Crane Costing
Crane Costing
Niina Ekqvist
Keywords: cost management, cost estimating, cost structure, product cost reporting,
cost estimation accuracy
This study aims to find out the average cost structure of standard industrial cranes.
Focus of the study is in the installation costs where the biggest uncertainty and the cost
reduction potential lie. The study is conducted as a case study in which data from five
case countries is collected, analysed, and cost structures are compiled and compared.
Additionally, a current level of cost estimation accuracy is evaluated and possible
improvements in cost estimation, cost accounting and site operations are considered.
The greatest challenge of this case study was the disintegration of the cost data. Thus,
the need for harmonizing product cost reporting was raised. Current level of the cost
estimation accuracy was not satisfactory; thus, improvement needs were seen especially
in installation cost estimations. One suggested way was to exploit previous knowledge
and experience more efficiently. It was also discovered that product life cycle cost and
other value creating factors as reliability of the crane and availability of spare parts
should be considered in the selling process.
TIIVISTELMÄ
This thesis is dedicated to my dear mother, Terhi, who sadly passed away during this
process. I wish she could see me finally graduating. I owe her everything.
This study was conducted already in 2011. However, I jumped into the (working) life and
publishing my thesis was delayed for several years. Thus, I would kindly thank everyone at
LUT university for their flexibility and gentle push towards finishing my degree. Special
thanks go to my supervisor Timo Kärri for his support and advices regarding this thesis.
You are all doing a great job in providing students the foundation for their careers.
I would like to thank also my supervisor in the case company for his support with this
study, and for the years we worked together. The case company and its people gave me
invaluable support and experience that I have been able to exploit on my career.
Finally, I want to thank my family and friends for being there for me. My husband and
children have taught me what really is important in life and have brought balance between
work and personal life. I couldn’t be more grateful at this very moment!
Sincerely,
Niina Ekqvist
TABLE OF CONTENTS
1 INTRODUCTION ................................................................................................. 1
6 CONCLUSIONS ................................................................................................. 61
LIST OF ABBREVIATIONS
CM Contribution Margin
KM Knowledge Management
LL Lessons Learned
VE Value Engineering
1 INTRODUCTION
1.1 Background
Accurate, up-to-date and easily available cost information is essential for decision-making,
as the product cost information is used in pricing, cost estimating, profitability analyses,
make-or-buy decisions etc. Unfortunately, cost accounting and cost management in
international companies has its challenges because of diverse cost accounting practices and
separated systems. This challenge has been recognized in Konecranes and measures have
been taken. Project for harmonizing and activating product cost reporting in Konecranes
was launched in 2009. In addition, global SAP ERP system implementation project has
been set in train which will resolve some problems, also around the area of cost reporting
and cost management.
In 2010, orders received for equipment business area totaled 1004.9 million Euros, from
which share of industrial cranes was around 45 %. Industrial cranes sales thus accounts for
almost half of the equipment sales. Industrial cranes business unit is further divided into
three business lines: standard duty cranes (SDC), heavy duty cranes, and work station
lifting systems. Volumes of SDC are the highest of the industrial cranes business line.
Therefore, potential cost saving in this product line is significant. Need for further research
related to recent product cost harmonization project emerged. This thesis aims to fulfill the
need of clarifying costs of industrial cranes, and therefore, to produce support information
for decision-making. (Konecranes 2010, p. 63)
How the total costs of standard industrial cranes are divided into cost categories?
How big proportion installation costs are from the total costs?
What is the current level of cost estimation accuracy and can it be improved?
The main research question is how the total costs of standard industrial cranes are divided
into cost categories. The objective of this research is to examine the cost structure of an
average industrial crane. Focus of this research is on the tag end of a cost breakdown
structure because the biggest uncertainty lies in those costs, i.e. the installation/site
operations costs. After clarifying the cost structures and proportions of installation costs,
these average cost structures of each case country are compared, and differences are
reported. Additionally, a current level of cost estimation accuracy is evaluated and possible
improvements in cost estimation, cost accounting, pricing, and site operations are
considered.
Research is limited to three standard duty crane models which are introduced in chapter 4.
These crane models are chosen as the sales volumes of these models are the biggest.
Countries in scope are limited to five countries which are chosen because of their
importance for the case company. Chosen case countries are Finland, Germany, Hungary,
China, and USA. Other limitations are related to the cost categories. Because costs of the
components including material, labor, and other production costs are well known already,
there is no need to concentrate on how these costs are incurred. Concentration of the
research, thus, is on the site operations and final installation costs as estimating those costs
is the most challenging part of product cost estimating. This research doesn’t focus either
on the freight costs because freight costs are changing all the time, and it is not very
3
worthwhile to find out the accurate freight and transportation costs, as the information
would be outdated quickly.
Theoretical part of this thesis concentrates on cost accounting and cost engineering.
Research objectives of this part are related to the challenges in cost accounting and
engineering. Main concepts are introduced and previous studies about cost engineering,
especially cost estimating, are examined. Theoretical research problems are as follows:
How total costs of industrial products are composed of and how these costs can be
estimated?
What are the biggest challenges in cost engineering and how these challenges can
overcome?
goes through examining current practices in site operations and cost accounting aiming to
spot the strengths and weaknesses in those practices, and by giving suggestion how to
develop the weakest links. (Aaltola & Valli 2001, p. 158-177)
Case
Finland Germany Hungary USA China country
INPUT OUTPUT
Concepts and theoretical Chapter 2: Costs and Cost accounting and cost
frameworks of cost Cost Management management practices in
management theory
2.1 Costs
Cost is the monetary amount i.e. the value of an activity or an asset which is sacrificed or
forgone to achieve a specific objective. Budgeted cost is the forecasted or estimated cost,
actual cost is the cost incurred. Costs are divided into direct and indirect costs. Direct costs
are costs that are directly related to completing an activity, or an asset. They can be traced
to this cost object in a cost-effective way. Assignment of direct costs is thus called cost
tracing, whereas, indirect costs cannot be traced to the particular cost object in a cost-
effective way. Indirect costs are those resources that are needed to support the activity or
asset, but these costs are also related to other activities. Assignment of indirect costs is
called cost allocation. (Horngren et al. 2009, p. 53-54; Amos 2007, p. 1.1-1.2)
The two basic types of cost-behavior patterns are fixed costs and variable costs. Fixed costs
don’t change during a certain defined period of time, and they are not depending on the
volume or the level of an activity. Variable costs depend on the volume of a work activity
or asset, so they change in total at the related level of changes in the volume of an activity.
Both variable and fixed costs can be either direct or indirect. Generally, costs can be
divided as shown in the Figure 3. (Horngren et al. 2009, p. 56-57; Amos 2007, p. 1.3)
As indirect costs constitute a large share of overall costs assigned to cost objects, allocating
these costs has four different purposes. First, cost allocation provides information for
economic decisions, so it helps managers in decision making. Secondly, cost allocation is a
good motivator for managers and other employees. Third reason is to justify costs or
compute reimbursement amounts. And last, incomes and assets are measured through cost
allocation. There are also four different criteria that are used in cost allocation decisions.
These criteria are cause and effect, benefits received, fairness or equity, and ability to bear.
Cost-allocation base is one way how company can link an indirect cost, or group of indirect
costs, to a cost object. An example of a cost-allocation base is machine-hour. The reason
why companies usually use the cost driver of indirect costs as the cost-allocation base, is
that there is a certain cause-effect relationship between the changes in the level of a cost
driver, and changes in indirect costs. (Horngren et al. 2009, p. 124, 527-528)
costs is quite complicated, and might result in distorted product costs. On that account,
companies have been moving from the traditional way to activity-based calculations. By
using activity-based costing, defining the product costs is improved because of better way
of allocation the costs of support activities. Maskell (2006) suggests using value stream
costing as a way solving the standard cost problem. He also states that using standard
costing distorts product costs, and thus misleads people and results in unfavorable decisions
about pricing, profitability, make-or-buy and so on. Value stream costing suits especially
for lean manufacturing companies, and it takes into consideration all the costs in the value
stream. Costs included in value stream costing are shown in Figure 4. Value stream costs
are usually calculated weekly or monthly, and it considers all costs as direct costs, so the
value stream contains almost no allocations. (Brimson 1992, p. 235-252; Maskell 2006, p.
