EMTP Final Report Bogra Rahanpur14.11.2021
EMTP Final Report Bogra Rahanpur14.11.2021
ACRONYMS ......................................................................................................... 4
A. EXECUTIVE SUMMARY.............................................................................. 10
1 INTRODUCTION .......................................................................................... 14
5.3 400 KV DOUBLE CIRCUIT LINE FROM ADANI TO RAHANPUR SUBSTATIONS ......... 43
5.3.1 SINGLE POLE RECLOSURE STUDIES - STEADY STATE ANALYSIS .................................................... 43
5.3.2 INDUCED VOLTAGES DURING STUCK BREAKER CONDITIONS ...................................................... 47
5.3.3 INDUCED VOLTAGES ON DE-ENERGIZED CIRCUIT ........................................................................ 51
5.3.4 SUMMARY OF NGR STUDIES ........................................................................................................ 52
5.3.5 TECHNICAL SPECIFICATIONS OF NGR ........................................................................................... 53
5.3.6 SUCCESSFUL SINGLE POLE AUTO RECLOSURE FEASIBILITY STUDY FOR ALL 400 KV LINES .......... 54
Page 1 of 115
REPORT ON EMTP STUDIES
6 REACTOR SWITCHING AND BREAKER TRV STUDY ............................. 56
8.3 Switching surge analysis for by passing Rahanapur 400 kV substation ....................................... 83
8.3.1 LINE ENERGIZATION ..................................................................................................................... 83
8.3.2 Line Re-energization .................................................................................................................... 84
Page 2 of 115
REPORT ON EMTP STUDIES
10.6 400 kV Rahanpur Substation................................................................................................ 91
10.6.1 Temporary overvoltages .......................................................................................................... 91
10.6.2 Ferro resonance study of power transformer ......................................................................... 92
10.6.3 Switching Overvoltages ........................................................................................................... 94
10.6.4 Lightning overvoltages ............................................................................................................. 94
10.6.5 Very fast transients .................................................................................................................. 99
Page 3 of 115
REPORT ON EMTP STUDIES
ACRONYMS
SA Surge Arrester
Page 4 of 115
REPORT ON EMTP STUDIES
TERMINOLOGY AND DEFINITIONS
Page 5 of 115
REPORT ON EMTP STUDIES
Impedance is minimum, current is maximum limited only by resistance in
the circuit.
• Parallel resonance: One of the ways to define resonance for a parallel
RLC circuit is the frequency at which the impedance is maximum. Another
definition: the parallel resonant frequency is the frequency at which the
voltage and current are in phase.
• Single-phase tripping: The opening of the faulted phase during single
phase to ground fault.
• Single-phase auto-reclosure: The reclosing of the faulted phase following
a single-phase trip.
• Primary arc current: The current in the phase to ground arcing fault prior
to single phase tripping.
• Secondary arc current (Residual Current): The current, which flows in
the arc after single phase tripping is completed. This is the resultant of
currents derived from the electrostatic and electromagnetic coupling from
the two energized phases and adjacent lines after the primary arc current
is cleared via the line circuit breaker.
• Recovery voltage: The voltage, which appears across the secondary arc
path as soon as the arc is extinguished.
• Dead time (of Single Pole Switching): Dead time is the time from the
initial pulse until another pulse can be produced.
• Shaft torsional oscillation of thermal units: The series compensated
transmission lines have line inductance, resistance and series capacitance,
which result in electrical resonant frequencies (fe) below the fundamental
power frequency. Turbine-generators have rotating shaft systems
comprised of large inertial masses that are interconnected with shafts that
act as springs. These large masses and shafts create torsional resonant
frequencies, fm, some of which are also sub synchronous. If the
transmission line resonant frequency, (fe), is close to the complementary
mechanical system frequency (50-fm) of the generating machine, then the
two oscillatory systems can interact with each other. In some operating
conditions, the interaction can result in damaging shaft torques on a turbine
generator shaft. This interaction is called Sub synchronous Resonance
(SSR), and it occurs because of the interchange of energy between the
Page 6 of 115
REPORT ON EMTP STUDIES
series capacitors on the transmission lines and the mass-spring system of
the turbine-generator shaft. This interchange occurs at the sub
synchronous resonance frequency by modulating the 50 Hz waveform.
• Sensitivity Analysis: Transient analysis for examining the sensitivity of
various parameters on secondary arc current and recovery voltage in
function of neutral reactor and the fault location along the line.
• Surge arrester: A device designed to protect electrical apparatus from high
transient voltage and to limit the duration and frequently the amplitude of
follow-current. The term "surge arrester" includes any external series gap
which is essential for the proper functioning of the device as installed for
service, regardless of whether or not it is supplied as an integral part of the
device.
• Rated voltage of an arrester: the designated maximum permissible r.m.s
value of power-frequency voltage between its terminals at which it is
designated to operate correctly. This voltage may be applied to the arrester
continuously without changing its operating characteristics.
• Duty-cycle voltage rating: The designated maximum permissible voltage
between its terminals at which an arrester is designed to perform its duty
cycle.
• Impulse: a unidirectional wave of voltage or current, which, without
appreciable oscillations, rises rapidly to a maximum value and falls, usually
less rapidly, to zero with small, if any, loops of opposite polarity.
• Maximum continuous operating voltage (MCOV): The maximum
designated root mean square (rms) value of power frequency voltage that
may be applied continuously between the terminals of the arrester.
• Residual voltage (discharge voltage) of an arrester: The voltage that
appears between the terminals of an arrester during the passage of
discharge current.
• Standard lightning voltage impulse: An impulse voltage having a wave
shape designation of 1.2/50 μs.
• Switching voltage impulse: An impulse having a virtual front time greater
than 30 ms.
• Front of an impulse: that part of an impulse, which occurs prior to the peak.
• Tail of an impulse: that part of an impulse, which occurs after the peak.
Page 7 of 115
REPORT ON EMTP STUDIES
• Continuous (power frequency) voltage: Power frequency voltage,
considered having constant r.m.s value, continuously applied to any pair of
terminals of an insulation configuration.
• Temporary overvoltage: An oscillatory phase-to-ground or phase-to-
phase overvoltage that is at a given location of relatively long duration
(seconds, even minutes) and that is undamped or only weakly damped.
Temporary overvoltage usually originates from switching operations or
faults (e.g., load rejection, single-phase fault, fault on a high-resistance
grounded or ungrounded system) or from nonlinearities (ferro resonance
effects, harmonics), or both. They are characterized by the amplitude, the
oscillation frequencies, the total duration, or the decrement.
• Transient overvoltage: short duration overvoltage of few milliseconds or
less, oscillatory or non-oscillatory, usually highly damped. Transient over
voltages may be immediately followed by temporary over voltages.
• Slow-front over voltages: They can originate from faults, switching
operations or direct lightning strokes to the conductors of overhead lines.
• Fast-front over voltages: They can originate from switching operations,
lightning strikes or faults.
• Resonance and Ferro resonance overvoltage: Temporary over voltages
in this category arise from the interaction of capacitive elements (lines,
cables, series capacitors) and inductive elements having nonlinear
magnetizing characteristics (transformers, shunt reactors). The resonant
overvoltage is initiated by a sudden change in the system configuration,
such as a load rejection, single phase switching of a transformer terminated
line, or isolation of a bus potential transformer (PT) through breaker
capacitance. Resonant and ferro-resonant over voltages can have
magnitudes greater than 3.0 p.u and last until the condition is cleared. They
should be limited by detuning the system from the resonant frequency, by
changing the system configuration, or by damping resistors.
• Switching Over voltages: A phase to ground or a phase-to-phase
overvoltage at a given location on a system due to one specific switching
operation, fault, or other cause, the shape of which can be regarded, for the
purpose of insulation coordination, as similar to that of the standard
Page 8 of 115
REPORT ON EMTP STUDIES
switching impulse. Such over voltages are usually highly damped and of
short duration.
Switching over voltages may have times-to-crest from 20–5000 μs, and time
to half value of less than 20000 μs. They are generally a result of the
following:
Page 9 of 115
REPORT ON EMTP STUDIES
A. EXECUTIVE SUMMARY
Summary: This report presents the results of reactor sizing studies, neutral reactor
design studies, switching surge analysis, reactor switching studies and earthing switch
design studies performed according to scope of work to establish adequacy of reactor
sizing, neutral reactor sizing, circuit breaker adequacy with pre-insertion resistors and
control switching device and earth switch design in 400 kV Rahanpur and Bogura west
substations.
Detailed Studies for the above phenomenon have been conducted and Calculation’s basis,
methods, detailed results and conclusions are attached in subsequent pages of this report.
According to the computation results and conclusions at Clause 9.0, following are
summarized result of study:
• 1x125 MVAr, 420 kV bus reactor is proposed at 400 kV Rahanpur, Bogura (west)
and Rooppur substations.
• 1x25 MVAR, 420 kV line reactor is proposed for 400 kV line from Rooppur to
Kaliakoir at Rooppur end.
Circuit Breakers:
• Bus and line reactors should be equipped with CSD 400 kV SF6 circuit breaker.
• HV side of ICT transformers should be equipped with CSD control.
• For all line circuit breakers, no PIR and CSD is required.
NGR Specification:
Page 10 of 115
REPORT ON EMTP STUDIES
Rated Voltage 84 kVrms, for 10 seconds
21 kVAr Continuous
Rated Frequency 50 Hz
No. of Phases 1
420 160 10 18 20
Page 11 of 115
REPORT ON EMTP STUDIES
Resonance Studies
• Shunt compensated 400 kV double circuit line between Adani to Rahanpur for a
selected NGR value during stuck pole operations no parallel resonance
phenomena is observed.
• Overhead line terminated with ICT transformer at receiving end and stuck pole
operation at source end causes Ferro resonance. Hence, it is recommended that
the system configuration leading to an energisation of overhead line terminated by
unloaded ICT transformer should be avoided.
• Based on the TOV studies conducted, it is recommended to use 360 kV rms surge
arrester for 400 kV system rather than 396 kV rms system. It is also noted that
proposed surge arrester ratings 120 kV rms and 30 kV rms for 132 kV and 33 kV
system respectively are in order.
• Based on the switching overvoltage studies conducted, it is recommended to use
class-IV surge arresters to control switching over voltages.
• Based on the lightning overvoltage studies conducted, proposed surge arresters
rating (360 kV rms) and their locations namely one SA at gantry, one SA at GIS
Busbar and one SA at ICT Transformer HV terminal are adequate to achieve
proper protection margins in Rahanpur -400 kV substation.
• Based on the TOV studies conducted, it is recommended to use 360 kV rms surge
arrester for 400 kV system rather than 396 kV rms system. It is also noted that
proposed surge arrester ratings 216 kV rms and 30 kV rms for 230 kV and 33 kV
system respectively are in order.
• Based on the switching overvoltage studies conducted, it is recommended to use
class-IV surge arresters to control switching over voltages.
• Based on the lightning overvoltage studies conducted, proposed surge arresters
rating (360 kV rms) and their locations namely one SA at gantry, one SA at GIS
Busbar and one SA at ICT Transformer HV terminal are adequate to achieve
proper protection margins in Bogura -400 kV substation.
Page 12 of 115
REPORT ON EMTP STUDIES
• By keeping ground leads as short and straight as possible in order to minimize the
inductance.
• By increasing the number of connections to ground.
• By introducing shielding to prevent internally generated VFT from reaching the
outside of the enclosure.
Page 13 of 115
REPORT ON EMTP STUDIES
B. MAIN REPORT
1 INTRODUCTION
The utility electricity sector in Bangladesh has one national grid with an installed
capacity of 21,419 MW as of September 2019. Recently Bangladesh started
construction of the 2.4-gigawatt (GW) Rooppur Nuclear Power Plant expected to
go into operation in 2023. In Bangladesh electricity is generated at 50 Hertz
frequency and at a nominal voltage of 11 kV (kilo Volts) or 15 kV to be stepped up
through transformers to 132 kV to 400 kV for feeding to the grid. Bangladesh power
grid has given the project of expansion of their 400 kV network by 2025 and to
conduct the EMTP studies for Bogura and Rahanpur Substation.
• Methodology for carrying out the EMTP studies in line with the scope of
work,
• Data collected so far and its validation
• Reactor sizing studies, neutral reactor design studies, switching surge
analysis, reactor switching studies, earthing switch design studies &
insulation coordination studies performed according to scope of work to
establish adequacy of reactor sizing, neutral reactor sizing, circuit breaker
adequacy with pre-insertion resistors and control switching device and earth
switch design in 400 kV Rahanpur and Bogura west substations.
• Incorporation of comments issued by PGCB vide their letter dated
01.03.2021.
• Incorporation of comments issued by PGCB vide email dated 12.05.2021.
• Incorporation of comments issued by PGCB vide email dated 31.05.2021
• Incorporation of comments issued by PGCB vide email dated 02.06.2021.
• Incorporation of comments issued by PGCB vide email dated 21.06.2021.
• Incorporation of comments issued by PGCB vide email dated 16.08.2021.
• Incorporation of points discussed in meeting with PGCB on 18.08.2021.
2 SCOPE OF WORK
The scope of work related to EMTP studies as per TOR is given below
Page 14 of 115
REPORT ON EMTP STUDIES
Reactor
• To determine the required and the size of the Bus reactor at each 400kV
Bus (400kV Bogura & Rahanpur Substation) and Rating of LA for Reactor
• To determine the requirement, rating (kV, kJ, kA etc.), location and number
of lighting arrester at each 400kV switchyard (400kV Bogura & Rahanpur
Substation).
• Switching and lighting Over voltage study of each 400kV substation (400kV
Bogura & Rahanpur) and determine the Flash-over rate.
• To assess the requirement Bus Reactor or Shunt/ Line Reactor for each
400kV Bus (400kV Bogura & Rahanpur Substation) and selection of Bus or
Shunt/ Line Reactor with Technical & Economic aspects.
• To determine the requirement and the size of NGR for Line/Bus Reactor at
each 400kV Bus to reduce the secondary arc Current at acceptable limit so
as to facilitate the Single-Phase-auto-reclosing (SPAR) of line Circuit
Breaker
Page 15 of 115
REPORT ON EMTP STUDIES
• to determine the rating ES for Bus/Line Reactor & NCR at each 400kV
Substation
Training
• The Employer owns license of PSCAD software. Hence, The EMTP study
shall have to be performed using PSCAD software and shall include training
of six (08) Design Engineers of the Employer for two (2) weeks regarding
the use of PSCAD software for typical EMTP study including/having
example of the said EMTP study under this project.
