DTP 2068937 Tulsi Bag
DTP 2068937 Tulsi Bag
Date of
Cost of Last Date of
Amount Put To opening of e-
EMD Blank submission
Tender Tender Time Limit in Class of Tender at 4.00
Name of work Tender of e-Tender
No Days Contractor PM
upto 3.00
PM
(In Rs) (In Rs) (In Rs) (if possible)
Construction of
Toilet And
Covering Of
Shade and
Providing And 500+18
6 %GST= I to V-
1 Fixing Iblock And 2068937/- 21000/-
Month Rs.590. A
Various Civil work 00
at NMC
Vyamashala at
Tulsibag Mahal in
Pr. No. 18
Tender form, conditions of contract, specifications and contract drawings can be downloaded from the e-Tendering portal i.e.
https://mahatenders.gov.in. Payment of tender cost shall be paid online using payment gateway only. The fees of tender document shall
be non-refundable. Further information regarding the work can be obtained from the office of Executive Engineer, NMC, Civil Lines,
Nagpur. Tender acceptance is subject to verification of documents uploaded by the Bidder. Uploading of any false information or
documents by the Contractor shall result in rejection of bid and action as may deem fit will be taken by NMC against the Contractor.
Executive Engineer
DPDC
NMC, Nagpur
NAME OF WORK :- Construction of Toilet And Covering Of
Shade and Providing And Fixing Iblock And Various Civil
work at NMC Vyamashala at Tulsibag Mahal in Pr. No. 18
INDEX
VOLUME – I
2 Details of Work
4 Earnest Money
5 Security Deposit
7 Scope of work
8 Memorandum
10 Condition Of Contract
12 Memorandum
Volume– III
15 Special Conditions
19 Annexure
21 Appendix – II
22 Scheduled – A
23 Scheduled – B
( In word : Twenty Lakh Sixty Eight Thousand Nine Hundred and Thirty Seven Rs. Only)
NAME OF WORK:-Construction of Toilet And Covering Of Shade and Providing And Fixing Iblock And
Various Civil work at NMC Vyamashala at Tulsibag Mahal in Pr. No. 18
3. Total Security Deposit shall be 2% ( Two percent) : Rs. 42000/-[ 1% EMD of Lowest
Bidder shall be appropriated as SD + 1% from R. A. Bill]
4. TENDER SCHEDULE
Last date and time for online bid :As per Notice Inviting Tender
preparation and hash submission (technical
and financial)
I/We have quoted my/our offer in percentage rate in words as well as in figures.
I/We further undertake to enter into contract in regular “B-1” form in NAGPUR
MUNICIPAL CORPORATION.
NAME OFWORK : Construction of Toilet And Covering Of Shade and Providing And Fixing
Iblock And Various Civil work at NMC Vyamashala at Tulsibag Mahal in Pr. No. 18
Online percentage rate tenders in 'B-1' Form are invited by the Commissioner, NMC, NAGPUR for the
following works from registered Contractors in appropriate class of theNagpur
Municipal Corporation, Nagpur. The name of work, estimated cost, earnest money,
security deposit, time limit for completion etc. are as under:
Tender form, conditions of contract, specifications and contract drawings can be downloaded from the e-
Tendering portal i.e. https://mahatenders.gov.in. Payment of tender cost shall be paid online using payment gateway
only. The fees of tender document shall be non-refundable. Further information regarding the work can be obtained
from the office of Executive Engineer, NMC, Civil Lines, Nagpur. Tender acceptance is subject to verification of
documents uploaded by the Contractor. Uploading of any false information or documents by the Contractor shall result
in rejection of bid and action as may deem fit will be taken by NMC againstthe Contractor.
Date of
Amount Last Date of
Cost of opening of
Put To submission
EMD Time Blank Class e-Tender at
Tende Tender of e-
Name of work Limit in Tender of --------PM
r No Tender
(In Rs) month Contractor
upto3.00
(In Rs) ( if
(In Rs) PM
possible)
Construction of Toilet
And Covering Of
--500----
Shade and Providing -+-
1 And Fixing Iblock And 2068937/- 21000/- 6 Four 90.00- I To ---- -----
Various Civil work at Months (18%GST V-A
=590.00
NMC Vyamashala at
Tulsibag Mahal in Pr.
No. 18
1.00 A. Blank Tender Forms
Tender Forms can be purchased from the e-Tendering Portal i.e. https://mahatenders.gov.in.
after paying Tender Fees via online mode as per the Tender Notice.
1.00 B. Pre-Tender Conference for work casting more than 50Lakhs : AS per NIT
1.00 C. The tender submitted by the tenderer shall be based on the clarification, additional
facility offered (if any) by the NMC, and this tender shall be unconditional. Conditional
tenders shall be REJECTED.
1.00 D. All tenderers are cautioned that tenders containing any deviation from the contractual
terms and conditions, specifications or other requirements and conditional tenders will
be treated as non-responsive. The tenderer should clearly mention in forwarding letter
that his offer (in envelope No. 1 & 2) does not contain any conditions, deviations from
terms and conditions stipulated in the tender.
1.00 E. Tenderers should have valid Digital Signature Certificate (DSC) obtained from Certifying
Authorities. In case of requirement of DSC, interested Contractors should go to
https://mahatenders.gov.inand follow the procedure mentioned in the document
‘Procedure for application of Digital Certificate’.
1.00 F. For work casting more than 100 lakhs , post Tender Qualification Criteria is applicable
as given in tender document.
1.00 G. The Contractor shall have to submit on hard copy of Tender document within 72 hrs
from bid lock. This copy will only be opened in case deficiencies in the E-Tender
procedure.
1.00 H. for works casting more than 150 Lakhs , Registration of contractor will not be essential
condition.
(i) Earnest money shall be paid online using payment gateway mode only.
(ii) Earnest money Exemption Certificate if allowed in Envelope (1)
(iii) Tenderer of those who do not deposit earnest money in one of the above acceptable
form shall be summarily rejected.
(iv) The amount will be refunded to the unsuccessful tenderer on deciding about the
acceptance or otherwise after expiry of tender validity period of the tender. In
case of successful tenderer, it will be appropriated initial as Security Deposit.
1.2 A SECURITY DEPOSIT:
The successful tenderer whose tender is accepted will have to pay the balance
amount towards the Security Deposit as per tender notice.
After opening of Envelop No. 1 and 2, the L1 Bidder will have to submit
Additional Performance Security Deposit within a period of 8 days to the concerned
Executive Engineer.
The limit of 8 days will not be relaxable on any grounds. If the L1 bidder fails to
submit additional performance security deposit within a period of 8 days, the bid of
second lowest bidder (L2) shall be considered.
For 14.23 % below rates – 1 % up to 10 % & 4.23 % for 14.23 % - 10 %, total shall be
5.23 %
If tender submitted is more than 15 % below the estimated cost, the amount of
additional performance security for the balance percentage over 15 % shall be doubled
& will be as under :
If the total amount of additional performance security is less than Rs 1,000, then
Original Demand Draft shall be of Rs 1,000 minimum.
3.The Demand Draft shall bedrawn from Nationalized/Scheduled Bank in favor of “The
Commissioner,NMC, NAGPUR” payable at NAGPUR.
4. If the Demand Draft found to be false, earnest money of the tenderer shall be
forfeited. He will be barred from participating in any tender of NMC, Nagpur and will be
included in the black list. The MICR and IFSC code of the issuing bank shall be printed
on the Demand Draft.
1.5 IMPORTANT : The Awardee of the work shall download complete tender
document and make ONE hard copy from the downloaded soft copy.
All the pages of this hard copy shall be signed by the Contractor.
The lowest quoted tenderer (L1) shall submit this signed hard copy
within three days after receipt of Letter of Acceptance of his offer at
office of the Executive EngineerDPDC NMC, Nagpur.
1.6 The rates quoted by the Contractor shall be deemed to be inclusive of the labour
welfare cess and all other taxes (other than G.S.T.) that the Contractor will have
to pay for the performance of this Contract. The Employer will perform such
duties in regard to the deduction of such taxes at source as per applicable law.
Payment of GST
i) Bidder shall quote his rate excluding GST.
1.7VALIDITY PERIOD
The offer shall remain open for acceptance for period as below & as
specified in tender notice from the date of opening of Envelope No. 2 (Financial
Bid) and thereafter until it is withdrawn by the Contractor by notice in writing
duly addressed to the authority opening the tender and sent by Registered Post
Acknowledgment due.
1. As the rates are excluding of royalty charges, the contractor has to procure all the required minors
minerals required for the work by paying royalty charges. The contractor shall have to submit royalty
paid passes for the consumption of the miner minerals used for the quantities in the respective bill.
In absence to Royalty passed details, amount will be withheld from R. A. Bills.
2. The contractor will have to submit Royalty Clearance Certificate along with final bills, without which
the final bills will not be passed and payment will not be released to the contractor.
1.9 Stamp Duty
The successful bidder should enter into the agreement on stamp paper as per current
practice in NMC, Nagpur within a period of one week from the date of issue of “LoA”. The cost
of such expenses must be borne by contractor for that he should quote his offer considering all
such aspects specified in tender document.
1.10Eligibility Criteria :-
1. The Tenderer Should be Registered Contractor in Nagpur Municipal Corporation in
appropriated class . (I to V-A)
2. The bidders shall have experience of similar type of Civil Engineering works i.e.
Building Work and Paver Block as per G.R. No. CAT/2017/ . 04/इमा.2 िदनांक
3. The certificate shall be obtained from the officer not below the rank of Executive
Engineer.
4. The Bidder shall have valid GST certificate.
5. Bidders Shall have to Submit EPF Registration. If bidder have no EPF Registration
then bidder shall have to submit Affidavit of Rs. 500/- Stamp Paper as per
Annexture II.
6. Bidder Shall have to submit Affidavit of Rs. 500/- Stamp Paper as per Appendix- I
7. The Bidder Shall have owned/hire all the necessary equipment & machinery at the
time of Tendering. (As per qualification Form No. 1)
8. The Bid capacity shall not be less than the amount put to tender for which the bid
is submitted. Bid capacity will be evaluated as part of post qualification in the
following manner. Calculation of Bid capacity should be required on contactors
letter head.
Bid Capacity = (A x N x 2) – B
A– Maximum Annual Turnover of civil engineering works excluding private work during
last Five years (updated to the current Value) which will take into Account the
Completed and part of ongoing works completed during last Five years (Such
certificate are required to be obtained from the Chartered Accountant of
Maharashtra State/Any State of India)
The financial figure will be escalated by multiplying factor as specified below
Year M. F.
2024-25 1.0
2023-24 1.10
2022-23 1.20
2021-22 1.30
2020-21 1.40
VOLUME - II
2 – TENDERING PROCEDURE
2.1.Tender Forms.
2.1.1 Tender Forms can be downloaded from the e-Tendering portal. https://mahatenders.gov.in.
Tender Document Fee and EMD to be paid Via SBI MOPS Online Payment Gateway Mode Only. The
contractor shall upload successful payment receipt in ENVELOPE NO.1 TECHNICAL BID Documents.The
tender submitted by the tenderers shall be based on the clarification, additional facility
offered (if any) by the NMC, and this tender shall be unconditional. Conditional tenders
will be REJECTED.
2.1.2 All tenderers are cautioned that tenders containing any deviation from the
contractual terms and conditions, specifications or other requirements and conditional
tenders will be treated as non-
responsive.Thecontractorshouldclearlymentioninforwardingletterthathisoffer(inEnvelope
No.1 & 2) does not contain any condition, deviations from terms and conditions
stipulated in the tender.
2.1.3 Tenderers should have valid Digital Signature Certificate (DSC) obtained from Certifying Authorities.
2.1.4 For any assistance on the use of Electronic Tendering System, the Users may call the below Toll Free
Ph. No. 0120-4200462, 0120-4001002,0120-4001005
2.1.5 Special Instructions to the Contractors for the e-submission of the bids :
Contractor must register themselves on https://mahatenders.gov.in portal.
2.1.6 The registered DSC e-token shall be used by the contractor and should not be
misused by others.
2.1.7 The Contractors can update well in advance, the documents such as certificates,
purchase order details etc., under My Documents option and these can be selected as
per tender requirements and then attached along with bid documents during bid
submission.
2.1.8 After Purchasing / getting the tender schedules, the Contractor should go through
them carefully and then submit the documents as asked, otherwise, the bid will be
rejected.
2.1.9 If there are any clarifications, this may be obtained online through the tender site,
or through the contact details. Contractor should take into account of the corrigendum
/ CSD if any published before submitting the bids online.
2.1.10 Contractor, in advance, should get ready the bid documents to be submitted as
indicated in the tender schedule and they should be in PDF/XLS/RAR formats. If there
is more than one document, they can be clubbed together.
2.1.11 Document Tender Fee and EMD to be paid via Offline Mode only and
upload successful payment receipt in ENVELOPE NO.1 TECHNICAL BID Documents.
2.1.12 The contractor shall read the terms & conditions and accepts the same to
proceed further to submit the bids.
2.1.13 The contractor has to submit the tender document offline well in advance before
the prescribed time to avoid any delay or problem during the submission
process.
2.1.14 After the bid submission, the acknowledgement number, given by the e-
tendering system should be printed by the contractor and kept as a record of
evidence for online submission of bid for the particular tender.
2.1.15 The Tender Inviting Authority (TIA) will not be held responsible for any sort of
delay or the difficulties faced during the submission of bids offline by the
contractors.
2.1.16 The contractor shall submit the bid documents by offline mode in the office od
Executive Engineer, (DPC) NMC, Civil Lines, Nagpur. as indicated in the tender
documents.
2.1.17 The Tender Inviting Authority (TIA) will not be held responsible for any sort of
delay or the difficulties faced during the submission of bids online by the
contractors.
