &
places of
variable cross
sections by
the following
norms -- 3 1.5 Crossing of welded
without - joint
ultrasonic
testing 1 0.5 Portions of the
with 100 welded joints found
ultrasonic defective by
testing ultrasonic welding
TABLE – 4
ERECTION TOLERANCES
DESCRIPTION TOLERANCE
(mm)
COLUMNS
Note :
Tolerance specified under 3(a) & 3(b) should be read in conjunction with
4 & 5. 'H' above is the column height in mm.
contnd..
TRUSSES
± 1/250 of height of
Shift, at the centre of span of top chord member truss at centre of span
with respect to the vertical plan passing through or
the centre of bottom chord. ± 15 mm whichever is
less.
± 10 mm whichever is
less.
contnd..
Shift in the centre line of crane rail with respect ± ( web thickness + 2
to centre line of web of crane girder. )/2
2 mm subject to
Relative shift of crane rail surfaces at a joint in grinding of surfaces
plan and elevations. for smooth transitions.
BUNKERS
BF SHELL
STOVE SHELL
TOP STRUCTURES
DOWN COMERS
Deviations of support axes from the vertical 0.002 h, but not more
plane. than 20 mm, h is the
height of the support.
DUST CATCHER
BUSTLE PIPE
Note :
ANNEXURE-A
cracks on
the hole
edges
d) (i) Non-coin- -- -- Upto 50% Upto 50%
cidence of
holes in
separate
details of
the assem-
bled unit,
upto 1mm
(ii) Above 1 mm -- -- Upto 10% Upto 10%
upto 1.5 mm