23IN01 IGN REP WR 022.00 (Weekly Construction Report 230710 230716)
23IN01 IGN REP WR 022.00 (Weekly Construction Report 230710 230716)
00 Rev:
Submitted : _______________________________
Checked : _______________________________
Approved : _______________________________
TABLE OF CONTENTS
1 MILESTONES COMPLETED
• 100% bored pile construction is finished at Data Hall and Admin Building.
• 100% spun pile installation is finished in all areas.
• DC Building: already finished casting concrete of pile cap and tie beam, in the process of
backfilling and rectifying defect list.
• Admin Building: already finished casting concrete of pile cap and tie beam, in the process
of backfilling and rectifying defect list.
• MUW Tank: already finished casting concrete of raft foundation, in the process of
removing the formwork.
• Fire & Raw Water Tank, Fire & Domestic Pump Room, MUW Treatment Room, Bin
Center, and Guard House: already finished casting concrete for pile cap, in the process of
removing the formwork.
2 KEY EVENTS SUMMARY FOR THIS WEEK
• Pile cap construction at DC Block, Admin Building, MUW Tank, Fire and Raw Water Tank,
Fire & Raw Water Tank, and Guard House. Already finished casting concrete of pile cap
and tie beam in all area scope of Geotekindo.
• Earthing system installation.
• Rectification work for pile cap and tie beam in DC Block and Admin Block.
• Pile testing for spun pile diameter of 300 mm at Guard House.
• Pile cap works QC: work inspection (rebar, formwork, casting concrete), concrete
compressive strength test, and rebar tensile test.
Total bored pile 448 448 448 1-Mar-23 4-May-23 4-May-23 1.7 100.00% 100.00% 0.00% Bore Pile
Total spun pile 819 819 819 30-Mar-23 5-Jun-23 17-Jun-23 3.5 100.00% 100.00% 0.00% Spun Pile
TOTAL 1267 1267 1267 1-Mar-23 5-Jun-23 17-Jun-23 3.0 100.00% 100.00% 0.00%
Ignite Data Center Project Construction Weekly Report
• Housekeeping to keep the work area and road safe and clean.
Activities: Rebar installation DC Building A9 Activities: Rebar installation Fire Dom. Pump
Date: 11.07.2023 PIC: KSI Date: 11.07.2023 PIC: KSY
Activities: Tie rod cutting tie beam DC Activities: Concrete surface finishing DC
Date: 12.07.2023 PIC: DS Date: 12.07.2023 PIC: DS
Activities: Earthing inspection by Aurecon Activities: As wall and column checking MUW
Date: 13.07.2023 PIC: AH Date: 13.07.2023 PIC: AH
Activities: PHT installation MUW Treatment Activities: Formwork installation Fire Dom.
Date: 13.07.2023 PIC: KSY Date: 13.07.2023 PIC: KSY
Ignite Data Center Project Construction Weekly Report
Activities: Sagging beam in Admin rectification Activities: Formwork installation Bin Center
Date: 14.07.2023 PIC: AF Date: 14.07.2023 PIC: KSY
Activities: Formwork installation MUW Treat. Activities: Formwork installation Fire Dom.
Date: 14.07.2023 PIC: KSY Date: 14.07.2023 PIC: KSY
Activities: Rebar installation MUW Treatment Activities: Formwork installation MUW Treat.
Date: 15.07.2023 PIC: AH Date: 15.07.2023 PIC: KSI
Activities: BC conductor for earthing works Activities: Rebar installation Fire Dom. Pump
Date: 15.07.2023 PIC: KSY Date: 15.07.2023 PIC: KSI
Activities: Rebar installation MUW Treatment Activities: Formwork installation MUW Treat.
Date: 16.07.2023 PIC: KSY Date: 16.07.2023 PIC: KSY
Ignite Data Center Project Construction Weekly Report
4 ATTACHMENTS
2 Pilecap & Tiebeam Design 100% 72 days Wed 1/3/23 Tue 9/5/23 Wed 1/3/23 Tue 9/5/23 9/5
Approval
3 Pile Cap Area 1, 2, 3 100% 39.35 days Tue 9/5/23 Mon 5/6/23 Tue 9/5/23 Fri 16/6/23
4 Excavation for Pilecap & 100% 2 12 days Tue 9/5/23 Sun 21/5/23 Tue 9/5/23 Sat 10/6/23 9/5 12 days 10/6
Tiebeam
5 Cut Off Pile Head & Rectify 100% 4SS+1 day 12 days Thu 11/5/23 Mon 22/5/23 Thu 11/5/23 Sat 10/6/23 11/5 12 days 10/6
6 Cushion of Pilecap 100% 5SS+2 days 12 days Sat 13/5/23 Wed 24/5/23 Sat 13/5/23 Tue 13/6/23 13/5 12 days 13/6
7 Rebar Installation 100% 6SS+3 days 10.89 days Mon 15/5/23 Sat 27/5/23 Mon 15/5/23 Wed 14/6/23 15/5 10.89 days 14/6
8 Formwork Installation 100% 7SS+2 days 9.69 days Wed 17/5/23 Mon 29/5/23 Wed 17/5/23 Fri 16/6/23 17/5 9.69 days 16/6
9 Cast Concrete 100% 8SS+1 day 12 days Thu 18/5/23 Tue 30/5/23 Thu 18/5/23 Fri 16/6/23 18/5 12 days 16/6
10 Remove Formwork & 100% 9SS+1 day 12 days Mon 22/5/23 Mon 5/6/23 Thu 25/5/23 Fri 16/6/23 25/5 12 days 16/6
Backfilling
11 Pile Cap Area 6, 7 100% 39.8 days Wed 17/5/23 Fri 9/6/23 Wed 17/5/23 Sat 24/6/23
12 Excavation for Pilecap & 100% 12 days Wed 17/5/23 Fri 26/5/23 Wed 17/5/23 Mon 12/6/23 17/5 12 days 12/6
Tiebeam
13 Cut Off Pile Head & Rectify 100% 12SS+1 day 12 days Thu 18/5/23 Sat 27/5/23 Mon 22/5/23 Mon 12/6/23 22/5 12 days 12/6
14 Cushion of Pilecap 100% 13SS+2 days 9 days Sat 20/5/23 Mon 29/5/23 Fri 26/5/23 Fri 16/6/23 26/5 9 days 16/6
15 Rebar Installation 100% 14SS+3 days 9 days Mon 22/5/23 Thu 1/6/23 Mon 29/5/23 Wed 21/6/23 29/5 9 days 21/6
16 Formwork Installation 100% 15SS+2 days 9 days Wed 24/5/23 Sat 3/6/23 Sat 3/6/23 Fri 23/6/23 3/6 9 days 23/6