❖ Transmission line:
❖ Power Transformers
Transformers are modeled for the studies of temporary and switching overvoltage
studies by considering leakage impedances as per the standard [1]. In addition, for
the fast transient study, the effect of stray capacitances between terminal to ground
of transformer is considered.
❖ Tower Model
Page 16 of 115
REPORT ON EMTP STUDIES
The tower model directly affects the wave shapes of lightning surges, which appear
on the arcing horn gap. Hence, multi-section tower model with distributed line
parameters is used for high accuracy transmission tower model as per standard
[1].
❖ Tower footing resistance
The lightning surges would travel to the substation if the backflashover occurs in
the tower depending on the length of the insulator air gap distance. Arcing horn
gap of insulator of 4500 mm is considered based on the input data provided.
Leader-progression model
For strokes to shield wire, first stroke conditions are assumed because the
amplitudes are usually the highest [2]. The steepness of the voltage surge on the
phase conductor after backflashing of the respective insulator is determined by the
speed of the leader discharge short circuiting the insulator. The leader velocity and
its propagation are described by [2]:
dl u (t )
= v1 = k u (t ) − E0
dt (d g − ll )
Where:
❖ Surge arrester
Page 17 of 115
REPORT ON EMTP STUDIES
Surge arrester dynamic characteristics are significant for studies involving lightning
and other fast transients’ surges. The time to crest for surges used in lightning
studies can range from 0.5 µs to several µs. For a given current magnitude in an
arrester, the voltage developed across the arrester can increase by approximately
6% as time to crest of current is decreased from 8 µs to 1.3 µs. One approach for
an arrester model for lightning studies would be to use a simple non-linear V-I
characteristics based on 0.5 µs discharge voltage. This would give conservative
results (higher voltages) for surges with slower time to crest. The frequency
dependent model will give good results for current surges with times to crest from
0.5 µs to 40 µs [3].
The model proposed by Pinceti [4] derives from IEEE model is used to performing
fast transient studies and presented in Figure 1.
The details of surge arrester frequency dependent model parameters have been
presented in following sections.
Page 18 of 115
REPORT ON EMTP STUDIES
Figure 2: Flow chart for calculations of L0 and L1
Where
V8/20 is the residual voltage at 10 kA current surge with a 8/20 µs shape (kV)
L1 and LO in µH
The nonlinear resistors A0 and A1 can be modeled as a piecewise linear V-I curve
with characteristics defined point by point. V-I characteristics of A1 arrester have
been selected from manufacturer data sheet and V-I characteristics of A0 is
selected based on curves proposed by IEEE W.G.3.4.11 which are shown in Figure
3.
Page 19 of 115
REPORT ON EMTP STUDIES
.
The V-I characteristics of A0 are adjusted in surge arrester model to get a good
match between model and manufacturer’s switching surge voltages and currents.
Page 20 of 115
REPORT ON EMTP STUDIES
B0/2(mho/km) 0.149682E-5
Quad ACCC Dhaka (Single Circuit)
R1(ohm/km) 0.0109
X1(ohm/km) 0.22345
B1/2 (mho/km) 0.25546E-5
R0(ohm/km) 0.166645
X0(ohm/km) 0.71764
B0/2(mho/km) 0.125485E-5
R1(ohm/km) 0.036406
X1(ohm/km) 0.313697
B1/2(mho/km) 0.182814E-5
R0(ohm/km) 0.183886
X0(ohm/km) 0.915977
B0/2(mho/km) 0.13202E-5
Twin ACSR Mallard (Quad circuit)
R1(ohm/km) 0.03726
X1(ohm/km) 0.35064
B1/2(mho/km) 0.164499E-5
R0(ohm/km) 0.15315
X0(ohm/km) 0.78264
B0/2(mho/km) 0.137112E-5
R1(ohm/km) 0.06959
X1(ohm/km) 0.41448
B1/2(mho/km) 0.144493E-5
R0(ohm/km) 0.22064
X0(ohm/km) 1.04067
B0/2(mho/km) 0.091265E-5
ACSR Grosbeak (Double circuit)
Page 21 of 115
REPORT ON EMTP STUDIES
R1(ohm/km) 0.091575
X1(ohm/km) 0.41476
B1/2(mho/km) 0.1412E-5
R0(ohm/km) 0.242652
X0(ohm/km) 1.04095
B0/2(mho/km) 0.09128E-5
ACSR Grosbeak (Single circuit)
R1(ohm/km) 0.091633
X1(ohm/km) 0.42531
B1/2(mho/km) 0.137502E-5
R0(ohm/km) 0.242536
X0(ohm/km) 1.01985
B0/2(mho/km) 0.06555E-5
AAAC (Double circuit)
R1(ohm/km) 0.069831
X1(ohm/km) 0.40502
B1/2(mho/km) 0.144709E-5
R0(ohm/km) 0.220908
X0(ohm/km) 1.03121
B0/2(mho/km) 0.093172E-5
Page 22 of 115
REPORT ON EMTP STUDIES
Spacing between bundled conductors (m) 0.3
Ground Wire Data (7/36mm)
Overall Diameter (m) 0.012825
DC Resistance (ohm/km) 0.2216
Conductor Data (132kV ACSR Grosbeak)
No of sub-conductors/phase 1
Overall Diameter (m) 0.01258
DC Resistance (ohm/km) 0.08959
Strand radius (m) 0.0019865
Spacing between bundled conductors (m) 0.3
Ground Wire Data (7/36mm)
Overall Diameter (m) 0.012825
DC Resistance (ohm/km) 0.2216
Conductor Data (132kV AAAC)
No of sub-conductors/phase 1
Overall Diameter (m) 0.014615
DC Resistance (ohm/km) 0.0671
Strand radius (m) 0.002088
Spacing between bundled conductors (m) 0.3
Ground Wire Data (7/36mm)
Overall Diameter (m) 0.012825
DC Resistance (ohm/km) 0.2216
Page 23 of 115
REPORT ON EMTP STUDIES
C2 (0,21.8)
C3 (5.5,21.8)
Ground Wire Coordinates (width in m, height in m)
G1 (-4,31)
G2 (4,31)
Page 24 of 115
REPORT ON EMTP STUDIES
Table 11: 132 kV Single Circuit Tower Configuration
Conductor Coordinates (width in m, height in m)
C1 (-2.925,104.625)
C2 (2.925,108.625)
C3 (-2.925,112.625)
Ground Wire Coordinates (width in m, height in m)
G1 (0,118)
Page 25 of 115
REPORT ON EMTP STUDIES
Power Rating 990 150 75
(MVA)
No. of transformers 2 1 1
Page 26 of 115
REPORT ON EMTP STUDIES
4 BARAPUKUR NEW BOGURA WEST 2 230 120
Table 17: Simulated 3-phase fault currents for network model validation
Sl No Faulted Bus Bus kV 3-phase fault 3-phase fault
current (kA) current (kA)
Data PSCAD
provided Simulation
1 ADANI_INDIA 400 14.8 14.85
2 BOGURA WEST 400 28.7 28.9
3 KALIAKOIR 400 50.4 46.3
Page 27 of 115
REPORT ON EMTP STUDIES
4 RAHANPUR 400 16.8 16.4
5 ROPPUR 400 34.7 34.6
6 BARAPUKUR NW 230 20.3 20.8
7 BARAPUKIRIA 230 19.1 18.9
8 BOGURA 230 36.3 35.9
9 BOGURA WEST 230 39.6 41.0
10 NAOGAON 230 21.2 18.0
11 PALASHBARI 230 17.8 17.3
12 SIRAJGANJ 230 40.6 39.0
13 AMNURA 132 12.3 15.5
14 BOGURA NEW 132 36.5 36.8
15 CHAPAI NAWAB 132 16.3 16.9
16 JOYPURHAT 132 10.3 8.6
17 NAOGAON 132 29.0 25.1
18 NIYAMATPUR 132 15.5 14.2
19 PATNITOLA 132 10.1 8.84
20 RAHANPUR 132 25.7 27.4
21 RAJSHAHI NEW 132 19.4 19.2
It is observed from Table 17, simulated 3-phase fault current magnitudes are
closely matching with the data provided. Hence, the network configuration and
parameters considered are to be in order.
Page 28 of 115
REPORT ON EMTP STUDIES
The following reactors are considered in the network configuration:
Full generation of 150 MW at CHAPAI (100 MW) and AMNURA (50 MW)
substations is considered and distributed this generation to 132 kV load centres,
maintained constant for all possible study scenarios.
Page 29 of 115
REPORT ON EMTP STUDIES
B 50% loading on Kaliakoir Case-1-B All 400 kV buses except
Transformers and Auxiliary BIBIYANA violate the allowable
Load equivalent to 8% of one maximum voltage limit of 1.05
generation unit at Rooppur p.u.
400 kV Bus
C 50% loading on Kaliakoir Case-1-C All 400 kV buses except
Transformers, Auxiliary Load BIBIYANA violate the allowable
equivalent to 8% of one maximum voltage limit of 1.05
generation unit each at Adani p.u.
and Rooppur 400 kV Bus
respectively.
2 A 20% loading on Kaliakoir Case-2-A All 400 kV buses except
Transformers, Auxiliary Load BIBIYANA violate the allowable
equivalent to 8% of one maximum voltage limit of 1.05
generation unit at Adani 400 p.u.
kV Bus
B 20% loading on Kaliakoir Case-2-B All 400 kV buses except
Transformers, Auxiliary Load BIBIYANA violate the allowable
equivalent to 8% of one maximum voltage limit of 1.05
generation unit at Rooppur p.u.
400 kV Bus
C 20% loading on Kaliakoir Case-2-C All 400 kV buses except
Transformers, Auxiliary Load BIBIYANA violate the allowable
equivalent to 8% of one maximum voltage limit of 1.05
generation unit at Adani and p.u.
Rooppur 400 kV Bus
respectively.
3 A One unit at Adani with Case-3-A All 400 kV buses except
technical minimum 50% BIBIYANA violate the allowable
generation, 95% of generation maximum voltage limit of 1.05
feeding at Rahanpur 132 kV p.u.
side (5% of generation flow on
400 kV lines), 20% loading on
Kaliakoir transformers are
considered.
B One unit at Adani with Case-3-B All 400 kV buses except
technical minimum 50% BIBIYANA violate the allowable
Page 30 of 115
REPORT ON EMTP STUDIES
generation, 90% of generation maximum voltage limit of 1.05
feeding at Rahanpur 132 kV p.u.
side (10% of generation flow
on 400 kV lines), 20% loading
on Kaliakoir transformers are
considered.
C One unit at Adani with Case-3-C All 400 kV buses except
technical minimum BIBIYANA violate the allowable
50%generation, 85% of maximum voltage limit of 1.05
generation feeding at p.u.
Rahanpur 132 kV side (15% of
generation flow on 400 kV
lines), 20% loading on
Kaliakoir transformers are
considered.
D One unit at Adani with Case-3-D All 400 kV buses except
technical minimum BIBIYANA violate the allowable
50%generation, 75% of maximum voltage limit of 1.05
generation feeding at p.u.
Rahanpur 132 kV side (25% of
generation flow on 400 kV
lines), 20% loading on
Kaliakoir transformers are
considered.
E One unit at Adani with Case-3-E All 400 kV buses except
technical minimum BIBIYANA violate the allowable
50%generation, 60% of maximum voltage limit of 1.05
generation feeding at p.u.
Rahanpur 132 kV side (40% of
generation flow on 400 kV
lines), 20% loading on
Kaliakoir transformers are
considered.
4 A One unit at Rooppur with Case-4-A All 400 kV bus voltage are
technical minimum within limits
50%generation, 95% of
generation feeding at Bogura
Page 31 of 115
REPORT ON EMTP STUDIES
230 kV side (5% of generation
flow on 400 kV lines), 20%
loading on Kaliakoir
transformers are considered.
B One unit at Rooppur with Case-4-B All 400 kV bus voltage are
technical minimum within limits
50%generation, 90% of
generation feeding at Bogura
230 kV side (10% of
generation flow on 400 kV
lines), 20% loading on
Kaliakoir transformers are
considered.
C One unit at Rooppur with Case-4-C Rahanpur and Bogura 400 kV
technical minimum 50% buses violate the allowable
generation, 85% of generation maximum voltage of 1.05 p.u.
feeding at Bogura 230 kV side
(15% of generation flow on
400 kV lines),20% loading on
Kaliakoir transformers are
considered.
D One unit at Rooppur with Case-4-D Rahanpur and Bogura 400 kV
technical minimum 50% buses violate the allowable
generation, 75% of generation maximum voltage of 1.05 p.u.
feeding at Bogura 230 kV side
(25% of generation flow on
400 kV lines),20% loading on
Kaliakoir transformers are
considered.
E One unit at Rooppur with Case-4-E Rahanpur and Bogura 400 kV
technical minimum 50% buses violate the allowable
generation, 60% of generation maximum voltage of 1.05 p.u.
feeding at Bogura 230 kV side
(40% of generation flow on
400 kV lines),20% loading on
Kaliakoir transformers are
considered.
Page 32 of 115
REPORT ON EMTP STUDIES
5 A One unit at Rooppur and Case-5-A All 400 kV bus voltage are
Adani with technical minimum within limits
50%generation, 95% of
generation feeding at Bogura
230 kV side and Rahanpur
132 kV side (5% of generation
flow on 400 kV lines),20%
loading on Kaliakoir
transformers are considered.
B One unit at Rooppur and Case-5-B All 400 kV bus voltage are
Adani with technical minimum within limits
50%generation, 90% of
generation feeding at Bogura
230 kV side and Rahanpur
132 kV side (10% of
generation flow on 400 kV
lines),20% loading on
Kaliakoir transformers are
considered.
C One unit at Rooppur and Case-5-C All 400 kV bus voltage are
Adani with technical minimum within limits
50%generation, 85% of
generation feeding at Bogura
230 kV side and Rahanpur
132 kV side (15% of
generation flow on 400 kV
lines),20% loading on
Kaliakoir transformers are
considered.