27-35)
Value stream
One way to look at the total costs of a product, is life cycle costing (LCC) which is
designed for cost management and focuses on long term performance of the products. LCC
approach has one basic assumption that future costs of the products can be affected
beforehand by planning the use of the product, or by improving the product or the asset. At
early stages, the focus of the LCC is on estimating the future costs, but later, the focus will
9
change into monitoring and tracking incurred costs. At the very end, the focus is on total
life cycle statement. Fabrycky & Blanchard represented a cost breakdown structure for total
product costs through its life cycle, which is shown in Figure 5. (Asiedu & Gu, p. 886-888;
Lindholm & Suomala 2007, p. 651-654)
Product Manufacturing/
Operation/
Management Constructing Disposal of Non-
Maintenance
Management Repairable
Management
Industrial
Product Planning Engineering and
Operations Analysis Product Operation
Product Retirement
Operator and
Maintenance
Initial Logistic
Support Training
Product Test and
Evaluation
Technical Data
Product
Modification
Figure 5. Fabrycky’s & Blanchard’s total product cost breakdown structure (Asiedu & Gu
1998, p. 887).
10
Operations and maintenance costs constitute the biggest portion of the total product costs.
Unfortunately, these costs are also the most difficult to estimate and forecast. Maximum
availability and maximum customer satisfaction are received by producing a product that is
reliable and easily serviceable. Serviceability can be improved particularly through product
design. The case products of this thesis are standard, established products so the R&D costs
are relatively small, and that’s why, excluded from the total product cost. Production and
construction costs are quite well known already, and the main costs of this category are
costs of the components, steel structures, manufacturing, and assembly. Operation costs of
this case include freight costs, and the site operation costs which are the focus of this
research. Although the retirement and disposal costs are excluded from the cost calculations
of this research, these costs are not fully ignored or left behind, when considering the total
costs of industrial cranes. (Asiedu & Gu 1998, p. 888)
The basic cost of the machine: $1 500 000 Hard costs = $ 1 500 000
Taxes $ 60 000
During the past decades, equipment users have, however, changed their decision criteria
from initial cost to total lifetime cost of equipment ownership. That’s why, equipment
manufacturers should examine also the whole life-cycle cost of their products. One
example about life cycle costs is the LCC elements for pumps which are: system design,
acquisition cost, installation, operation, energy, maintenance and disposal. What comes to
industrial cranes, the cost elements are nearly the same. Noteworthy from this example is
that one should know how different LCC elements interact. As an example: installation cost
optimization can have a negative effect on the maintenance costs, so the whole life cycle
costs might be rocketed, even the installation costs are decreased. That’s why, we cannot
ignore the maintenance, retirement, and disposal costs of the products, even though these
costs are not included in the total cost calculation of the industrial cranes. (Carsten &
Erickson 2007, p. 32)
cost throughout the life cycle of any enterprise, program, facility, project, product or
service.” The TCM process creates the basis for cost management before the cost occurs.
Medley (1994) states, that managing costs before they occur, requires six things. First, the
implementation of TCM requires a life cycle perspective for managers to fully appreciate
the long-term and short-term cost impact on the decision making. Secondly, managers need
to be familiar with the factors that affect costs either in a positive, or a negative way. These
factors can be related to, for example, the political system, economy, legal or financial
systems, location, or internal policies. Thirdly, cost managers need to be aware of the cost
implications of the events, as they occur. By knowing the factors that influence costs,
managers are able to create and maintain an ongoing awareness of the cost implications of
the events, and the risks they bring with. Fourthly, managers need to be familiar with the
tools available for cost management. These tools include cost estimating and engineering,
planning and scheduling, economic and financial analysis, performance measurement, and
management methods. Fifthly, managers must have a sense of responsibility for responding
to the circumstances, in a timely manner. And the last required matter for cost management
is planning the implementation of cost management throughout the life cycle; this plan
should be based on the strategy. (AACE International 2009; Medley 1994, p. GVT.2.1-2.7)
Traditionally has been stated that 80-95 % of the product costs are determined by the
design of the product, therefore, cost management should focus on the design phase, not
manufacturing. However, research done by Cooper & Slagmulder (2004) suggests
otherwise. They found out that it is possible to manage cost throughout the product life
cycle. Therefore, a company shouldn’t focus only on reducing costs in production or
manufacturing, but throughout the product life cycle. From the supplier’s perspective, the
after sales period is critical both in the terms of total product revenues and generated profit.
They introduce five techniques for managing costs, from which each one is critical factor in
the company’s integrated approach to cost management. These major techniques are:
1) Target costing: applied in product design phase, and objective is cost reduction.
13
Target costing technique is defined as a profit planning and cost management system. There
are six key principles for target costing, which are: price led costing, customer focused,
design centered, cross-functional teams, value chain involvement, and lifecycle cost
reduction. Target cost technique is hence usually applied during the design phase, and the
aim is to reduce costs of a new product by closing the gap between estimated target cost
and cost projections for the new product, based on current designs and manufacturing
capabilities. Target cost is simply calculated by deducting profit from the price of the
product. (Ansari et al. 2006, p. 20-21; Cooper & Slagmulder 2004, p. 46)
One difference between target costing and kaizen costing is, that target costing is usually
applied in the product design phase, and kaizen costing in the manufacturing phase. Shank
and Fisher (1999) however think that target costing may be applied also during the
manufacturing stages of the product life cycle. Target cost is derived from estimating the
selling price and eligible profit, and it is a financial target for the total cost of a product.
Kaizen costing doesn’t focus on market prices as target costing does, but the focus is more
on the continual incremental product cost improvements. The product-specific technique
aims to correct any possible cost overruns during the early manufacturing stage, by
redesigning a new product, and the focus of general kaizen costing is on the way how
product is produced. (Shank & Fisher 1999, p. 73-74)
14
In the functional group management, production processes are grouped and treated as
different profit centers, instead of cost centers. That how, employees and managers can be
motivated through understanding their contribution to the company, as instead of working
in the production line, they are a part of a profit center. Also, by using functional group
management, the most efficient and profit increasing production processes can be chosen,
even if the costs might increase at the same time. Product costing is a tool for providing
information, and that way coordinating the efforts of four cost reduction techniques.
(Cooper & Slagmulder 2004, p. 47-48)
Table 1. Pricing Strategies for Industrial Pricing (Noble & Cruca 1999, p. 438).
Pricing strategy Description Related strategies
Price Skimming Set initial price and then Premium Pricing, Value-in-Use
systematically reduce it over time. Pricing
New product Pricing
Experience Curve Set the price low to build volume and Learning Curve Pricing
Pricing reduce costs through accumulated
experience.
Leader Pricing Initiate a price change and expect Umbrella Pricing, Cooperative
others to follow. Pricing, Signaling
Competitive Pricing
Parity Pricing Match the price set by the overall Neutral Pricing, Follower Pricing
market or the price leader.