17 Cast Concrete 100% 16SS+1 day 7 days Thu 25/5/23 Sun 4/6/23 Sat 3/6/23 Fri 23/6/23 3/6 7 days 23/6
18 Remove Formwork & 100% 17SS+1 day 10 days Sat 27/5/23 Fri 9/6/23 Sun 4/6/23 Sat 24/6/23 4/6 10 days 24/6
Backfilling
19 Pile Cap Area 4, 5 100% 37.92 days Fri 19/5/23 Sun 11/6/23 Mon 22/5/23 Tue 27/6/23
20 Excavation for Pilecap & 100% 10 days Fri 19/5/23 Sun 28/5/23 Mon 22/5/23 Sat 10/6/23 22/5 10 days 10/6
Tiebeam
21 Cut Off Pile Head & Rectify 100% 20SS+1 day 10 days Sat 20/5/23 Tue 30/5/23 Wed 24/5/23 Sun 11/6/23 24/5 10 days 11/6
22 Cushion of Pilecap 100% 21SS+2 days 9 days Mon 22/5/23 Thu 1/6/23 Mon 29/5/23 Wed 14/6/23 29/5 9 days 14/6
23 Rebar Installation 100% 22SS+2 days 10 days Wed 24/5/23 Sat 3/6/23 Wed 31/5/23 Tue 20/6/23 31/5 10 days 20/6
24 Formwork Installation 100% 23SS+2 days 10 days Fri 26/5/23 Mon 5/6/23 Sat 3/6/23 Fri 23/6/23 3/6 10 days 23/6
25 Cast Concrete 100% 24SS+1 day 10 days Sat 27/5/23 Tue 6/6/23 Sat 3/6/23 Mon 26/6/23 3/6 10 days 26/6
26 Remove Formwork & 100% 25SS+1 day 10 days Mon 29/5/23 Sun 11/6/23 Mon 5/6/23 Tue 27/6/23 5/6 10 days 27/6
Backfilling
27 Pile Cap Area 8, 9 97% 54.15 days Sun 28/5/23 Wed 14/6/23 Sun 28/5/23 Wed 19/7/23
28 Excavation for Pilecap & 100% 12 days Sun 28/5/23 Wed 7/6/23 Sun 28/5/23 Sun 2/7/23 28/5 12 days 2/7
Tiebeam
29 Cut Off Pile Head & Rectify 100% 28SS+1 day 12 days Mon 29/5/23 Thu 8/6/23 Mon 29/5/23 Sat 8/7/23 29/5 12 days 8/7
30 Cushion of Pilecap 100% 29SS+1 day 10 days Wed 31/5/23 Sat 10/6/23 Wed 14/6/23 Sat 8/7/23 14/6 10 days 8/7
31 Rebar Installation 100% 30SS+1 day 9 days Fri 2/6/23 Sun 11/6/23 Fri 16/6/23 Mon 10/7/23 16/6 9 days 10/7
32 Formwork Installation 100% 31SS+1 day 8 days Sun 4/6/23 Tue 13/6/23 Sat 17/6/23 Mon 10/7/23 17/6 8 days 10/7
33 Cast Concrete 100% 32SS+1 day 8 days Mon 5/6/23 Wed 14/6/23 Tue 20/6/23 Mon 10/7/23 20/6 8 days 10/7
34 Remove Formwork & 80% 33SS+1 day 11.37 days Wed 7/6/23 Mon 19/6/23 Thu 22/6/23 Wed 19/7/23 22/6 11.37 days 19/7
Backfilling
35 Handover 0% 1 day Thu 15/6/23 Thu 15/6/23 Wed 19/7/23 Thu 20/7/23
36 Handover 0% 33FS-1 1 day Thu 15/6/23 Thu 15/6/23 Wed 19/7/23 Thu 20/7/23 19/7 1 day
20/7
day,10,18,26,34
Page 1
ID 任务名称 % Complete Duration Baseline Start Baseline Finish Start Finish 7 May '23 14 May '23 21 May '23 28 May '23 4 Jun '23 11 Jun '23 18 Jun '23 25 Jun '23 2 Jul '23 9 Jul '23 16 Jul '23 23 Jul '23
8 9 10111213141516171819202122232425262728293031 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930 1 2 3 4 5 6 7 8 9 1011121314151617181920212223
1 Pile Cap Construction at Admin 99% 145.75 days Wed 1/3/23 Thu 22/6/23 Wed 1/3/23 Wed 19/7/23
2 Pilecap & Tiebeam Design 100% 79 days Wed 1/3/23 Tue 16/5/23 Wed 1/3/23 Tue 16/5/23 16/5
Approval
3 Pile Cap Area 1 100% 43.05 days Tue 16/5/23 Thu 15/6/23 Tue 16/5/23 Mon 26/6/23
4 Excavation for Pilecap & 100% 5.2 days Tue 16/5/23 Sat 27/5/23 Tue 16/5/23 Thu 25/5/23 16/5 5.2 days 25/5
Tiebeam
5 Cut Off Pile Head & Rectify 100% 12 days Thu 18/5/23 Mon 29/5/23 Sat 20/5/23 Fri 2/6/23 20/5 12 days 2/6
6 Cushion of Pilecap 100% 12 days Sat 20/5/23 Wed 31/5/23 Thu 25/5/23 Thu 8/6/23 25/5 12 days 8/6
7 Rebar Installation 100% 12 days Tue 23/5/23 Sat 3/6/23 Mon 29/5/23 Tue 13/6/23 29/5 12 days 13/6
8 Formwork Installation 100% 12 days Fri 26/5/23 Tue 6/6/23 Sat 3/6/23 Sat 24/6/23 3/6 12 days 24/6
9 Cast Concrete 100% 10 days Sun 28/5/23 Fri 9/6/23 Mon 5/6/23 Mon 26/6/23 5/6 10 days 26/6
10 Remove Formwork & 100% 8 days Wed 31/5/23 Thu 15/6/23 Thu 8/6/23 Mon 26/6/23 8/6 8 days 26/6
Backfilling
11 Pile Cap Area 2 98% 54.75 days Tue 23/5/23 Wed 21/6/23 Sat 27/5/23 Tue 18/7/23
12 Excavation for Pilecap & 100% 14 days Tue 23/5/23 Tue 6/6/23 Sat 27/5/23 Sat 24/6/23 27/5 14 days 24/6
Tiebeam
13 Cut Off Pile Head & Rectify 100% 14 days Fri 26/5/23 Fri 9/6/23 Sat 27/5/23 Sat 24/6/23 27/5 14 days 24/6
14 Cushion of Pilecap 100% 13 days Sat 27/5/23 Sun 11/6/23 Tue 30/5/23 Sun 25/6/23 30/5 13 days 25/6
15 Rebar Installation 100% 13 days Tue 30/5/23 Wed 14/6/23 Mon 12/6/23 Tue 27/6/23 12/6 13 days 27/6
16 Formwork Installation 100% 11 days Fri 2/6/23 Sat 17/6/23 Wed 14/6/23 Sat 8/7/23 14/6 11 days 8/7
17 Cast Concrete 100% 5 days Sun 4/6/23 Sun 18/6/23 Wed 21/6/23 Sat 8/7/23 21/6 5 days 8/7
18 Remove Formwork & 80% 8.75 days Wed 7/6/23 Wed 21/6/23 Fri 23/6/23 Tue 18/7/23 23/6 8.75 days 18/7
Backfilling
19 Handover 0% 1 day Thu 22/6/23 Thu 22/6/23 Tue 18/7/23 Wed 19/7/23
20 Handover 0% 1 day Thu 22/6/23 Thu 22/6/23 Tue 18/7/23 Wed 19/7/23 18/7 1 day
19/7
Page 1
ID 任务名称 % Complete Duration Baseline Start Baseline Finish Start Finish 21 May '23 28 May '23 4 Jun '23 11 Jun '23 18 Jun '23 25 Jun '23 2 Jul '23 9 Jul '23 16 Jul '23
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 Pile Cap Construction at MUW 99% 130.46 days Wed 15/3/23 Fri 30/6/23 Wed 15/3/23 Tue 18/7/23
Tank
2 Spun Pile D600 Production 100% 64 days Wed 15/3/23 Mon 15/5/23 Wed 15/3/23 Mon 15/5/23
Spun pile production will be finished until 15th May.