D One unit at Rooppur and Case-5-D All 400 kV bus voltage are
Adani with technical minimum within limits
50%generation, 75% of
generation feeding at Bogura
230 kV side and Rahanpur
132 kV side (25% of
generation flow on 400 kV
lines), 20% loading on
Page 33 of 115
REPORT ON EMTP STUDIES
Kaliakoir transformers are
considered.
E One unit at Rooppur and Case-5-E All 400 kV bus voltage are
Adani with technical minimum within limits
50%generation, 60% of
generation feeding at Bogura
230 kV side and Rahanpur
132 kV side (40% of
generation flow on 400 kV
lines), 20% loading on
Kaliakoir transformers are
considered.
The power flow results of 400 kV bus voltages are presented in Table 19. It is
observed from the power flow results, under various light load conditions for
majority of power flow scenarios 400 kV bus voltages are more than the maximum
allowable limit i.e. 1.05 p.u. For few power flow scenarios 400 kV bus voltages are
within limit provided that generation sources can absorb any amount of reactive
power, however this may not be feasible in practical operating scenarios as thermal
power plant operators will not allow reactive power absorption.
Table 19: Power Flow results for 400 kV system bus voltages
400 kV substation voltages in per unit Voltage
Case ID Rahanpur Rooppur Adani Bogura West Kaliakoir Bibiyana Violation
CASE-1-
A 1.10 1.10 1.09 1.11 1.07 1.00 Yes
CASE-1-
B 1.10 1.10 1.09 1.11 1.07 1.00 Yes
CASE-1-
C 1.10 1.10 1.09 1.10 1.06 1.00 Yes
CASE-2-
A 1.13 1.12 1.12 1.13 1.09 1.00 Yes
CASE-2-
B 1.13 1.12 1.12 1.13 1.09 1.00 Yes
CASE-2-
C 1.12 1.12 1.11 1.13 1.09 1.00 Yes
CASE-3-
A 1.05 1.08 1.03 1.08 1.06 1.00 Yes
CASE-3-
B 1.05 1.08 1.03 1.08 1.06 1.00 Yes
CASE-3-
C 1.05 1.08 1.03 1.08 1.06 1.00 Yes
Page 34 of 115
REPORT ON EMTP STUDIES
CASE-3-
D 1.06 1.08 1.03 1.08 1.06 1.00 Yes
CASE-3-
E 1.06 1.08 1.03 1.08 1.06 1.00 Yes
CASE-4-
A 1.05 1.03 1.04 1.05 1.03 1.00 No
CASE-4-
B 1.05 1.03 1.04 1.05 1.03 1.00 No
CASE-4-
C 1.05 1.03 1.04 1.05 1.04 1.00 No
CASE-4-
D 1.05 1.03 1.04 1.05 1.04 1.00 No
CASE-4-
E 1.06 1.03 1.05 1.06 1.04 1.00 Yes
CASE-5-
A 1.02 1.02 1.01 1.03 1.02 1.00 No
CASE-5-
B 1.02 1.02 1.01 1.03 1.03 1.00 No
CASE-5-
C 1.02 1.02 1.01 1.03 1.03 1.00 No
CASE-5-
D 1.03 1.02 1.01 1.04 1.03 1.00 No
CASE-5-
E 1.03 1.03 1.01 1.04 1.03 1.00 No
Various power flow scenarios are simulated to size the bus reactor, one of the light
load situations Case-2A is considered to show that various bus reactor sizes are
considered for simulation. Simulation results are presented in Table 1820.
Page 35 of 115
REPORT ON EMTP STUDIES
1x100MVa
13 1x100MVAr 1x80MVAr r 1.052 1.062 1.064 1.071 1.052 Yes
1x100MVa
14 1x100MVAr 1x100MVAr r 1.048 1.058 1.061 1.067 1.05 Yes
1x100MVa
15 1x100MVAr 1x125MVAr r 1.044 1.053 1.056 1.062 1.046 Yes
1x125MVa
16 1x100MVAr 1x80MVAr r 1.048 1.058 1.058 1.067 1.049 Yes
1x125MVa
17 1x100MVAr 1x100MVAr r 1.044 1.054 1.055 1.063 1.046 Yes
1x125MVa
18 1x100MVAr 1x125MVAr r 1.039 1.049 1.05 1.058 1.043 Yes
19 1x125MVAr 1x80MVAr 1x80MVAr 1.049 1.059 1.065 1.07 1.052 Yes
20 1x125MVAr 1x100MVAr 1x80MVAr 1.045 1.055 1.062 1.066 1.049 Yes
21 1x125MVAr 1x125MVAr 1x80MVAr 1.04 1.05 1.057 1.061 1.046 Yes
1x100MVa
22 1x125MVAr 1x80MVAr r 1.046 1.055 1.06 1.066 1.049 Yes
1x100MVa
23 1x125MVAr 1x100MVAr r 1.042 1.051 1.057 1.062 1.047 Yes
1x100MVa
24 1x125MVAr 1x125MVAr r 1.037 1.046 1.052 1.057 1.043 Yes
1x125MVa
25 1x125MVAr 1x80MVAr r 1.041 1.051 1.054 1.062 1.046 Yes
1x125MVa
26 1x125MVAr 1x100MVAr r 1.038 1.047 1.051 1.058 1.043 Yes
1x125MVa
27 1x125MVAr 1x125MVAr r 1.033 1.042 1.046 1.05 1.04 No
In addition to the exiting or proposed bus and/or line reactors (as given section
4.1), the following bus reactors are proposed.
Power flow results with these reactors are presented in Annexure-3. The power
flow results of 400 kV system bus voltages with shunt reactor compensation are
presented in Table 21. It is observed from power flow results that for all the case
scenarios 400 kV bus voltages are within limits and reactive power absorption by
generating sources is minimum.
Table 191: 400 kV system bus voltages with shunt reactor compensation
Page 36 of 115
REPORT ON EMTP STUDIES
CASE-2-
A-R 1.04 1.05 1.03 1.05 1.04 1.00 No
CASE-2-
B-R 1.04 1.05 1.03 1.05 1.04 1.00 No
CASE-2-
C-R 1.04 1.04 1.03 1.05 1.04 1.00 No
CASE-3-
A-R 1.01 1.03 1.00 1.03 1.03 1.00 No
CASE-3-
B-R 1.01 1.03 1.00 1.03 1.03 1.00 No
CASE-3-
C-R 1.01 1.03 1.00 1.03 1.03 1.00 No
CASE-3-
D-R 1.02 1.03 1.00 1.03 1.03 1.00 No
CASE-3-
E-R 1.02 1.03 1.00 1.04 1.03 1.00 No
CASE-4-
A-R 1.00 1.00 0.99 1.01 1.01 1.00 No
CASE-4-
B-R 1.00 1.00 0.99 1.01 1.01 1.00 No
CASE-4-
C-R 1.00 1.01 0.99 1.01 1.01 1.00 No
CASE-4-
D-R 1.01 1.01 1.00 1.01 1.02 1.00 No
CASE-4-
E-R 1.01 1.01 1.00 1.02 1.02 1.00 No
CASE-5-
A-R 0.99 1.00 0.99 1.00 1.01 1.00 No
CASE-5-
B-R 0.99 1.00 0.99 1.00 1.01 1.00 No
CASE-5-
C-R 1.00 1.00 0.99 1.01 1.01 1.00 No
CASE-5-
D-R 1.00 1.00 0.99 1.01 1.01 1.00 No
CASE-5-
E-R 1.00 1.01 1.00 1.01 1.01 1.00 No
Page 37 of 115
REPORT ON EMTP STUDIES
Open end voltage
Open end voltages with existing reactors 70% SIL Loading
and line charging and line charging condition, Load end
MVAr under no load MVAr under no load voltage/ source end
condition (Ferranti condition (Ferranti reactive power
Circuit ID Effect) effect) absorption
Voltage Charging Voltage Charging Voltage Charging
(pu) MVAr (pu) MVAr (pu) MVAr
1 1.054 211.4 1.02 24.29 0.999 -32.97
2 1.033 128.1 1.033 128.1 1.0 64.93
3 1.058 222.4 1.058 222.4 1.026 145.6
4 1.074 273.1 1.064 218.8 1.028 128.1
5 1.05 159 1.039 133.5 1.017 95.81
6 1.024 90.7 1.024 90.7 1.016 69.3
1084.7 817.79 470.77
Circuit ID -1: 400 kV, 133.7 km double circuit line between ADANI INDIA to RAHANPUR
Substations
Circuit ID -2: 400 kV, 104 km double circuit line between RAHANPUR to BOGURA WEST
Substations
Circuit ID -3: 400 kV, 140 km double circuit line between BOGURA WEST to KALILOIR
Substations
Circuit ID -4: 400 kV, 168.4 km double circuit line between BIBIYANA to KALILOIR
Substations
Circuit ID -5: 400 kV, 177 km single circuit line between ROOPPUR to KALILOIR
Substations
Circuit ID -6: 400 kV, 104 km single circuit line between ROOPPUR to BOGURA WEST
Substations
Hence, one need to compensate at least 50% of the charging MVAr around 470
MVAr. Therefore, it is recommended to use 3x125 MVAr, 420 kV bus reactors.
Table 23: Active power loss for bus and line reactors
Page 38 of 115
REPORT ON EMTP STUDIES
60 0.0866 46.66 0.350 1.050 6.299
75 0.0866 37.33 0.280 0.840 5.039
100 0.0866 27.99 0.210 0.630 3.778
It is seen from the Table 23 that overall active power losses for both bus and line
reactors are similar; however, the following are the drawbacks for line reactors
• With line reactors one need 3 additional circuit breakers and it will add the
extra cost to the system.
• Line reactors will limit the power transfer capability of the line when
compared to uncompensated line.
• 140 km,400 kV double circuit line between Bogura west and Kolikoir
substations
• 237.7 km, 400 kV double circuit line between Bogura west to Adani
substations (bypassing 400 kV Rahanpur substation) with 1x63 MVAr
existing reactor at the ADANI station is considered.
Based on the short circuit data, maximum fault levels at Bogura end and Kolikor
end with network configuration are computed. 50% of maximum 3-phase fault MVA
is considered for minimum fault level conditions. Further, source voltage is varied
from 1.0 pu to 1.05 insteps 0.005 pu to find open end voltages. Simulation results
are presented in Table 20 and PSCAD simulation waveforms are presented in
Annexure-4B.
Table 20: Line requirement study results for different fault MVA levels
400 kV Bogura-Kolikoir line; Charge from Bogura end ;3-phase Fault level 13000 MVA
Source
voltage 1.0 1.005 1.01 1.015 1.02 1.025 1.03 1.035 1.04 1.045 1.05
(pu)
Page 39 of 115
REPORT ON EMTP STUDIES
Open end
voltage 1.021 1.026 1.031 1.036 1.041 1.047 1.052 1.057 1.062 1.067 1.072
(pu)
400 kV Bogura-Kolikoir line; Charge from Bogura end ;3-phase Fault level 6500 MVA
source
voltage 1.0 1.005 1.01 1.015 1.02 1.025 1.03 1.035 1.04 1.045 1.05
(pu)
Open end
1.081
voltage 1.029 1.034 1.04 1.045 1.05 1.055 1.06 1.065 1.07 1.076
(1.056)
(pu)
400 kV Bogura-Kolikoir line; Charge from Kolikoir end; 3-phase Fault level 30000 MVA
source
voltage 1.0 1.005 1.01 1.015 1.02 1.025 1.03 1.035 1.04 1.045 1.05
(pu)
Open end
voltage 1.016 1.021 1.027 1.032 1.037 1.042 1.047 1.052 1.057 1.062 1.067
(pu)
400 kV Bogura-Kolikoir line; Charge from Kolikor end; 3-phase Fault level 15000 MVA
source
voltage 1.0 1.005 1.01 1.015 1.02 1.025 1.03 1.035 1.04 1.045 1.05
(pu)
Open end
1.071
voltage 1.02 1.025 1.03 1.035 1.04 1.045 1.05 1.056 1.061 1.066
(1.052)
(pu)
400 kV Bogura-Adani bypassing rahanpur s/s; Charge from Bogura end; 3-phase Fault level 17000 MVA (1x63 MVAr
line reactor is considered
source
voltage 1.0 1.005 1.01 1.015 1.02 1.025 1.03 1.035 1.04 1.045 1.05
(pu)
Open end
voltage 1.021 1.027 1.032 1.037 1.042 1.047 1.052 1.057 1.062 1.067 1.073
(pu)
400 kV Bogura-Adani bypassing rahanpur s/s; Charge from Bogura end; 3-phase Fault level 8500 MVA (1x63 MVAr
line reactor is considered
source
voltage 1.0 1.005 1.01 1.015 1.02 1.025 1.03 1.035 1.04 1.045 1.05
(pu)
Open end 1.079
voltage 1.028 1.033 1.038 1.043 1.048 1.053 1.059 1.064 1.069 1.074 (1.045/
(pu) 1.072)
It is observed from Table 20 that, the open-end voltages are more than 1.05 pu
for different source voltage and fault levels. Also, a note from Table 20 the values
presented in parenthesis are simulated using a 1x63 MVAr line reactor. However,
even with the line reactor, open-end voltages are more than 1.05 pu. Based on the
practice, the operating conditions resulting in higher open-end voltages are very
remote in practice. The proposed 3x125 MVAr bus reactors will maintain the bus
voltages very close to 1.0 per unit, hence open-end voltages will be maintained
within 1.05 pu. Hence, no additional line reactors are recommended for these lines.
Page 40 of 115
REPORT ON EMTP STUDIES
4.5 CONCLUSIONS AND RECOMMENDATIONS
The following conclusions are from power flow studies:
• It is seen that under light load condition 400 kV bus voltages violate the
maximum allowable voltage limit of 1.05 p.u.
• To reduce the steady-state over voltages, it is recommended to use 3x125
MVAr, 420 kV switchable bus reactors. (Rahanapur, Bogura west and
Rooppur 400 kV substations).
• With the proposed bus reactors, all 400 kV bus voltages are within the limits
under light load conditions.
• No line reactors recommended for Bogura-Kolkoir line.
A properly designed NGR in the system will reduce the over voltages caused by
resonance as mentioned above and the secondary arc current due to single pole
switching.