Low-Price Supplier Strive to have the lowest price in the Parallel Pricing, Adaptive Pricing,
market. Opportunistic Pricing
Cost-Plus Pricing Establish the price of the product at a Contribution pricing, Rate-of-Return
Cost-based Pricing
New product pricing situation is excluded from this discussion because case products are
not new, but standardized products. Also, the competitive pricing situation is not entirely
applicable for this case. That’s why, the focus of the discussion is on complementary
product pricing, customer value pricing, and cost-plus pricing. In cost-based pricing the
consideration is in the internal costs of the company. The basic cost-based pricing formula
is cost base plus the markup component. For example, if the full unit cost is 1000 € and
intended markup is 20 %, the prospective selling price is: 1000 € + (0.20 x 1000 €) = 1200
€. (Horngren et al. 2009, p. 467)
In complementary product pricing, the main product is sold for a low price, while the price
for complementary products or services is much higher. Customer value pricing has
become common in industrial markets, where the appeal of value-prices products varies by
the intensity of product usage and geographical scope of usage. As an example, low
intensity crane users are much more price sensitive than heavy users, when acquiring the
crane. Other important factors for the customer might include the reliability of the machine,
availability of spare parts and service, and the growth rate of the customer’s business. In
conclusion, the initial acquiring price is not always the most important factor for a
customer, but the complementary service and spare parts, and reliability might be much
more valuable. In this kind of situations, the customer value pricing strategy or
complementary product pricing can be applied. (Noble & Gruca 1999, p. 442)
Market-based pricing begins with setting a target price which is the estimated price
customer is willing to pay. The process of developing the target prices and target costs has
five steps:
Value engineering (VE) is a method for acquiring and applying knowledge, and it enables
the realization of life cycle cost and cost effectiveness of projects. It evaluates
systematically all the value chain elements. The objective of the method is to optimize cost
or performance of a facility or a system, and to achieve a quality level that satisfies the
customers. In VE method functions are defined and classified, and through this process
most potential and valuable functions can be spotted. (Horngren et al. 2009, p. 460-462;
Naderpajouh & Afshar 2008, p. 363-364)
2.4 Conclusion
Accurate cost information is essential for companies to be able to make appropriate
decisions about product pricing, new product cost estimates, and profitability. Total product
costs include costs that belong to certain product, through its life cycle from design to
disposal, i.e. R&D costs, production and construction costs, operations and maintenance
costs, and retirement and disposal costs. However, in this thesis calculation of the product
cost is limited to cover the product life cycle only till the product i.e. industrial crane is
installed and signed over to the customer. Therefore, the aim is to find out the initial cost of
the equipment. As equipment users have been moving from considering the initial cost of
the equipment, to considering the whole life cycle cost of equipment ownership, some
attention needs to be given for the costs occurring after the equipment has been delivered.
When analyzing and evaluating total costs of the case products, the affection of the
installations to the usage, maintenance and retirement of the product should also be
considered. Installation cost reduction can have a negative effect on product reliability and
serviceability, and thus detract customer’s image of the original equipment manufacturer
and affect the customer’s decision, when choosing the equipment deliverer. Whole life
cycle cost management techniques introduced were target costing, kaizen costing,
18
functional group management, and product costing. From these techniques functional group
management and product costing might be best possible techniques to apply in the case
company.
Several industrial product pricing methods were introduced in this chapter. Out of these
methods, noteworthy is customer value pricing, as the customer value of the industrial
crane varies greatly by the intensity of the usage and geographical scope of the usage. Low
intensity crane users look at the price much more than heavy users, so the intensity of the
crane usage should be found out at the offering stage, for being able to compete in the
bidding. Other factors that influence the customer’s decision in buying an industrial crane,
include reliability of the machine, availability of spare parts and service, and the growth
rate of customer’s business. When considering those customer requirements, the case
company is very competitive, as the service network of the corporation is wide, and spare
parts are easily available around the world. As these after sales services add more value for
the customer, they should also be marketed and used as a selling argument, even more
efficiently by the crane sales persons.
19
3 COST ESTIMATING
While scanning through the publication databases, can be observed that the literature and
previous studies about cost estimating, have been focusing on cost estimates mainly in the
construction or software industries. That’s why, it can be challenging to examine these
publications critically enough to be able to apply these theories and conclusions to this
particular case. AACE (the Association for the Advancement of Cost Engineering)
International is in 1956 founded non-profit professional educational association. They have
several publications in the field of cost engineering, for example a monthly issued technical
journal called Cost Engineering. In this thesis the cost engineering terminology defined by
AACE International is used. AACE defines cost estimating as follows: “A predictive
process used to quantify, cost, and price the resources required by the scope of an asset
investment option, activity, or project. As a predictive process, estimating must address
risks and uncertainties. The outputs of estimating are used primarily as inputs for
budgeting, cost or value analysis, decision making in business, asset and project planning,
or for project cost and schedule control process”. Cost estimating is usually used for
establishing a project budget, but it can also be used for determining the economic
feasibility of a project, evaluating project alternatives, or proving a basis for project cost
and schedule control. (AACE International 2009, p. 8; Dysert 2006, p. EST.01.1)
The basic steps of cost estimating are the same in costing or pricing any investment
activity. First step is to understand the scope of the activity to be able to quantify required
resources. Usually cost estimation begins with establishing the project scope and the format
of providing information for business decisions. Next step is to apply cost to the quantified
resources, and then to apply pricing adjustments. Finally, outputs are organized into the
format that supports decision-making. When estimating cost of equipment Uppal (1996)
suggests that cost information can be collected using one of the following methods:
Basically, there are three different sources for acquiring cost-related data: published cost
information, costs from similar projects and project equipment costs, and historical data
from company’s own systems and files. (Amos 2007, p. 9.1; Uppal 1996, p. EST.10.1;
Uppal 1997, p.168-C)
Product Cost
Estimation
Techniques
Qualitative Quantitative
Back-propagation
Decision support Breakdown
neural-network
systems (DSS) approach
models
Tolerance-based
cost models
Feature-based
cost estimation
Activity-based
costing system
Figure 6. Product Cost Estimation Techniques (adapted from Niazi et al. 2006, p. 569).
Intuitive estimation methods are based on exploiting the previous experience and
knowledge. Knowledge used in these techniques may be stored as series of rules, decision
trees, judgement etc. Case-based method is often called case-based reasoning (CBR), and it
uses the information of previous cases in estimating new product costs. CBR has been one
solution for matching previous cases to new cases, working as a problem-solving paradigm.
CBR cycle is shown in Figure 7 and is described as four “REs”: 1) Retrieve similar cases,
2) Reuse information and knowledge from the previous cases to solve the current case
problem, 3) Revise the proposed solution if needed, and 4) Retain the knowledge from new
experience in order to utilize it in future cases. In the Figure 6, the abbreviation LL refers to
22
lessons learned, which is introduced in chapter 3.3. (Naderpajouh & Afshar 2008, p. 365;
Niazi et al. 2006, p. 564)
Figure 7. CBR cycle (adapted from Naderpajouh & Afshar 2008, p. 365; Watson 2004, p.
676).
Decision support systems (DSS) are interactive computer-based systems aiming to help
decision-making. They are useful tools in evaluating and comparing different alternatives.
They are a great help in retrieving, summarizing, and analyzing data that is relevant to
current case problem. There are five DSS types introduced in “Decision support systems
resources”, which include communications-driven DSS, data-driven DSS, document-driven
23
DSS, knowledge-driven DSS, and model-driven DSS. DSS can be exploited in cost
estimating and decision-making process not only for acquiring support information, but for
discussing the rules cost estimators apply, when making decisions according to the support
information. (Decision Support Systems Resources 2011; Niazi et al. 2006, p. 564; Power
1997)
Parametric models are mathematical representations of cost relationship e.g. between the
equipment cost and its key parameters like weight, volume, and complexity. Parametric
cost estimation techniques suit well for preparing early conceptual estimates, and for
example, in situations where local unique conditions need to be considered in estimates. To
be able to estimate equipment costs by using parametric models, historical data is needed.
By applying this cost data about recent projects, using regression models and statistical
tests, a final model can be created. Parametric estimating usually includes seven stages
which are: 1) determining the cost model scope, 2) collecting data, 3) normalizing data, 4)
analyzing data, 5) data application, 6) testing, and 7) documentation. (Amos 2007, p. 9.11-
9.12; Shabani & Yekta 2006, p. 26)
In general, cost estimating methods are divided into two different groups: conceptual and
deterministic (detailed). One example of detailed estimating activities associated with a
process or industrial project has been introduced by AACE International. In this example
preparation of detailed estimate includes, for example preparing project estimate basis and
schedule, preparing direct field cost, indirect field cost and home office cost estimates,
preparing cost risk analysis or contingency determination, and validating the estimate.
Lesson to be learned from this example is estimating the equipment installation costs. As it
has been stated also earlier, estimates shouldn’t be prepared only by the estimator, but also
construction assistance is needed, when special installation methods are used. In the case of
installing process equipment, installation work hours are usually based on weight and
equipment dimensions and are typically determined from curves of historical data.