2.1.18 The tendering system will give a successful bid updating message after uploading
all the bid documents submitted & then a bid summary will be shown with the
bid no, date & time of submission of the bid with all other relevant details. The
documents submitted by the contractors will be digitally signed using the DSC e-
token of the contractor and then submitted. The bid summary has to be printed
and kept as an acknowledgement as a token of the submission of the bid. The
bid summary will act as a proof of bid submission for a tender floated and will
also act as an entry point to participate in the bid opening date.Deleted
2.1.19 Contractor should log into the site well in advance for bid submission so that he
submits the bid in time i.e on or before the bid submission end time. If there is
any delay, due to other issues, contractor shall only be responsible.
2.1.20 The contractor should see that the bid documents submitted should be free from
virus and if the documents could not be opened, due to virus, during tender
opening, the bid is liable to be rejected.
2.1.21 The time settings fixed in the server site & displayed at the top of the tender site,
will be valid for all actions of requesting, bid submission, bid opening etc., in the
e-tender system. The contractors should follow this time during bid submission.
2.1.22 All the data being entered by the contractors would be encrypted using PKI
encryption techniques to ensure the secrecy of the data. The data entered will
not viewable by unauthorized persons during bid submission & not be viewable
by any one until the time of bid opening. Overall, the submitted tender
documents become readable only after the tender opening by the authorized
individual.
2.1.23 The contractors are requested to submit the bids through online e-tendering
System to the TIA well before the bid submission end date & time (as per Server
System Clock).
2.1.24 The contractor should upload the Technical Bid in .rar format file to upload in
Technical cover and then BOQ in .xls format single file to be uploaded in
ENVELOPE NO.2 FINANCIAL BID Documents.
2.1.25
The first envelope “Envelope No. 1” shall contain the following documents:
vii) The tenderer shall have to submit all the documents required for
qualification as per Eligibility criteria mentioned for this work.
vii) As per Govt. of Maharashtra Resolution dated 27.11.2018, it has been made
mandatory that the contractor shall submit an affidavit in Envelope No. I on
stamp paper of Rs. 500, stating that the documents submitted by him along with
the tender, along with the bills & documents submitted with related letters are
true, genuine and correct. The format of Affidavit is attached at Appendix-I. This
affidavit shall be part & parcel of tender document.
(i) Submit Blank Tender Copy only in Word Format Issued by the NMC.
(ii) Rate offer to be submitted offline ONLY. In case of discrepancy, if any, between the
offers quoted in figure and that appearing in words, the lower of the two only will be taken
as the offer quoted by the tenderer.
2.1.30TIME LIMIT:
The work is to be completed within time limit as specified in the NIT
which shall be reckoned from the date of written order for commencing
the work and shall be inclusive of monsoonperiod.
2.1.31 TENDER RATE:
No alteration in the form of tender and the schedule of tender and no additions
in the scope of special stipulations shall be permitted. Rates quoted for the
tender shall be taken as applicable for all leads, lifts and taxes unless otherwise
specified in the tender.
2.1.32TENDER UNITS:
The tenderers should particularly note the units mentioned in the Schedule “B”,
on which the rates are based. No change in the units shall be allowed. In the
case of difference between the rates written in figures and in words, the correct
rate will be the one, which is lower of the two.
2.1.32 CORRECTION:
No corrections shall be made in the tender documents. Any corrections that are
to be made shall be made by crossing the incorrect portion and writing the
correct portions above with the initials of tenderer.
2.1.34
Cess @ 1% (One percent) shall be deducted at source from every bill of the Contractor by the
Executive Engineer Under “Building and Other Construction for workers Welfare Cess
Act1996
(2) English
I .................................................... age......................................address
authorized signatory and I am submitting the documents in envelope no.1 for the
purpose of scrutiny of the contract. I hereby agree to the conditions mentioned below
:-
(Signature of contractor)
(seal of company)
Name of work:- Construction of Toilet And Covering Of Shade and Providing And Fixing Iblock
And Various Civil work at NMC Vyamashala at Tulsibag Mahal in Pr. No. 18
Schedule ‘A’
Material to be brought by contractor
1 2 3 4 5
1
1) All the materials are to be
procured and brought by the
contractor at the site at his own
risk and cost.
APPENDIX -I
¼1½ ejkBh
uequklR;izfrKki= ¼:-100@&P;kLVWEi isioj½
lR;izfrKki= (Affidavit)
eh-------------------------------------------------o; o”ksZ ---------------------------jkg.kkj ;k
lR;izfrKki=k}kjsfygwunsrks dh] eh----------------------;k QeZpk@daiuhpkekydvlwu----------------------- ;k
dkeklkBhfufonklknjdjhrvkgs- R;kfufonsP;kfyQkQk Ø- 1 e/;s dkxni=s lknjdsyhvkgsrrh
[kjh] cjkscj o iw.kZvkgsr] R;ke/;s dks.kR;kgh =qVh] pqdkukghr] ;kph eh [kk=h dsyy s hvlwuvls
‘kiFkiwoZd [kkyhyvVh o ‘kFkhZlgekU; djhrvkgs- ;k dkxni=kae/;s dkghpqdhph]
fn’kkHkwydj.kkjh] [kksVh o rlspviw.kZekfgrhvk<Gy;kl eh Hkkjrh;
naMlafgrkvarxZrdk;ns’khjdk;Zokghlik= jkghu-
1- tj da=kV dkyko/khnjE;ku] eh
ekÖ;kdk;kZy;kusfdaokekÖ;kdeZpkÚ;kauhlkoZtfudcka/kdkefoHkkxkykdks.krhgh
[kksVhekfgrhfdaokns;dkleosrrlspi=O;ogkjkr [kksVh@cukoVlkfgR; [kjsnhphdkxni=s
lknjdsyhvly;kl] eh Hkkjrh; naMlafgrkvarxZrdk;ns’khjdk;Zokghlik= jkghu-
2- tj da=kV dkyko/khnjE;kuvkf.kdkelekIrhuarj] vafrens;d
ns.;kP;krkj[ksi;Zarlknjdsysysdks.krsghdkxni=s [kksVh@cukoV] Qlohvk<GY;kl] eh Hkkjrh;
naMlafgrkvarxZrdk;ns’khjdk;Zokghlik= jkghu-
3- tjdkelekIrhuarjnks”knkf;Rodkyko/khnjE;kufdaokR;kuarjdks.kR;kghosGh]
dks.krhghekfgrhfdaokdkxni=s [kksVh@cukoV] Qlohfadaokfn’kkHkwydj.kkjhvk<GY;kl] eh Hkkjrh;
naMlafgrkvarxZrdk;ns’khjdk;Zokghlik= jkghu-
DECLARATION
CONTRACTOR’S SIGNATURE.
3 - STANDARD
B-1 CONDITIONES OF CONTRACT
CONDITIONS OF CONTRACT
Clause1Security Deposit:-The person / persons whose tender may be accepted (herein after called
the Contractor, which expression shall unless excluded by or repugnant to the context include his,
heirs executors, administrators, Contractor and assigns) shall (A) within 10 days (which may be
extended by the Superintending Engineer concerned upto 15 days if the Superintending Engineer
thinks fit to do so) of the receipt by him of the notification of the acceptance of his tender deposit
with the Executive Engineer in cash or Govt. securities endorsed to the Executive Engineer (if
deposited for more than 12 months) of sum sufficient which will make up the full security deposit
specified in tender or (B) permit NAGPUR MUNICIPAL CORPORATION at the time of making any
payment to him for work done under the contract to deduct such as will amount to 10 ( Ten)
percent of all moneys so payable, such deduction to be held by NAGPUR MUNICIPAL CORPORATION
by way of security deposit, provided always, that, in the event of the Contractor depositing a lump
sum by way of security deposit as contemplated at (A) above, then and in such case, a the sum so
deposited shall not amount to 10 (Ten) percent, of the total estimated cost of the work, it shall be
lawful for NAGPUR MUNICIPAL CORPORATION at the time of making any payment to the Contractor
for work done under the contract, to make up the payment to the Contractor for work done under
the contract to make up the full amount of 10 (ten) percent, by deducting a sufficient sum from
every such payment as last aforesaid, until the full amount of the security deposit is madeup.
All compensation or other sum of money payable by the Contractor to NMC under the terms
of his contract may be deducted from or paid by the sale of sufficient part of his security deposit or
from the interest arising there from or from any sums which may be due or may become due by
NMC to the Contractor under any other contract or transaction of any nature on any account
whatsoever, and in the event of his security deposit being reduced by reason of any such deduction
or sale as aforesaid the Contractor shall within ten days thereafter make good in cash or NAGPUR
MUNICIPAL CORPORATION securities endorsed as aforesaid, any sums or sums which may have
been deducted from or raised by sale of his security deposits or may part thereof. The security
deposit referred to, when paid in cash may, at the cost of the depositor, be converted into interest
bearing securities provided that the depositor has expressly desired this in writing.
If the amount of the Security Deposit to be paid in lump sum within the period specified at
(A) above is not paid, the tender / Contract already accepted shall be considered as cancelled and
legal step will be taken against the Contractor for recovery of the amounts. The amount of the
Security Deposit lodged by a Contractor shall be refunded along with the payment of the final bill, if
the date up to which the Contractor has agreed to maintain the work in good order is over. If such
date is not over, only 50% amount of security deposit shall be refunded along with the payment of
the final bill.
The amount of security deposit retained by the NAGPUR MUNICIPAL CORPORATION shall be
released after expiryof period up to which the Contractor has agreed to maintain the work in good
order is over. In the event of the Contractor failing or neglecting to complete rectification work
within the period up to which the Contractor has agreed to maintain the work in good order, then
subject to provisions of clause 17 and 20 here of the amount of security deposit retained by
NAGPUR MUNICIPAL CORPORATION shall be adjusted towards the excess cost incurred by the NMC
on rectification work.
Contractor No. of Correction Executive Engineer
22
Clause 2Compensation for delay:-The time allowed for carrying out the work as entered in the
tender shall be strictly observed by the contractor and shall be reckoned from the date on which the
order to commence work is given to the contractor. The work shall throughout the stipulated period
of the contract be proceeded with, all due diligence (time being deemed to be the essence of the
contract on part of the contractor) and the contractor shall pay as compensation an amount equal
to one percent, or such smaller amount as the Superintending Engineer (whose decision in writing
shall be final) may decide, of the amount of the estimated cost of the whole work as shown in the
tender for every day that work remains un- commenced, or unfinished after the proper dates. And
further to ensure good progress during the execution of the works, the contractor shall be bound in
all cases, in which the time allowed for any work exceeds one month to complete. 1/4 of the work
in 1/4 of the time 1/2 of the work in 1/2 of the time 3/4 of the work in 3/4 of the time Full work in
time limit specified in NIT including Monsoon. In the event of the contractor failing to comply with
these conditions he shall be liable to pay as compensation an amount equal to one percent, or such
smaller amounts as the Superintending Engineer (whose decision in writing shall be final) may
decide of the said estimated cost of the whole work for every day that the due quantity of work
remains incomplete. Provided always that the total amount of compensation to be paid under
provision of this clause shall not exceed 10 percent of the estimated cost of the work shown in the
tender. Superintending Engineer should be the final authority in this respect irrespective of the fact
that the tender is accepted by Executive Engineer.
Clause 3 : Action when whole of Security Deposit is forfeited In any case in which under any clause
or clauses of this contracts the contractor shall have rendered himself liable to pay compensation
amounting to the whole of his security deposit (whether paid in one sum or deducted by
installments) or in the case of abandonment of the work owing to serious illness or death of the
contractor or any other cause, the Executive Engineer on behalf of the Governor of Maharashtra
shall have power to adopt any of the following courses as he may deem best suited to the interest
of NAGPUR MUNICIPAL CORPORATION.
a) To rescind the contract (of which rescission notice in writing to the contractor under the hand of
the Executive Engineer shall be conclusive evidence) and in that case the security deposit of the
Contractor shall stand forfeited and be absolutely at the disposal of NAGPUR MUNICIPAL
CORPORATION.
b) To carry out of work or any part of the work NM ally debiting the contractor with the cost of the
work, expenditure incurred on tools and plant, and charges on additional supervisory staff including
the cost of work charged establishment employed for getting unexecuted part of the work
completed and crediting him with the value of the work done NMC ally in all respects in the same
manner and at the same rates as if it had been carried out by the contractor under the terms of the
contract. The certificate of the Executive Engineer as to the cost of the work and other
allied expenses so included and the value of the work so done NMC ally shall be final and
conclusive against the contractor.
c) To order that the work of the contractor be measured up and to take such part thereof as shall be
unexecuted out of his hands and to give it to another contractor to complete, in which case all
expenses incurred on advertisement for fixing a new contracting agency, additional supervisory staff
including the cost of work charged establishment and cost of the work executed by the new
contract agency will be debited to contractor and the value of the work done or executed in the
same manner and at the same rates as if it had been carried out by the through the new contractor
shall be credited to the contractor in all respects and in the same manner and at the same rates as if
had been carried out by the contractor under the terms of his contract. This certificate of the
Contractor No. of Correction Executive Engineer
23
Executive Engineer as to all the cost of the work and other expenses incurred as aforesaid for or in
getting the unexecuted work done by the new contractor and as to the value of the work done by
the new contractor and as to the value of the work so done shall be final and conclusive against
contractor.
In case the contract shall be rescinded under clause (a) above, the contractor shall not be entitled to
recover or be paid any sum for any work thereto actually performed by him under this contract
unless and until the Executive Engineer shall have certified in writing the performance of such work
and the amount payable to him in respect thereof he shall only be entitled to be paid the amount so
certified. In the event of either of the courses referred to in clause (b) or (c) being adopted and the
cost of the work executed NMC or through a new contractor and other allied expenses exceeding
the value of such work creditedto the contractor, the amount of excess value shall be deducted
from any money due to the contractor by the Govt. under the contract or otherwise, howsoever or
from his security deposit or the sale proceeds thereof provided howsoever, that the contractor shall
have no claim against NAGPUR MUNICIPAL CORPORATION even if certified value of the work done
NMC or through a new contract except the certified cost of such work and allied expenses provided
always that whichever of the three courses mentioned in clause (a) (b) or (c) is adopted by the
Executive Engineer, the contractor shall have no claim to compensation for any loss sustained by
reason of him having no claim to compensation for any materials, or entered into engagement or
made any advance on account of or with a view of the execution of the work or the performance of
contract.