The shunt reactor is a four-legged reactor. The sensitivity analysis of the effect of
fault location and neutral reactor values on the secondary arc current and recovery
voltage are studied by considering the various system parameters like:
➢ Sending end and receiving end fault levels.
➢ Shunt reactor compensation levels.
For each of the cases, the fault location is varied and for each fault location the
percentage neutral reactance (Xn/Xs) is varied from 0% to 35%. The computations
are carried out for determining the following:
• Single line to ground fault (primary arc) current for different fault buses and
the corresponding neutral current and neutral voltage at the reactor buses.
• Secondary arc current by effecting single phase tripping.
• Recovery voltage that appears across the secondary arc path.
• Induced voltage on a de-energized circuit.
Based on these studies initial value of the neutral reactor shall be selected and
final value of neutral reactor shall be decided based on the transient analysis
described in section 5.2.
Page 42 of 115
REPORT ON EMTP STUDIES
e) Reclosure of the line.
f) Line energization voltages.
In addition to this, studies also shall also be carried out to simulate three poles
opening of the breaker at both ends of one circuit while the other circuit remains in
the energized condition to examine the probability of any resonating over voltage.
A load throws off condition at the receiving end also shall also be carried out.
Based on these studies the final size of the neutral reactor shall be decided.
B1 = w.C1
B0 = w.C0
1
F=
X r .B1
B1 − B0
X n= .....................(1)
3F .B1.[ B0 − (1 − F ).B1]
where
A single phase to ground fault is created for the analysis. Single pole switching
(SPS) viz, opening of the single phase of the breakers at both the ends of one
Page 43 of 115
REPORT ON EMTP STUDIES
circuit, is carried out. Single line to ground fault is applied at different locations on
one circuit of the double circuit line with the NGR values varying from 0% to 60%
(i.e., Xn/Xs) of the phase reactor value. Primary arc current is calculated at fault
location by applying a single line to ground fault. Primary arc current values at fault
locations and neutral current/voltage at reactor neutral points are presented Table
25 & Table 26 respectively.
Table 26: Neutral Current & Neutral Voltage of Reactors (in RMS)
Fault Type: SLG (no SPS)
For Adani_India to Rahanpur 133.7 km line (with actual transposition)
Xn/Xs Fault Bus (Adani_India) Xn/Xs Fault Bus (Adani_India)
Line Reactor-1 Line Reactor-2
V-n(kV) I-n(A) V-n(kV) I-n(A)
0% - 147 0% - 146
5% 17.083 128 5% 17.084 127
10% 30.254 113 10% 30.254 113
15% 40.713 102 15% 40.715 101
20% 49.223 92 20% 49.226 92
30% 62.232 78 30% 62.236 77
Page 44 of 115
REPORT ON EMTP STUDIES
35% 67.319 72 35% 67.319 72
Xn/Xs Fault Bus (Midpoint) Xn/Xs Fault Bus (Midpoint)
The steady state analysis is conducted to find out the secondary arc current
(residual current) at fault bus and to determine the neutral current through the
neutral reactor and neutral voltage across the neutral reactor for Xn/Xs (ratio of
neutral to shunt reactance) values varying from 0% to 35%, when fault is applied
at different locations in one circuit of the system. Neutral current and neutral
voltages are measured for all the reactors. The secondary arc currents (residual
current) at the fault locations are presented in Table 27 & Table 28 respectively.
Page 45 of 115
REPORT ON EMTP STUDIES
Xn/Xs Bus Name
Adani_India Midpoint Rahanpur
0% 32 33 32
5% 27 28 26
10% I res(A) 23 24 22
15% 19 20 19
20% 17 18 16
30% 13 13.5 12
Table 28: Neutral Current & Neutral Voltage of Reactors (in RMS)
Fault Type: SLG (with SPS)
For Adani_India to Rahanpur 133.7 km line (with actual transposition)
Xn/Xs Fault Bus (Adani_India) Xn/Xs Fault Bus (Adani_India)
Line Reactor-1 Line Reactor-2
V-n(kV) I-n(A) V-n(kV) I-n(A)
0% - 84 0% - 113
5% 17.198 74 5% 14.182 98
10% 30.454 65 10% 25.103 87
15% 40.985 58 15% 33.772 78
20% 49.553 53 20% 40.82 71
30% 62.65 45 30% 51.586 60
35% 67.767 41 55.789 55
Xn/Xs Fault Bus (Midpoint) Xn/Xs Fault Bus (Midpoint)
V-n(kV) I-n(A) V-n(kV) I-n(A)
0% - 46 0% - 114
5% 7.09 40 5% 14.167 100
10% 12.567 35 10% 25.088 88
15% 16.919 32 15% 33.762 79
20% 20.462 29 20% 40.82 72
30% 25.882 24 30% 51.606 60
Page 46 of 115
REPORT ON EMTP STUDIES
Xn/Xs Fault Bus (Rahanpur) Xn/Xs Fault Bus (Rahanpur)
V-n(kV) I-n(A) V-n(kV) I-n(A)
0% - 26 0% - 119
5% 3.278 22 5% 14.244 103
10% 5.809 20 10% 25.234 92
15% 7.821 18 15% 33.972 82
20% 9.461 16 20% 41.085 75
One phase could be left open with the other two phases energized during stuck
breaker condition while energizing the line or a single pole open condition arises
while performing single pole reclosing. Similarly, two phases could be left open
with the other phase energized during line de-energization. Shunt reactors
increase the open-phase voltage considerably because of unequal compensation
of the positive and zero-sequence line capacitance. As reactors are in parallel with
the line conductor capacitance to ground, the equivalent phase-to-ground
reactance at power frequency is inductive and very high when the shunt
compensation is large (above about 65%). In such cases, parallel combination of
the shunt reactor and the line shunt capacitance in series with the inter-phase
capacitance forms a series resonant circuit. These conditions could result in series
resonance on shunt compensated lines with attendant over voltages and their
detrimental effects on the connected equipment.
Page 47 of 115
REPORT ON EMTP STUDIES
The systems considered for the analysis is presented in Fig. B3 (8 figures for the
cases as listed below).
Different cases considered for the studies under this section are;
• Case 1: Single pole stuck breaker condition with remote end fully open
and parallel line de-energized.
• Case 2: Single pole stuck breaker condition with remote end fully closed
and parallel line de-energized
• Case 3: Two pole stuck breaker condition with remote end fully open and
parallel line de-energized.
• Case 4: Two pole stuck breaker condition with remote end fully closed
and parallel line de-energized.
• Case 5: Single pole stuck breaker condition on either end of the line and
parallel line energized.
• Case 6: Single pole stuck breaker condition on either end of the line and
parallel line de-energized.
• Case 7: Two pole stuck breaker condition on either end of the line and
parallel line energized.
• Case 8: Two pole stuck breaker condition on either end of the line and
parallel line de-energized.
The voltage induced on the de-energized phase(s) during one and two pole stuck
breaker conditions for the above-mentioned cases (case 1 to case 8) are presented
in Tables 29 to 36 respectively.
Table 29: Stuck Breaker Condition: phase voltage in open phase and
reactor neutral voltage of circuit 1: Case 1
Xn/Xs Adani Bus Midpoint Rahanpur Neutral Neutral current
Value (R phase Bus Bus voltage at Adani (in
voltage in (R phase (R phase at Adani Arms)
kV rms) voltage in voltage in end
kV rms) kV rms) (In kV
rms)
0% 98.40 101.273 102.983 0 62.225
15% 129.131 130.92 131.627 36.604 86.974
30% 71.020 71.656 71.918 47.407 56.568
Page 48 of 115
REPORT ON EMTP STUDIES
Table 30: Stuck Breaker Condition: phase voltage in open phase and
reactor neutral voltage of circuit 1: Case 2
Xn/Xs Adani Bus Midpoint Rahanpur Neutral Neutral current
value (R phase Bus Bus voltage At Adani (in
voltage in (R phase (R phase at Adani Arms)
kV rms) voltage in voltage in end
kV rms) kV rms) (In
kVrms)
0% 232.632 234.717 235.675 0 0
15% 232.633 234.718 235.677 0.084 0.2
30% 232.633 234.719 235.677 0.1286 0.1533
Table 31: Stuck Breaker Condition: phase voltage in open phase and
reactor neutral voltage of circuit 1: Case 3
Xn/Xs Adani Adani Midpoint Midpoint Rahanpur Rahanpur Neutral Neutral
value Bus Bus Bus Bus Bus Bus voltage current
(R (Y (R phase (Y phase (R phase (Y phase at at Adani
phase phase voltage voltage voltage in voltage in Adani (in
voltage voltage in in kV rms) kV rms) end A rms)
in in kV rms) kV rms) (in kV
kV rms) kV rms) rms)
Table 32: Stuck Breaker Condition: phase voltage in open phase and
reactor neutral voltage of circuit 1: Case 4
Xn/Xs Adani Adani Midpoint Midpoint Rahanpur Rahanpur Neutral Neutral
value Bus Bus Bus Bus Bus Bus voltage current
(R (Y (R phase (Y phase (R phase (Y phase at at
phase phase voltage voltage voltage in voltage in Adani Adani
voltage voltage in in kV rms) kV rms) end (in
in in kV rms) kV rms) (in kV A rms)
kV rms) kV rms) rms)
Table 33: Stuck Breaker Condition: phase voltage in open phase and
reactor neutral voltage of circuit 1: Case 5
Xn/Xs Adani Bus Midpoint Rahanpur Bus Neutral voltage Neutral current
value (R phase Bus (R phase at Adani end at Adani (in
voltage in (R phase voltage in (in kV rms) Arms)
Page 49 of 115
REPORT ON EMTP STUDIES
kV rms) voltage in kV rms)
kV rms)
0% 95.115 96.359 96.599 0 115.955
15% 38.418 38.873 38.913 27.855 66.468
30% 15.962 16.239 16.170 39.026 46.669
Table 34: Stuck Breaker Condition: phase voltage in open phase and
reactor neutral voltage of circuit 1: Case 6
Xn/Xs Adani Bus Midpoint Rahanpur neutral voltage neutral current
value (R phase Bus Bus at Adani end at Adani (in
voltage in (R phase (R phase (in kV rms) Arms)
kV rms) voltage in voltage in
kV rms) kV rms)
0% 93.475 96.126 96.602 0 88.388
15% 132.405 133.812 134.041 37.369 89.095
30% 71.531 72.225 72.295 47.658 57.275
Table 35: Stuck Breaker Condition: phase voltage in open phase and
reactor neutral voltage of circuit 1: Case 7
Xn/Xs Adani Adani Midpoint Midpoint Rahanpur Rahanpur Neutral Neutral
value Bus Bus Bus Bus Bus Bus voltage current
(R (Y (R phase (Y phase (R phase (Y phase at at
phase phase voltage voltage voltage in voltage in Adani Adani
voltage voltage in in kV rms) kV rms) end (in
in in kV rms) kV rms) (in kV A rms)
kV rms) kV rms) rms)
Table 36: Stuck Breaker Condition: phase voltage in open phase and
reactor neutral voltage of circuit 1: Case 8
Xn/Xs Adani Adani Midpoint Midpoint Rahanpur Rahanpur Neutral Neutral
value Bus Bus Bus Bus Bus Bus voltage current
(R (Y (R phase (Y phase (R phase (Y phase at at
phase phase voltage in voltage voltage in voltage in Adani Adani
voltage voltage kV rms) in kV rms) kV rms) end (in
in in kV rms) (in kV Arms)
kV rms) kV rms) rms)
0% 72.943 69.61 74.455 71.326 75.205 72.173 0 46.669
15% 299.84 303.39 303.416 306.874 304.401 307.797 85.429 202.93
4 7 9
30% 101.49 105.16 102.826 106.412 102.946 106.444 69.046 82.024
1 7
Page 50 of 115
REPORT ON EMTP STUDIES
5.3.3 INDUCED VOLTAGES ON DE-ENERGIZED CIRCUIT
A shunt compensated de-energized circuit running on the same right of way with
an energized circuit is subjected to high-induced voltages due to parallel
resonance. The phenomenon of induced voltages, due to electrostatic and
electromagnetic coupling, on a shunt compensated de-energized circuit from a
parallel-energized circuit is presented in this section. The de-energized circuit may
be subjected to over voltages due to parallel resonance between the reactor and
the line capacitance. The occurrence of parallel resonance is defined by the de-
energized circuit parameters and the value of induced voltages is determined by
the mutual coupling with the energized circuit.
As the NGR is connected at the neutral point of the phase reactor, this may lead
to a sustained oscillation in the ring down voltage on the de-energized circuit in a
double circuit line. In the extreme case, depending upon the line length and degree
of shunt reactive compensation on the line, it may result into resonating over
voltages. Hence suitability of NGR value needs to be examined, considering
opening of the all three phases on both ends of the one circuit while other circuit
remains in energized condition.
The system considered for the analysis of induced voltages on the de-energized
circuit with other circuit is de-energized. Both electrostatic and electromagnetic
coupling between the two circuits have been duly considered for the analysis and
results are presented in Table 37.
Page 51 of 115
REPORT ON EMTP STUDIES
neutral to earth
The summary of NGR system studies presented in Table 218 and specifications
are chosen accordingly.
Rated Impedance From steady state analysis with SPS, stuck breaker studies
and induced voltages on de-energized studies, NGR value
30% of Xs is selected. To achieve dead time of 1.0s, it is noted
that secondary arc fault current should be less than 40 A, The
NGR rated impedance of 840 ohm is selected.
Rated For 10 sec From steady state analysis with SPS and stuck breaker the
current maximum neutral current observed is 82.5Arms (From struck
and breaker studies). Hence short time current and voltage rating
voltage for 10 sec is selected as 100Arms and 70.0kVrms respectively.
Rated peak current From IEEE Std 32-1972, page no.3&4, table3, NGRs should
be able to withstand, without mechanical failure, forces
associated with the crest of the offset current wave, assuming
sub transient reactance fault conditions. This current shall be
determined from the following equation:
I C = K IT
1
The X/R ratio at point A (thevenins equivalent X/R at neutral point of the reactor) for the system
shown in Fig B2 [Annexure-B] is around 50. The calculated K value is, [From IEEE 32-1972]
K = 1.2*1 + e[ − ( R / X )] * 2 3.3
Page 52 of 115
REPORT ON EMTP STUDIES
Neutral voltage during From steady state analysis with SPS, transient analysis with
abnormal conditions SPS, and stuck breaker, it is seen that the maximum neutral
voltage is 70 kVrms. From the IEEE Std 32-1972, insulation
class is selected as 69 kVrms and BIL of the neutral reactor is
selected as 350 kVpeak.