24
Estimator needs to make sure that all labor associated with the pieces of equipment and all
the other activities, like testing, are considered. Situations where installations are conducted
by subcontractor, and cases that require special installation, materials should also be
identified and estimated. (Amos 2007, p. 9.4-9.17)
“Reliability of an estimate refers to the closeness of the initial estimated value(s) to the
subsequent estimated values. Accuracy of an estimate refers to the closeness between the
estimated value and the (unknown) true value that the statistics were intended to measure.”
(Boeschoten 2005, p. EST.20.1)
Accuracy of the estimate is usually represented as a +/- percentage range around the point
estimate, in along with the level of confidence. The Government Accountability Office
(GAO) has created a list of nine basic characters, that have an effect on the accuracy and
reliability of cost estimates. These characters are:
Cost estimating is one key factor to the success of a project. Thus, accurate cost estimates
are critical in project management. The cost estimate doesn’t serve only the budget
establishment but works as a scheduling and cost control tool for projects. Term cost
engineering is used for this combination of estimating, scheduling, and cost control.
Because cost estimating is only predicting the expected final cost, uncertainty and
possibility for errors at some level, are related to the cost estimate. Thus, there is always a
possibility that predicted costs might overrun or underrun. Especially in site operations
several uncertainties exist. When considering the uncertainties, an amount that is often
called contingency, is added to the created point value, which then forms the final estimate
cost. (Amos 2007, p. 9.1-9.19; Wang & Huang 2000, p. 131; Dysert 2006, p. EST.01.1)
Lund (2005) states that accuracy of project estimates in many cases is not fully understood.
and accuracies are not valid until estimators can state confidence about the estimate. On the
other hand, one can’t determine confidence. He suggests that this riddle can be solved by
estimators by accepting the inevitable, establishing standard accuracies, establishing
deliverable standards, and/or helping others to understand the estimates better. Of course,
all the uncertainties cannot be eliminated by improving cost estimate accuracy, but one
should anticipate these uncertainties, and ponder how they can be managed. (Lund 2005, p.
61-62)
“Accurately forecasting the scope, cost and duration of future projects is vital to the
survival of any business. Cost estimators develop the cost information that business owners
or managers need to make a bid for a contract or to decide on the profitability of a
proposed new product or project. They also determine which endeavors are making a
profit.” Cost estimating has been described as a combination of science, art, and voodoo.
The science part is quite clear and simple, specifying an accurate composition of the
estimate. In the art part, the judgement and knowhow of the estimator is needed, because
although there are databases, historical data and information about required resources and
26
costs available in every company, using this data requires evaluation of the characteristics
of the specific project, and evaluation of how standard costs should be modeled to fit these
characteristics. The voodoo part is mainly about anticipating future in business, usually
meaning anticipating the changes in the market and economic conditions and evaluating the
sources of risk. Certified cost engineer William Kraus emphasizes in his article in Cost
engineering journal that qualified, experienced, and knowledgeable people cannot be
replaced in the parts of art and voodoo. Computers are a great aid in searching for the
historical data about costs, but still the evaluation and judgement by an estimator is needed,
in order to be able to receive more accurate cost estimates. (Kraus 2008, p. 3-4)
The cost estimation process and its stages can be seen in Figure 8. The process model of
cost estimation and pricing includes four critical decision stages: three internal decisions
whether to continue with bidding process or not, and one external decision where customer
decides whether to approve or reject the bid. In these decision stages, the information
should be collected so that it could be utilized in similar decisions in the future. Six
27
different estimator roles can be identified in the process: enquiry evaluator, estimation time
evaluator, time estimator, prime cost assembler, price evaluator, and final price producer.
These roles are usually divided up among several people, but one estimator can also have
several roles in the process. There are 11 stages in the process, and they are categorized to
stages that require judgements or decisions, and stages that include actions and information
transfers. (Kingsman & Souza 1997, p. 125)
28
Companies rarely compare their estimates with the actual cost, which leads into situation
that cost estimator doesn’t know how large the cost variances are, and hence, how accurate
the cost estimations really are. The ratios between actual and estimated costs can be ranging
both ways extremely. And that’s why, it is important for a company to learn from the past
cases and possible mistakes made in estimation process. By calculating the risk with cost
variances, company prepares to inaccuracies of cost estimate. Risk with mistakes by the
estimator includes adjustments to compensate possible errors made by the cost estimator.
Sources of these errors can be, for example, the limited time for preparing the estimations,
reliability of information provided by the customer, confidence in the cost/time ratios used
in the costing system, dependency on others’ estimates, and a lack of self-confidence.
Mark-up on materials is just a preparation for possible changes in the costs of materials
caused by inflation, shortage of suppliers, or expected variation in exchange rates.
(Kingsman & de Souza 1997, p.128-129)
Knowledge management (KM) has become more and more important asset for companies.
One of the most essential knowledge management tools is the exploitation of previous
experience, or so-called lessons learned (LL). Lessons learned means the valuable
knowledge which is learned through previous experiences and projects. Watson (2004) has
described one way of capturing and reusing the LL from the installation of engineering
equipment. In this case, a case-based reasoning system has been designed to support the
installation of heating ventilation and air conditioning equipment. The goals of using this
system included reducing the installation specification and quotation time, reducing the
margin of error build-in to pricing, and eliminating the need of checking every detail of the
30
specifications by head office engineers. The problem in this system was that system didn’t
offer relevant LLs to engineers, thus, LL couldn’t be applied efficiently enough during
design and installation. Improvements to the systems were made by enhancing the role of
knowledge management. When preparing estimation for new projects, system offers files
including drawings, technical specifications, bill of quantities, and notes or so-called
trouble tickets from previous similar cases. By saving and reusing trouble tickets, lessons
from previous cases can be learned and reused. Improved system offers reminders of
lessons learned information at two stages. At the first stage, the set of all similar installation
records are sent, so that LL can be reused in the current cases. During the installation stage,
a reminder is also sent to engineers to encourage them to create trouble tickets about the
current case. (Jeon 2009, p. 13-14; Watson, p. 672-677)
estimating methods alone are not enough, but analysis of uncertainty and risk is needed
while making cost estimates. Range estimating is a tool for considering the risk and
sensitivity of the cost estimates, so it is not a cost estimating tool but aims to improve cost
estimates. Range estimating helps to eliminate or reduce the risk of cost overrun.
(Kingsman & de Souza 1997, p. 121, Noor et al. 2006, p. OWN.05.1-OWN.05.4, Curran
1989)
Risk ranging example about turnkey power plant projects is, of course, not fully applicable
for other industries but some lessons could be learned from it. In this case example, cost
estimating templates were used for base cost estimates. Cost estimating templates utilize
data about former similar projects, and the aim is to compare prior estimates with the actual
cost data. The key factor is the ability to choose most suitable reference from earlier
projects and apply that data for new cost estimating template so that one doesn’t need to
start filling a fully blank template. That’s how filled-in form only needs to be tailored to
meet the specific requirements for a project. By using templates, some of the uncertainty is
reduced but also some residual cost risks and unknown factors need to be considered in the
estimate. When the base cost estimate has been finished and inspected, risk range
estimating should be performed. First task of the risk ranging exercise is to identify the
potential risks that could impact the base cost estimate. Risk lists created for previous
projects can be used. As previous experience is exploited in risk ranging, the prepared risk
list only needs to be reviewed so that it is applicable to the current project. When the list of
risks is finished, the risks are grouped into categories. After risks are identified and
grouped, the question how the base cost estimate could be affected by the listed risks is
answered so that the risk range can be captured. (Noor et al. 2006, p. OWN.05.1-
OWN.05.4)
When talking about risks, uncertainty, and potential cost overrunning the term contingency
should be perceived. AACE International defines contingency as follows: “An amount
32
added to an estimate to allow for items, conditions, or events for which the state,
occurrence, and/or effect is uncertain, and that experience shows will likely result, in
aggregate, additional costs”. The most common elements and characteristics of
contingency include for example covering all the unforeseen elements of cost within a
defined project scope, in association with the risk of overrunning the target cost with a
certain probability of occurrence, and intention to cover additional costs that might occur
during a project because of incidents, like abnormal start-up problems. Contingency
estimation can be done by using one of the contingency methods that are divided to
deterministic and probabilistic methods. Examples of deterministic methods are overall
value method and item by item value. Probabilistic techniques are further categorized to
independent and correlated methods which both are further divided into direct and
simulation techniques. Sources of risks and uncertainty have been studied in the
construction industry. These sources could be considered also when estimating the risks
and uncertainties of site operations. These project-specific uncertainties that might raise a
risk that should be considered in the project contingency are:
usually excludes changes in scope, human errors, natural disasters, unexpected work
stoppages, inflation etc. (AACE International 2009, p. 5; Amos 2007, p. 9.22; Moselhi
1997, p. A.06.1-A.06.3)
Industrial product-service systems (IPS²) represent a new way of delivering value for
customer during the whole product life cycle. They are a combination of product and
services that provide higher customer value in business-to-business markets. IPS² is
characterized as an integrated product and service offering that delivers values in industrial
applications. IPS² has been noticed to deliver competitive advantage for the manufacturers.