3 Spun Pile D600 Installation 100% 66 days Sun 2/4/23 Sun 4/6/23 Sun 2/4/23 Sun 4/6/23 4/6
4 Cut Off Pile Head & Install Rebar 100% 35 days Sun 7/5/23 Fri 9/6/23 Sun 7/5/23 Fri 23/6/23 23/6
Cage
5 Pile Cap Area 1 100% 23 days Mon 29/5/23 Fri 9/6/23 Sat 27/5/23 Sun 18/6/23
6 Cushion of Pilecap 100% 3 days Mon 29/5/23 Wed 31/5/23 Sat 27/5/23 Mon 29/5/23 27/5 3 days29/5
7 Rebar Installation 100% 2 days Mon 5/6/23 Mon 5/6/23 Wed 7/6/23 Sat 10/6/23 7/6 2 days 10/6
8 Formwork Installation 100% 3 days Mon 5/6/23 Wed 7/6/23 Sat 10/6/23 Mon 12/6/23 10/6 3 days12/6
9 Cast Concrete 100% 1 day Thu 8/6/23 Thu 8/6/23 Mon 12/6/23 Fri 16/6/23 12/6 1 day 16/6
10 Remove Formwork 100% 2 days Fri 9/6/23 Fri 9/6/23 Fri 16/6/23 Sun 18/6/23 16/6 2 days
18/6
11 Pile Cap Area 2 100% 27.5 days Thu 1/6/23 Sat 17/6/23 Mon 29/5/23 Sun 25/6/23
12 Cushion of Pilecap 100% 3 days Thu 1/6/23 Sat 3/6/23 Mon 29/5/23 Fri 2/6/23 29/5 3 days 2/6
13 Rebar Installation 100% 3 days Thu 8/6/23 Mon 12/6/23 Sat 17/6/23 Tue 20/6/23 17/6 3 days 20/6
14 Formwork Installation 100% 1 day Sun 11/6/23 Wed 14/6/23 Wed 21/6/23 Thu 22/6/23 21/6 1 day
22/6
15 Cast Concrete 100% 1 day Wed 14/6/23 Thu 15/6/23 Thu 22/6/23 Fri 23/6/23 22/6 1 day
23/6
16 Remove Formwork & 100% 1 day Fri 16/6/23 Sat 17/6/23 Sat 24/6/23 Sun 25/6/23 24/6 1 day
25/6
Backfilling
17 Pile Cap Area 4 100% 26.38 days Sat 3/6/23 Sat 24/6/23 Sat 10/6/23 Wed 5/7/23
18 Cushion of Pilecap 100% 3 days Sat 10/6/23 Tue 6/6/23 Sat 10/6/23 Mon 12/6/23 10/6 3 days12/6
19 Rebar Installation 100% 6 days Wed 14/6/23 Mon 19/6/23 Sun 11/6/23 Tue 27/6/23 11/6 6 days 27/6
20 Formwork Installation 100% 4 days Sat 17/6/23 Wed 21/6/23 Wed 14/6/23 Mon 26/6/23 14/6 4 days 26/6
21 Cast Concrete 100% 1 day Wed 21/6/23 Thu 22/6/23 Mon 26/6/23 Sun 2/7/23 26/6 1 day 2/7
22 Remove Formwork 100% 2 days Fri 23/6/23 Sat 24/6/23 Mon 3/7/23 Wed 5/7/23 3/7 2 days
5/7
23 Pile Cap Area 3 94% 36.46 days Tue 6/6/23 Thu 29/6/23 Mon 12/6/23 Mon 17/7/23
24 Cushion of Pilecap 100% 3 days Tue 6/6/23 Fri 9/6/23 Mon 12/6/23 Thu 15/6/23 12/6 3 days 15/6
25 Rebar Installation 100% 4 days Wed 21/6/23 Mon 26/6/23 Tue 20/6/23 Sat 8/7/23 20/6 4 days 8/7
26 Formwork Installation 100% 3 days Sat 24/6/23 Tue 27/6/23 Fri 23/6/23 Sat 8/7/23 23/6 3 days 8/7
27 Cast Concrete 100% 1 day Tue 27/6/23 Wed 28/6/23 Sat 8/7/23 Sun 9/7/23 8/7 1 day
9/7
28 Remove Formwork 80% 4.8 days Wed 28/6/23 Thu 29/6/23 Sun 9/7/23 Mon 17/7/23 9/7 4.8 days 17/7
29 Handover 0% 1 day Thu 29/6/23 Fri 30/6/23 Mon 17/7/23 Tue 18/7/23
30 Handover 0% 1 day Thu 29/6/23 Fri 30/6/23 Mon 17/7/23 Tue 18/7/23 17/7 1 day
18/7
Page 1
ID Task Name % Complete Duration Baseline Start Baseline Finish Start Start Finish Predecessors June 2023 July 2023
28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27
1 Pile Cap Construction at Fire 84% 48.7 days Fri 2/6/23 Fri 30/6/23 Fri 2/6/23 Fri 2/6/23 Thu 20/7/23 2/6 48.7 days 20/7
and Raw Water Tank
2 Cut-off Pile Head & Install 100% 14 days Fri 2/6/23 Thu 15/6/23 Fri 2/6/23 Fri 2/6/23 Thu 15/6/23 2/6 14 days 15/6
Rebar Cage
3 Pile Cap Area 1 78% 20.7 days Fri 16/6/23 Fri 23/6/23 Thu 29/6/23 Thu 29/6/23 Wed 19/7/23 29/6 20.7 days 19/7
4 Cushion of Pile Cap 100% 1 day Fri 16/6/23 Sun 18/6/23 Thu 29/6/23 Thu 29/6/23 Thu 29/6/23 2 29/6 1 29/6
day
5 Rebar Installation 100% 4 days Sun 18/6/23 Tue 20/6/23 Sat 1/7/23 Sat 1/7/23 Tue 4/7/23 4SS+2 days 1/7 4 days4/7
6 Formwork Installation 100% 3 days Tue 20/6/23 Wed 21/6/23 Thu 6/7/23 Thu 6/7/23 Sat 8/7/23 5SS+2 days 6/7 3 days
8/7
7 Cast Concrete 100% 1 day Thu 22/6/23 Thu 22/6/23 Sun 9/7/23 Sun 9/7/23 Sun 9/7/23 6 9/7 1 9/7
day
8 Remove Formwork 10% 3 days Fri 23/6/23 Fri 23/6/23 Tue 11/7/23 Tue 11/7/23 Wed 19/7/23 7 11/7 3 days 19/7
9 Pile Cap Area 2 78% 20.7 days Sat 24/6/23 Thu 29/6/23 Thu 29/6/23 Thu 29/6/23 Wed 19/7/23 29/6 20.7 days 19/7