21 kVAr Continuous
Rated Frequency 50 Hz
Page 53 of 115
REPORT ON EMTP STUDIES
Minimum BIL value at neutral bushing LI 380 kVpeak
of reactor
No. of Phases 1
Table 40: Recovery voltage and secondary arc current without 125 MVAr bus
reactors
Circui
t ID Sending End Mid-Point Receiving Point
Page 54 of 115
REPORT ON EMTP STUDIES
Recover Secondar
y Secondar Arc Recover Secondar Arc Recovery y Arc Arc
Voltage y Current Extinguis y Voltage y Current Extinguis Voltage Current Extinguis
(kV rms) (Arms) h time (s) (kV rms) (Arms) h time (s) (kV rms) (Arms) h time (s)
144.1
1 142.4 24.75 0.87 6 24.75 0.87 145.04 24.75 0.87
2 40.44 13.4 0.585 41 14.14 0.604 41.44 14.14 0.604
3 48.8 26.87 0.92 48.8 26.87 0.92 50.2 27.6 0.94
4 62.1 32.5 1.06 62.72 32.53 1.06 62.8 33.23 1.08
5 74.9 45.96 1.4 74.81 45.25 1.38 72.76 43.84 1.35
6 60.8 26.8 0.92 60.1 26.16 0.9 59.18 25.45 0.89
Circuit ID -1: 400 kV, 133.7 km double circuit line between ADANI INDIA to RAHANPUR
Substations
Circuit ID -2: 400 kV, 104 km double circuit line between RAHANPUR to BOGURA WEST
Substations
Circuit ID -3: 400 kV, 140 km double circuit line between BOGURA WEST to KALILOIR
Substations
Circuit ID -4: 400 kV, 168.4 km double circuit line between BIBIYANA to KALILOIR Substations
Circuit ID -5: 400 kV, 177 km single circuit line between ROOPPUR to KALILOIR Substations
Circuit ID -6: 400 kV, 104 km single circuit line between ROOPPUR to BOGURA WEST
Substations
Table 41: Recovery voltage and secondary arc current with 125 MVAr bus
reactors
Circui
t ID Sending End Mid-Point Receiving Point
Recover Recover
y Secondar Arc y Secondar Arc Recovery Secondar Arc
Voltage y Current Extinguis Voltage y Current Extinguis Voltage y Current Extinguish
(kV rms) (Arms) h time (s) (kV rms) (Arms) h time (s) (kV rms) (Arms) time (s)
144.7
1 4 24.75 0.87 146.5 24.75 0.87 147.43 24.75 0.87
14.141
2 41.51 14.14 0.604 42 4 0.604 42.42 14.14 0.604
3 48.79 27.6 0.94 48.79 27.6 0.94 49.07 27.6 0.94
4 62.08 32.53 1.06 62.72 32.53 1.06 62.8 33.23 1.08
5 76.15 46.66 1.42 75.73 45.96 1.4 74.45 45.25 1.38
6 61.51 26.87 0.92 60.81 26.87 0.92 60.6 26.16 0.904
Circuit ID -1: 400 kV, 133.7 km double circuit line between ADANI INDIA to RAHANPUR
Substations
Circuit ID -2: 400 kV, 104 km double circuit line between RAHANPUR to BOGURA WEST
Substations
Circuit ID -3: 400 kV, 140 km double circuit line between BOGURA WEST to KALILOIR
Substations
Circuit ID -4: 400 kV, 168.4 km double circuit line between BIBIYANA to KALILOIR Substations
Circuit ID -5: 400 kV, 177 km single circuit line between ROOPPUR to KALILOIR Substations
Circuit ID -6: 400 kV, 104 km single circuit line between ROOPPUR to BOGURA WEST
Substations
Page 55 of 115
REPORT ON EMTP STUDIES
It is seen from the results, Circuit ID 4 and 5 are not satisfying dead time of 1.0 s for
successful single pole auto reclosure. In order to achieve successful SPAR for these
circuits High Speed Ground Switch (HSGS) technique is applied and simulation results
are presented in Table 42. The operation procedure for HSGS technique is shown in
Figure 5.
Table 42: Recovery voltage and secondary arc current with HSGS technique
Circuit
Sending End Mid-Point Receiving Point
ID
Page 56 of 115
REPORT ON EMTP STUDIES
of transmission lines. Reactors are normally disconnected at heavy load and
are connected to the bus bars/lines at periods of lightly load. Consequently,
frequent switching is a significant characteristic of reactors. The reactors absorb
the reactive power and reduce the over voltages during light load conditions,
and also reduce transient over voltages due to switching and lightning surges.
However, shunt reactors can reduce line load ability if they are not disconnected
under full load conditions and during the energisation, a high unsymmetrical
current can occur. The unsymmetrical phase inrush currents during a shunt
reactor energization will cause saturation of the reactor, hence overheating.
Page 57 of 115
REPORT ON EMTP STUDIES
Tperiod
3. The delay time ( Td = (2n + 1) − Tpc , where Tperiod is the time period
4
of power frequency and Tpc is predicted closing time of circuit breaker,
n is an integer) is calculated and set in the timer. The delay time refers
to the difference in time between the target-closing phase minus the
predicted closing time and the latest zero-crossing point.
4. With the closing command input, the zero-crossing point is detected to
start the timer. After the elapse of the delay time, the controlled closing
command is output to start the closing operation of the circuit breaker.
After the elapse of the closing time, the circuit breaker is closed. The actual
closing time is measured from the main circuit current or travel sensor, which is
then reflected in the prediction of the next closing time.
Page 58 of 115
REPORT ON EMTP STUDIES
substations. For these reactors energization and de-energization studies are
conducted. Also, 1x63 MVAr line along with NGR is considered for reactor
switching study.
Zero
Inrush sequence
current current
Sl No Substation Reactor Reactor Size Control (kA) (kA)
1 Rahanpur BUS 1x125 MVAr 0.455 0.08
2 Bogura west BUS 1x125 MVAr 0.457 0.08
3 Rooppur BUS 1x125 MVAr 0.449 0.08
4 Adani Line 1x63 MVAr No control 0.232 0.028
5 Rahanpur BUS 1x125 MVAr 0.36 0.08
PIR -400
6 Bogura west BUS 1x125 MVAr 0.362 0.08
ohms and
7 Rooppur BUS 1x125 MVAr insertion 0.357 0.08
8 Adani Line 1x63 MVAr 10 ms 0.232 0.028
0.07
(spike for
9 Rahanpur BUS 1x125 MVAr 0.24 5 ms)
0.07
(spike for
10 Bogura west BUS 1x125 MVAr 0.241 5 ms)
0.07
(spike for
11 Rooppur BUS 1x125 MVAr 0.237 5 ms)
0.025
(spike for
12 Adani Line 1x63 MVAr CSD 0.139 5 ms)
It is noted from the Table 43 simulation results, with controlled switching dc offset
current is almost eliminated while energizing reactor. With PIR switching dc offset
current is minimized or reduced when compared to without any control.
Page 59 of 115
REPORT ON EMTP STUDIES
It is recommended to use control switching device for reactor breakers while
energizing reactors for both bus and line reactors. [
ich = NCt A
lie between 6.623 104 and 13.245 104 A / F . According to IEC 61223 the
chopping number is a function of arcing time and can be approximated by the
following equation
Within the range of arcing time 5ms < Ta < 14ms with standard deviation
s = 0.8 104
Page 60 of 115
REPORT ON EMTP STUDIES
The arcing time can be computed by principle of synchronous trip operation, which
is shown in Figure .
where,
The energy trapped in the load side inductance and capacitance at the instant of
current chopping will oscillate between the inductance and the parallel
capacitance. The first peak of the oscillation has the same polarity as the system
voltage at the time of interruption, leading to the chopping over voltage. The
chopping over voltage factor ka can be calculated by observing the energy balance.
Vam 3N2
ka = = 1+
V0 2Q
where,
Page 61 of 115
REPORT ON EMTP STUDIES
V0 is the power frequency crest voltage across the shunt reactor at the
instant of current interruption and is usually practically the peak voltage
of the power frequency system voltage to ground
A
is the chopping number for a single interrupter
F
3𝑁𝜆2
Then Chopping overvoltage factor 𝑘𝑎 = √1 + = 1.472𝑝𝑢 = 480 𝑘𝑉
2𝜔𝑄
And the magnitude of recovery voltage across the circuit breaker contacts is
𝑘𝑟 = 1 + 𝑘𝑎 = 2.472𝑝𝑢 = 806 𝑘𝑉
Since small inductive current interruption is similar to that of no load and may be
approximated by the cold gas dielectric recovery characteristic. The increase of
power frequency (50 Hz) withstand voltage as a function of time and contact gap
for cold SF6 gas can be, based upon experiments on a 400 kV circuit breaker,
approximated by equation;
2
Switching of shunt reactors – Theoretical and practical determination of High voltage Circuit Breaker
Behavior proceedings of the CIGRE SC 13 Colloquium pp 13-95, September 1995
Page 62 of 115
REPORT ON EMTP STUDIES
Figure 8: Dielectric recovery characteristics for the SF6 cold gas
Chopping
Current TRV RRRV
Sl No Substation Reactor Reactor Size (A) (kV) (kV/µs)
1 Rahanpur BUS 1x125 MVAr 883 5.7
2 Bogura west BUS 1x125 MVAr 885 5.8
3 Rooppur BUS 1x125 MVAr 877 5.7
Line with
4 Adani NGR 1x63 MVAr 1207 6.9
Line with
NGR
5 Adani bypass 1x63 MVAr 10 1079 8
Page 63 of 115
REPORT ON EMTP STUDIES
6 Rahanpur BUS 1x125 MVAr 722 4.1
7 Bogura west BUS 1x125 MVAr 725 4.1
8 Rooppur BUS 1x125 MVAr 722 4.1
Line with
9 Adani NGR 1x63 MVAr 908 4.3
Line with
NGR
10 Adani bypass 1x63 MVAr 5 799 4.2
11 Rahanpur BUS 1x125 MVAr 662 3.45
12 Bogura west BUS 1x125 MVAr 664 3.47
13 Rooppur BUS 1x125 MVAr 656 3.42
Line with
14 Adani NGR 1x63 MVAr 781 3.25
Line with
NGR
15 Adani bypass 1x63 MVAr 2 669 3.1
It is noted from the results that the maximum transient recovery voltage for circuit
breaker is around 890 kV peak and 1207 kV peak for bus and line reactor
respectively.
The recovery voltage is the voltage that appears across the terminals of a pole of
a circuit breaker after interruption. This voltage may be considered in two
successive time intervals: one during which a transient recovery voltage (TRV)
exists, followed by a second during which a power frequency voltage alone exists.
During the interruption process, the arc rapidly loses conductivity as the
instantaneous current approaches zero. Within a few microseconds after current
zero, current stops flowing in the circuit. The power system response to current
interruption generates the TRV. TRV is the difference in the power system
Page 64 of 115
REPORT ON EMTP STUDIES
response voltages on the source side and on the load side of the circuit breaker.
The nature of the TRV depends on the circuit being interrupted: primarily resistive,
capacitive, or inductive (or some combination). Additionally, distributed and lumped
circuit elements will produce different TRV wave shapes.
In principle, the response of the load side and source side of the circuit breaker
can be analyzed separately, and the results can be subtracted point by point on a
time line. The driving voltage is the instantaneous voltage across the circuit
elements at the instant of current interruption.
Table 22: TRV study results for 400 kV transmission lines and Inter
Connecting Transformers
No load /
Charging
S. Current TRV RRRV
No. Line/ Transormer (Arms) (kV) (kV/µs)
400 kV circuit between Adani to
Rahahpur substations without line
1 Reactors 160 744 0.2
400 kV circuit between Adani to
2 Rahahpur substations with line Reactors 72 737 0.2
400 kV circuit between Rahanpur to
3 Bogura west substations 97 723 0.15
400 kV circuit between kaliakoir to
4 Bogura west substations 168 748 0.21
400 kV circuit between kaliakoirto
Bibiyana substations without line
5 reactors 205 767 0.17
400 kV circuit between kaliakoir to
6 Bibiyana substations with line reactors 169 762 0.2
400 kV circuit between Rooppur to
kaliakoir substations without line
7 reactors 244 796 0.51
400 kV circuit between Rooppur to
8 kaliakoir substations with line reactors 208 765 0.55
400 kV circuit between Rooppur to
9 Bogura west substations 140 746 0.62
Page 65 of 115
REPORT ON EMTP STUDIES
520 MVA, 400/132/33 kV Transformer
10 switching under no load condition 9.0 701 0.82
750 MVA, 400/230/33 kV Transformer
11 switching under no load condition 5.0 788 0.86
It is observed from Table 22 that, TRV and RRRV for line and transformer breaker
is within limits. However, it is recommended to use the CSD for transformer circuit
breaker on 400 kV side and line breakers should have the capability of capacitive
current breaking for 400 A.
Based on Rahanpur and Bogura west substation configurations the following faults
are considered for breaker TRV study.
• 3-phase to ground fault at the breaker terminals
• Transformer limited 3-phase to ground fault
• Short line 1-phase to ground fault
Standard values of transient recovery voltages are considered from IEC 62271-
100 standard and presented in Table 23 for ready reference. SF6 circuit breaker
ratings for Rahanpur and Bogura west substations are presented in Table 24.
Typical stray capacitance values considered for various equipment are considered
from IEEE C37.011-2019 standard and presented in Table 25.