However, to be able to benefit from IPS² one needs to understand the uncertainties that
have an effect on the value creation during the product-service projects. Higher value
creation for customer can be reached through shifting from mere product sales to value
34
sales. Thus, the contact phase between customer and original equipment manufacturer
(OEM) will extend to whole product life cycle from design and development to the actual
use of the product. This results in better knowledge of the usage of OEM’s products which
can raise opportunities for the OEM. As customers are concentrating on their own core
competencies and outsourcing secondary tasks, they demand flexibility, quality, fast
delivery dates, and reasonable prices from their suppliers. These requirements demand
supplier’s development from leadership in technology to leadership in use. Motivations for
the OEM to shift from technology leadership to leadership in use are, for example, the rise
of customer loyalty, opening of new business fields, development of market shares, and
information about the use of its products for creating innovations. Integration of products
and services and development of product-service systems enables the suppliers contact their
machines through the whole product life cycle, and thus a possibility to optimize them.
(Erkoyuncu et al. 2011, p. 1224; Meier et al. 2011, p. 1175-1177)
Intensive collaboration between the factory and the service organization brings also more
value to the customer, because this way they can buy the installation service with most
expertise, and at competitive price. Advantages of equipment installation conducted by the
OEM include offering the best knowledge of installation and usage of the equipment for the
customer, eliminating the extended communications as serving the customer as single-
source provider, offering the best project coordination time-efficiently, and bringing the
familiarity with the equipment, installation expertise, and equipment usage training. OEMs
also have the best connections to the sub vendors, so it is possible to offer the installation at
competitive price. Fast installations also create more customer value as the equipment will
be ready to use quicker. (Ditzer 1998, p. 118-120)
3.6 Conclusion
Cost estimating process begins with understanding the project scope and perceiving the
information needed in decision-making in costing and pricing a product. Cost information
35
used in cost estimations can be gathered from the published cost information, cost data
saved about previous products, and other historical data from company’s own systems and
files. All this information is available also in the case company and can be utilized in cost
estimates. Cost estimation techniques include both qualitative and quantitative methods.
Qualitative methods can be applied in situations where previous experience and knowledge
is available to be exploited. CBR method is one of the suitable techniques for the case
company as information of the previous cases is available. The challenge, however, is that
this information is much dispersed, and thus difficult to collect. One solution for gathering
and saving knowledge and experience is lessons learned and use of the trouble tickets. That
is one way to retain valuable information about previous cases and learn from earlier
experience.
Cost estimating accuracy often is one of the biggest stumbling stones. Estimating,
forecasting, and predicting are not an easy task as there are several uncertainties and
possible risks included in the cost estimates. Cost estimating accuracy may be improved by
identifying the tasks clear enough, involving several participants in estimate preparations,
gathering valid data, recognizing the inflation and excluded costs, predicting uncertainties
and risks, and receiving independent reviews of the estimates. Use of previous experience
is also essential in cost estimating. The important of experience-based knowledge and
ability for judgement cannot be overemphasized especially when talking about installation
and site operations costs. Historical data and information create the base for cost
estimating but using this data efficiently requires evaluation and judgement of experienced
people. That’s why, installation cost estimation should be done in co-ordination with an
estimator and someone who knows the field of site operations well.
The challenges in cost estimation are often raised because of limited information and data
received, short estimation time, and multiple uncertainties and possible risks involved. To
be able to prepare for possible changes and risks, contingency is usually added to the
36
estimates. Uncertainties that might raise a risk and that should be considered in the project
contingency include, for example, characters of project delivery system, project location,
complexity, logistics, and project schedule. Risks and uncertainties can be managed at
some level by using experience-based knowledge and judgement, and by evaluating the
possible risks in the estimation phase. If a machine is not only manufactured but also
delivered and installed by the OEM, more challenges are faced. Thus, also uncertainties
related to the service part of the product need to be considered. Service uncertainty is
driven by the quality of information flow and knowledge in the service network, so the
importance of the co-operation between participants of the supply chain and service
network is essential. One solution for improving product and service delivery is the
adoption of an industrial product-service system.
37
Standard
duty cranes
Port cranes
Konecranes Lifttrucks
business areas
Crane service
Port service
Service
Machine Tool
Service
Parts
Modernization
38
Products in scope of this research are standard duty industrial cranes. The main components
needed usually includes one or at some cases two hoists, two pieces of end carriages, two
pieces of bridge drives which are also called traveling machinery, one bridge panel, power
supply package which includes bridge power supply and trolley power supply, and control
system which may include push button or radio controlling system. Total costs of the
cranes include costs of crane components, cost of main girder and assembly of the crane,
freight costs and crane installation costs. Crane component costs refer to the cost of the
components listed above. Two sample pictures of the products in scope are shown below in
Figures 10 and 11. SP code means the strategic product code. SP11 code products are
profile industrial cranes and SP12 products box industrial cranes. Box and profile refer to
the shape of the main girder. Main girder is the girder between the crane runways and they
are usually manufactured locally by subcontractors.
Usually in SP 11 and SP 12 projects experienced sales person is the key factor in the
project. They can calculate project costs quite accurately already at the bidding stage, so
that there is no much need for adjusting in later phases. Standard offer can be made in
around 20 minutes if sales person is well-experienced. More time is demanded when the
product is more complicated and additional features or manual adjustments are needed.
Sales person’s experience is also essential for cost optimization. Customers also need to
know well what they require from the crane, and how and where the crane is going to be
40
used to prevent possible claims after crane delivery. Even small adjustments can have
significant effects on the total price of the crane. So, if no special components or characters
are needed, standard and automatic selections should be used to make the most competitive
offer as possible.
Crane sales offer is compiled by first creating the crane technical calculations in which all
the components are defined. After crane technical calculation is finished technical drawings
can be created with DAS (Drawing Automation System). DAS has been in use since 2003
in Konecranes. DAS can be used for creating the drawings fast and efficiently, so that
further designing is not necessarily needed. Thanks to DAS, design costs are relatively
small or there are no design costs at all in the total costs of standard duty cranes. For
example, CAD drawings and 3D drawings can be viewed, printed, and attached to the offer
sent to customer. By running technical calculations, only the crane ex works can be
calculated and priced so also the calculation of delivery items is needed. First distances to
the site are entered. These include the journey of the crane transportation, and the travel
kilometers of the erection team and mobile crane. Then further information about crane
delivery is entered including the transportation method and possible special packing and
loading needed. That way, packing and transportation costs are calculated. Transportation
costs are thus estimated automatically by multiplying transportation distance with estimated
cost/kilometer. Costs of the crane erection work are estimated automatically according to
the technical data of the crane entered earlier. These work hours can be however adjusted
manually if needed, and if additional information about the site has been received. Erection
hours are usually estimated by the sales person who adjusts the hours according to the
information about the site. As an example, two totally different kind of cases are explained
below:
• In case A, the site is a brand-new factory which is not operating at the time crane
will be installed, and it is possible to drive the crane delivery truck inside the factory
41
to the actual place where crane is going to be operating at. In this case can be
presumed that there is no need to adjust the erection hours or to add any additional
erection costs like accommodation costs because erection is assumed to finish in
less than one working day.