10 Cushion of Pile Cap 100% 1 day Sat 24/6/23 Sun 25/6/23 Thu 29/6/23 Thu 29/6/23 Thu 29/6/23 8 29/6 1 29/6
day
11 Rebar Installation 100% 4 days Mon 26/6/23 Tue 27/6/23 Sat 1/7/23 Sat 1/7/23 Tue 4/7/23 10SS+2 days 1/7 4 days4/7
12 Formwork Installation 100% 3 days Tue 27/6/23 Tue 27/6/23 Thu 6/7/23 Thu 6/7/23 Sat 8/7/23 11SS+1 day 6/7 3 days
8/7
13 Cast Concrete 100% 1 day Wed 28/6/23 Wed 28/6/23 Sun 9/7/23 Sun 9/7/23 Sun 9/7/23 12 9/7 1 9/7
day
14 Remove Formwork 10% 3 days Thu 29/6/23 Thu 29/6/23 Tue 11/7/23 Tue 11/7/23 Wed 19/7/23 13 11/7 3 days 19/7
15 Handover 0% 1 day Fri 30/6/23 Fri 30/6/23 Wed 19/7/23 Wed 19/7/23 Thu 20/7/23 19/7 1 day
20/7
16 Handover 0% 1 day Fri 30/6/23 Fri 30/6/23 Wed 19/7/23 Wed 19/7/23 Thu 20/7/23 14 19/7 1 20/7
day
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 1
ID Task Name % Complete Duration Baseline Start Baseline Finish Start Finish Predecessors July 2023
8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23
1 Pile Cap Constrcution Schedule at 69% 35 days Fri 16/6/23 Wed 28/6/23 Fri 16/6/23 Thu 20/7/23
Fire and Domestic Pump Room,
MUW Treatment Room, and Bin
Center
2 Pile Cap Constrcution at Fire 74% 33.85 days Fri 16/6/23 Fri 23/6/23 Fri 16/6/23 Wed 19/7/23
and Domestic Pump Room
3 Excavation for Pilecap 100% 1 day Fri 16/6/23 Fri 16/6/23 Fri 16/6/23 Fri 16/6/23 16/6 1 day
16/6
4 Cut Off Pile Head & Install 100% 2 days Sat 17/6/23 Sun 18/6/23 Mon 26/6/23 Tue 27/6/23 3 26/6 2 days27/6
Rebar Cage
5 Cushion of Pilecap 100% 1 day Sun 18/6/23 Sun 18/6/23 Wed 28/6/23 Wed 28/6/23 4SS+1 day 28/6 1 day
28/6
6 Rebar Installation 100% 3 days Mon 19/6/23 Wed 21/6/23 Tue 11/7/23 Thu 13/7/23 5 11/7 3 days 13/7
7 Cast Concrete 100% 1 day Thu 22/6/23 Thu 22/6/23 Fri 14/7/23 Fri 14/7/23 6 14/7 1 day
14/7
8 Remove Formwork 5% 3 days Fri 23/6/23 Fri 23/6/23 Sat 15/7/23 Wed 19/7/23 7 15/7 3 days 19/7
9 Pile Cap Constrcution at MUW 63% 33 days Sat 17/6/23 Mon 26/6/23 Sat 17/6/23 Wed 19/7/23
Treatment Room
10 Excavation for Pilecap 100% 1 day Sat 17/6/23 Sat 17/6/23 Sat 17/6/23 Sat 17/6/23 3 17/6 1 day
17/6
11 Cut Off Pile Head & Install 100% 2 days Mon 19/6/23 Tue 20/6/23 Mon 26/6/23 Tue 27/6/23 10,4 26/6 2 days27/6
Rebar Cage
12 Cushion of Pilecap 100% 1 day Wed 21/6/23 Wed 21/6/23 Wed 28/6/23 Wed 28/6/23 11 28/6 1 day
28/6
13 Rebar Installation 100% 0 days Thu 22/6/23 Sat 24/6/23 Sat 15/7/23 Sat 15/7/23 12 15/7
14 Cast Concrete 100% 1 day Sun 25/6/23 Sun 25/6/23 Sun 16/7/23 Sun 16/7/23 13 16/7 1 day
16/7
15 Remove Formwork & 0% 3 days Mon 26/6/23 Mon 26/6/23 Mon 17/7/23 Wed 19/7/23 14 17/7 3 days 19/7
Backfilling
16 Pile Cap Constrcution at Bin 74% 32 days Sun 18/6/23 Tue 27/6/23 Sun 18/6/23 Wed 19/7/23
Center
17 Excavation for Pilecap 100% 1 day Sun 18/6/23 Sun 18/6/23 Sun 18/6/23 Sun 18/6/23 10 18/6 1 day
18/6
18 Cut Off Pile Head & Install 100% 2 days Wed 21/6/23 Thu 22/6/23 Mon 26/6/23 Tue 27/6/23 17,11 26/6 2 days27/6
Rebar Cage
19 Cushion of Pilecap 100% 1 day Fri 23/6/23 Fri 23/6/23 Wed 28/6/23 Wed 28/6/23 18 28/6 1 day
28/6
20 Rebar Installation 100% 3 days Sat 24/6/23 Sun 25/6/23 Tue 11/7/23 Thu 13/7/23 19 11/7 3 days 13/7
21 Cast Concrete 100% 1 day Mon 26/6/23 Mon 26/6/23 Fri 14/7/23 Fri 14/7/23 20 14/7 1 day
14/7
22 Remove Formwork 5% 3 days Tue 27/6/23 Tue 27/6/23 Mon 17/7/23 Wed 19/7/23 21 17/7 3 days 19/7
23 Handover 0% 1 day Wed 28/6/23 Wed 28/6/23 Thu 20/7/23 Thu 20/7/23
24 Handover 0% 1 day Wed 28/6/23 Wed 28/6/23 Thu 20/7/23 Thu 20/7/23 22 20/7 1 day
20/7
Project: 5. MUW Treatment Roo Split Inactive Task Duration-only Finish-only Critical
Date: Mon 17/7/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split
Page 1
ID Task Task Name % Complete Duration Baseline Start Baseline Finish Start Finish 25 Jun '23 2 Jul '23 9 Jul '23 16 Jul '23 23 Jul '23