Table 23 : Standard values of transient recovery voltages for solidly earthed
systems representation by four parameters
first
pole Frist TRV
Voltage to Amplitud reference Time peak Time Time Voltag RRRV
Test Time
Class clear e factor voltage t1 value t2 delay e u' u1/t1
duty t' (µs)
(kV) facto kaf (p.u) u1 (µs) uc (us) td (µs) (kV) (kV/µs)
r kpp (kV) (kV)
(p.u)
Termin
1.3 1.4 334 167 624 668 2 167 86 2
al fault
420
Short
line 1 1.4 257 129 480 516 2 129 66 2
fault
Termin
1.3 1.4 195 98 364 392 2 98 51 2
al fault
245
Short
line 1 1.4 150 75 280 300 2 75 40 2
fault
Termin
145 1.5 1.4 133 67 249 268 2 67 35 2
al fault
Page 66 of 115
REPORT ON EMTP STUDIES
Short
line 1 1.4 89 44 166 176 2 44 24 2
fault
Table 24: Circuit breaker ratings for Rahanpur and Bogura west substations
Breaker Ratings
Voltage Voltage Continuous Short time
Substation level (kV) rating rating
400 420 4000 A 50 kA/3s
Rahanpur 132 145 3150 A 40 kA/3s
Bogura 400 420 4000 A 63 kA/3s
west 230 245 3150 A 50 kA/3s
Line and transformer breaker TRV study under various fault conditions for
Rahanpur 400 kV substation has been conducted and results are presented in
Table 26. PSCAD simulation waveforms are presented in Annexure-8.
Page 67 of 115
REPORT ON EMTP STUDIES
Table 26: Breaker TRV study for 400 kV Rahanpur substation under fault
conditions
Breaking
Sl. TRV RRRV
Substation Test Duty Element Current Adequacy
No. (kV) (kV/µs)
(kA rms)
Rahanpur
1 -Adani- 13.2 440 0.67 yes
Circuit1
Terminal
Rahanpur
Fault
-Bogura
2 11.5 498 0.8 yes
west-
Circuit1
LV side
fault and
3 HV 3.2 400 6.3 yes
breaker
Transform
operation
Rahanpur er limited
HV side
fault
fault and
4 LV 3.5 53 1.9 yes
breaker
operation
Rahanpur
5 -Adani- 10.6 379 1.72 yes
Circuit1
Short line
Rahanpur
fault
-Bogura
6 9.7 400 1.75 yes
west-
Circuit1
Line and transformer breaker TRV study under various fault conditions for Bogura
west 400 kV substation has been conducted and results are presented in Table 27.
PSCAD simulation waveforms are presented in Annexure-9.
Table 27: Breaker TRV study for 400 kV Rahanpur substation under fault
conditions
Breaking
Sl. Test TRV RRRV
Substation Element Current Adequacy
No. Duty (kV) (kV/µs)
(kA rms)
Bogura
west-
1 25.6 449 0.88 yes
Bogura Terminal Rahanpur
West Fault -Circuit1
Boguraw
2 23.6 463 0.79 yes
est-
Page 68 of 115
REPORT ON EMTP STUDIES
kaliakoir-
Circuit1
Bogura
west-
3 21.4 471 0.8 yes
Rooppur
circuit
LV side
fault and
4 HV 3.6 312 6.2 yes
Transfor breaker
mer operation
limited HV side
fault fault and
5 LV 5.0 138 3.9 yes
breaker
operation
Bogura
west-
6 19.7 373 3.5 yes
Rahanpur
-Circuit1
Bogura
Short line west-
7 18.9 383 2.9 yes
fault kaliakoir-
Circuit1
Bogura
west-
8 17.5 397 2.8 yes
Rooppur
circuit
Based on the simulation studies conducted with normal and fault conditions for
Rahanpur and Bogura west 400 kV substations, it is observed that breaker TRV
for line and transformers breakers are well within the limits of ratings of the circuit
breaker.
Page 69 of 115
REPORT ON EMTP STUDIES
8.1 400 KV RAHANPUR SWITCHING SURGE ANALYSIS
Line energization study for Rahanpur substation is carried out with the following
control options:
No Control
The resultant switching over voltages are presented in Table 51. PSCAD
simulation waveforms are presented in Annexure-10A.
Page 70 of 115
REPORT ON EMTP STUDIES
Case- With line No
A15 reactor 1.07 1.08
Case- Without line No
A16 2ckt reactor 1.13 1.26
Case- With line No
A17 reactor 1.68 1.95
Case- Without line No
A18 1ckt reactor 1.67 1.94
Case- With line No
A19 Surge reactor 1.33 1.69
Case- Arrester Without line No
A20 Line Closing Control 2ckt reactor 1.35 1.71
It is observed from Table 51 that switching over voltages are within limits (840 kV
i.e. 80% of 1050 kV). Hence 360 kV surge arresters with class-4 are recommended
to limit the switching over voltages.
Line re-energization study for Rahanpur substation is carried out with the following
control options:
• No Control
The resultant switching over voltages are presented in Table 52. PSCAD
simulation waveforms are presented in Annexure-10B.
Open Zero
Switchi end missing
ng end Volta phenome
Voltage ge na
400 kV ADANI to RAHANPUR 133.7 km double circuit line (p.u) (p.u)
Case- With line No
B1 reactor 2.01 2.76
Case- Without line No
B2 1ckt reactor 1.81 2.22
Case- With line No
B3 reactor 1.35 1.96
Case- Re- Without No
B4 Line Closing No Control 2ckt reactor 1.31 2.07
Case- With line No
B5 reactor 1.15 1.15
Case- Without line No
B6 1ckt reactor 1.18 1.29
Case- Re- With line No
B7 Line Closing PIR-8ms 2ckt reactor 1.13 1.20
Page 71 of 115
REPORT ON EMTP STUDIES
Case- Without line No
B8 reactor 1.16 1.29
Case- With line No
B9 reactor 1.14 1.14
Case- Without line No
B10 1ckt reactor 1.18 1.26
Case- With line No
B11 reactor 1.11 1.15
Case- Re- Without line No
B12 Line Closing PIR-10ms 2ckt reactor 1.17 1.23
Case- With line No
B13 reactor 1.14 1.15
Case- Without line No
B14 1ckt reactor 1.13 1.16
Case- With line No
B15 reactor 1.11 1.15
Case- Re- Without line No
B16 Line Closing PIR-12ms 2ckt reactor 1.17 1.28
Case- With line No
B17 reactor 1.85 2.08
Case- Without line No
B18 1ckt reactor 1.74 2.04
Case- With line No
B19 reactor 1.38 1.77
Case- Re- Without line No
B20 Line Closing SA Control 2ckt reactor 1.31 1.86
It is observed from Table 52 that, switching over voltages are within limits (840 kV
i.e., 80% of 1050 kV) for PIR and SA control. Hence 360 kV surge arresters with
class-4 are recommended to limit the switching over voltages.
Line energization with SOTF study for Rahanpur substation is carried out with the
following control options:
• No Control
Table 53: Results for 133.7 km double circuit line energization with SOTF
Zero
missi
Switching Open ng
end end phen
400 kV ADANI to RAHANPUR 133.7 km double circuit line Voltage Voltage omen
switch to on to fault (p.u) (p.u) on
Page 72 of 115
REPORT ON EMTP STUDIES
Case-D1 With line reactor 1.86 2.35 NO
1ck Without line
Case-D2 t reactor 1.88 2.38 NO
Case-D3 Lin No 2ck With line reactor 1.48 1.85 NO
Case-D4 e Closing Control t Without reactor 1.53 1.97 NO
Case-D5 With line reactor 1.26 1.26 NO
1ck Without line
Case-D6 t reactor 1.28 2.28 NO
Case-D7 With line reactor 1.26 1.28 NO
Lin 2ck Without line
Case-D8 e Closing PIR-8ms t reactor 1.35 1.51 NO
Case-D9 With line reactor 1.26 1.25 NO
1ck Without line
Case-D10 t reactor 1.27 1.31 NO
Case-D11 With line reactor 1.27 1.28 NO
Lin 2ck Without line
Case-D12 e Closing PIR-10ms t reactor 1.34 1.44 NO
Case-D13 With line reactor 1.26 1.25 NO
1ck Without line
Case-D14 t reactor 1.28 1.31 NO
Case-D15 With line reactor 1.27 1.28 NO
Lin 2ck Without line
Case-D16 e Closing PIR-12ms t reactor 1.35 1.49 NO
Case-D17 With line reactor 1.78 1.99 NO
1ck Without line
Case-D18 t reactor 1.78 2.00 NO
Case-D19 With line reactor 1.50 1.81 NO
Lin SA 2ck Without line
Case-D20 e Closing Control t reactor 1.52 1.84 NO
It is observed from Table 53 that, switching over voltages are within limits (840 kV
i.e., 80% of 1050 kV) for PIR and SA control. Hence 360 kV surge arresters with
class-4 are recommended to limit the switching over voltages.
Transformer energization study for Rahanpur substation is carried out with the following
control options:
• No Control
• CSD no delay (only considered on HV side breaker because independent pole
operation)
• CSD with +/- 2ms (only considered on HV side breaker because independent
pole operation)
• CSD with +/- 3ms (only considered on HV side breaker because independent
pole operation)
The results for transformer energization study without remnant flux are presented in Table
28. PSCAD simulation waveforms are presented in Annexure-11A.
Page 73 of 115
REPORT ON EMTP STUDIES
Table 28: 520 MVA Transformer energization study results without remnant
flux
time to reach
Switching 0.95/0.9 pu Inrush
520 MVA 400/132/33 kV Auto end Voltage from voltage Current
transformer energization in pu dip (s) (kA)
CASE- HV
C1 end 0.916 0.4 6.31
CASE- MV
C2 Transformer No Control end 0.936 0.2 4
CASE- HV
C3 end 0.914 0.6 6.34
CASE- MV
C4 Sympathetic No control end 0.944 0.2 4.91
CASE-
C5 Transformer 0.99 1.52
CASE- CSD -no HV
C6 Sympathetic delay end 0.99 1.5
CASE-
C7 Transformer 0.98 2.53
CASE- CSD with HV
C8 Sympathetic 2ms delay end 0.98 2.5
CASE-
C9 Transformer CSD with 0.94 0.2 5.24
CASE- 2ms HV
C10 Sympathetic advance end 0.935 0.3 5.27
CASE-
C11 Transformer 0.95 3.76
CASE- CSD with HV
C12 Sympathetic 3ms delay end 0.95 3.75
CASE-
C13 Transformer CSD with 0.916 0.4 6.28
CASE- 3ms HV
C14 Sympathetic advance end 0.914 0.7 6.314
The results for transformer energization study with remnant flux are presented in Table 29.
PSCAD simulation waveforms are presented in Annexure-11B.
Table 29: 520 MVA Transformer energization study results with remnant
flux
520 MVA 400/132/33 kV Auto time to
transformer energization reach 0.95
Page 74 of 115
REPORT ON EMTP STUDIES
pu from
Switching voltage dip Inrush
end Voltage (s) Current
in pu (kA)
CASE- HV
0.87 0.8 9.14
E1 end
Transformer No Control
CASE- MV
0.876 0.4 6.6
E2 end
CASE- HV
0.866 1.5 9.3
E3 end
Sympathetic No control
CASE- MV
0.9 1.5 8.1
E4 end
CASE-
Transformer 1 - 0.44
E5 CSD -no HV
CASE- delay end
Sympathetic 1 - 0.38
E6
CASE-
Transformer 0.944 0.1 4.5
E7 CSD with HV
CASE- 2ms delay end
Sympathetic 0.941 0.2 4.52
E8
CASE-
Transformer CSD with 0.982 - 2.45
E9 HV
2ms
CASE- end
Sympathetic advance 0.979 - 2.464
E10
CASE-
Transformer 0.915 0.5 6.63
E11 CSD with HV
CASE- 3ms delay end
Sympathetic 0.912 0.6 6.67
E12
CASE-
Transformer CSD with 0.963 - 3.44
E13 HV
3ms
CASE- end
Sympathetic advance 0.96 - 3.46
E14
It is observed from Table 28 and Table 29 that the voltage dip and inrush currents are
minimal for CSD, hence it is recommended to use transformer HV breaker with CSD
control.
• Switching over voltages are under control for both PIR and 360 kV line class
surge arresters.
• Voltage dip at switching end and inrush currents are minimal for transformer
energization with CSD.
Page 75 of 115
REPORT ON EMTP STUDIES
The following recommendations are suggested:
• Switching over voltages during line energization are under control with 360
kV, class-4 surge arrester. Hence no PIR and CSD suggested for line circuit
breakers.
Line energization study for Bogura west substation is carried out with the
following control options:
• No Control
The resultant switching over voltages are presented in Table 56. PSCAD
simulation waveforms are presented in Annexure-12A.
Table 56: Line energization study results for 400 kV Bogura west
substations
Switching
Line-1 :400 kV 140 km double circuit line from Bogura west to end Open end
kaliakoir;Line-2: kaliakoir to Rooppur 177 km 400 kV single Voltage Voltage
circuit (p.u) (p.u)
Case-A1 1ckt 1.72 2.33
Case-A2 Line-1 Closing No control 2ckt 1.37 1.85
Case-A3 1ckt 1.18 1.31
Case-A4 Line-1 Closing PIR-8ms 2ckt 1.16 1.33
Case-A5 1ckt 1.19 1.30
Case-A6 Line-1 Closing PIR-10ms 2ckt 1.16 1.31
Case-A7 1ckt 1.17 1.29
Case-A8 Line-1 Closing PIR-12ms 2ckt 1.17 1.31
Case-A9 1ckt 1.67 1.95
case-A10 Line-1 Closing SA Control 2ckt 1.33 1.70
Case-A11 With Line Reactor 1.61 2.22
Without Line
Case-A12 Line-2 Closing No control Reactor 1.61 2.25
Case-A13 With Line Reactor 1.28 1.46
Without Line
Case-A14 Line-2 Closing PIR-8ms Reactor 1.31 1.55
Case-A15 Line-2 Closing PIR-10ms With Line Reactor 1.23 1.39
Page 76 of 115
REPORT ON EMTP STUDIES
Without Line
Case-A16 Reactor 1.29 1.52
Case-A17 With Line Reactor 1.21 1.37
Without Line
Case-A18 Line-2 Closing PIR-12ms Reactor 1.29 1.51
Case-A19 With Line Reactor 1.6 1.91
Without Line
Case-A20 Line-2 Closing SA Control Reactor 1.59 1.92
It is observed from Table 56 that switching over voltages are within limits (840 kV
i.e., 80% of 1050 kV). Hence 360 kV surge arresters with class-4 are recommended
to limit the switching over voltages.
Line re-energization study for Bogura west substation is carried out with the
following control options:
• No Control
The resultant switching over voltages are presented in Table 57. PSCAD
simulation waveforms are presented in Annexure-12B.
