The document outlines the manpower work details for HSC Engineer in April 2025, detailing tasks performed at the POWDER and LMP locations, including steam isolation, valve additions, and various installations. Each entry includes the date, description of work, manpower involved, and time consumed, with a total of 32 tasks listed. The report is certified by the site engineer, Durga Agrahari, on April 30, 2025.

Uploaded by

ronitarafder11
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views1 page

HSE Work Details

The document outlines the manpower work details for HSC Engineer in April 2025, detailing tasks performed at the POWDER and LMP locations, including steam isolation, valve additions, and various installations. Each entry includes the date, description of work, manpower involved, and time consumed, with a total of 32 tasks listed. The report is certified by the site engineer, Durga Agrahari, on April 30, 2025.

Uploaded by

ronitarafder11
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

HSC Engineer Supply Manpower work details for April 2025

Time consumed
Sr.No. Date Work Location Description of work (Equipment) Manpower Work advised by Remarks
Working Days OT in HRS
Steam isolation 3 nos valve addition as per dryer
1 1-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
pending list
Steam isolation 3 nos valve addition as per dryer
2 2-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
pending list
Atex bottle stiffner fixing at 34 MTR -01 nos
3 3-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3 -
AHU temprory Ice water supply and return line
Atex bottle stiffner fixing at 34 MTR -01 nos
4 4-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
AHU temprory Ice water supply and return line
Air compressor - One support modification and
5 5-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
shifting as per requirement

6 6-Apr-25 POWDER 26 MTR - Air line and drail line for mainsteam heater 2 Fitter + 1 Welder + 4 Helper Durga 0 6

Steam line tapping at 15 MTR , Condensate line


7 7-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
correction and conect it to 8 MTR
Air line for PIG tank connection , Condenstae line
8 8-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
correction
HOC dryer commissioning support
9 9-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
Air line connection for divertor valve
LMP - Sludge tank connection from saperator and
10 10-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3 -
bactofuge
Baghouse - Air line connection , LMP commissiong
11 11-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
support
12 12-Apr-25 POWDER Main stem heater 6 nos samson valve addition 2 Fitter + 1 Welder + 4 Helper Durga 1 3
WDH - Condensate line fabrication along with
13 13-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 0 6
condensate assembly
WDH - Condensate line fabrication along with
14 14-Apr-25 POWDER condensate assembly 2 Fitter + 1 Welder + 4 Helper Durga 1 3
LMP commissioning support
8 MTR - Sugar section rotary valve air supply
15 15-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
Additional support
Pnumatic hammer installation and its air line fixing at
16 16-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
baghouse
Pnumatic hammer installation and its air line fixing at
17 17-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
baghouse
Pnumatic hammer installation and its air line fixing at
18 18-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 6
baghouse
19 19-Apr-25 POWDER Dummy fabrication snd installtion at 15 MTR 2 Fitter + 1 Welder + 4 Helper Durga 1 3
PRS - flanges leak arrest , LMP Bactofuge sample
20 20-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 0 6
valve installation
Drain trayn installation in cream -UHT valve cluster at
21 21-Apr-25 POWDER 2 Fitter + 1 Welder + 4 Helper Durga 1 3
6 MTR LMP

22 22-Apr-25 POWDER 34 MTR - Baghouse CIP nozzle fixing as per drawing 2 Fitter + 1 Welder + 4 Helper Durga 1 3

23 23-Apr-25 POWDER 34 MTR - Baghouse CIP nozzle fixing 2 Fitter + 1 Welder + 3 Helper Durga 1 3
24 24-Apr-25 POWDER Sludge tank installation and its piping 2 Fitter + 2 Helper Durga 1 3
25 24-Apr-25 POWDER Sludge tank installation and its piping 1Welder + 2 Helper Durga 1 4
Bctofuge commissioning support and sludge tank
26 25-Apr-25 LMP installation, 2 Fitter + 1 Welder + 4 Helper Durga 1 3
Camera cooling PHE shifting and installation
27 26-Apr-25 LMP Bactofuge commissioning support 2 Fitter + 2 Helper Durga 1 3
Camera cooling PHE - Ice water supply and return
28 26-Apr-25 Powder 1Welder + 2 Helper Durga 1 4
line connection
Steam filter drain line activity at 12.5 MTR
29 27-Apr-25 POWDER 1 Fitter + 1 Welder + 2 Helper Durga 0 6

Steam filter drain line activity at 12.5 MTR


30 28-Apr-25 POWDER 1 Fitter + 1 Welder + 2 Helper Durga 1 3

Steam filter drain line activity at 12.5 MTR


31 29-Apr-25 POWDER 1 Fitter + 1 Welder + 2 Helper Durga 1 3

Steam filter drain line activity at 12.5 MTR


32 30-Apr-25 POWDER 2 Fitter + 1 Welder + 3 Helper Durga 1 3

Certified by:
Name of the Site Engineer:- Durga agrahari
Date 30/04/2025.