Clause 4 :Action when process of particular work is unsatisfactory If the progress of any particular
portion of the work is unsatisfactory the Executive Engineer shall not withstanding that the general
progress of the work is satisfactory in accordance with clause 2 be entitled to take action under
clause 3 (b) after giving the contractor 10 days notice in writing and the contractor will have no
claim for compensation for any loss sustained by him owing to such action.
Clause 5:Contractor Remains liable to pay compensation if action not taken under clause 3 Power
to take possession of or required removal of or all contractors plantIn any case in which any of the
powers conferred upon the Executive Engineer by clause 3 and 4 hereof shall have become
exercisable and the same shall not have been exercised the e non-exercise there o shall not
constitute a waver of any of the conditions hereof and such powers shall not-with standing be
exercisable in any future case of default by the contractor for which by under any clause or clauses
hereof he is declared liable to pay compensation amounting to the whole of his security deposit and
the liability of the contractor for past and future compensation shall remain unaffected. In the event
of the Executive Engineer taking action under sub-clause (a) or (c) of clause (3) he may, if he so
desires, take possession of all or any tool plant, materials and stores in or upon the works or the site
thereof or belonging to the contractor or procured by him and intended to be used for the
execution of the works or the site thereof or belonging to the contractor, or procured by him and
intended to be used for the execution of the work or any part thereof, paying or allowing, for the
same in account at the contract rates, or in the case of contract rates not being applicable at current
market rates, to be certified by the Executive Engineer whose certificate there of shall be final. In
the alternative the Executive Engineer may, by notice in writing to the contractor or to his clerk of
the works, foreman or other authorized agent require him to remove such tools, plant materials or
stores from the premises within a time to be specified in such notice and in the event of contractor
failing to comply with any such requisition the Executive Engineer may remove them at the
contractor’s expenses or sale them by auction or private sale, at risk and account of the contractor
in all such removal and the amount of the proceeds and expenses of any such sale be final and
conclusive against the contractor.
Contractor No. of Correction Executive Engineer
24
Clause 6Extension of time limit: If the contractor desires an extension of the time for completion of
the work on the ground of his having unavoidable hindering in it execution or on the other ground,
he shall apply in writing to the Executive Engineer before the expiration of the period stipulated in
the tender or before the expiration of 30 days from the date to which he was hindered as aforesaid
or on which the cause for asking ever extension occurred, whichever is earlier and the Executive
Engineer may, if in his opinion there are reasonable ground for granting an extension, grant such
extension as he thinks necessary or proper. The decision of the Executive Engineer in this matter
shall be final.
Clause 6 A : In the case of delay in handing over the land required for the work due to unforeseen
cause, the contractor shall not be entitled for any compensation what so ever from the NAGPUR
MUNICIPAL CORPORATION on the ground that the machinery or the Labour was idle for certain
period. Contractor may, however apply for extension of time limit which may be granted on the
merit of the case.
Clause 7 Final Certificate: On completion of the work the contractor shall be finished with a
certificate by the Executive Engineer (Hereinafter called the Engineer-in-charge) in such completion
but no certificate shall be given nor shall the work be considered to be complete until the contractor
shall have removed from the premises on which the work shall have been executed, all scaffolding,
surplus materials and rubbish and shall have cleaned of the dirt from all wood work, doors, floors or
other parts of any building in or upon which the work has been executed or on which he may have
had possession for the purpose of executing the work or until the work shall have been measured by
the Engineer-in-charge or where the measurements have been taken by his subordinates until they
have received the approval of the Engineer -in charge the said measurement being binding and
conclusive against the contractor. If the contractor fails to comply with the requirement of the
clause as to the removal of scaffolding, surplus material and rubbish and cleaning of dirt on or
before the date fixed for the completion of the work. The Executive-in- charge may at the expense
of the contractor, remove such scaffolding, surplus materials and rubbish and dispose off the same
as he think fit and clean of such dirt as aforesaid and the contractor shall forthwith pay the amount
of all expenses so incurred but shall have no claim in respect of any such scaffolding or surplus
materials as aforesaid except for any sum actually realized by the sale thereof.
Clause8A- Henceforth the construction of concrete road work, 20% amount of PQC work shall be
retained from running bills in addition to the amount retained for test results of PQC for execution
& completion of remaining provisions to be executed within ROW in the tender such as Paver blocks
or Asphalting, ducts, drains or footpath work, divider and beautification in divider portion, approach
road and square development etc.
However, in case where execution & completion of such works are delayed due to technical reasons
beyond the scope of the contract, Executive Engineer in-charge may take suitable decision in this
regard.
Clause 8B - Additional 20% amount of Asphalting work shall be retained from running bills in
addition to the amount retained for test results of B.M, D.B.M, B.C. for satisfaction execution of
development of side shoulders in expected slope and compaction thereof, proper slope of
formation, drain work, as also execution of provision in the tender such as road marking paint, fixing
of Km. stone, furlong stone, Tree plantation etc. Payment of this 20% retained amount shall be
made only after satisfactory completion of above work.
Clause 8C - In case provision available in the tender for Tree plantation, the same
be executed through Contractor or by appointing any agency through contractor
and planning of open space be kept around trees for breathing. Payment may be
retained for this too in the work of Asphalting and PQC.
Clause 9Payments at reduce rates on account of items of work not accepted as completed to be at
the discretion of the engineer-in-charge: The rates for several items of work estimated to cost more
than Rs. One thousand agreed to within shall be valid only when the item concerned is accepted as
having been completed fully in accordance with the sanctioned specifications. In case where the
items of work are not accepted as so completed the Engineer-in-charge may make payment on
account of such items at such reduced rates as he may consider reasonable in preparation of final or
on account bills. Bill to be submitted monthly Bill to be on printed form.
Clause 10 Bills to be submitted monthly: A bill shall be submitted by the contractor each month on
or before the date fixed by the Engineer-in-charge for all work executed submitted in the previous
month, and the Engineer-in-charge shall take or cause to be taken the requisite measurement for
the purpose of having the same verified and the claim so far as it is admissible shall be adjusted, if
possible within ten days from the presentation of the bill. If the contractor does not submit the bill
within time fixed as aforesaid, the Engineer-in-charge may depute a subordinate to measure up the
said work in the presence of the contractor or his duly authorised agent whose counter signature to
the measurement list shall be sufficient warrant and the Engineer-in-charge may prepare a bill from
such list which shall be binding on the contractor in all respects.
Clause 11Bill to be on printed form: The contractor shall submit all bills on the printed forms to be
had on application at the office of the Engineer-in-charge. The charges to be made in the bills shall
always be entered at the rates specified in the tender or in the case of any extra work ordered in
pursuance of these conditions and not mentioned or provided for in the tender, at the rate
hereinafter provided for such work.
Clause 12 A Store Material : All store of contractor material such as cement ,steel Bitumen etc
Supplied by the contractor at his own cost should be kept by the contractor under lock and key and
will be accessible for inspection by the Executive Engineer or his agent at all times. These materials
shall be purchased from Authorised Agencies only . In Case of Bitumen , if insert be purchased from
Government Refineries Only & Original bill to be Submitted by the Contractor along with R. A. Bill.
Clause 14Alteration in Specifications and designsnot to invalidate contract and Rate for work not
entered in estimateorscheduleof rates of NMC: The Engineer-in-charge shall have power to make
any alterations in, or additions to, location of site, the original specifications, drawings, designs and
instructions, that may appear to him to be necessary or advisable during the progress of the work
and the contractor shall be bound to carry out the work in accordance with any instructions in this
connection which may be given to him in writing signed by the Engineer-in-charge and such
alteration shall not invalidate the contract, and any additional work which the contractor may be
directed to do in the manner above specified as a part of the work shall be carried out by the
contractor in the same conditions in all respects on which he agreed to the main work and at the
same rates as per specified in the tender for the main work. And if the additional or altered work,
includes any class of work for which no rate is specified in this contract, then such class of work shall
Contractor No. of Correction Executive Engineer
27
be carried out at the rates entered in Schedule of Rates of the division or at the mutually agreed
upon between the Engineer-in-charge and the contractor, whichever are lower. If the additional or
altered work, for which no rate is entered in the schedule of rates of the division, is ordered to be
carried out before the rates are agreed upon, then the contractor shall within seven days of the
date of receipt by him of order to carry out work inform the Engineer-in-charge of the rate which it
is his intention to charge for such class of work, and if the Engineer-in-charge does not agree to this
rate he shall by notice in writing be at liberty to cancel his order to carry out such class of work and
arrange to carry it out in such manner as he may consider advisable, provided always that if the
contractor shall commence work or incurs any expenditure in regard thereto before the rate shall
have been determined as lastly here in-before mentioned then in such case he shall only be entitled
to be paid in-respect if the work carried out or expenditure incurred by him prior to the date of the
determination of the rate as aforesaid according to such rate or rates as shall be fixed by the
Engineer-in-charge. In the event of a dispute the decision of the Competent authority of the NMC
will be final.
Where however, the work is to be executed according to the designs, drawings, and
specification recommended by the contractor and accepted by the competent authority the
alterations above referred to shall be within the scope of such designs, drawing and specifications to
the tender.
The time limit for the completion of work shall be extended in the proportion that the
increase in its cost occasioned by alterations or additions bears to the cost of the original contract
work and the certificate of the Engineer-in-charge as to such proportion shall be conclusive.
However no extra payment on account of extension of site shall be entertained.
receipt of such notice in respect of the work already done by the contractor. Such payment shall not
in any manner prejudice the right of the contractor to any further compensation under the
remaining provision of this clause.
(3) Where the Engineer in charge requires the contractor to suspend the work for a period in excess
of 30 days at any time or 60 days in the aggregate, the contractor shall be entitled to apply to the
Engineer in charge within 30 days of the resumption of the work after such suspension for payment
of compensation to the extent of pecuniary loss suffered by him in respect of working machinery
rendered idle on the site or on account of his having, had to pay the salary or wages of labour
engaged by him during the said period of suspension. Provided always that, the contractor shall not
be entitled to any claim in respect of any such working machinery, salary or wages for the first 30
days whether consecutive or in the aggregate of such suspension or in respect of any suspension
what-so-ever occasioned by unsatisfactory work or any other default on his part. The decision of the
Engineer in charge in this regard shall be final and conclusive against thecontractor.
(4) In the event of (i) Any total stoppage of work on notice from the Engineer in charge under sub-
clause(1). (ii) (ii) Withdrawal by the contractor from the contractual obligation to complete the
remaining unexecuted work under sub-clause (2) on account of continued suspension of work for a
period exceeding 90 days(iii) Curtailment in the quantity of any item or items originally tendered on
account of any alteration, omission or substitution in the specifications, drawings, designs or
instructions under clause 14(1) where such curtailment exceeds 25% in quantity and the value of
the quantity curtailed beyond 25% at the rate for the items specified in the tender is more than Rs.
Five Thousand(Rs.5000/-)It shall be open to the contractor within 90 days from the service of (i) the
notice of stoppage of work or (ii) the notice of withdrawal from the contractual obligation under the
contract on account of the continued suspension of the work (iii) notice under clause 14(1) resulting
such curtailment or produce to the Engineer in charge satisfactory documentary evidence, that he
had purchased or agreed to purchase material for use in the contracted work, before receipt by him
of the notice of stoppage, suspension or curtailment and require the NAGPUR MUNICIPAL
CORPORATION to take over on payment such material at the rates determined by the Engineer,
provided however, such rates shall in no case exceed the rates at which the same were acquired by
the contractor. The NAGPUR MUNICIPAL CORPORATION shall thereafter take over the material so
offered, provided the quantities offered are not in excess of the requirement of the unexecuted
work as specified in the accepted tender and are of quality and specification approved by the
Engineer in charge.
Clause 16Time limit for unforeseen claims: Under no circumstance what so ever shall the
contractor be entitled to any compensation from NAGPUR MUNICIPAL CORPORATION on any
account unless the contractor shall have submitted claim in writing to the Engineer -in Charge within
one month of the cause of such claim occurring.
Clause 17 Action and compensation payable in case of bad work: If any time before the security
deposit or any part thereof is refunded to the contractor it shall appear to the Engineer -in Charge
or his subordinate in-charge or the work, that any work has been executed with unsound, imperfect
unskilled workmanship or with materials of inferior quality, or that any materials or articles
provided by him for the execution of the work are unsound or of a quality inferior to that contracted
for or are otherwise not in accordance with the contractor, it shall be lawful for the Engineer-in-
charge to intimate this fact in writing to the contractor and then notwithstanding the fact that the
work, materials or articles complained of may have been inadvertently passed, certified and paid
for, the contractor shall be bound forthwith to rectify, or remove and reconstruct the work so
specified in whole or in part, as the case may be require or if so required, shall remove the materials
Contractor No. of Correction Executive Engineer
29
or articles so specified and provided other proper and suitable materials or article at his own charge
and cost and in the event of his failing to do so within a period to be specified by the Engineer-in-
charge in the written intimation aforesaid, the contractor shall be liable to pay compensation at the
rate of 1% on the amount of the estimate for every day not exceeding 10 days, during which the
failure so continues and in the case of any such failure, the Engineer-in-charge may rectify or
remove and re- execute the work or remove and replace the materials or article complained of, as
the case may be, at the risk and expense in all respects of the contractor should the Engineer-in-
charge consider that any such inferior work or materials as described above may be accepted or
made use of it shall be within his discretion to accept the same at such reduced rates as he may fix
therefore and the certificate of the Engineer-in –charge shall be binding upon the contractor.