Mode T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 Pile Cap 70% 17.85 days Fri 23/6/23 Fri 30/6/23 Mon 3/7/23 Thu 20/7/23 3/7 17.85 days 20/7
Construction at
2 Guardhouse
Excavation for 100% 1 day Fri 23/6/23 Fri 23/6/23 Mon 3/7/23 Mon 3/7/23 3/7 1 day
3/7
Pilecap &
3 Tiebeam
Cut Off Pile Head 100% 2 days Sat 24/6/23 Sun 25/6/23 Tue 4/7/23 Wed 5/7/23 4/7 2 days 5/7
& Rectify
4 Cushion of Pilecap 100% 1 day Sun 25/6/23 Mon 26/6/23 Thu 6/7/23 Thu 6/7/23 6/7 1 day
6/7
5 Rebar Installation 100% 4 days Mon 26/6/23 Tue 27/6/23 Fri 7/7/23 Tue 11/7/23 7/7 4 days 11/7
6 Cast Concrete 100% 1 day Wed 28/6/23 Wed 28/6/23 Tue 11/7/23 Wed 12/7/23 11/7 1 day
12/7
7 Removing 5% 3 days Thu 29/6/23 Thu 29/6/23 Thu 13/7/23 Wed 19/7/23 13/7 3 days 19/7
Formwork
8 Handover 0% 1 day Fri 30/6/23 Fri 30/6/23 Wed 19/7/23 Thu 20/7/23 19/7 1 day
20/7
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 1
GENERAL NOTES
4
3
2
1
NO REVISION /ISSUE DATE
KEY PLAN
F1 F2 F3
10525 11525 SITE BOUNDARY
32.40
32.20
32.20
32.20
32.10
32.10
32.30
32.90
32.70
33.00
32.20
11000
32.50
31.90
BCL 32.350 32.80
32.60
U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL
TANKS TANKS TANKS TANKS TANKS TANKS
SECONDARY ENTRANCE
5775
FGL 32.430
FGL 32.430
FGL 33.100
FUTURE DEVELOPMENT AREA
DATA HALL
33.00
32.80
FGL +33.10
32.90
33.10
32.70
32.90
32.80
32.6
32.5
32.4
0
0
32.30
BCL 32.350
BCL 32.350
TOPC : +32.500
32.20
32.7
32.20
0
Green Zone Area
32.20
9000
10000
BLOCK EE/2
EXTERNAL ROAD
1.3
1.4 FGL 32.430
10000
10000
BCL 32.350 BCL 32.350 BCL 32.350
4.1 4.2
2.1 PL +32.75 FGL 32.430 2.2
3.1 FGL 32.430 3.2
SATELLITE ZONE
FGL 33.100 FGL 33.100
1200 1200
FGL 32.700
FGL 32.430
ADMIN BLOCK
GUARD HOUSE /
ARM BARRIER
FGL +32.05 3.4
FCC
12000 3.3
2.4 7.1 7.2 2.3
5.1 5.2 4.4 4.3
BCL 32.330
8000
CENTRE
PLN SUBSTATION BCL 32.350
BIN
6.4 6.3
F8-1
9.4 3.5
7.4 7.3 5.4 5.3
6000
4500
FGL 32.700
10000
BCL 32.350
6800
FGL 32.700 BCL 32.350 BCL 32.350 FGL 32.700
F5-1
8000
F5-3
FGL 32.700
FGL 32.700 FGL 32.700
FA
4525
fB1
IGNITE DATA CENTRE
fB1
fB1
F9
F6-1 F6-2
fB1 fB1
INFRASTRUCTURE
fC1
FINISHED LEAN CONCRETE
9050
fC1 fC1
4525
fB1
fB1
fB1
FIRE AND DOMESTIC PUMP
F8-2 ROOMS LEAN CONCRETE
F5-2 F5-4
fB1 fB1
FB fC1
fC1
fC1
CONTRACTOR
OWNER
DRAWING NO
PAGE 1
GENERAL NOTES
4
3
2
1
NO REVISION /ISSUE DATE
KEY PLAN
F1 F2 F3
10525 11525 SITE BOUNDARY
32.40
32.20
32.20
32.20
32.10
32.10
32.30
32.90
32.70
33.00
32.20
11000
32.50
31.90
BCL 32.350 32.80
32.60
U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL
TANKS TANKS TANKS TANKS TANKS TANKS
SECONDARY ENTRANCE
5775
FGL 32.430
FGL 32.430
FGL 33.100
FUTURE DEVELOPMENT AREA
DATA HALL
33.00
32.80
FGL +33.10
32.90
33.10
32.70
32.90
32.80
32.6
32.5
32.4
0
0
32.30
BCL 32.350
BCL 32.350
TOPC : +32.500
32.20
32.7
32.20
0
Green Zone Area
32.20
9000
10000
BLOCK EE/2
EXTERNAL ROAD
1.3
1.4 FGL 32.430
10000
10000
BCL 32.350 BCL 32.350 BCL 32.350
4.1 4.2
2.1 PL +32.75 FGL 32.430 2.2
3.1 FGL 32.430 3.2
SATELLITE ZONE
FGL 33.100 FGL 33.100
1200 1200
FGL 32.700
FGL 32.430
ADMIN BLOCK
GUARD HOUSE /
ARM BARRIER
FGL +32.05 3.4
FCC
12000 3.3
2.4 7.1 7.2 2.3
5.1 5.2 4.4 4.3
BCL 32.330
8000
CENTRE
PLN SUBSTATION BCL 32.350
BIN
6.4 6.3
F8-1
9.4 3.5
7.4 7.3 5.4 5.3
6000
4500
FGL 32.700
10000
BCL 32.350
6800
FGL 32.700 BCL 32.350 BCL 32.350 FGL 32.700
F5-1
8000
F5-3
FGL 32.700
FGL 32.700 FGL 32.700
FA
fB1
IGNITE DATA CENTRE
fB1
fB1
F9
F6-1 F6-2
fB1 fB1
INFRASTRUCTURE
fC1
INSTALL REBAR
9050
fC1 fC1
4525
fB1
fB1
fB1
FIRE AND DOMESTIC PUMP
F8-2 ROOMS INSTALL REBAR
F5-2 F5-4
fB1 fB1
FB fC1
fC1
fC1
CONTRACTOR
OWNER
DRAWING NO
PAGE 1
GENERAL NOTES
4
3
2
1
NO REVISION /ISSUE DATE
KEY PLAN
F1 F2 F3
10525 11525 SITE BOUNDARY
32.40
32.20
32.20
32.20
32.10
32.10
32.30
32.90
32.70
33.00
32.20
11000
32.50
31.90
BCL 32.350 32.80
32.60
U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL
TANKS TANKS TANKS TANKS TANKS TANKS
SECONDARY ENTRANCE