Table 57: Line Re-energization study results for 400 kV Bogura west
substations
Switching
Line-1 :400 kV 140 km double circuit line from Bogura west to end Open end
kaliakoir;Line-2: kaliakoir to Rooppur 177 km 400 kV single Voltage Voltage
circuit (p.u) (p.u)
Case-B1 1ckt 1.90 2.65
Case-B2 Line-1 Re-Closing No control 2ckt 1.50 2.36
Case-B3 1ckt 1.23 1.33
Case-B4 Line-1 Re-Closing PIR-8ms 2ckt 1.36 1.43
Case-B5 1ckt 1.23 1.33
Case-B6 Line-1 Re-Closing PIR-10ms 2ckt 1.36 1.43
Case-B7 1ckt 1.23 1.33
Case-B8 Line-1 Re-Closing PIR-12ms 2ckt 1.36 1.43
Page 77 of 115
REPORT ON EMTP STUDIES
without line
Case-B12 reactor 1.91 2.72
It is observed from Table 57 that, switching over voltages are within limits (840 kV
i.e., 80% of 1050 kV) for PIR and SA control. Hence 360 kV surge arresters with
class-4 are recommended to limit the switching over voltages.
Transformer energization study for Bogura west substation is carried out with the
following control options:
• No Control
• CSD no delay
• CSD with +/- 2ms
• CSD with +/- 3ms
The results for transformer energization study from 400 kV side without remnant
flux are presented in Table 30. PSCAD simulation waveforms are presented in
Annexure-13A.
Table 30: 750 MVA Transformer energization study results from 400 kV side
without remnant flux
Time
to
Switchin recove
Inrush
750 MVA 400/230/33 kV Auto transformer g end r the
Curren
energization voltage voltag
t (kA)
(pu) e to
0.95
pu
Page 78 of 115
REPORT ON EMTP STUDIES
from
voltag
e dip
(s)
Transform
CASE-C1 0.915 0.4 9.1
er Charg
Sympatheti No e from
CASE-C2 0.919 0.6 9.4
c Control HV
Sympatheti end
CASE-C3 0.923 0.7 9.6
c
Transform
CASE-C4 0.99 - 2.2
er Charg
Sympatheti CSD-No e from
CASE-C5 0.988 - 2.24
c delay HV
Sympatheti end
CASE-C6 0.985 - 2.3
c
Transform
CASE-C7 0.98 - 3.63
er Charg
Sympatheti CSD-2 e from
CASE-C8 0.98 - 3.67
c ms delay HV
Sympatheti end
CASE-C9 0.978 - 3.74
c
Transform
CASE-C10 0.936 0.2 7.54
er Charg
CSD-2
Sympatheti e from
CASE-C11 ms 0.938 0.2 7.79
c HV
advance
Sympatheti end
CASE-C12 0.94 0.2 8
c
Transform
CASE-C13 0.95 - 5.42
er Charg
CSD-
Sympatheti e from
CASE-C14 3ms 0.952 - 5.53
c HV
delay
Sympatheti end
CASE-C15 0.952 - 5.66
c
Transform
CASE-C16 0.915 0.4 9.04
er Charg
CSD- 3
Sympatheti e from
CASE-C17 ms 0.919 0.6 9.34
c HV
advance
Sympatheti end
CASE-C18 0.922 0.6 9.6
c
The results for transformer energization study from 400 kV side with remnant flux
are presented in Table 31. PSCAD simulation waveforms are presented in
Annexure-13B.
Page 79 of 115
REPORT ON EMTP STUDIES
Table 31: 750 MVA Transformer energization study results from 400 kV side
with remnant flux
Time to
recover
Switching the
Inrush
750 MVA 400/230/33 kV Auto transformer end voltage
Current
energization voltage to 0.95
(kA)
(pu) pu from
voltage
dip (s)
CASE-D1 Transformer Charge 0.866 0.8 13.23
CASE-D2 Sympathetic from 0.873 2 13.67
No Control
HV
CASE-D3 Sympathetic end 0.88 2 14.03
CASE-D4 Transformer Charge 1 - 1.12
CASE-D5 Sympathetic CSD-No from 1 - 1.06
delay HV
CASE-D6 Sympathetic end 1 - 1.05
CASE-D7 Transformer Charge 0.939 0.2 6.74
CASE-D8 Sympathetic CSD-2 ms from 0.94 0.2 6.95
delay HV
CASE-D9 Sympathetic end 0.942 0.2 7.1
CASE-D10 Transformer Charge 0.986 - 3.26
CASE-D11 Sympathetic CSD-2 ms from 0.984 - 3.37
advance HV
CASE-D12 Sympathetic end 0.982 - 3.46
CASE-D13 Transformer Charge 0.911 0.6 9.8
CASE-D14 Sympathetic CSD- 3ms from 0.914 0.6 10.1
delay HV
CASE-D15 Sympathetic end 0.917 0.8 10.33
CASE-D16 Transformer Charge 0.967 - 4.69
CASE-D17 Sympathetic CSD- 3 ms from 0.966 - 4.85
advance HV
CASE-D18 Sympathetic end 0.966 - 4.97
The results for transformer energization study from 230 kV side without remnant
flux are presented in Table 32. PSCAD simulation waveforms are presented in
Annexure-13C.
Table 32: 750 MVA Transformer energization study results from 230 kV side
without remnant flux
Time to
Switching recover
Inrush
750 MVA 400/230/33 kV Auto transformer end the
Current
energization voltage voltage
(kA)
(pu) to 0.95
pu from
Page 80 of 115
REPORT ON EMTP STUDIES
voltage
dip (s)
Table 33: 750 MVA Transformer energization study results from 230 kV side
with remnant flux
time to
recover
Switching the
Inrush
750 MVA 400/230/33 kV Auto transformer end voltage
Current
energization voltage to 0.95
(kA)
(pu) pu from
voltage
dip (s)
CASE-F1 Transformer Charge 0.908 0.7 8.26
CASE-F2 Sympathetic from 0.923 1.2 8.87
No Control
MV
CASE-F3 Sympathetic end 0.932 1.2 9.26
CASE-F4 Transformer Charge 1 - 0.68
CASE-F5 Sympathetic CSD-No from 0.995 - 0.65
delay MV
CASE-F6 Sympathetic end 0.991 - 0.63
Page 81 of 115
REPORT ON EMTP STUDIES
CASE-F7 Transformer Charge 0.957 - 4.2
CASE-F8 Sympathetic CSD-2 ms from 0.962 - 4.4
delay MV
CASE-F9 Sympathetic end 0.964 - 4.6
CASE-F10 Transformer Charge 0.989 - 2.1
CASE-F11 Sympathetic CSD-2 ms from 0.986 - 2.28
advance MV
CASE-F12 Sympathetic end 0.985 - 2.36
CASE-F13 Transformer Charge 0.937 0.3 6.15
CASE-F14 Sympathetic CSD- 3ms from 0.946 0.2 6.49
delay MV
CASE-F15 Sympathetic end 0.95 - 6.76
CASE-F16 Transformer Charge 0.976 - 2.95
CASE-F17 Sympathetic CSD- 3 ms from 0.976 - 3.22
advance MV
CASE-F18 Sympathetic end 0.976 - 3.36
It is observed from Table 30 to Table 33 that, voltage dip and inrush currents are
minimal for CSD, hence it is recommended to use transformer HV and MV breaker
with CSD control.
• Switching over voltages are under control for both PIR and 360 kV line class
surge arresters.
• Voltage dip at switching end and inrush currents are minimal for transformer
energization with CSD.
• Switching over voltages during line energization are under control with 360
kV, class-4 surge arrester. Hence no PIR and CSD suggested for line circuit
breakers.
Page 82 of 115
REPORT ON EMTP STUDIES
8.3 SWITCHING SURGE ANALYSIS FOR BY PASSING RAHANPUR 400 KV
SUBSTATION
Line energization study for 400 kV line from Bogura west to Adani 400 kV
substations with bypassing 400kV rahanpur substation and switching from Bogura
end is carried out with the following control options:
• No Control
The resultant switching over voltages are presented in Table 62. PSCAD
simulation waveforms are presented in Annexure-14A.
Page 83 of 115
REPORT ON EMTP STUDIES
Without 1.47 (10 1.88 No
Case-A18 Reactor kJ) (125 kJ)
1.81 (73 No
Case-A19 With Reactor 1.25 kJ)
Without 1.81 No
Case-A20 2ckt Reactor 1.24 (108 kJ)
It is observed from Table 62 that switching over voltages are within limits (840 kV
i.e. 80% of 1050 kV). Hence 360 kV surge arresters with class-4 are recommended
to limit the switching over voltages.
Line re-energization study for 400 kV line from Bogura west to Adani 400 kV
substations with bypassing 400kV Rahanpur substation and switching from Bogura
west end is carried out with the following control options:
• No Control
The resultant switching over voltages are presented in Table 63. PSCAD
simulation waveforms are presented in Annexure-14B.
Page 84 of 115
REPORT ON EMTP STUDIES
Case- 10m Without No
B10 s Reactor 1.31 1.60
Case- With No
B11 Reactor 1.14 1.22
Case- Without No
B12 2ckt Reactor 1.30 1.47
Case- PIR With No
B13 12m Reactor 1.13 1.22
Case- s Without No
B14 1ckt Reactor 1.15 1.31
Case- With No
B15 Reactor 1.18 1.23
Case- Re- Without No
B16 Line Closing 2ckt Reactor 1.31 1.56
Case- Contro With 1.66 (19 2.08 (290 No
B17 l Surge Reactor kJ) kJ)
Case- Arrest without 1.62 (17 No
B18 er 1ckt Reactor kJ) (435 kJ)
Case- With 1.93 (166 No
B19 Reactor 1.25 kJ)
Case- Re- Without 2.05 (247 No
B20 Line Closing 2ckt Reactor 1.29 kJ)
It is observed from Table 63 that, switching over voltages are within limits (840 kV
i.e., 80% of 1050 kV) for PIR and SA control. Hence 360 kV surge arresters with
class-4 are recommended to limit the switching over voltages.
Page 85 of 115
REPORT ON EMTP STUDIES
Case-A: Un-transposed line with line reactors including NGR
From results it seen that, from IEC 62271-102, 420 kV, Class B earth switch is
selected. Hence, it is confirmed that the earth switch rated values proposed by M/s.
Adani is in order.
From results it seen that, from IEC 62271-102, 420 kV, Class B earth switch is
selected.
Page 86 of 115
REPORT ON EMTP STUDIES
10 Insulation co-ordination study
One of the most important and primary requirements in the design of the extra high
voltage (EHV) / Ultra high voltage (UHV) system is the determination of expected
over voltages on the various lines / cables and buses constituting the system. In
the initial system design, the geographical arrangement of the system,
transmission capabilities and number of EHV/UHV lines, transformer sizes and
locations as well as shunt reactor compensation to maintain acceptable bus
voltages and generator reactive loadings for peak and light loads are determined
on the basis of load flow and stability analysis for various power scenarios.
The over voltages that occur on this initially designed network under various
switching conditions will then be carefully studied and refinements made, as
necessary to arrive at a final design of the network and its electrical parameters.
In point of fact, the main risks are malfunctions, destruction of the equipment and,
consequently, lack of continuity of service. These disturbances may occur on the
installations of both energy distributors and users. They may occur:
• Between different phases or circuits. They are said to be differential
mode;
• Between live conductors and the frame or earth. They are said to be
common mode.
Disturbances may result in:
• Short disconnections (automatic reclosing on MV public distribution
networks by overhead lines);
• Long disconnections (intervention for changing damaged insulators or
even replacement of equipment).
Their varied and random nature makes them hard to characterize, allowing only a
statistical approach to their duration, amplitudes and effects. Table 66 presents the
main characteristics of these disturbances.
Table 66: Characteristics of the various overvoltage types
Steepness of
Overvoltage type Term Damping
frequency front
Page 87 of 115
REPORT ON EMTP STUDIES
Protective devices limit these risks. Their use calls for careful drawing up of
consistent insulation and protection levels.
Over voltages in EHV/UHV system are usually classified as:
• Steady state over voltages
• Temporary over voltages
• Switching over voltages
• Fast-front voltages
• Very Fast Front over voltages
The steady state over voltages is normally preceded by those of transient and
dynamic periods, but these are generally first to be investigated. This investigation
must be done in advance so that, if necessary, modification in basic system could
be done so that these over voltages remain within the capabilities/ratings of
equipment.
The steady state over voltages arises generally when a transmission line is
connected to the system only at one end i.e., the sending end, and the receiving
end being disconnected. Such situation arises during normal operation and can
persist for many minutes.
The control of such over voltages can be achieved through several methods. The
magnitude of steady state over voltages is a function of no. of system variables.
Some of the important parameters are as under:
• Transformer tap (leakage reactance and air core reactance)
Page 88 of 115
REPORT ON EMTP STUDIES
• Shunt reactor
• Equivalent reactance of the system at the source
• Line length
• Operating conditions and procedures
• Effect of generator voltage regulator
Page 89 of 115
REPORT ON EMTP STUDIES
The energisation of a line from the low side of the transformer can some time lead
to very high over voltage which may be of the same order as obtained on re-
energisation of line with trapped charges. In case of 400 kV system the circuit
breakers may be equipped with the closing resistance for control of switching over
voltage, whereas the breakers of 115 kV system (or) lower voltages are generally
not provided with such resistors and therefore low side switching of the transformer
and the line are in most cases will be examined, specially where the reactance of
low side system is quite high. In 400 kV system the predominant switching
transient over voltages are those due to energisation and re-energisation.
The control of switching over voltages is possible through several means, which
may include even the modification of the basic design of the system. However more
feasible and practical are the four principal methods for control of switching surge
over voltages which are as follows:
• Resistor Insertion
• Surge Arresters
The fast transients in power systems cover a frequency range from 10 kHz up to 1
MHz. One of the primary causes of such transients is the lightning stroke to the
transmission lines or on tower top and associated back flashovers. The lightning
over voltages is caused by either shielding failures or back flashovers of the tower
insulation on the transmission lines. Direct strokes to the phase conductors may
also become a concern if the transmission line and/or substation are not shielded
due to relatively low lightning activity in the area. This study is usually carried out
for insulation coordination purposes.