Clause 18Work to be open to inspection, Contractor or responsible agent to be present: All works
under or in course of execution or executed in pursuance of the contract shall at all times be open
to the inspection to inspection and supervision of the Engineer-in-charge and his subordinates
Quantity check agencies PMC(it appointed) and the contractor shall at all times during the usual
working hours, and at all other times at which reasonable notice of the intention of the Engineer-in-
charge of his subordinates to visit the works shall have been given to the contractor, either himself
be present to receive order and instructions, or have a responsible agent duly accredited in writing,
present for that purpose. Orders given to the contractor’s duly authorized agent shall be considered
to have the same force and effect as if they had been given to the contractor himself.
Clause 19Notice to be given before the work is cover up : The contractor shall give not less than 5
days notice in writing to the Engineer-in-charge or his subordinates in charge of the work before
covering up or otherwise placing beyond the reach of measurement any work in order that the
same may be measured and correct dimensions hereof taken before the same is so covered up or
placed beyond the reach of measurement and shall not cover up or placed beyond the reach of
measurement any work without the consent in writing of the Engineer-in-charge or his subordinate
in charge of the work, and if any work shall be covered up or placed beyond the reach of
measurement without such notice having been given or consent obtained the same shall be
uncovered at the contractors expense and in default thereof payment or allowance shall be made
for such work or for the materials with which the same was executed.
Clause 20Contractor liable for damage done and for imperfection : If during the period of 60
months from the date of completion as certified by the Engineer-in-charge pursuant to the clause 7
of the contract or 28 monthsafter commissioning of the work whichever is earlier in the opinion of
the Engineer-In- charge , the said work is defective in any manner whatsoever, the contractor shall
forthwith on receipt on the notice in that behalf from the Engineer-In- charge, duly commence
execution and completely carry out at his cost in every respect all the work that may be necessary
for rectifying and setting right the defects specified therein including dismantling and reconstruction
of unsafe portions strictly in accordance with and in the manner prescribed and under the
supervision of the Engineer-In- charge. In the event of the contractor failing and neglecting to
commence execution of the said rectification work within the period prescribed therefore in the
said notice the Engineer-In- charge may get the same executed and carried out NMC or by other
agency at the risk on account and at the cost of the contractor. The contractor shall forthwith on
demand pay to the NAGPUR MUNICIPAL CORPORATION the amount of such costs, charges and
expenses sustained or incurred by the NAGPUR MUNICIPAL CORPORATION of which the certificate
of the Engineer-In- charge shall be final and binding on the contractor. Such costs, charges and
expense shall be deemed to be arrears of land revenue and in the event of contractor failing or
Contractor No. of Correction Executive Engineer
30
neglecting to pay the same on demand as aforesaid without prejudice to any other rights and
remedies of the Nagpur Municipal Corporation. The same may be recovered from the contractor as
arrears of land revenue. The NAGPUR MUNICIPAL CORPORATION shall also be entitled to deduct the
same from any amount which may then be payable or which may thereafter become payable by
NAGPUR MUNICIPAL CORPORATION to the contractor either-in-respect of the said work or any
other work whatsoever, or from the amount of the security deposit retained by NAGPUR
MUNICIPAL CORPORATION.
Clause 21Contractors to supply plant, ladders, scaffolding etc. And is liable for damages arising
from non- provisions of lights, fencing etc : The contractor shall supply at his own cost all materials
(except such special material if any) as may be supplied from the Public Works NMC Stores, in
accordance with the contract, plant, tolls, appliances, implements, ladders, cordage, tackle,
scaffolding and any temporary works which may be required for the proper execution of the work,
in the original, altered or substituted form, whether included in the specification or other
documents forming part of the contract or referred to in these conditions or not and which may be
necessary for the purpose of satisfying or complying with requirements of the Engineer-in-charge as
to any matter on which under these Conditions he is entitled to be satisfied, or which be entitled to
require together with carriage therefor, to and from the work. The contractor shall also supply
without charge the requisite number of persons with the means and materials necessary for the
purpose of setting out works and counting, weighing and assisting in the measurement or
examination at any time and from time to time of the work or materials. Failing this the same may
be provided by the Engineer-in-charge at the expense of the contractor and the expenses may be
deducted from any money due to the contractor under the contract or from his security deposit or
the proceeds of sale thereof or of sufficient portion thereof. The contractor shall provide all
necessary fencing and lights required to protect the Public from accident and shall also be bound to
bear the expenses of defense every suit, action or other legal proceedings at law that may be
brought by any person for injury sustained owing to the neglect of the above precautions, and to
pay damages and cost such person or which may with the consent of the contractor be paid in
compromising any claim by any such person.
Clause 21A: The contractor shall provide suitable scaffolds and working platforms, gangways, and
stairways and shall comply with the following regulations in connection there with :
a) Suitable scaffolds shall be provided for workmen for all work that cannot be safely done from a
ladder or by other means
Clause 24Employment of female labour: The employment of female laborers on works in the
neighborhood of soldier’s barracks should be avoided as far as possible.
Clause 25Work on Sunday: No work shall be done on a Sunday without the sanction in writing of
the Engineer-in-charge.
Clause 26Work not to be sublet. Contractmay rescind and security deposit forfeited for subletting
it without approval or for bribing a public officer or if contractor becomes insolvent: The contract
shall not be assigned or sublet without the written approval of the Engineer-in-charge. And if the
contractor shall assign or sublet his contract, or attempt so to do, or become insolvent or
commence any proceedings to be adjudicated and insolvent or make any composition with his
creditors, or attempt so to do the Engineer-in-charge may be notice in writing rescind the contract.
Also if any bribe, gratuity, gift, loan, perquisite, reward or advantage, pecuniary or otherwise, shall
either directly or indirectly be given, promised by the contractor or any of his servants or agents to
any public officer or person in the employment of NAGPUR MUNICIPAL CORPORATION in any way
relating to his office or employment, or if any such officer or person shall become in any way
directly or indirectly interested in the contract, the Engineer-in-charge may be giving notice in
writing rescind the contract. In the event of a contract being rescinded, the security deposit of the
contractor shall thereupon stand forfeited and be absolutely at the disposal of the NAGPUR
MUNICIPAL CORPORATION and same consequences shall as ensure as if the contract has been
rescinded under clause 3 hereof and in addition the contractor shall not be entitled to recover or be
paid for any work therefore actually performed under the contract.
Contractor No. of Correction Executive Engineer
33
Clause 32Lump sums in estimates : Where the estimate on which a tender is made includes lump-
sumps in respect of parts of the work the contractor shall be entitled to payment in respect of items
of work involved or the part of the work in question at the same rates as are payable under this
contract for such items, or if part of the work question is not in the opening of the Engineer-in-
charge capable of measurement the Engineer-in-charge may at his discretion pay lump sum amount
entered in the estimate, and the certificate in writing of the Engineer-in-charge shall be final and
conclusive against the contractor with regard to any sum or sums payable to him under the
provision of this clause.
Clause 33Action where no specification: In the case of any class of work for which there is no such
specification as in mentioned in Rule-1, such work shall be carried out in accordance with the
Divisional specifications, and in the event of there being no Divisional specification, then in such
case the work shall be carried out in all respects in accordance with the instruction and requirement
of the Engineer-in- charge.
Clause 34 Definition of work: The expression ‘works’ or ‘work’ where used in these condition shall,
unless there be something in the subject or context repugnant to such construction be constructed
to mean the work or the work contractor to be executed under or in virtue of the contract, whether
temporary or permanent and whether original altered substituted or additional.
Clause 35Contractor’s percentage whether applied to net or gross amount of bill: The percentage
referred to in the tender shall be deducted from / added to the gross amount of the bill before
deducting the value of any stock issued.
Clause 36Quarry fees and royalties: All quarry fees, royalties, Octroi dues and ground rent for
stacking materials if any, should be paid by the contractor.
Clause 37 A: The contractor shall be responsible for and shall pay expenses of providing Medical aid
to any workmen who may suffer a bodily injury as a result on an accident. If such expenses are
incurred by NAGPUR MUNICIPAL CORPORATION the same shall be recoverable from the contractor
forthwith and be deducted without prejudice to any other remedy of NAGPUR MUNICIPAL
CORPORATION from any amount due or that may become due to the contractor.
Clause 37 B : The contractor shall provide all necessary personal safety equipment and first-aid
apparatus available for the use of the persons employed on the site and shall maintain the same in
condition suitable for immediate use at any time and shall comply with the following regulation in
connection therewith.
(a)The worker shall be required to use the equipment so provided by the contractor and the
contractor shall take adequate steps to ensure proper use of the equipment by those concerned.
(b) When work carried on in proximity to any place where there is no risk of drawing, all necessary
Contractor No. of Correction Executive Engineer
35
equipment’s shall be provided and kept ready for use and all necessary steps shall be taken prompt
rescue of any person indanger.
(c) Adequate provision shall be made for prompt first-aid treatment for all injuries likely to be
sustained during the course of the work.
Clause 37C: The contractor shall duly comply with the provision of “The Apprentices Act 1961 (III of
1961) the rules made there under and the orders that may be issued from time under the said Act
and the said Rules and on his failure or neglect to do so he shall be subject to all the liabilities and
penalties provided by the said Act and said Rules”.
Clause 38 : 1) Quantities in respect of the several items shown in the tender are approximate and
no revision in the tendered rate shall be permitted in respect of any of the items so long as subject
to any special provision contained in specifications prescribing different percentage of permissible
variation, the quantity of the item does not exceed the tender quantity by more than 25 percent
and so long as the value of the excess quantity beyond this limit at the rate of item specified in the
tender rates does not exceed Rs. 5,00,000/-
2) The contractor shall, if ordered in writing by the Engineer / Executive Engineer so to do, also
carry out any quantities in excess of the limit mentioned in sub-clause (1) here of on the same
conditions as and in accordance with the specification in the tender and at the rate (i) derived from
the rates entered in the current schedule of rates and in the absence of such rates. (ii) At the rate
prevailing in the market the said rates being increase or decreased as the case may be by the
percentage which the total tendered amount bears to the estimated cost of the work as put to
tender based upon the schedule of rates applicable to the year in which the tenders were invited.
3) Claims arising out of reduction in the tendered quantity of any item be beyond 25 percentage will
be governed by the provision of clause 15 only when the cost of such reduction beyond 25 percent
at the rate of the item specified in the tender is more than Rs. 50,000/-
4) This clause is not applicable to extra items.
5) There is no change in the rate if the excess is more than 25% of the tendered quantity, but the
value of the excess work at the tendered rates does not exceed Rs. 5,00,000/- .
6) No variations would be entertained for any/all unforeseen items/conditions.
Clause 39Employment of female or other labour: The contractor shall employ any female, convict
or other labour of a particular kind of class if ordered in writing to do so by the Engineer-in-charge.
Clause 40 Claim for compensation for delay in starting work : No compensation shall be allowed for
any delay caused in the starting of the work on account of acquisition of land and in the case of the
clearance work of any delay in according sanction to estimates.
Clause 41 Claim for compensation for delay in the execution of work: No compensation shall be
allowed for any delay in execution of the work on account of water standing in borrows pits or
compartments. The rates are inclusive for hard or cracked soil excavation in mud, subsoil water or
water standing in borrow-pits and no claim for an extra rate shall be entertained unless otherwise
expressly specified.
Clause 42Entering upon or commencing any portion of work: The contractor shall not enter upon
or commence any portion of work except with the written authority and instructions of the
Engineer-in-charge or of his subordinate in charge of the work failing such authority the contractor
shall have no claim to ask for measurements of or payment for work.
Clause43Minimum age of persons employed, the employment of donkey and/or other animals
and the payment of fair wages:
(i) No contractor shall employ any person who is under the age of 18 years.
(ii) No contractor shall employ donkeys or other animals with breeching of string or thin rope. The
breeching must be at least 3 inches wide and should be of tape (Newar)
(iii) No animals suffering from sores, lameness or emaciation or which is immature shall be
employed on the work.
(iv) The Engineer-in-charge or his agent authorized to remove from the work any person or animal
found working which does not satisfy these conditions and no responsibilities shall be accepted by
the NAGPUR MUNICIPAL CORPORATION for any delay caused in the completion of the work by such
removal.
(v) The contractor shall pay fair and reasonable wages to the workmen employed by him in the
contract undertaken by him. In the event of any disputes arising between the contractor and his
workmen on the grounds that the wages paid are not fair and reasonable the dispute shall be
referred without delay to the Executive Engineer who shall decide the same. The decision of the
Executive Engineer shall be conclusive and binding on the contractor, but such decision shall not in
any way affect the condition in the contract regarding the payment to be made by the NAGPUR
MUNICIPAL CORPORATION at the sanctioned tender rates.
(vi) The contractor shall provide drinking water facilities to the workers. Similar amenities shall be
provided to the workers engaged on large work in urban areas.
Clause 44Method of payment: Payments to contractor shall be made by RTGS/ Cheques drawn on
any treasury within the Division convenient to them. Provided the amount exceeds Rs. 100/-
Amount not exceeding Rs. 100/- will be paid in cash.
Clause 45 Acceptance of conditions compulsory before tendering the work: Any contractor who
does not accept these conditions shall not be allowed to tender for works.
Clause 46 Employment of scarcity labour: If NAGPUR MUNICIPAL CORPORATION declares a state of
scarcity or famine to exist in any village situated within 1 Km. of work, the contractor shall employ
upon such parts of the work as suitable for unskilled labour any person certified to him by the
Engineer in charge or by any person to whom Executive Engineer may have delegated this duty in
writing to be in need of relief and shall be bound to pay to such persons wages not below minimum
which may arise in connection with the implementation of this clause shall be decided by the
Executive Engineer whose decision shall be final and binding on the contractor.
Clause 47: The price quoted by the contractors shall not in any case exceed the control price, if any,
fixed by NAGPUR MUNICIPAL CORPORATION or reasonable price which is permissible for him to
charge as private purchaser for the same class and description of goods under the provisions of
Hoarding and profiteering Prevention Ordinance 1984 as amended from time to time. If the price
quoted exceeds the controlled price or the price permissible under Hoarding and Profiteering
Prevention Ordinance, the contractor will specifically mention this fact in his tender along with
reasons for quoting such higher price. The purchaser at his tender along with reasons for quoting
such higher price. The purchaser at his discretion will in such higher price. The purchaser at his
discretion will in such case exercises the right of revising the price at any stage so as to confirm with
the controlled price on the permissible under the Hoarding and Profiteering Ordinance. This
discretion will be exercised without prejudice to any other action that may be taken against the
contractor.