5775
FGL 32.430
FGL 32.430
FGL 33.100
FUTURE DEVELOPMENT AREA
DATA HALL
33.00
32.80
FGL +33.10
32.90
33.10
32.70
32.90
32.80
32.6
32.5
32.4
0
0
32.30
BCL 32.350
BCL 32.350
TOPC : +32.500
32.20
32.7
32.20
0
Green Zone Area
32.20
9000
10000
BLOCK EE/2
EXTERNAL ROAD
1.3
1.4 FGL 32.430
10000
10000
BCL 32.350 BCL 32.350 BCL 32.350
4.1 4.2
2.1 PL +32.75 FGL 32.430 2.2
3.1 FGL 32.430 3.2
SATELLITE ZONE
FGL 33.100 FGL 33.100
1200 1200
FGL 32.700
FGL 32.430
ADMIN BLOCK
GUARD HOUSE /
ARM BARRIER
FGL +32.05 3.4
FCC
12000 3.3
2.4 7.1 7.2 2.3
5.1 5.2 4.4 4.3
BCL 32.330
8000
CENTRE
PLN SUBSTATION BCL 32.350
BIN
6.4 6.3
F8-1
9.4 3.5
7.4 7.3 5.4 5.3
6000
4500
FGL 32.700
10000
BCL 32.350
6800
FGL 32.700 BCL 32.350 BCL 32.350 FGL 32.700
F5-1
8000
F5-3
FGL 32.700
FGL 32.700 FGL 32.700
FA
fB1
IGNITE DATA CENTRE
fB1
fB1
F9
F6-1 F6-2
fB1 fB1
INFRASTRUCTURE
fC1
FINISHED POURING CONCRETE
9050
fC1 fC1
4525
fB1
fB1
fB1
FIRE AND DOMESTIC PUMP
F8-2 ROOMS INSTALL REBAR
F5-2 F5-4
fB1 fB1
FB fC1
fC1
fC1
CONTRACTOR
OWNER
DRAWING NO
PAGE 1
GENERAL NOTES
P1 P2
7100 4
3
TOPC : +32.500 2
1
F5-T1 NO REVISION /ISSUE DATE
tC1
F3-T1 tB3 tC1 KEY PLAN
PA
SITE BOUNDARY
32.40
32.20
32.20
32.20
32.10
32.10
32.30
32.90
32.70
33.00
32.20
11000
32.50
31.90
BCL 32.350 32.80
32.60
U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL
TANKS TANKS TANKS TANKS TANKS TANKS
SECONDARY ENTRANCE
5713
tB1
tB1
FGL 32.430
FGL 32.430
FGL 33.100
FUTURE DEVELOPMENT AREA
DATA HALL
33.00
32.80
FGL +33.10
32.90
33.10
32.70
32.90
32.80
32.6
32.5
32.4
0
0
32.30
BCL 32.350
BCL 32.350
32.20
32.7
32.20
0
Green Zone Area
32.20
9000
10000
BLOCK EE/2
F6-T1
EXTERNAL ROAD
1.3
1.4 FGL 32.430
10000
10000
BCL 32.350 BCL 32.350 BCL 32.350
4.1 4.2
2.1 PL +32.75 FGL 32.430 2.2
3.1 FGL 32.430 3.2
SATELLITE ZONE
FGL 33.100 FGL 33.100
FGL 32.700
FGL 32.430
ADMIN BLOCK
GUARD HOUSE /
ARM BARRIER
FGL +32.05 3.4
FCC
12000 3.3
2.4 7.1 7.2 2.3
5.1 5.2 4.4 4.3
BCL 32.330
8000
CENTRE
PLN SUBSTATION BCL 32.350
BIN
6.4 6.3 3.5
9.4
7.4 7.3 5.4 5.3
6000
4500
FGL 32.700
10000
BCL 32.350
6800
FGL 32.700 BCL 32.350 BCL 32.350 FGL 32.700
8000
FGL 32.700
FGL 32.700 FGL 32.700
11500
PLN ENTRANCE PRIMARY ENTRANCE EXTERNAL ROAD
5788
tB1
tB1
IGNITE DATA CENTRE
F6-T2
F4-T2 INFRASTRUCTURE
FINISHED LEAN CONCRETE
tC1 tB2 tC1
PB
MAPPING PROGRESS
MUW TREATMENT ROOM
5838
tB1
tB1
F6-T3
F4-T3 CONTRACTOR
tC1 tB2 tC1
11600
5763
tB1
tB1
DRAFTED RAYHAN T. H.
F5-T2
APPROVED WEI PING
F3-T2 tB3
tC1 tC1
PC
OWNER
DRAWING NO
PAGE 1
GENERAL NOTES
P1 P2
7100 4
3
TOPC : +32.500 2
1
F5-T1 NO REVISION /ISSUE DATE
tC1
F3-T1 tB3 tC1 KEY PLAN
PA
SITE BOUNDARY
32.40
32.20
32.20
32.20
32.10
32.10
32.30
32.90
32.70
33.00
32.20
11000
32.50
31.90
BCL 32.350 32.80
32.60
U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL
TANKS TANKS TANKS TANKS TANKS TANKS
SECONDARY ENTRANCE
5713
tB1
tB1
FGL 32.430
FGL 32.430
FGL 33.100
FUTURE DEVELOPMENT AREA
DATA HALL
33.00
32.80
FGL +33.10
32.90
33.10
32.70
32.90
32.80
32.6
32.5
32.4
0
0
32.30
BCL 32.350
BCL 32.350
32.20
32.7
32.20
0
Green Zone Area
32.20
9000
10000
BLOCK EE/2
F6-T1
EXTERNAL ROAD
1.3
1.4 FGL 32.430
10000
10000
BCL 32.350 BCL 32.350 BCL 32.350
4.1 4.2
2.1 PL +32.75 FGL 32.430 2.2
3.1 FGL 32.430 3.2
SATELLITE ZONE
FGL 33.100 FGL 33.100
FGL 32.700
FGL 32.430
ADMIN BLOCK
GUARD HOUSE /
ARM BARRIER
FGL +32.05 3.4
FCC
12000 3.3
2.4 7.1 7.2 2.3
5.1 5.2 4.4 4.3
BCL 32.330
8000
CENTRE
PLN SUBSTATION BCL 32.350
BIN
6.4 6.3 3.5
9.4
7.4 7.3 5.4 5.3
6000
4500
FGL 32.700
10000
BCL 32.350
6800
FGL 32.700 BCL 32.350 BCL 32.350 FGL 32.700
8000
FGL 32.700
FGL 32.700 FGL 32.700
11500
PLN ENTRANCE PRIMARY ENTRANCE EXTERNAL ROAD
5788
tB1
tB1
IGNITE DATA CENTRE
F6-T2
F4-T2 INSTALL REBAR INFRASTRUCTURE
tC1 tB2 tC1
PB
MAPPING PROGRESS
MUW TREATMENT ROOM
5838
tB1
tB1
F6-T3
F4-T3 CONTRACTOR
tC1 tB2 tC1
11600
5763
tB1
tB1
DRAFTED RAYHAN T. H.