• In case B, the site is an already operating factory where space is limited, and it will
be difficult to get the crane inside the factory. The space where crane is going to be
installed is narrow, and there is a possibility that crane cannot be erected without a
hitch. In this case, the sales person or other Konecranes representative who visits
the site before cost estimation and offer making, needs to estimate if more erection
hours will be needed than suggested.
Other factors that have an effect on the site operations costs include, for example, erection
tools and equipment and number of workers needed. Mobile crane and erection platform
costs are usually calculated automatically according to the type of the model crane and
working time needed. Costs of delivery items also include commissioning costs like
compulsory inspection costs and test load costs. After all these data has been entered, total
costs of the crane can be calculated at the pricing section. Costs and offer prices are
calculated automatically but they can be adjusted by adding discounts, and by adjusting
intended CM2-% or CM2 for each cost item.
When calculations are ready, an offer to the customer can be created. Information needed at
this stage includes customer data like contact information and delivery address, terms,
times and status including delivery time, length of the warranty period, and payment terms.
After offer has been created and sent to the customer, offer is managed through ProCom
system. If the offer is accepted by the customer, the status will be changed into an order
when manufacturing factory is noticed, and the crane manufacturing stage can begin. Order
is managed through several systems by project managers.
42
Crane installation costs are highly influenced by the characters of production environment
where the crane is going to be operating in. The most challenging cases are the production
sites which are in operation while crane is supposed to be installed. Other challenges
include narrowness of the facilities and roadways, the level of crane build-up and operating
height of the crane. (Hartikainen 2005, p. 61)
then results in the state of harmony where the participants cluster around one method of
accounting, or limited number of almost similar methods.
Currently there are several ERP and other IT systems in use at Konecranes. This may
sometimes inflict on data modification when transferring data between different systems
and sometimes even confusion which system to use. Different departments or cost centers
may be using different systems for their reports and data needs to be moved sometimes
even manually between systems. Thus, data is often modified and differences between
figures that should be the same may be remarkable in some cases.
OneKonecranes process has been depicted in Figure 13. It introduces the factors, functions,
and systems during the product life cycle. There are three core processes: product, sales and
delivery that are supported by five functions: engineering, procurement, manufacturing,
people and finance. As stated in chapter 3.5 intensive collaboration between the sales
organization, factory, and the service organization brings more value to the customer. As
well Konecranes is aiming to serve customer as one single-source provider, which brings
competitive edge. Therefore, functions of OneKonecranes need to collaborate and develop
harmonized practices. During the product life cycle, costs should be more visible to all the
functions. Cost accumulation should be noticed and reported in every process phase. This
demands collaboration and transparency between different functions. OneKonecranes
project therefore might be one good stepping stone for harmonizing also financial practices
and systems, and product cost reporting through the whole corporation. (Konecranes
2010D)
46
Cost data for this research was collected by requesting cost data about around ten recent
SDC projects from business controllers from each case country. Requested data included:
order/project number, crane description, sales price, total costs divided into costs of
component and freight, and total site operations cost, which were further separated to work
hour costs, traveling costs, lifting equipment rents, installation material and other site
operations costs. In addition, cost estimates for total crane costs and installation costs were
requested. After receiving these cost details, CM2 and the proportions of the cost categories
were calculated. Cost data was collected to one summary spreadsheet and average cost
structures for each case country and average cost structure of all the cases together were
formed. In this chapter, this analysis is explained case by case, and then results are
introduced and compared with each other.
of their SP and model, and because of their character as the aim was to find average
projects. When these projects were selected, data about site operations was gathered from
the ERP system of Konecranes Service Finland. As well, the total costs of cranes have been
saved to this ERP system and the costs have been divided into cost categories which
include among others:
This division of costs seemed rough, and the data seemed not reliable enough to be used
without comparing it with the data received from other systems. That’s why, more detailed
data about components, manufacturing and freight was searched from the other ERP system
called iLM by searching for confirmation of orders by project numbers. Through this
system detailed information about sale prices of design and project management,
components, steel structures, and freight was collected. This data and data received from
Service’s system were compared and costs were divided into four cost categories:
components, steel structures and other external manufacturing, freight and installation.
There was some variation between the total costs calculated and total costs saved in
Service’s ERP system. Calculated numbers were 86-112 % from the total costs saved to
Service’s ERP system and their roundup table. These differences can greatly be explained
by the different ways of calculating costs. In ERP system, total costs include adjuncts
which were excluded from the total cost calculations as the aim was to find out actual total
costs without adjuncts added to internal purchases. After the actual sales prices were
acquired also post-calculations were run from the iLM ERP system. From these post-
calculations the actual costs without any adjunctions were received. These costs are the
actual costs of components including material and labor costs. Actual costs of the crane ex
works could be collected but defining the actual installation and transportation costs was
49
more challenging. The actual working hour and traveling costs of the installation could be
received from the Service’s ERP system, but other installation costs, like installation
material and lifting equipment rents had to be estimated according to received invoices and
by reducing estimated adjuncts from the sales prices of the internal transactions.
Average cost division of Finland’s projects was: components 46 %, steel structures and
external manufacturing 38 %, freight 4 %, and installation 12 %. This cost structure is
shown in Figure 14. Installation cost variation was from 5 % to 20 %.
4% 12%
46%
38%
Cost estimation accuracy in Finland was the lowest of all the case countries. Indexes of the
site cost estimation accuracy are shown in Figure 15. Seems that installation costs tend to
overrun more often than underrun. For 7 projects actual and estimated installation work
hours were collected. Actual installation hours were received from Service’s round-up
spreadsheets, and estimated hours from Markman offer reports. Average actual installation
hours were over two times more than the estimated ones. However, these estimated and
actual work hours cannot be directly compared as the Markman offers include only the
50
estimated erection hours. The actual incurred installation work hours, however, might
include also, for example, testing and commissioning hours. Unfortunately, these actual
work hours cannot be revised, because work hours are reported as total and have not been
separated out for each site operations activity.
3,30
2,80
2,30
0,80
0,30
0 2 4 6 8 10
3,30
2,80
2,30
0,80
0,30
0 2 4 6 8
Average cost structure of case Germany was: components (including steel structure) 82 %,
freight 4 %, and installation 14 %. As can be seen in the Figure 17, the cost structure in
Germany is very similar to the one in Finland.
14%
4%
82%
Average cost structure of SDC projects in Hungary is shown in Figure 18. One of the
example projects was manufacturing and delivering a 60-ton SP12 crane which doesn’t
quite fit to the scope and was thus excluded from the analysis. There were also four projects
which included more than one crane. Costs in those projects were divided and then re-
evaluated. From case projects share of component costs is 58 %. Other costs which include
locally purchased materials accounts for 27 %. Average proportion of installation is 15 %
and the variation from 8 % to 39 %. Unfortunately, cost estimations for installation costs
were not received and thus cannot be compared with other cases.
53
15%
27%
58%
This average cost structure differs a bit from the sample case which was also received for
the research. This was a sample SP 12, 5-ton SDC project which costs were calculated
according to previous standard cases. In this example, the proportions were as follows:
components 62 %, steel structures 21 %, freight 5 %, and installation 12 %. According to
previous SDC cases in Hungary the proportion of installation costs is 10-15 % in most of
the cases. Because the calculation of the example case is derived from wider range of
previous projects than the cases received for this research, these proportions are used in the
evaluation of all the case countries in total.
would be comparable at some level with other case countries. The challenge was also to
evaluate the actual costs and prices because naturally the prices for projects consisting of
several cranes vary from the prices of projects with one single crane. For eliciting cost data
about certain cranes of the projects, iLM system was used. First sales-order queries were
run for gathering the crane numbers and definitions of the cranes under received order
numbers. After clarifying the crane specific order numbers post-calculation queries could
be done. Currency rates were estimated by searching for saved currency rates from iLM
system. Average cost structure in China is shown in Figure 19. Component costs accounts
for 44 %, steel structures 37%, freight 3 %, and installation 16 %.