Clause 48: The rates to be quoted by the contractor must be inclusive of the labour welfare Cess
and other taxes (Other than GST ). No extra payment on this account will be made to the contractor.
Clause 48 A : The contractors are bound to pay to the laborers wages according to the Minimum
Wages Act 1948 applicable to the Zone in accordance with the order issued in NAGPUR MUNICIPAL
CORPORATION P.W.D./Circular No. MWA/ 1063, dated 07/12/1968.
Clause 49: In case of materials that remains surplus with the contractor for those issued for the
work contracted from the date of ascertainment of the materials being surplus be taken as the date
of sale for the purpose of sales tax and the sale tax will be recovered on such sale.
Clause 50: The contractor shall employ the unskilled labour to be employed by him on the said work
only from locally available labors and shall give preference to those persons enrolled under
Maharashtra NAGPUR MUNICIPAL CORPORATION Employment and Self Employment NMC Scheme.
Provided, however, that if the required unskilled laboured are not available locally, the contractor
shall in the first instance employ such number of persons as is available and thereafter may with
previous permission, in writing of the Engineer-in-charge of the said work obtained the rest of
requirement of unskilled the labour from outside the above scheme.
Clause 51: All amount whatsoever which the contractor is liable to pay to the NAGPUR MUNICIPAL
CORPORATION in connection with the execution of the work including the amount payable in
respect of (1) Material and / or stores supplied / issued hereunder by the NAGPUR MUNICIPAL
CORPORATION to the contractor, (2) Hire charges in-respect of heavy plant machinery and
equipment given on hire by the NAGPUR MUNICIPAL CORPORATION to the contractor, for execution
by him of the work and / or on which the advance have been given by the NAGPUR MUNICIPAL
CORPORATION to the contractor shall be deemed to be arrears of the lands revenue and the
NAGPUR MUNICIPAL CORPORATION may without prejudice to any other rights and remedies of the
NAGPUR MUNICIPAL CORPORATION recover the same from the contractor as arrears of land
revenue.
Clause 52: The contractor shall duly comply with all the provisions of the contract labour (Regulation
and Abolition) Act 1970. (37 of 1970) and the Maharashtra Contract Labour (Regulation and
Abolition) Rules 1971 as amended from time to time and all other relevant statutes and statutory
provision concerning payment of wages particularly to workmen employed by the contractor and
working on the site of the work. In particular the Contractor shall pay wages to each worker
employed by him on the site of the work at the rates prescribed under the Maharashtra Contract
Labour (Regulation and Abolition) Rules 1971. If the contractor fails or neglects to pay wages at the
said rates or make short payment and the NAGPUR MUNICIPAL CORPORATION makes such payment
of wages in full or part thereof less paid by the contractor, as the case may be the amount so paid
by the NAGPUR MUNICIPAL CORPORATION to such worker shall be deemed to be arrears of land
revenue and the NAGPUR MUNICIPAL CORPORATION shall be entitled to recover the same as such
from the contractor or deduct the same from the amount payable by the NAGPUR MUNICIPAL
CORPORATION to the contractor hereunder or from any other amounts payable to him by the
NAGPUR MUNICIPAL CORPORATION (Minimum Wages Act, as per NAGPUR MUNICIPAL
CORPORATION Circular (AT / 1284/(120) / Building, dated 14/08/1988).
1) During the tender process, if it is noticed that any false documents are submitted by the
contractor along with tender, contractor shall be liable for action under various clauses of
Indian Pinal Code. In such case, the tender shall be liable for rejection and contractor shall be
put in black list.
2) After issue of work order, if it is noticed that any false documents are submitted by the
contractor along with bills, contractor shall be liable for action under various clauses of
Indian Pinal Code. In such case, if the work is in the initial stage the tender shall be liable for
rejection and contractor shall be put in black list.
3) If during contract period and defect liability period, any false information, false bill of
purchases, supporting proof of purchase, proof of testing submitted by the contractor, he
will be liable for action under Indian Penal Code. The contractor shall also be liable for
action under Indian Penal Code if any papers are found false / fraudulent even after the
completion of contract (finalization of final bill).
4) In all the circumstances stated above, the contractor shall be held fully responsible. The
NMC officers shall not be responsible for the acts of contractor. The NMC officers, who
scrutinize the tender documents shall not be held responsible for the correctness of
documents submitted by the contractor.
TENDERFORM B-1
(iv) If after submitting the tender, the Contractor withdraws his offer or
modifies the same or if after the acceptance of his tender the Contractor fails or
neglects to furnish the balance of security deposit, without prejudice to any
other rights and powers of the NAGPUR MUNICIPAL CORPORATION hereunder,
or in law, NAGPUR MUNICIPAL CORPORATION shall be entitled to forfeit the
full amount of the earnest money deposited by him.
iv) In the event of his tender not being accepted, the amount of earnest money
deposited by the contractors shall, unless it is prior thereof forfeited under the
provision of sub-clause (ii) above, be refunded to him on his passing receipt
therefore.
3) Receipt for payments made on account of any work, when executed by a firm,
should also be signed by all the partners. Except where the contractors are
described in their tender as a firm, in which case the receipts shall be signed in
the name of the firm by one of the partners, or by some other person having
authority to give effectual receipts for the firm.
4) Any person who submits a tender shall fill up the usual printed form including
the column of estimated quantities stating at what rate he is willing to
undertake all item of the work.
5) Tenders which propose any alteration in the work specified in the said form of
invitation to tender, or in the time allowed for carrying out the work or which
contain any other conditions of any sort, will be liable for rejection. No single
tender shall include more than one work, but contractors who wish to tender
for two or more works shall submit a separate tender for each. Tenderers shall
have the name and the number of work to which they refer written outside the
envelope
i. The Executive Engineer, NMC, Nagpuror his duly authorized assistant will
open tenders in the presence of any intending contractors who may be present
at the time and will enter the amount of the several tenders in a comparative
statement in a suitable form. In the event of a tender being accepted, the
Contractor shall thereupon, for the purpose of identification, sign copies of the
specifications and other documents mentioned in Rule1.
ii. The Officer competent to dispose of the tender shall have the right to reject any
or all of the tenders.
iii. No receipt for any payment alleged to have been made by a contactor in regard
to any matter relating to this tender or the contract shall be valid and binding
on NMC unless it is signed by the Executive Engineer.
iv. The memorandum of the work to be tendered for and the schedule of materials
to be supplied by the NMC and their rates shall be filled in and completed by
the office of the Executive Engineer before the tender form is issued if a form
issued to an intending tenderer has not been so filled in and completed he shall
request the said office to have done this before the completes and delivers his
tender
v. All work shall be measured net by standard measure and according to the rules
and customs of the NMC without reference to any local custom.
vi. Under no circumstance shall any Contractor be entitled to claim enhanced
rates for any item in this contract.
vii. All correction and additions or pasted slips should be initialed.
viii. The measurement of work will be taken according to the usual method in the
NMC and no proposal to adopt alternative methods will be accepted. The
Executive Engineer’s decision as to what is “the usual method in use in NMC
will be final”.
1. The Contractor shall give a list of machinery in their possession and which
they propose to use on the work.
2. The Contractor will have to construct shed for storing materials procured
by him at his own cost at the work site having double locking arrangement. The
materials will be taken for use in the presence of the NMC Person. No materials
will be allowed to be removed from site of the work.
6)The tender will be liable to be rejected, if while submitting it, the tenderer or in the case of a firm
each partner thereof does not sign or the signature / signatures is / are not attested by a witness of
the tender in the space provided for the purpose.
(b) No security will be taken from the Contractor, so long as the machinery is
worked by the NMC all staff and under the entire control of NMC and is not
handed over to the Contractor at all for operation by his crew and staff and the
charges for the use of machinery are levied on hourly basis and as per
prevailing schedule of rate for hire charges.
(c) Machinery should be worked only where the NMC staff is confidant to use it
safely & never in difficult situation and dangerous spot.
(d) The recovery of plant hire charges will be immediately made through the
next Running Accounts bills.
7) The tendering contractors shall furnish a declaration along with the tender showing all works for
he has already entered into contract, and the value of work that remains to be executed in each
case on the date of submitting tender.
ii. The Contractor will have to construct shed for storing controlled and valuable
materials issued to him under schedule ‘A’ of the agreement. The materials will
then be taken for use in the presence of the NMC person. No material will be
allowed to be removed from the site of works.
iii. The tendering Contractor should furnish a detailed statement of works in hand,
showing the cost of works in hand, the works completed against each with
certificate from head of the office concerned.
MEMORANDUM
(a) If several sub work are a) General Description:- Construction of Toilet And Covering Of Shade and
included they should be
Providing And Fixing Iblock And Various Civil work at NMC Vyamashala at
detailed in a separate list.
Tulsibag Mahal in Pr. No. 18
(b) The amount of earnest
money to be deposited shall
be in accordance with the (b) Estimated cost: As per tender notice
provision of the paras206 and (c) Earnest Money: As per tender notice
207 of the M.P.W. Manual.
Total: Rs.42000.00
(d) This percentage where no
security deposit is taken will
vary from 5% to 10%
according to the requirement (e) Percentage, if any, to be deducted from bill so as to make up the total
of the case. Where security amount required as security deposit by time the half the work as measured
deposit is taken see note to by the cost is done (2 percent).
clause
I / We hereby agree that this offer shall remain open for acceptance for a
minimum period of 70 days from the date fixed for opening the same and
thereafter until it is withdrawn by us / by notice in writing duly addressed to
the authority opening the tenders and sent by registered post A.D. The
amount of earnest money shall not bear interest and shall be liable to be
forfeited to the NAGPUR MUNICIPAL CORPORATION should I / We fail to (1)
abide by the stipulation to keep the offer open for the period mentioned
above or (2) signed and complete the contract documents required by the
Engineer and furnish the security deposit as specified in item (3)
ofmemorandum contained in paragraph 1 above, within the time limit laid
down in clause (i) of the annexed conditions of the contract. The amount of
earnest may be adjusted towards the security deposit or refunded to me / us
if so desired by me / us in writing unless the same or any part thereof has
been forfeited as aforesaid above, within the time limit laid down inclauseI /
I /we hereby agree to abide by and fulfill all the terms and provision of the
conditions of contract annexed hereto so far as applicable and in default to
forfeit and pay to NMC the sum of money mentioned in the said condition.
Receipt no------------- dt -------------- from the NAGPUR MUNICIPAL
CORPORATION Treasury at in respect of the sum Rs............. /- forwarded
representing the earnest money (a) the full value of which is to be absolutely
forfeited to NMC should/we not deposit the fully amount of security
specified in the above memorandum in accordance with Clause 1(A) of the
said conditions of the contract. otherwise the said sum of Rs ............ /- shall
be refunded.
Contractor
Signature of Contractor
before (Address)
submission of tender Dated the _______ day of _________ 2025
Witness
contractor.
The Engineer in charge may from time to time in writing delegate to his
representative any of the powers and authorities vested in the Engineer in charge
and shall furnish to the contractor a copy of all such delegations of powers and
authorities. Any written instructions of the approval given by the representative of
the engineer in charge to the contractor within the terms of such delegations (but
not otherwise) shall bind the contractor and NMC as though it had been given by the
Engineer in charge provided always as follows.
a) Failure of the representative of the engineer in charge to disapprove any work or
materials shall not prejudice the power of the engineer in charge. Thereafter to
disapprove such work or materials and to order pulling down, removal or
b) If the contractor is dissatisfied with any decision of the representative of the
engineer in charge he shall be entitled to refer the matter to the engineer in
charge who shall thereupon confirm reverse or vary such decisions.
i) The contractor shall be deemed to have carefully examined the work and site
conditions including labours, the general and he special conditions, the
specification schedule and drawing and shall be deemed to have visited the site of
the work and to have fully informed himself regarding the local conditions and
carried out his own investigations to arrive at the rates quoted in the tender. In
this regards he will be given necessary information to the best of the knowledge of
NMC but without any guarantee about it.
ii) It is presumed that the contractor has carefully gone through the works
specifications. MOS&T, P.W.D. Hand Book and the Schedule of rates of the division
and studied the site conditions before arriving at the rates quoted by him.
D. TREASURE TROVE
In the event of discovery by the contractor or his employees during the progress of
the works of the any treasure, fossils, minerals or any other article of value or
interest, the contractor shall give immediate intimation thereof to the Engineer.
And forth with mark over to the Engineer his representative such treasure or
things, which shall be the property of NAGPUR MUNICIPAL CORPORATION.
5.1 Layout of the workwill be done by the contractor in consultation with the
Executive Engineer, of the NMC or his representative. Some permanent marks
should however be established to indicate the demarcation of the structures
or any component thereof made to this permanent marks in measurement
books and drawing, signed by the contractor and the NMC officer,
responsibility regarding layout will be joint.
5.2.1The contractor shall himself engage an authorized all time agent on the
Contractor No. of Correction Executive Engineer
48
work capable of managing and guiding the work and understanding the
specifications and contract conditions. A qualified and experienced Engineer
shall be provided by the contractor as his agent for technical matters. Site
engineer can also be designated as an agent of the contractor. Agent will
takeorders as will be given by the Engineer in charge or his representative and
shall be responsible for carrying them out. This agent shall not be changed
without prior intimation of the Engineer in charge and his representative on
the work site. The Engineer-in-charge have the unquestionable right to ask for
changes in the quality and strength of supervisory staff of contractor and to
order removal from work of any of such staff. The contractor shall comply with
such order and effect replacements of the satisfaction of the Engineer-in-
charge.