Page 90 of 115
REPORT ON EMTP STUDIES
important for the overvoltage characterization at the sub-station. These over
voltages will provide the data required for detailed arrester specifications. Based
on this, the insulation levels (i.e., BIL) of the sub-station equipment can be
coordinated with the protective level of the arresters.
Page 91 of 115
REPORT ON EMTP STUDIES
133.7 km, 400 kV double circuit line 3 SLG Fault 1.19
between Adani to Rahanpur 400 kV
5 SLG Fault accompanying 1.24
stations
with Load rejection
Based on the various cases studied, it is seen that the steady state temporary
overvoltage is 1.24 per unit. Considering the maximum system operating voltage
as 420 kV for 400 kV systems, the maximum temporary voltage is 300 kVrms. It is
recommended to have surge arrester rated voltage greater than maximum
temporary overvoltage, hence 360 kVrms surge arrester is recommended for 400
kV system. It is also noted that the maximum steady state temporary overvoltage
for 132 kV system is 1.09 per unit, considering maximum system operating voltage
for 132 kV system is 145 kV, the maximum TOV is 92 kVrms. It is recommended
to have surge arrester rating for 132 kV system is 120 kVrms and 30 kVrms surge
arrester for 33 kV system (as per single line diagram 33 kV system zig-zag earthed
system) respectively.
The simulation study results are presented in Table 68 and PSCAD simulation
waveforms are presented in Annexure-18.
It is observed from Table 68 for single pole or two-pole opening of overhead lines
terminated by unloaded transformer at receiving end results in ferro-resonance, a
minimum 25 MW loading on each power transformer assist in damping out these
Page 93 of 115
REPORT ON EMTP STUDIES
Ferro resonance oscillations, so it is recommended that system configuration
leading to an energisation of overhead line terminated by unloaded power
transformer should be avoided.
Voltage Surge
(kVpeak) arrester
Transmission line Case (Phase to Energy
considered No Events Simulated earth) (kJ)
Based on the various cases studied, it is seen that the maximum switching
overvoltage is 636 kVpeak which is well within the limits of switching coordination
withstand voltage (80% of 1050 kVpeak SIL, i.e 840 kVpeak). Hence, proposed
switching impulse level of 1050 kVpeak is adequate. It is also noted from the Table
69, the maximum energy absorbed by surge arrester is 150 kJ and its specific
energy is 0.42 kJ/kV. Hence it is proposed that the energy class of surge arrester
is minimum of class-4 i.e., its specific energy is 4kJ/kV.
Page 94 of 115
REPORT ON EMTP STUDIES
The GIS substation model considers only one transmission line and one ICT
Transformer with all other lines and ICT Transformers disconnected to create a
worst-case scenario. The following capacitance values have been selected for the
various components for 400 kV substation.
All the input data considered for the fast transient analysis have been compiled in
Table 70 for ready reference.
Table 70: Data considered for FTA study
Applied Parameters Base Model
Page 95 of 115
REPORT ON EMTP STUDIES
Applied Parameters Base Model
Length =60 m
GIS busbar
Zs=57.9 ,
v=2.9e+8 m/sec
Bus duct between gantry Length = 109 m; Zs=57.9 ,
and GIS v=2.9e+8 m/s
SA Characteristics 360 kV
Substation
Disconnector open 4.2 pF [6]
Disconnector Close 200 pF [6]
VT 80 pF [6]
Circuit Breaker close 150 pF [6]
CHG=5854.1 pF;
CLG=8057.6 pF;
CTG=14424.6 pF;
ICT Transformer CHL=3023.8 pF;
CHT=1889 pF;
CLT=5033.8 pF
Further, the study focuses on four locations for analyzing the overvoltages viz.:
• At Gantry (Point A).
• At entry to GIS (Point B).
• At outgoing point of GIS (Point C).
• At ICT Transformer HV side (Point D).
Page 96 of 115
REPORT ON EMTP STUDIES
• At ICT Tranformer LV side (Point E)
• At ICT Transformer TV side (Point F)
For direct stroke at first tower from gantry, 20 kA (peak) 0.46/77 µs lightning current
is considered. The maximum voltages and energy absorbed by surge arresters
measured at the selected locations and are presented in Table 71. Simulated
waveforms are shown in Annexure-20 for ready refrence.
Table 71: FTA Results for Direct Stroke with Lightning Current of 20 kA at 1st
tower from gantry for 400 kV Rahanpur substation.
Specific
Voltage in kVPEAK Energy
Location at % BIL Energy
(Phase-earth)
(kJ) (kJ/kV)
For a backflashover at first tower from gantry, a lightning current of 259 kA (peak),
8.42/77 µs is computed using semi static and determinstic method[2]. One failure
for 400 years considered as design failure rate. Tower footing resistance of 5 to
20 in steps of 5 is considered for frist five towers from substation.
The arcing horn air gap of insulator for 400 kV system is considered as 3050 mm.
Simulation studies have been carried out for the above parameters with tower
footing resistance of 5 ohm and it is seen that no backflashover occurs. Simulation
studies are also performed with tower footing resistance of 20 ohm, it is seent that
there is a back flashover for air gap length of 3050 mm. Simulation results are
presented in Table 72 and resultatnt waveforms are presented in Annexure-20.
Page 97 of 115
REPORT ON EMTP STUDIES
Table 72: FTA Results for Back flashover with Lightning Current of 259 kA at 1st
tower from gantry for 400 kV Rahanpur substation.
Specific
Voltage in kVPEAK Energy
Location at % BIL Energy
(Phase-earth)
(kJ) (kJ/kV)
Page 98 of 115
REPORT ON EMTP STUDIES
GIS Bus and one one SA at ICT Transformer HV terminal, the % of BIL at
transformer HV side is 68.14% which is well within acceptable range (according to
saftey margin, % BIL of the equipment should not exceed 80% of lightning BIL of
the equipment).
Hence proposed surge arresters rating (360 kVrms) and their locations namely one
SA at gantry, one SA at GIS Busbar and one SA at ICT Transformer HV terminal
are adequate to achieve proper protection margins in RAHANPUR -400 kV
switching substation.
The generation and propagation of Very Fast Transient Overvoltages (VFTO) from
their original location throughout a GIS can produce internal and external
overvoltages. The main concern is internal overvoltages between the center
conductor and the enclosure.
When the current is interrupted during opening operation or making current during
closing operation, a spark is formed, which equalizes the potential on both sides of
the contacts. VFTO developed because of the above, can continue for a fraction
of a micro second to several micro seconds depending upon the configuration of
Page 99 of 115
REPORT ON EMTP STUDIES
the GIS. Just before spark extinction, the load side and the source side voltages
become equal. Following the spark extinction, source side voltage will follow the
supply voltage, while the load side voltage will remain as the trapped voltage. The
shape of these VFTOs, therefore, depends on the configuration of GIS.
VFT in GIS can be divided into internal and external. Internal transients can
produce overvoltages between inner conductors and the encapsulation. External
transients can cause stresses on secondary and adjacent equipments. A summary
of both the phenomena is explained in the following section.
Internal Transients
External transients
An internally generated VFT propagates throughout the GIS and reaches the
bushing where it causes a transient enclosure voltage and a traveling wave that
propagates along the overhead transmission line.
The transient enclosure voltages (TEV), also known as transient ground potential
rise (TGPR), are short duration high voltage transients which appear on the
enclosure of the GIS through the coupling of internal transients to enclosure at
enclosure discontinuities. The usual location for these voltages is the transition
GIS-overhead line at an air bushing, although they can also emerge at other points
such as visual inspection ports, insulated spacers for CTs or insulated flanges at
GIS/cables interfaces.
TEV has two components; the first one has a short initial rise time and is followed
by high frequency oscillations (5 to 10MHz), determined by the various lengths of
the GIS section. The second component is of lower frequency, in the range of
The TEV wave that couples onto the enclosure encounters, earthing connections,
which form transmission line discontinuities and attenuate TEV. Mitigation methods
include grounding using low surge impedance, short length leads and installation
of metal-oxide arresters across any insulating spacers.
Table 74: Results of Temporary Over voltages conducted for BOGURA 400
kV substation
Based on the various cases studied, it is seen that the steady state temporary
overvoltage is 1.13 per unit for 400 kV system. Considering the maximum system
operating voltage as 420 kV for 400 kV systems, the maximum temporary voltage
is 275 kVrms. It is recommended to have surge arrester rated voltage greater than
maximum temporary overvoltage, hence 360 kVrms surge arrester is
recommended for 400 kV system. It is also noted that the maximum steady state
temporary overvoltage for 230 kV system is 1.14 per unit, considering maximum
system operating voltage for 230 kV system is 253 kV, the maximum TOV is 167
kVrms. It is recommended to have surge arrester rating for 230 kV system is 198
kVrms and 30 kVrms surge arrester for 33 kV system (as per single line diagram
33 kV system zig-zag earthed system) respectively.
The simulation study results are presented in Table 75 and PSCAD simulation
waveforms are presented in Annexure-22.
It is observed from Table 75 for single pole or two-pole opening of overhead lines
terminated by unloaded transformer at receiving end results in ferro-resonance, a
minimum 25 MW loading on each power transformer assist in damping out these
ferro-resonance oscillations, so it is recommended that system configuration
leading to an energisation of overhead line terminated by unloaded power
transformer should be avoided.
Table 76: Results of Switching Over voltages conducted for BOGURA 400
kV substation
Voltage
(kVpeak) Surge
Transmission line (Phase to arrester
considered Case No Events Simulated earth) Energy (kJ)
Based on the various cases studied, it is seen that the maximum switching
overvoltage is 654 kVpeak which is well within the limits of switching coordination
withstand voltage (80% of 1050 kVpeak SIL, i.e 840 kVpeak). Hence, proposed
switching impulse level of 1050 kVpeak is adequate. It is also noted from the Table
76, the maximum energy absorbed by surge arrester is 287 kJ and its specific
energy is 0.8 kJ/kV. Hence it is proposed that the energy class of surge arrester is
minimum of class-4 i.e., its specific energy is 4kJ/kV.
The GIS substation model considers only one transmission line and one ICT
Transformer with all other lines and ICT Transformers disconnected to create a
worst-case scenario. The following capacitance values have been selected for the
various components for 400 kV substation.
All the input data considered for the fast transient analysis have been compiled in
Table 77 for ready reference.
Table 77: Data considered for FTA study-Bogura 400 kV Substation
Applied Parameters Base Model
v=2.9e+8 m/sec
Bus duct between gantry Length = 109 m; Zs=57.9 ,
and GIS v=2.9e+8 m/s
CHG=5854.1 pF;
CLG=8057.6 pF;
Further, the study focuses on four locations for analyzing the overvoltages viz.:
▪ At Gantry (Point A).
▪ At entry to GIS (Point B).
For direct stroke at first tower from gantry, 20 kA (peak) 0.46/77 µs lightning current
is considered. The maximum voltages and energy absorbed by surge arresters
measured at the selected locations and are presented in Table 78. Simulated
waveforms are shown in Annexure-24 for ready reference.
Table 78: FTA Results for Direct Stroke with Lightning Current of 20 kA at 1st
tower from gantry for 400 kV Bogura substation.
Specific
Voltage in kVPEAK Energy
Location at % BIL Energy
(Phase-earth)
(kJ) (kJ/kV)
For a backflashover at first tower from gantry, a lightning current of 264.2 kA (peak),
8.52/77 µs is computed using semi static and determinstic method[2]. One failure
for 400 years considered as design failure rate. Tower footing resistance of 5 to
20 in steps of 5 is considered for frist five towers from substation.
The arcing horn air gap of insulator for 400 kV system is considered as 3050 mm.
Table 79: FTA Results for Back flashover with Lightning Current of 264.2 kA at
1st tower from gantry for 400 kV Bogura substation.
Specific
Voltage in kVPEAK Energy
Location at % BIL Energy
(Phase-earth)
(kJ) (kJ/kV)
Hence proposed surge arresters rating (360 kVrms) and their locations namely one
SA at gantry, one SA at GIS Busbar and one SA at ICT Transformer HV terminal
are adequate to achieve proper protection margins in BOGURA -400 kV switching
substation.
The generation and propagation of Very Fast Transient Overvoltages (VFTO) from
their original location throughout a GIS can produce internal and external
overvoltages. The main concern is internal overvoltages between the center
conductor and the enclosure.
VFT in GIS can be divided into internal and external. Internal transients can
produce overvoltages between inner conductors and the encapsulation. External
transients can cause stresses on secondary and adjacent equipments. A summary
of both the phenomena is explained in the following section.
Internal Transients
External transients
An internally generated VFT propagates throughout the GIS and reaches the
bushing where it causes a transient enclosure voltage and a traveling wave that
propagates along the overhead transmission line.
The transient enclosure voltages (TEV), also known as transient ground potential
rise (TGPR), are short duration high voltage transients which appear on the
enclosure of the GIS through the coupling of internal transients to enclosure at
enclosure discontinuities. The usual location for these voltages is the transition
GIS-overhead line at an air bushing, although they can also emerge at other points
TEV has two components; the first one has a short initial rise time and is followed
by high frequency oscillations (5 to 10MHz), determined by the various lengths of
the GIS section. The second component is of lower frequency, in the range of
hundreds of kHz, and is often associated with the discharge of capacitive devices
with the earthing system. Both components are damped quickly as a result of the
lossy nature of the enclosure-to-ground plane transmission mode. TEV generally
persists for a few microseconds. The magnitude varies along the enclosure.
The TEV wave that couples onto the enclosure encounters, earthing connections,
which form transmission line discontinuities and attenuate TEV. Mitigation methods
include grounding using low surge impedance, short length leads and installation
of metal-oxide arresters across any insulating spacers.
The detailed calculations for shielding failures and back flashover analysis are
presented in Annexure-25.
It is observed that 0.011 shielding failures per 100 km-year and 0.967 back
flashover failures per 100 km-year. Overall transmission line flashover rate is 0.978
failures per 100 km-year.
Circuit Breakers:
• Bus and line reactors should be equipped with CSD 400 kV SF6 circuit
breaker.
• HV side of ICT transformers should be equipped with CSD control.
• For all line circuit breakers, no PIR and CSD is required.
NGR Specification:
Rated Frequency 50 Hz
No. of Phases 1
420 160 10 18 20
Resonance Studies
13 REFERENCES