F5-T2
APPROVED WEI PING
F3-T2 tB3
tC1 tC1
PC
OWNER
DRAWING NO
PAGE 1
GENERAL NOTES
P1 P2
7100 4
3
TOPC : +32.500 2
1
F5-T1 NO REVISION /ISSUE DATE
tC1
F3-T1 tB3 tC1 KEY PLAN
PA
SITE BOUNDARY
32.40
32.20
32.20
32.20
32.10
32.10
32.30
32.90
32.70
33.00
32.20
11000
32.50
31.90
BCL 32.350 32.80
32.60
U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL
TANKS TANKS TANKS TANKS TANKS TANKS
SECONDARY ENTRANCE
5713
tB1
tB1
FGL 32.430
FGL 32.430
FGL 33.100
FUTURE DEVELOPMENT AREA
DATA HALL
33.00
32.80
FGL +33.10
32.90
33.10
32.70
32.90
32.80
32.6
32.5
32.4
0
0
32.30
BCL 32.350
BCL 32.350
32.20
32.7
32.20
0
Green Zone Area
32.20
9000
10000
BLOCK EE/2
F6-T1
EXTERNAL ROAD
1.3
1.4 FGL 32.430
10000
10000
BCL 32.350 BCL 32.350 BCL 32.350
4.1 4.2
2.1 PL +32.75 FGL 32.430 2.2
3.1 FGL 32.430 3.2
SATELLITE ZONE
FGL 33.100 FGL 33.100
FGL 32.700
FGL 32.430
ADMIN BLOCK
GUARD HOUSE /
ARM BARRIER
FGL +32.05 3.4
FCC
12000 3.3
2.4 7.1 7.2 2.3
5.1 5.2 4.4 4.3
BCL 32.330
8000
CENTRE
PLN SUBSTATION BCL 32.350
BIN
6.4 6.3 3.5
9.4
7.4 7.3 5.4 5.3
6000
4500
FGL 32.700
10000
BCL 32.350
6800
FGL 32.700 BCL 32.350 BCL 32.350 FGL 32.700
8000
FGL 32.700
FGL 32.700 FGL 32.700
11500
PLN ENTRANCE PRIMARY ENTRANCE EXTERNAL ROAD
5788
tB1
tB1
IGNITE DATA CENTRE
F6-T2
F4-T2 FINISHED POURING CONCRETE INFRASTRUCTURE
tC1 tB2 tC1
PB
MAPPING PROGRESS
MUW TREATMENT ROOM
5838
tB1
tB1
F6-T3
F4-T3 CONTRACTOR
tC1 tB2 tC1
11600
5763
tB1
tB1
DRAFTED RAYHAN T. H.
F5-T2
APPROVED WEI PING
F3-T2 tB3
tC1 tC1
PC
OWNER
DRAWING NO
PAGE 1
GENERAL NOTES
4
3
2
1
NO REVISION /ISSUE DATE
B1 B2 KEY PLAN
5600
32.40
32.20
32.20
32.20
32.10
32.10
32.30
32.90
32.70
33.00
32.20
11000
32.50
31.90
BCL 32.350 32.80
32.60
U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL
TANKS TANKS TANKS TANKS TANKS TANKS
SECONDARY ENTRANCE
FGL 32.430
FGL 32.430
FGL 33.100
FUTURE DEVELOPMENT AREA
DATA HALL
33.00
32.80
FGL +33.10
32.90
33.10
32.70
32.90
32.80
32.6
32.5
32.4
0
0
32.30
BCL 32.350
BCL 32.350
32.20
32.7
32.20
0
Green Zone Area
32.20
175 175
9000
125 125
10000
BLOCK EE/2
EXTERNAL ROAD
1.3
1.4 FGL 32.430
10000
10000
BCL 32.350 BCL 32.350 BCL 32.350
4.1 4.2
2.1 PL +32.75 FGL 32.430 2.2
3.1 FGL 32.430 3.2
SATELLITE ZONE
FGL 33.100 FGL 33.100
FGL 32.700
FGL 32.430
ADMIN BLOCK 150 KV SUBSTATION
6.1 6.2 FGL 32.05
FGL +33.10 10000
FGL +33.10
FGL 32.700
MEP YARD
GUARD HOUSE /
ARM BARRIER
FGL +32.05 3.4
FCC
12000 3.3
2.4 7.1 7.2 2.3
F2-B1 F2-B2
5.1 5.2 4.4 4.3
BCL 32.330
8000
CENTRE
PLN SUBSTATION BCL 32.350
BIN
6.4 6.3 3.5
9.4
7.4 7.3 5.4 5.3
6000
4500
FGL 32.700
10000
BCL 32.350
6800
FGL 32.700 BCL 32.350 BCL 32.350 FGL 32.700
8000
FGL 32.700
FGL 32.700 FGL 32.700
bB1
1
1
bC
bC
BA
IGNITE DATA CENTRE
INFRASTRUCTURE
bB1
bB1
BIN CENTER
4600
MAPPING PROGRESS
CONTRACTOR
F2-B3 F2-B4
bB1
1
1
bC
bC
BB DRAFTED RAYHAN T. H.
OWNER
FILE NAME
Bin Center Mapping Progress
DRAWING NO
23IN01-IGN-BS-FP-SD-01
PAGE 1
GENERAL NOTES
4
3
2
1
NO REVISION /ISSUE DATE
B1 B2 KEY PLAN
5600
32.40
32.20
32.20
32.20
32.10
32.10
32.30
32.90
32.70
33.00
32.20
11000
32.50
31.90
BCL 32.350 32.80
32.60
U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL
TANKS TANKS TANKS TANKS TANKS TANKS
SECONDARY ENTRANCE
FGL 32.430
FGL 32.430
FGL 33.100
FUTURE DEVELOPMENT AREA
DATA HALL
33.00
32.80
FGL +33.10
32.90
33.10
32.70
32.90
32.80
32.6
32.5
32.4
0
0
32.30
BCL 32.350
BCL 32.350
32.20
32.7
32.20
0
Green Zone Area
32.20
175 175
9000
125 125
10000
BLOCK EE/2
EXTERNAL ROAD
1.3
1.4 FGL 32.430
10000
10000
BCL 32.350 BCL 32.350 BCL 32.350
4.1 4.2
2.1 PL +32.75 FGL 32.430 2.2
3.1 FGL 32.430 3.2
SATELLITE ZONE
FGL 33.100 FGL 33.100
FGL 32.700
FGL 32.430
ADMIN BLOCK 150 KV SUBSTATION
6.1 6.2 FGL 32.05
FGL +33.10 10000
FGL +33.10
FGL 32.700
MEP YARD
GUARD HOUSE /
ARM BARRIER
FGL +32.05 3.4
FCC
12000 3.3
2.4 7.1 7.2 2.3
F2-B1 F2-B2
5.1 5.2 4.4 4.3
BCL 32.330
8000
CENTRE
PLN SUBSTATION BCL 32.350
BIN
6.4 6.3 3.5
9.4
7.4 7.3 5.4 5.3
6000
4500
FGL 32.700
10000
BCL 32.350
6800
FGL 32.700 BCL 32.350 BCL 32.350 FGL 32.700
8000
FGL 32.700
FGL 32.700 FGL 32.700
bB1
1
1
bC
bC
BA
IGNITE DATA CENTRE
PROGRESS DATE: 13-07-2023 INFRASTRUCTURE
INSTALL REBAR
bB1
bB1
BIN CENTER
4600
MAPPING PROGRESS
CONTRACTOR
F2-B3 F2-B4
bB1
1
1
bC
bC
BB DRAFTED RAYHAN T. H.