5.2.2 A work order book shall be maintained on site and it shall be the
property of NAGPUR MUNICIPAL CORPORATION and the contractor shall
promptly sign orders given therein by the Executive Engineer in charge or his
representative and his superior officer, and comply with them. The compliance
shall be reported by contractor to the Engineer in charge in good time so that
it can be checked, the blank work order book, with machine numbered pages
will be provided by the NMC free of charge for this purpose. The contractor will
be allowed to copy out the instruction therein from time to time.
All work and materials before being finally taken over by NAGPUR MUNICIPAL
CORPORATION will be the entire liability of the contractor for guarding,
maintaining and making good any damages of any magnitude. It is however to
be understood that before taking over such work, NAGPUR MUNICIPAL
CORPORATION will not put it to its regular use as distinct from casual or
incidental use except as specially mentioned elsewhere in this contract or as
mutually agreedto.
5.4 CO-ORDINATION:
Contractor No. of Correction Executive Engineer
49
When several agencies for different sub works of the project are to work
simultaneously on the project site, there must be full co-ordination between
the contractors to ensure timely completion of the whole project smoothly. The
scheduled dates for completion specified in each contract shall, therefore be
strictly adhered to. Each contractor may make his independent arrangements
for water, power, housing etc. if they so desire. On the other hand the
Contractors are at liberty to come to mutual agreement on his behalf and
make joint agreement with the approval of the Engineer in charge. No
contractor shall take or cause to take any steps or action that may cause
destruction, discontent or disturbance to work, labour or arrangements etc.of
other contractors in the project localities. Any action by any Contractors
which the Engineer in charge in his unquestioned discretion may consider as
infringement of the above code would be considered as a breach of the
contract conditions and shall be dealt withaccordingly.
In case of any dispute or disagreement between the various contractors, the
Engineer in charge decision regarding the co-ordination, co-operation and
facilities to be provided by any of the contractor shall be final and binding on
the contractor concerned & such a decision shall not vitiate any contract nor
absolve the contractor of his obligations under the contract nor form the
grounds for any claim or compensation.
5.7 INDEMNITY:
The contractor shall indemnify the NAGPUR MUNICIPAL CORPORATION
against all actions, suits, claims, and demands brought or made against it in
respect of anything done or committed to be done by the Contractor in
execution of or in connection with the work of this contract and against any
loss or damage to the NAGPUR MUNICIPAL CORPORATION in consequence to
any action or suit being brought against the contractor for anything done or
committed to be done for the execution of this contract.
The NAGPUR MUNICIPAL CORPORATION may at its discretion and entirely at
the cost of the contractor defend such suit, either jointly with the contractor
or single in case the latter chooses not to defend the case.
5.9The contractor shall at his own expenses, engage watchman for guarding
the Materials and plant and machinery and the work during day and night
against any pilferage or damage and also for prohibiting tress passers.
5.10 No Materials brought to site shall be removed from the sitewithout prior
approval of the Engineer–in-charge.
5.11 INSPECTION OF SITE
5.11.1 The contractor shall inform the Engineer in charge in writing when any
portion of the work is ready for inspection giving him sufficient notice to
enable him to inspect these without affecting the further progress of the work.
5.11.2 The contractor shall provide at his cost necessary ladders and such
arrangements as are considered safe by the Engineer in charge for proper
inspection of all parts of the work.
5.11.3 The contractor shall extend his full co-operation and make all
necessary arrangement when needed for carrying out inspection of the work or
any part of the work by the local representative, M.L. A’s M.P.’s and officers
and dignitaries / delegates of various Government NMC, local bodies, private
sectors etc. no compensation shall be paid to the Contractor on this account.
5.12.1 The work shall be carried out by the contractor without causing
damage to the existing Govt. property and / or private property. If any such
damages are caused the contractor shall pay for restoration of the property to
the original condition and any other consequent damages.
5.12.2 In the event of an accident involving serious injuries or death of any
persons, at site of work or quarry or at place in connection with the work the
same shall be reported in writing within 24 hours of the occurrence to the
Engineer in charge and the Commissioner of workmen’s compensation.
The contractor after completion of work shall clean the site of all debris and
remove all unused materials other than those supplied by the NMC and all
plant and machinery equipment, tolls, etc. belonging to him within one month
from the date of completion of the work, or otherwise the same will be removed
by the NMC at his cost or disposed off as per NMC procedure. In case the
materials is disposed off by NMC, the sale proceeds will be credited to the
contractor’s account after deducting the cost sale incurred. However no claim
of the contractor regarding the price or amount credited will be entertained
afterwards.
Contractor No. of Correction Executive Engineer
51
All constructional plant, provided by the contractor shall when brought on the
site be deemed to be exclusively intended for the construction and the
contractor shall not remove the same or any part thereof (Save for the purpose
of moving it from one part to the site to another) without the consent in
writing of the engineer in charge who shall record the reasons for with holding
the consent.
5.16.1 The work shall not be considered to have been completed in accordance
with the terms of the contract until the Engineer in charge shall have certified
in writing to that effect. No approval of material or workmanship or approval of
part of that during the progress of execution shall bind the engineer in charge
or any way prevent him for even rejecting the work which is claimed to be
completed and to suspend the issue or his certificate of completion until such
alterations and modification or reconstruction have been effected at the cost of
the contractor as shall enable him to certify that the work has been completed
to his satisfaction.
5.16.2 After the work is completed, the contractor shall give notice of such
completion to the Engineer in charge and within 30 days of receipt of such a
notice the Engineer in charge shall inspect the work and if there is no defect
in the work, shall furnish the contractor with a certificate indicating the date
of completion. However, if there are defects which in the opinion of the
engineer in charge are rectifiable he shall inform the contractor the defects
noticed. The contractor after rectification of such defects shall then inform the
engineer in charge and engineer in charge on his part shall inspect the work
and issue the necessary completion certificate within 30 days if the defects are
rectified to his satisfaction, and if not he shall inform the contractor indicating
defects yet to be rectified. The time cycle as above shall continue.
5.16.3 In case defects noticed by the Engineer in charge which in his opinion
are not rectifiable but otherwise work is acceptable at reduced payment, work
shall be treated as completed. In such cases completion certificate shall be
issued by the Engineer in charge within 30 days indicating the un-rectifiable
defects for which specified reduction in payment is being made by him.
5.16.3 The issue of completion certificate shall not be linked up with the site
clearance on completion of the work.
5.16.4 Should regular, public traffic be allowed on the bridge, road at any
stage prior to being taken over then the maintenance period shall be deemed
to commence from the date of such traffic passing over the bridge, road &shall
be upto 30 days after the date of issue of completion certificate by Engineer in
Contractor No. of Correction Executive Engineer
52
The contractor shall submit to Engineer in charge in writing the details of all
ancillary works including layout and specifications to be allowed for its
constructions. Ancillary work shall not be taken up in hand unless approved
by Engineer in charge. The Engineer in charge reserves the right to suggest
modification or make complete changes in the layout and specifications
proposed by the Contractor at any stage to ensure the safety on the work site.
The contractor shall carry out all such modifications to the ancillary works at
his own expenses as ordered by the Engineer in charge.
11) Taking the all-necessary precautions wherever divers are engaged on work.
Providing full length gum boots, leather hand gloves, leather jackets with
fireproof aprons to cover the chest and back reaching upto knees, plain
goggles for the eyes to the labour working with hot asphalt, handling,
vibrators in cement concrete and also where use of any or all these items
is, essential in the interest of health and well-bring of the labourers in the
opinion of the Engineer- in–charge.
5.20 Medical and sanitary arrangements to be provided for labour
employed in the construction by the contractor.
1) The contractor shall provide an adequate supply of pure and
wholesome water for the use of labourers on works and in camps.
2) The contractor shall construct trenches. Semi permanent latrines for
the use of labourers. Separate latrine shall be provided for men and
women.
3) The contractor shall build sufficient number of huts on suitable plot of
land for use of the labourers according to the following specifications.
4) Huts of bamboos and grass may be constructed.
5) There should be no over crowding. Floor space at the rate of 3 Sqm (30
Sq.ft.) per head shall is provided. Care should be taken to see that the
huts are kept clean and in good order.
6) The contractor must find his own land. If he wants Govt. land he
should apply for it. Assessment for it if demanded will be payable by
contractor. However the NMC does not bind itself for making available
the required land.
7) A good site not liable to submergence shall be selected on high ground
remote from jungle but well provided with trees; shall be chosen
wherever it is available. The neighborhood of tank, jungles, trees or
woods should be particularly avoided. Camps should not be
established close to large cutting of earthwork.
8) The lines of huts shall have open space of at least 10 meters between
rows. When a good natural site cannot be procured particular
attention should be given to the drainage.
9) The contractor shall construct sufficient number of bathing places,
sufficient number of washing places also be provided for the purpose
of the washing cloths.
10) The contractor shall make sufficient arrangement for draining away
the surface and sewage water as well as water from the bathing and
washing places and shall dispose of the waste water in such away as
not cause any nuisance.
11) The contractor shall engage a medical officer with a traveling
dispensary for a camp containing 500 or more person if there is no
NAGPUR MUNICIPAL CORPORATION or other dispensary situated
within eight Kilometers from the camp. In case of an emergency
contractor shall at his cost, free transport for quick medical help to
his sick workers.
12) The contractor shall provide the necessary staff for affecting the
satisfactory conservancy and cleanliness of the camp to the
satisfaction of the Engineer -in charge. At least one sweeper per 200
persons should engaged.
13) The Assistant Director of public health shall be consulted before
opening a labour camp and his instruction on matters such as water
supply, sanitary, convenience, the camp site, accommodation and food
Contractor No. of Correction Executive Engineer
54
4 The contractor shall employ sufficient plant, equipment and labour as may
be necessary to maintain the progress schedule. The working and shift hours
restricted to one shift a day for operations to be done under the NAGPUR
MUNICIPAL CORPORATION supervision shall be such as may be approved by
the Engineer in charge. They shall not be varied without prior approval of the
Engineer. Night work which requires supervision shall not be permitted except
when specially allowed by Engineer in charge on each item if required by
contractor. The contractor shall provide necessary lighting arrangement etc.
for night work as directed by Engineer without extra cost to NAGPUR
MUNICIPAL CORPORATION.
5The contractor shall submit reports on progress of work in forms and
statements etc. at periodical intervals in the form of progress chart, forms,
statements and / or reports as may be approved by the Engineer in charge.
Forms for the sending reports about the progress will be supplied by the
Engineer in charge.
5.24 PAYMENTS:
The contractor must understand clearly that the rates quoted are for
completed work and include all cost due to labour, all leads and lifts involved
and if further necessitated, scaffolding, plants, machineries, supervision
power, service works, royalties, octroies, taxes, etc. and should also include all
expenses to cover the cost of lighting, night works if and when required &no
claim for additional payment beyond the rates quoted will been entertained
and the contractor will not be entitled subsequently to make any claim on the
Contractor No. of Correction Executive Engineer
56
a. Availability of adequate water for work and sources thereof shall be confirmed
by the contractor before submitting thetender.
b. The contractor shall make his own arrangements at his own cost for entering
into contract with concerned authority for obtaining the connection and carry
the water upto the work site as required by him. The location of the pipeline
with respect to the road shall be decided by Engineer-in-charge and shall be
binding on the contractor. The NMC shall not bear any responsibility in
respect of any problems and contractor shall not be liable for getting the any
compensation on any ground. The progress of work shall not hamper for the
above reasons.
c. The contractor is advised to provide water storage tanks of adequate capacity
to take care of possible shut down of water supplysystem.
d. The contractor shall have to supply water required by the NMC for its
establishment at work site free ofcost.
e. In case Contractor uses NMC water, actual water charges shall be deducted
from his Bills.
5.29 ELECTRICITY:
a. The contractor will have to make his own arrangement at his own cost for obtaining or
providing electric supply at work site. The NMC shall not bear any responsibility in respect of
any problems and contractor shall not be liable for getting any compensation on any ground.
The progress of work shall not hamper for the abovereasons.
b. Electrical supply for the NMC’s use at work site shall be provided by the contractor on mutual
agreed terms. The contractor may not abide by these conditions when power supply at the
sitefails.
c. In case Contractor uses NMC Electricity, actual Consumption shall be deducted from his Bills.
5.30TELEPHONE FACILITIES:
The contractor will have to make his own arrangements at his own cost for a telephone
connections at work site if required.
The contractor shall take all precaution against damages by floods or from
accidents etc. No compensation will be allowed to the contractor on this
account or for correction and repairing any such damage to the work during
construction. The contractor shall be liable to make good at his cost any plant
or material belonging to the Govt. loss or damaged by floods or from any other
cause while in his charge. The proof of occurrence of flood report with flood
level will have to be furnished by the contractor. No compensation will be
allowed for damages on ancillary items and equipment sets which are brought
to the site by the contractor for effecting execution of work.
Immediately upon the receipt of the award of the contract, the contractor shall
inform the Engineer the exact location of the sources of the acceptable
material. The concrete mix to be used shall be got designed P.W.D laboratory
or NABL laboratory by the contractor with a optimum quantity of cement to
give the specified strength in the preliminary tests and the proportion got
approved by the engineer in writing. These proportions shall be used so long
as the materials continue to be of the same quality and from the same sources
subject only to slight changes in the relative quantities of fine and course
aggregate for the purpose of promoting workability provided the work tests
also shows the required strength.
5.36 CONTRACTOR TO INFORM HIMSELF FULLY:
The contractor shall be deemed to have carefully examined the work and site
conditions including labours, the general and the special conditions, the
specifications schedule and drawing and shall be deemed to have visited the
site of the work and to have fully informed himself regarding the local
conditions and carried out his own investigations to arrive at the rates quoted
in the tender. In this regards he will be given necessary information to the
best of the knowledge of NMC but without any guarantee about it. If he shall
have portion of these general conditions, or the special conditions to the scope
of working of the specification and drawings, or any other matter concerning
the contract, he shall in good time before submitting his tender set forth the
particulars thereof and submit them to the Engineer in writing in order that
such doubt may be clarified authoritatively before tendering. Once a tender is
submitted the matter will be decided in accordance to the tender conditions in
absence of such authentic clarification.