16%
3%
44%
37%
In addition, cost summaries of SDC projects delivered in December 2010 were received.
From these summaries cost estimation accuracy of the installations was calculated. Total 14
projects were delivered in December 2010. Out of these 14 projects, in two projects
installation was not included in the contract. Even though these projects were not the same
as the projects used for constituting the average cost structure, these 12 projects were used
along with the actual case projects to evaluate the cost estimating accuracy in China to
55
receive bigger sampling. As shown in Figure 20, the actual installation costs were higher
than the estimated ones in most of the cases.
1,90
1,70
1,50
0,90
0,70
0,50
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
There was a major change made in completing installations in 2010 as the responsibility of
installations was moved from Konecranes industrial crane organization to Konecranes
Service organization. Earlier IC organization sold and handed over the cranes to the
customer but from 2010 on Konecranes Service is completing the installations either by
using their own staff, or by using subcontractors. The main reason for this change was the
disaffection with the state of site operations and warranty period process. Earlier the
installation was completed by subcontractors that IC had hired, and the responsibility
moved to Service after the crane was installed, and the warranty period began. In some
cases, the installation wasn’t completed in a way that it satisfied the customer as the
installation was incomplete at the point where crane was handed over to the customer, or
there were some other problems occurred during the installation. If problems had occurred
during the installation and the subcontractor hadn’t clean the mess, Service organization
which took over at the beginning of the warranty period was the one to blame. That’s why,
currently the site operation process in China is much more like the one, for example, in
Finland as Service is informed when the crane leaves the factory and is ready to be
56
installed. The effects of this change have been very positive, and the current state of
installation is much better than before although there is still some lack of resources, and in
many cases the Service must buy the installation for subcontractors. But it can already be
seen that the current model in which IC is responsible for project management and Service
for site operations is working well.
26%
36%
6%
32%
installation would be completed by Service staff. The justifications for this statement are
the cost-effectiveness of the installation completed by Service staff, the direct customer
contact for Service as they complete the installation and natural handover of the crane. It is
a great benefit for Service organization that they receive the customer contact already in the
installation phase, so it will be easier to maintain these contacts during the whole crane life-
cycle.
Costs of the different industrial cranes in different countries are not straightly comparable
with each other because even the products in scope are standardized products, case projects
show that costs differ in each case. Every detail influences the total price of the crane, so
the final price is highly affected by the customer requirements. However, the cost structures
and CM2-% in different countries can be compared with each other. There were three
products in scope: SP11 profile crane, SP12 single girder crane and SP12 double girder
crane. If cases are compared according to their model, can be observed that the cost
proportion of installation is smaller in bigger cranes. Average proportion of installation for
SP11 cranes is 19 %, for SP12 single girder cases 18 % and for SP12 double girder cases
14 %. The proportion of component and manufacturing costs naturally rises when the size
of the crane grows. When examining the freight costs, the same kind of observation as in
installation costs, can be seen. The proportion of freight costs is smaller the bigger the
crane is. For SP11 average proportion of freight costs is 5 %, for SP12 single girder cases 4
% and for SP12 double girder cases 2 %. The reason for this is the same as for installation
costs: the share of component costs and the costs of steel structures rises with the size of the
crane which descends the proportion of freight and installation costs.
Cost estimation of total crane costs was quite accurate in each of the case countries, thus it
can be stated that Markman sales configurator is practical and useful tool at least in the
sales and cost estimation process of SDC projects. However, the level of installation cost
estimating accuracy was much lower. There are several uncertainties included in the crane
59
installation process and the question is, how to predict the unpredictable, and how to
perceive the uncertainties in the cost estimates. In Chapter 3.4, concept of contingency was
introduced, and this would be one possible way of managing the uncertainties. One way of
managing uncertainties would be first creating a risk list which would include all the typical
risks included in the site operation process, and then utilizing this risk list in future cases by
estimating which are the possible risks for the particular case, and according to that
evaluation adding a certain contingency to the final cost estimate.
Unfortunately, it was not possible to gather bigger cost data sampling because of restricted
time resources. Sampling of less than 10 cases is not big enough to put two and two
together but indicative conclusions can be made anyway. Results of the research confirm
the assumptions about relatively high proportion of installation costs from the total crane
costs. Fortunately, the results of the research will be utilized in the decision-making about
the practices of completing installations and in possible cost reduction efforts in site
operation costs. These indicative results could be the trigger for catching more attention to
cost estimating practices, more efficient exploiting of the previous knowledge and global
knowhow and the importance of accurate product cost reporting. It has been stated that the
crane delivery process is the most efficient in Finland and Sweden. This knowledge and
efficiency could be exploited more in other countries too. The significant factors in crane
sales and delivery process include cost management, direct customer contact and natural
handover in installations which are completed by Konecranes Service and uncomplicated
collaboration between the groups involved in the process. As the OneKonecranes project
highlights: it is important to appear as one functional entity for the end customer.
60
Interesting area of further research would also be the question of spreading the use of
Service staff in installations. According to this thesis, it would be more cost-efficient and
more valuable if the installations would be completed by Service staff. However, to be able
to assure that spreading the use of Service staff would be profitable in the long run, analysis
about managing current resources and enchasing the human resources of the Service
organization, and the analysis of the received benefits, should be done. According to the
research of the crane total costs till the crane handover, it seems most cost-efficient that the
installation is completed by the Service staff. However, the crane installation itself is not
very profitable business, but the received benefits like straight customer contact and natural
handover may be so remarkable that installations could be completed even unprofitably.
Cost analysis of the whole life-cycle of the crane should be thus examined.
61
6 CONCLUSIONS
The main research problem was to find out how the total costs of industrial cranes are
composed of. The chosen cost categories were: components, steel structures and other
external manufacturing, freight, and installation. Average cost structure of standard duty
cranes is shown in Figure 22. This cost structure was received by calculating the cost
divisions for each case country and for each case project. Some of the case projects didn’t
include for example installation costs at all and were therefore excluded from the total
average cost structure calculations. Because the cost structure in some of the cases was
notably different from the others these cases were not included in the evaluation of total
cost structure because the aim is to find average proportions of the cost categories. As
conclusion the proportion of installation costs from the total costs is relatively big: average
16 % and the variation from around 5 % to 54 %. These proportions are surprisingly high
as the assumption of several quarters in the beginning was that installation costs account for
maximum 15-20 % of the total crane costs.
16%
4%
48%
32%
Although installation costs are relatively high, there are several black spots included and
that’s why managing these costs is challenging. It can be seen that estimating installation
costs is quite difficult which may result in low installation budgets, and thus costs often
overrun. One proposed solution for this is more efficient exploitation of previous
experience and knowledge. This requires several actions and improvements in product cost
reporting and cost estimating. First of all, there are some deficiencies in the breakdown of
installation costs. Work hour costs should be specified more clearly, so that it would be
easier to estimate work hours needed in coming cases. Installation cost should be also
reported or saved into one place which is reachable at least by sales organization, finance
and service organization. At the moment in Finland as an example actual installation costs
have been saved only to Service’s own ERP system, thus costs are not available for people
outside Konecranes Service organization. Transparency in costs through the whole
corporation would probably make decision-making and cost estimating much easier. As
costs are reported more efficiently, exploiting previous knowledge becomes easier.
Previous experiences in installations could be used more efficiently also by saving
information about installations in a form of trouble tickets, for example. By saving
information about past cases lessons could be learned from troubles encountered, and
prevent same problems in future. As the competition is high, the prices of installations may
not be raised so installations should be completed more efficiently to be able to reduce
costs. Results from the country cases show that installations are conducted cheaper and
more efficiently by Konecranes service’s own staff. The costs of subcontracted installations
are high, and these costs cannot be managed by Konecranes company. The knowledge and
knowhow of the installations from the countries where installation is completed most
efficiently should be transferred to other countries too.