OWNER
FILE NAME
Bin Center Mapping Progress
DRAWING NO
PAGE 1
GENERAL NOTES
4
3
2
1
NO REVISION /ISSUE DATE
B1 B2 KEY PLAN
5600
32.40
32.20
32.20
32.20
32.10
32.10
32.30
32.90
32.70
33.00
32.20
11000
32.50
31.90
BCL 32.350 32.80
32.60
U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL
TANKS TANKS TANKS TANKS TANKS TANKS
SECONDARY ENTRANCE
FGL 32.430
FGL 32.430
FGL 33.100
FUTURE DEVELOPMENT AREA
DATA HALL
33.00
32.80
FGL +33.10
32.90
33.10
32.70
32.90
32.80
32.6
32.5
32.4
0
0
32.30
BCL 32.350
BCL 32.350
32.20
32.7
32.20
0
Green Zone Area
32.20
175 175
9000
125 125
10000
BLOCK EE/2
EXTERNAL ROAD
1.3
1.4 FGL 32.430
10000
10000
BCL 32.350 BCL 32.350 BCL 32.350
4.1 4.2
2.1 PL +32.75 FGL 32.430 2.2
3.1 FGL 32.430 3.2
SATELLITE ZONE
FGL 33.100 FGL 33.100
FGL 32.700
FGL 32.430
ADMIN BLOCK 150 KV SUBSTATION
6.1 6.2 FGL 32.05
FGL +33.10 10000
FGL +33.10
FGL 32.700
MEP YARD
GUARD HOUSE /
ARM BARRIER
FGL +32.05 3.4
FCC
12000 3.3
2.4 7.1 7.2 2.3
F2-B1 F2-B2
5.1 5.2 4.4 4.3
BCL 32.330
8000
CENTRE
PLN SUBSTATION BCL 32.350
BIN
6.4 6.3 3.5
9.4
7.4 7.3 5.4 5.3
6000
4500
FGL 32.700
10000
BCL 32.350
6800
FGL 32.700 BCL 32.350 BCL 32.350 FGL 32.700
8000
FGL 32.700
FGL 32.700 FGL 32.700
bB1
1
1
bC
bC
BA
IGNITE DATA CENTRE
PROGRESS DATE: 16-07-2023 INFRASTRUCTURE
bB1
bB1
BIN CENTER
4600
MAPPING PROGRESS
CONTRACTOR
F2-B3 F2-B4
bB1
1
1
bC
bC
BB DRAFTED RAYHAN T. H.
OWNER
FILE NAME
Bin Center Mapping Progress
DRAWING NO
PAGE 1
GENERAL NOTES
86083
4
43304 10969 6000 6500 6500 6000 7870 = EARTH ROD (17mm DIAMETER, LENGTH 3000mm)
3
21400 11258 = BARE COPPER 70mm2
2
= LIGHTNING PROTECTION DOWN CONDUCTOR
D1 D2 D3 D4 D4A D5 D5A D6 D6A D7
COOPER TAPE 25x3 mm 1 A -
= LIGHTNING EARTH ROD (COPPER 50mm2, 2400mm LENGTH)
c/w 300 x300 INSPECTION BOX NO REVISION /ISSUE DATE
14840
TOP EL.+32.70 TOP EL.+32.70 TOP EL.+32.70 EARTH ROD TO BE BURIED 1000mm DEPT BELOW SOIL SURFACE
TOP EL.+32.70 MAX 10 OHM RESISTIVITY)
KEY PLAN
DA = EXOTHERMIC WELDING
TOP EL.\+32.75
10075
1000 mm DEPTH BELOW SOIL SURFACE
8555
TOP EL.+32.75
= STRANDED BARE COPPER 70mm2
SITE BOUNDARY
32.20
32.40
32.20
32.20
32.10
32.30
32.10
32.70
32.90
32.20
33.00
31.90
BCL 32.350 32.80 32.50
11000
32.60
U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL U/G FUEL
TANKS TANKS TANKS TANKS TANKS TANKS
TOP EL.+32.70
1.2
DA1
FGL 32.430
1.1
SECONDARY ENTRANCE
INSPECTION PIT WITH 300X300
7024
12452
FGL 32.430
FGL 32.430
TOP EL.\+32.75
FGL 33.100
FUTURE DEVELOPMENT AREA
DATA HALL
33.00
32.80
32.90
FGL +33.10 32.70
33.10
32.90
32.80
32.5
32.6
32.4
0
0
32.30
BCL 32.350
BCL 32.350
32.20
32.7
32.20
0
Green Zone Area
32.20
9000
10000
BLOCK EE/2
EXTERNAL ROAD
1.3
8360
FGL 32.430
1.4
DB
10000
10000
BCL 32.350 BCL 32.350 BCL 32.350
SATELLITE ZONE
FGL 33.100
9900
FGL 32.700
FGL 33.100
FGL 32.430
ADMIN BLOCK 6.1 6.2 FGL 32.05 150 KV SUBSTATION
FGL +33.10 10000
FGL +33.10
FGL 32.700
MEP YARD
GUARD HOUSE /
ARM BARRIER
FGL +32.05 3.4
FCC
12000 3.3
2.3
TOP EL.+32.75
2.4 7.1 7.2
5.1 5.2 4.4 4.3
CENTRE
6000
BCL 32.350
BCL 32.330
8000
PLN SUBSTATION
42100
BIN
6.4 6.3 9.4 3.5
7.4 7.3 5.4 5.3
TOP EL.+32.70
6000
4500
FGL 32.700
10000
BCL 32.350
6800
FGL 32.700 BCL 32.350 BCL 32.350 FGL 32.700
8000
FGL 32.700
FGL 32.700 FGL 32.700
DB1
TOP EL.+32.75
6500
12785
FINISHED INSTALL BC
TOP EL.+32.70 IGNITE DATA CENTRE
FINISHED INSTALL EARTH ROD
DD INFRASTRUCTURE
TOP EL.\+32.75
TOP EL.\+32.75
TOP EL.+32.75
18800 2100 2100 20000 500
9500
107704
30000
TOP EL.+32.70
30000
DG
TOP EL.\+32.75
TOP EL.\+32.75
TOP EL.+32.75
10235
3000
TOP EL.+32.70
6880
DI
TOP EL.\+32.75
41000
12950
DJ
13620
TOP EL.+32.70
DK
TOP EL.\+32.75
FILE NAME
5241
DRAWING NO
PAGE 1