5.37 ERRORS, OMISSION&DISCREPANCIES:
a) In case of errors, omissions and / or disagreement between written and scaled
dimensions in the drawing or between the drawing and specifications etc., the
following order of preference shall apply.
Between actual scaled and written dimensions or description on a
drawing the latter shall be adopted.
Between the written description or dimensions in the drawing and
the corresponding one in the specifications, the latter shall apply.
Between the quantities shown in the schedule of quantities and
those arrived at from the drawing the latter shall preferred
c) The contractor should not sublet any part of work without written permission
of the Engineer in charge.
5.38 SAMPLES AND TESTING OF MATERIALS:
(i) All materials to be used on work, such as cement, steel, stones,
bricks, aggregates, asphalt, wood, tiles, etc. shall be got approved in advance
from the Engineer-in-charge and shall pass the tests and analysis required by
him.
(ii) The contractor shall at his risk and cost make all arrangement
and / or shall provide for all such facilities as the Engineer in charge may
require for collecting, preparing and forwarding required number of samples
for tests or for analysis to the nearest approved laboratory and bear all
charges and cost of testing. Such samples shall also be deposited with the
Engineer-in-charge till sent for testing. Out of total number of tests as per
frequency requirement 30 % of these tests shall be carried out in P.W. NMC
Laboratory.
(iii) The contractor shall if and when required submit at his cost the
samples of materials to be tested or analyzed and if so directed shall not make
use or in corporate in the work any material represented by the samples until
therequired tests or analysis have been made after the test of the materials
finally accepted by the Engineer-in-charge.
b) Where field laboratory is not established at the works site 100% tests as per
frequency shall be carried out in the Vigilance and quality laboratory of NMC /
PWD or NABL Laboratory NAGPUR.
c) Testing of cement and steel 100% in Vigilance and quality laboratory NMC
NAGPUR is compulsory.
frequencygiveninthespecificationwiththebill.Ifthetestresultsarenotsubmi
ttedalongwiththebill,amountequaltofivetimes the prevailing VQC testing
charges shall be deducted from thebill. More over the work will be
withheld for payment fully or partly for want of results as decided by
the Executive Engineer.
Samplesfortheitemsforwhichtesting
isnotdoneasperfrequency shall be collected and submitted for testing
by the engineer in charge or his representative for testing and testing
charges for this sample shall be paid by engineer in charge through the
amount deducted as
aboveandbalanceamountshallberemittedtorevenue.Tillsuchresults are
received contractor shall be paid (at part rate as decided by the
Engineer in Charge).
2) Mixing of concrete shall be done with concrete mixers.
3) The Contractor shall make field arrangements for testing of all materials for
cement concrete i.e. slump test, bulkage test, etc.. The concrete cube mould 3
Nos. of 15cmx15cmx15cm. size shall be kept at site during concreting
operation. One set of six 15 cm. (about 6”) cubes shall be prepared from the
concrete to be used in work for compression test on the first three days
operation and thereafter for every 60 cubic meter of concrete or three days
work whichever is less. If source of aggregate or grading is changed, one set of
six test cubes shall be taken for each changed batch. Three cubes shall be
tested for test at 7 days age and 3 at 28 days in Regional Testing Lab of NMC
NAGPUR All the testing charges shall be paid by the contractor. The entire
responsibilities of the testing of materials will be borne by the contractor.
4) For providing Electric Wiring, Duct tubes of the required diameter and length
shall be provided through walls, beams and floors, slabs as and when directed
without any extra cost.
5) (a) The contractor shall make his own arrangement for receiving all materials,
tools, etc. required for the work.
(b) No extra charges for carriages of water will be allowed.
(c) The rates for all items are inclusive of all charges such as carting, lifting,
etc. No extra payment for any lead and lift will be paid for any items.
(d) A frequency of testing shall be as per relevant works specification. In case
such frequency is not specified in the works specification then the IS code will
be referred and for other cases where IS code do not stipulated the frequency
of testing, it will be as directed by Engineer in charge and should be furnished
in specified test abstract Annexure III
(e) The Contract should not be sublet without written permission of Executive
Engineer
(f) Tender condition of tender notice will be binding on contractor and etc
tender notice will form a part of agreement.
5.39 WEIGH BATCHING:
The following instructions shall be followed as regards to preliminary designs of
mix and methods of batching of plain cement concrete and reinforced cement
concrete. The preliminary mix design and batching for various grades of concrete
shall be governed by the guidelines as per I.S.4562000. It will be the responsibility
of the contractor to obtain the mix design for various cement concrete grades at his
cost from the P.W.D laboratory.
5.40 MISCELLANEOUS:
1 ERASER:
Person tendering are informed that no erasers or any alteration by them in the text
of the documents set herewith will be allowed and any such eraser or an alteration
will be disregarded. If there is any error in writing no overwriting should be done but
the wrong words or figures should be struck out and the correct one written above or
near it in an unambiguous way. Such correction should be initialed and dated.
2 ACCEPTANCE:
Intimation of acceptance of tender will be given by a telegram or a letter sent by
registered post to the address given below the signature of the tenderer in the
tenders. The tenders which do not fulfill any of the above conditions or those in the
form and which are incomplete in any respect shall be liable for rejection.
3 COMPETENCY OF TENDERERS:
The work will be awarded only to those contractors who are considered to be
responsive contractors, capable of performing the class of work to be completed.
Before passing the final award any or all contractors may have to show that he has
the necessary experience, facilities, ability and financial resources to execute the
work in satisfactory manner and also within the stipulated time. The contractors
may also be required to furnish to the NMC a statement in respect of their
experience and financial resources.
ii) The wiring cable should not be taken near the live electric line and it should
be preferably shot firing cable as supplied by the supplier of explosives. If
such a cable is not available a substitute cable made up of several pieces
jointed and tapped be used.
iii) The blasting shed from where the exploder is to finally operate should be at
least 150 m. away from the area to be blasted. It should have a strong roof,
which can withstand the impact of flying stones at this range.
iv) Only trained hands shall be allowed to handle explosive cable detonators etc.
5 POLICE PROTECTION:
For the police protection of the camp of the contractor’s work, the Deptt. will help
the contractors as far as possible to arrange for such protection with the concerned
authorities the cost shall be borne by the contractor.
6 For providing electric line and water line etc. recesses shall be provided. If necessary,
through walls, slabs, beams, etc., and later on refilled it with a bricks or stones,
chipping cement mortar without any extra cost.
7 In case it becomes necessary for the due fulfillment of the contractor for contractor to
occupy land outside the NMC limits, the contractor will have to make his own
arrangement with the land owners and pay such a rents, if any, which are payable
as mutually agreed between them.
8 The contractor shall duly comply with the provisions of the Apprentices Act. 1961 (iii
of 1961) and the rule and orders made there under from time to time under the said
Act and the said Rules and on his failure or neglect to do so he shall be subject to
all the liabilities and penalties provided by the said Act and Rules.
9 It is presumed that the contractor has gone carefully through the standard
specification (Vol. I & II 1981 edition) and the schedule of rate of the Division, and
studied of site conditions before arriving at rates quoted by him. The special
provisions and detailed specification of wording of any item shall gain precedence
over the corresponding contrary provisions (if any) in the standard specification
given without reproducing the details in contract. Decision of Engineer-in-charge
shall be final in case of interpretation of specification.
10 If the standard specifications fall short for the items quoted in the schedule of this
contract reference shall be made to the latest Indian Standard Specifications, I.R.C.
codes, and MOST specification if any of items of this contract do not fall in reference
quoted above, the decision and specifications as directed shall be final.
5.41SPECIAL CONDITIONS:
1 The contractors should ensure that all safety precautions are observed by their
labours, working closed to the State Highway and while closing the state Highway
precautions are taken including insurance etc., for their labour at the cost of the
contractor etc. if any accident occur to the labour etc., no claim in this regard on
whatsoever account shall be entertained and the decision of the NMC will be final
and conclusive.
2Contractor shall observe the rules and regulations empowered by traffic police for
smooth flow of traffic on the diversion road and shall not be entitled for claim any
compensation arising thereof.
(5) Board0.90mx0.60mshowingfollowinginformationshallbeprovide
dby Contractor at no extra cost to theGovernment
1 foHkkxkpsuko :
2 dkekpsuko :
3 fd- eh- :
4 dkekphfdaer :
5 da=kVnkjkpsukao :
6 dkelq: >kY;kpkfnukad :
7 dkeiq.kZdj.;kpkdkyko/kh :
8 nks"kfuokj.kdkyko/kh :
o’kZ :
iklqufnukad :
Ik;Zarfnukad :
7-SPECIAL CONDITIONS
(1) Construction Machinery / Equipments :
1.1 The methodology and equipments to be used on the project shall be
furnished by the Contractor to the Engineer-In-Charge well in advance
of commencement of work and approval of the Engineer-In-Charge
obtained prior to its adoption and use.
1.2 The Contractor shall give, a trial run of the equipment for establishing
its capability to achieve the laid down specifications and tolerance to
the satisfaction of the Engineer-in-Charge before commencement of
work, if so desired by the Engineer-In-charge.
1.3 All equipments provided shall be of proven efficiency and shall be
operated and maintained at all times in the manner acceptable to the
Engineer-In-Charge.
1.4 No equipment or personnel shall be removed from the site without
permission of the Engineer-In-Charge.
(2) Work Programme and Methodology ofconstruction:
The Contractor shall furnish his programme of construction,for execution of
the work within the stipulated time schedule together with methodology of
construction of each item or work and obtain the approval of the Engineer-
In-Charge to the revised programme, if necessary/
(3) Revised Programme of Work in case of slippage:
In case of slippage from the approved work programme at any stage, the
Contractor shall furnish revised programme to make up slippage within the
stipulated time schedule and obtain the approval of the Engineer-in-charge
to the revised programme.
(4) Action in case disproportionate progress :
In case of extremely poor progress of the work or any item at any stages of
work which in the opinion of the Engineer-In-Charge can not be made good
by the Contractor considering his available resources, the Engineer-In-
Charge will get it accelerated to make up the lost time through any other
agency, and recover the additional cost incurred, If any, in getting the work
done from the Contractor after informing him about the action envisaged by
him.
(5) The responsibility of assuring the quality of work shall be on the
Contractor who shall take actions as stipulated in standard specification as
per “Schedule C”
6 )Labour License : It shall be obligatory on the part of the
Contractor to obtained the necessary labour License from the
labourNMC within fortnight of issue of work order.
2. T.M.T Steel
T.M.T. steel shall comply with IS: 1786 and “Mild Steel” bars shall comply with IS: 432.All
reinforcement shall be free from rust loose mill scale or coats of Oil, Paints etc. which may destroy
bond and protected by anticorrosive treatment before placing in position for concreting.
The agency should use the steel manufactured by the Main Producers only. No re-rolled steel
shall be incorporated in the work.
Materials not corresponding in character and quality with approved samples will be rejected by
the Engineer-in-charge or his representative and shall be removed from the site at the end of
working season will not be allowed to use for any component of work in the next seasons.
ADDITIONAL SPECIFICATION
A) FOR B. T. WORK :-
1) The contractor shall use Bulk Bitumen VG-30 (60/70 Grade) VG-10 (80-100)
grade received from the Refinery at Mumbai for the Hot mix treatment only. Bulk
Asphalt received as above will be entirely consumed at Hot mix plantsite.
3) The Contractor should be aware that delay may occur in getting the bulk
asphalt to be supplied at the refinery. They are, therefore, adIV-Ased to indent for their
requirement, sufficiently in advance allow for the period usually taken for supplying
Bulk Bitumen.
6) Asphalt shall be obtained specified in Schedule ‘A’ only Materials from other
source in lieu of the materials in Schedule ‘A’ shall not be allowed except under written
permission of the Executive Engineer .
7) Government does not undertake to take from the contractors whether before or
after completion of determination of the contract, surplus material which were originally
issued to them and charged to their accounts. Such material however, remains the
property of the Department and can be taken over by the Department, if required for use
on other works in progress only specials arrangement and the prevailing market rate or
the rates stipulated in Schedule ‘A’ excluding the element of storage charges of the issue
rate of DiIV-Asion excluding the element of storage charges which islowest.
(inspite of instructions to return the surplus materials from the Department) recovery at
penal rate i.e. the double the rate stipulated in Schedule ‘A’ shall be made from the
contractor.
10) Delay in supply of material included in schedule ‘A’ shall not entitle the
contractor to claim any compensation. The contractor will however, will be eligible fir
extension of time limit on thisaccount.
11) In the event of Asphalt consumed being more than the quantity required as per
specifications, recovery at penal rate i.e. double the rate stipulated in Schedule ‘A’ will
be made from the Contractor for the excess quantity of Asphaltconsumed.
12) The Contractor should note that the bouzars when received from Mumbai are
always unloaded at the plant
inthepresenceoftheJr.Engineer/otherrepresentativeoftheDeptt.During8.00A.M.to6.00P.M
.only.Heshouldarrange to give advance intimation in this behalf to Engineer-in-charge so
the arrangement to depute the Jr.Engr. / Representative at the plant site can be made.
13) Since the work lies in busy area the contractor shall have to make adequate
arrangement for regulating the traffic by providing barricading whenever necessary and
by displaying adequate number of requisite sign, an caution board etc. The work shall
have to the planned properly to avoid any inconvenience to thetraffic.
14) A register shall be maintained on site regarding daily item wise bitumen
consumption of the works ( Giving details of each item) as directed and shall be signed
daily by the contractor or his representative and got signed daily from the representative
of the Engineer-in-charge.
1)The pattern in which blocks are to be paved should be decided from the
choices available for getting better performance. For paving in trafficked areas,
herringbone pattern should be adopted. Paving should commence and progress
from one starting line only. Wherever possible, paving should commence
adjacent to or against edge restraint.
2)Blocks should be placed at the correct angle to the start line to achieve the
final orientation of the laying pattern. For curved or unfavorably oriented
edge restraints, a string line should be established to permit fast, easy laying
such that it is never necessary to force a block between blocks already paved.