As stated earlier, estimating installation costs is challenging and there is a need for
improving installation cost estimations. One suggested way was to exploit previous
knowledge and experience, but also installation knowhow in product cost estimations
should not be forgotten. Site manager’s evaluation would be valuable in installation cost
63
estimates already in sales phase, so that installation budgets could be set more accurately.
For more proper installation cost estimation more accurate classification of site operation
work hours is needed. If site operation work hours would be separated out to different site
operation activities, historical data could be collected more accurately, and estimating the
hours needed for certain installation activities would be much easier. Currently work hour
costs are invoiced without precise breakdown of costs, so invoiced installation costs may
even include costs of repairing a crane that has been installed earlier. Work hour costs
could be reported more strictly and hours could be classified under different activies, for
example: crane erection 8 hours, electric installation 4 hours, testing 2 hours and
commissioning 2 hours = total of 16 hours. Reporting work hour cost this way doesn’t
require much more time, but the benefits would be remarkable as through cost breakdown
of installation, cost estimation accuracy and installation efficiency could be improved. One
suggested way of calculating installation costs would be using activity-based calculations.
In general, there are some weaknesses in cost reporting and there certainly is a need for
harmonizing product cost reporting. Now when there are several different ERP and IT
systems in use, transferring data between these systems results in data modification and
even confusion which system should be used in which situation and where to find certain
information. Fortunately, global SAP project is already running strong and the
implementation of SAP will relieve also product cost reporting. Data searching will become
much easier as same system will be used in different locations and by several departments.
At the moment, finding accurate and up-to-date cost data has been quite complicated so in
future and especially during SAP implementation more focus should be put on saving and
reporting actual costs. In SDC projects, crane orders will be saved to SAP system so that
sales and costs are divided into three categories: 1) equipment, 2) transportation, and 3)
installation. Costs will be directed to these cost categories. All the rows will be reported
under crane SP. In SAP it should be easy to report how big proportion installation costs are
from the total costs for certain SP in certain unit/country/region etc. If installation is
completed by Konecranes Service, discrete service order is created and is related to sales
64
row of the installation. Service order will be entered as internal sales of Konecranes. One
important notice for saving the costs in SAP would be to secure that also the actual incurred
costs are entered. If Service enters their own service orders into the system also actual costs
without any internal margins or other adjuncts should be saved. Installation work hour costs
should be also classified more accurately than before so that it will be easier to track down
the installation costs.
Apropos of costing and pricing an industrial crane several factors should be considered. As
customers are changing their decision criteria from initial cost to total lifetime cost of
equipment ownership, in pricing situation the whole product life cycle should be
considered. In addition to the initial price of the equipment, there are other important
factors too. Customers value especially the reliability of the crane and availability of spare
parts and service. These complementary products and services are already available in
Konecranes and could be marketed more aggressively. Whereas high prices of installation
can be explained to customer by the quality of the installation. When installation is
completed well, latter costs of the crane are minimized as crane is installed properly and
tested before handover to the customer. Properly installed crane is more serviceable and
reliable thus maintenance costs are optimized. Therefore, there are possibilities for adding
more value that customers are willing to pay for.
65
REFERENCES
Amos, S.J. (edited) 2007. Skills and Knowledge of Cost Engineering. AACE International.
Ansari, S., Bell, J. & Swenson, D. 2006. A Template for Implementing Target Costing.
Cost Management, Vol. 20, No. 5, pp. 20-27.
Asiedu, Y. & Gu, P. 1998. Product life cycle cost analysis: state of the art review.
International Journal of Production Research, Vol. 36, No. 4, pp. 883-908.
Carsten, T. & Erickson, B. 2007. Gain a Competitive Edge by Calculation Total Ownership
Costs. Power Engineering, Feb. 2007, pp. 32-38.
Cooper, R. & Slagmulder, R. 2004. Achieving Full-Cycle Cost Management. MIT Sloan
Management Review, Fall 2004, pp. 45-52.
Ditzer, W. 1998. Line installations: Who’s the best for the job? Converting Magazine, Vol.
16, No. 8, pp. 116-120.
Erkoyuncu, J.A., Roy, R., Shehab, E. & Cheruvu, K. 2011. Understanding service
uncertainties in industrial product-service system cost estimation. International Journal of
Manufacturing Technology, Vol. 52, pp. 1223-1238.
Horngren, C.T, Datar, S.M., Foster, G., Rajan, M. & Ittner, C. 2009. Cost Accounting – A
managerial emphasis. 13th edition. Pearson prentice hall. pp. 869.
Kingsman, B.G. & de Souza, A.A. 1997. A Knowledge-based decision support system for
cost estimation and pricing decisions in versatile manufacturing companies. International
Journal of Production Economics. Vol. 53, pp. 119-139.
Konecranes. 2010A. Annual Report 2010. [Retrieved September 5th, 2011]. From:
http://www.konecranes.com/files/attachments/ir/annual_reports/kc_2010_en_v03.pdf. pp.
132.
Konecranes. 2010B. Equipment Business Area Organization and Products. Internal use
only. pp. 25.
Konecranes. 2010C. Site Operations and SAP. Internal use only. pp. 19.
Kraus, W.E. 2008. Cost Estimating and Analysis. Cost Engineering, Vol. 50, No. 4, pp. 3-
4.
Lindholm, A. & Suomala, P. 2007. Learning by costing – Sharpening cost image through
life cycle costing? International Journal of Productivity and Performance Management,
Vol. 25, No. 8, pp. 651-672.
Lund, R.D. 2005. Improve cost estimating accuracy. Plant Engineering, Vol. 25, No. 7, pp.
61-63.
Maskell, B.H. 2006. Solving the standard cost problem. Cost Management, Vol. 20, No. 1,
pp. 27-35.
Medley, L.G. 1994. TCM: Managing Cost Before It Occurs. AACE International
Transactions, 1994, pp. GVT.2.1-GVT.2.8.
Meier, H., Völker, O. & Funke, B. 2011. Industrial Product-Service Systems (IPS²).
International Journal of Advanced Manufacturing Technology, Vol. 52, pp. 1175-1191.
Neilimo, K. & Uusi-Rauva, E. 2007. Johdon laskentatoimi. Helsinki: Edita Prima Oy. pp.
366.
Niazi, A. & Dai, J.S. 2006. Product Cost Estimation: Technique Classification and
Methodology Review. Journal of Manufacturing Science and Engineering, Vol.128, pp.
563-575.
Noble, P.M. & Cruca, T.S. 1999. Industrial Pricing: Theory and Managerial Practice.
Marketing Science, Vol. 18, No. 3, pp. 435-454.
Noor, I., Grumo, M., Kniskern, M.W. & Kopach, A. 2006. Bid Preparation Using Cost
Templates and Range Estimating – An Equipment Manufacturer’s Perspective. AACE
International Transactions, pp. OWN.05.1-OWN.05.5.
Power, D.J. 1997. What is a Decision Support System? The On-line Executive Journal for
Data-Intensive Decision Support, Vol. 1, No. 3. [Retrieved August 2nd, 2011]. From:
http://dssresources.com/papers/whatisadss/index.html.
Roy, R. & Erkoyuncu, J.A. 2011. Service Cost Estimation Challenges in Industrial Product-
Service Systems. Functional Thinking for Value Creation: Proceedings of the 3rd CIRP
70
Shabani, M.R. & Yekta, R.B. 2006. Chemical Processes Equipment Cost Estimation Using
Parametric Models. Cost Engineering, Vol. 48, No. 5, pp. 26-32.
Shank, J.K & Fisher, J. 1999. Case Study: Target Costing as a Strategic Tool. MIT Sloan
Management Review, Vol. 41, No. 1, pp. 73-82.
Uppal, K.B. 1997. Cost estimating made simple. Hydrocarpon processing, September
1997, pp. 168-C-168-E.
Wang, C-H. & Huang, Y-C. 2000. A new approach to calculating project cost variance.
International Journal of Project Management, Vol. 18, pp. 131-138.
Watson, I. 2004. Capturing and Applying Lessons Learned During Engineering Equipment
Installation. M.Gh. Negoita et al. (Eds.): KES 2004, LNAI 3215, pp. 672-677.