Maintenance of control over alignment, laying pattern and joint width can be
assisted by the use of chalked string lines set at about 5m intervals. Nominal
joint width of 2 to 4 mm should be maintained by holding the paving unit lightly
against the face of the adjacent block and allowing it to slide into position.
Cutting paving units for filling the paving gaps occurring against edge
restraints etc. should be deferred until sufficient work has progressed to
allow reasonably continuous maintenance. When space does not permit the
use of cut pieces of blocks, the use of premixed or dry packed concrete is
recommended.
up before laying the paver blocks. No extra pavements will be made for this
purpose. It will be the responsibility of the Contractors to ensure that
undulations on the paver blocks are eliminated after the traffic is allowed on it.
Proper slope for drainage of water needs to be ensured.
Paver blocks shall be placed on the un-compacted screeded sand bed to the
nominated laying pattern, care being taken to maintain the specified bond
throughout the job. The first row shall be located next to an edge restraint.
Specially manufactured edge paving blocks are permitted or edge blocks may
be cut using a power saw, a mechanical or hydraulic guillotine, bolster or other
approved cutting machine.
In each row, all full blocks shall be laid first. Closure blocks shall be cut and
fitted subsequently.
Vibrate the blocks with 3 passes of the plate vibrator of adequate capacity.
Spread a thin layer of fine joint filing sand on top of the paved blocks and sweep
it into the joints using suitable brooms.
Contractor No. of Correction Executive Engineer
72
Vibrate the sand into the joints by making 3 passes of the compactor. Sweep of
the excess sand on top.
All work farther than one meter from the laying face shall be left fully
compacted at the completion of each day’s laying.
Any blocks that are structurally damaged prior to and during compaction shall
be immediately removed and replaced.
Sufficient plate compactors shall be maintained at the paving site for both
bedding compaction and joint filling.
6)As soon as possible after compaction and in any case prior to the termination
of work on that day and prior to the acceptance of vehicular traffic, sand for
joint filling shall be spread over the pavement.
The surface course should not be vibrated until the edge restraint, together with
any bedding or concrete haunching, has gained sufficient strength. It is
essential that edge restraints are adequately secured.
1.2] General:-
The work to be done under these items shall consists of furnishing
all plant, labour and materials and performing all the work required
to carry out excavation, conveyance and disposal of spoil and
maintaining the excavation in line, grade and alignment profile as
per drawing or as directed by the Engineer.
Excavation in Earth
Under this item excavation shall be carried out in earth, soft soil
this include soil of all sorts, sand, gravel & soft murum
atnight.
The withdrawal of the timber shall be done very carefully to prevent the
collapse of the pit or trench. It shall be started at one end and
proceeded systematically to the other end. Concrete or masonry shall
not be damaged during the removal of the timber. No claim shall be
entertained for any timber which cannot beretrieved.
2. Laying of Pipe:-
Pipes shall be lowered in to the trench carefully by
mechanical appliances. Under no circumstances shall the pipes
be dropped or dumped in to the trench.
In the case of pipes with joints to be made with loose collars, the
collars shall be slipped on before the next pipe is laid.
At times when pipe laying is not in progress the open ends of pipe shall
be closed by a water tight plug or canvas or other means approved by
the Engineer in charge.
Trench shall be kept free from water until material in the joints has
hardened.
When the pipe is closed and the trench liable to be flooded by
rain, care shall be taken to prevent the pipe from damage.
Jointing :-
The socket and spigot pipes are laid and jointed with rubber
gasket.
QUALIFICATION FORMS
FORM –1
LIST OF MACHINERY AVAILABLE WITH TENDERER WHICH WILL BE USED ON THIS WORK
NAME OF TENDERER :-
NAME OFWORK:- Construction of Toilet And Covering Of Shade and Providing And Fixing Iblock And
Various Civil work at NMC Vyamashala at Tulsibag Mahal in Pr. No. 18
Whether
Present location
machinery is
Kind with name & address
Sr. No. of Age of Present hypothecated to
Name of Equipment of Capacity of organization Remarks
No. Units machinery Conditions any division /
Make where machinery
Bank or other
under use at present
institution etc.
1 2 3 4 5 6 7 8 9 10
Notes :- The above machineries are readily available with me / us for use on this work
Contractors
:___________________________________________________________________
Name :-____________________________________________________________________
Address :-
____________________________________________________________________
FORM – 2
LISTOFTECHNICALPERSONNELOFTHETENDERERLIKELYTOBEAPPOINTEDONTHISWORK
NAME OF TENDERER :-
NAME OFWORK -: Construction of Toilet And Covering Of Shade and Providing And Fixing Iblock And
Various Civil work at NMC Vyamashala at Tulsibag Mahal in Pr. No. 18
Contractors :
____________________________________________________________________
Name :-____________________________________________________________________
Address :-
____________________________________________________________________
FORM-3
DETAILS OF WORKS TENDERED FOR IN HAND AS ON THE DATE OF SUBMISSION OF THE THIS
TENDER
NAME OF TENDERER :-
Sr. Name Name & address Place Works in hand Works tendered for Remarks
No. of of organization and Tendered Cost of Anticipated Estimate Date when Stipulated
Work for whom the country cost remaining date of d cost decisionis date or
work was done work completion expected period of
completion
1 2 3 4 5 6 7 8 9 10 11
NAME OFWORK-: Construction of Toilet And Covering Of Shade and Providing And Fixing Iblock And
Various Civil work at NMC Vyamashala at Tulsibag Mahal in Pr. No. 18
Contractors :
____________________________________________________________________
Name :-____________________________________________________________________
Address :-
____________________________________________________________________
Certificates from Heads of officers under whom the work are in progress should be enclose.
ANNEXURE’S
NAGPURMUNICIPALCORPORATION
ANNEXTURE 1
Sr. Materials Test Quantity Rate Per Amount
No.
02 Steel upto 16mm i) Ultimate Tensile Stress 2.00 1275 Each 2550.00
ii)Percentage Eleongation
(set of 3 Bars)
iii)Yield Stress
iv) Weight Per Meter
Note:-
1. The Number Of Test Mentioned above are indicative which may vary at the time of actual execution.
2. The Payment against third party quality testing will be as per the rates mentioned in schedule of testing charges for construction
material used for Government works for the year 2017-2018 By Vigilance and Quality Control Circle , Government Of Maharashtra.
3. The Test Which Are Not covered in the above table and schedule of Testing Charges By Vigilance and Quality Control Circle,
Government Of Maharashtra and if desiredby the Engineer In-charge to carry out this tests and payment of which will be reimbursed as
per actual on production of payment voucher.
Annexure-II
Contractor Photo
(Format of Self declaration to be given on Plain paper.)
I_____________________________________________________________________________
(Name of Contractor/ person,) Aged about ______ years, residing at _______________
_____________________________________________________________ (Postal Address) do hereby declare
that I am the proprietor/Partner of (Name of company/firm) Registered at ______________ .
I do hereby declare that, the documents submitted in envelope No.1 of the tender document for the
work of __________________________________________________ _________________________________ are
true correct and complete.
In case, the contents of envelope No. 1 and other documents pertaining to thetender
submitted by me are found to be incorrect or false, I shall be liable for action under the relevant
provision of Indian Penal Code and other relevant laws.
Signature of Contractor
Applicant/ Name
Address ___________________________
Place :-
Date :-
E-mail _________________________________
Mobile No ______________________________
Website ______________________________
Annexure-III
Format for Declaration of Authorized Signatory on plain paper regarding Work allotted, completed
/Incomplete works from Start of Registration
I do hereby declare that, the following information work of allotted through Lottery and Through on
line Contract under Unemployed Engineer Category Tender is true correct and complete.
Executed
Name of Name of Tendered Balance Status
Sr No Cost upto
Division Work Cost Cost of Work
this Tender
Total
Signature of Contractor
Applicant/ Name
Address ____________________________
Place :-
Date :-
E-mail _________________________________
Mobile No ______________________________
Website ______________________________
ANNEXURE – V
QUALITY CONTROL TESTS & THEIR FREQUENCIES
2 Metal i) Crushing Value One test per 200 cum or part PWD hand book
ii) Impact Value thereof. I.S.2386 Part-IV
iii) Abrasion value
iv) Water Absorption
v) Flakiness Index
vi) Stripping value
vii) Gradation
M.O.RT H.
Rigid specification 900
Pavement
(Fifth revision Table
No. 900-6)
4 Cement i) Comp. Strength One test for each I.S. 8112 -1989
ii) Initial setting time consignment of 50 MT
iii) Final setting time (1000 bags) or part thereof.
iv) Specific Gravity
v) Soundness
vi) Fineness
5 Steel i)Weight per meter One test for every 5.0 I.S. 432
ii) Ultimate Tensile METRIC TONNE or part
stress thereof for each diameter. IS 1786-1985
v) CBR
As required
8 Wet Mix i) Aggregate Impact One test per 1000 cum. M.ORTH.specificatio
Macadam value n Table 900-3
ii) Gradation
iii) Flakiness Index & .(fifth revision 2013)
One test per 200 cum.
Elongation Index.
iv) Atterberg limits of One test per 500 cum.
portion of aggregates
passing 425 Micron.
9 Prime coat i)Quality of binder No. of samples per lot and M.ORTH.specificatio
/ tack coat tests as per I.S. 73, I.S. 217 n Table 900-3
/ Fog spray and I.S. 8887 as applicable.
.(fifth revision 2013)
ii) Binder At regular close intervals,
Temperature
vi)Water sensitivity of
mix (if required)
vii)Gradation
x)Binder content
-----do-----
At Regular interval.
Concrete ii) Impact / Abrasion One test per 350 Cum of .(fifth revision 2013)
value aggregate for each source
and whenever there is
change in quality of
aggregate.
-----do-----
iii) Flakiness &
elongation index
iv) Soundness One test for each source and
whenever there is change in
quality of aggregate.
-----do-----
v) Water Absorption ----do-----
xii) Temperature of
One set for each 400
Binder in boiler,
tonnesof mix subjected
aggregate in drier and
Contractor No. of Correction Executive Engineer
93
xiv) Density of
compacted layer
ii) Ductility
v) Specific gravity
15 Chequred i) Water absorption Shall not exceed 10% Set of 6 Tiles shall be
Tiles tested per every
ii) Transverse strength The average width 2000 tiles or part
transverse strength shall not thereof.
be less than 30 Kg/cm2
Annexure VI
TESTING
STATEMENT
Contractors:-_________________________________________________
Name :-
Note:-
1 As Per Circular No.219/S.E./2022 dated 12/12/2022
2
The Government of Maharashtra Revenue and Forest Departments Gazette No.146
Date 04 June 2021
3
a) For Sand =Royalty + surcharge )2%) + Distt. Mineral Foundation Cess (10%)
=211.95+4.23+21.19=237.37 Per Cum.
b) For Other Minerals= royalty + suracharge (2%) =211.95+4.22=216.18 per cum
¼1½ ejkBh
uequklR;izfrKki= ¼:-500@&P;kLVWEi isioj½
lR;izfrKki= (Affidavit)
eh-------------------------------------------------o; o”ksZ ---------------------------jkg.kkj ;k
lR;izfrKki=k}kjsfygwunsrks dh] eh----------------------;k QeZpk@daiuhpkekydvlwu---------------------
-- ;k dkeklkBhfufonklknjdjhrvkgs- R;kfufonsP;kfyQkQk Ø- 1 e/;s dkxni=s
lknjdsyhvkgsrrh [kjh] cjkscj o iw.kZvkgsr] R;ke/;s dks.kR;kgh =qVh] pqdkukghr] ;kph
eh [kk=h dsyy s hvlwuvls ‘kiFkiwoZd [kkyhyvVh o ‘kFkhZlgekU; djhrvkgs- ;k
dkxni=kae/;s dkghpqdhph] fn’kkHkwydj.kkjh] [kksVh o rlspviw.kZekfgrhvk<Gy;kl eh
Hkkjrh; naMlafgrkvarxZrdk;ns’khjdk;Zokghlik= jkghu-
1- tj da=kV dkyko/khnjE;ku] eh
ekÖ;kdk;kZy;kusfdaokekÖ;kdeZpkÚ;kauhlkoZtfudcka/kdkefoHkkxkykdks.krhgh
[kksVhekfgrhfdaokns;dkleosrrlspi=O;ogkjkr [kksVh@cukoVlkfgR; [kjsnhphdkxni=s
lknjdsyhvly;kl] eh Hkkjrh; naMlafgrkvarxZrdk;ns’khjdk;Zokghlik= jkghu-
2- tj da=kV dkyko/khnjE;kuvkf.kdkelekIrhuarj] vafrens;d
ns.;kP;krkj[ksi;Zarlknjdsyy
s sdks.krsghdkxni=s [kksVh@cukoV] Qlohvk<GY;kl] eh
Hkkjrh; naMlafgrkvarxZrdk;ns’khjdk;Zokghlik= jkghu-
3- tjdkelekIrhuarjnks”knkf;Rodkyko/khnjE;kufdaokR;kuarjdks.kR;kghosGh]
dks.krhghekfgrhfdaokdkxni=s [kksVh@cukoV] Qlohfadaokfn’kkHkwydj.kkjhvk<GY;kl] eh
Hkkjrh; naMlafgrkvarxZrdk;ns’khjdk;Zokghlik= jkghu-
APPENDIX- II
1 2 3 4 5
1
1) All the materials are to be
procured and brought by the
contractor at the site at his own
risk and cost.
NMC, NAGPUR
NAME OF WORK:- Construction of Toilet And Covering Of Shade and Providing And
Fixing Iblock And Various Civil work at NMC Vyamashala at Tulsibag Mahal in Pr.
No. 18
As Per BOQ Attached
SCHEDULED – C
TECHNICAL SPECIFICATION
SCHEDULED 'C'
OFFICE OF EXECUTIVE ENGINEER DPDC
NMC, NAGPUR
SCHEDULED – D
DRAWINGS
As Per Attached