2020 Standard Specifications FINAL
2020 Standard Specifications FINAL
CONSTRUCTION
SPECIFI
CATI
ONS
ANDDETAILS
HARRI
SCOUNTYFLOODCONTROLDI
STRI
CT
2020 STANDARD
CONSTRUCTION
SPECIFICATIONS
AND DETAILS
HARRIS COUNTY FLOOD CONTROL DISTRICT
STANDARD SPECIFICATIONS BOOK
TABLE OF CONTENTS
SUMMARY
01181 Private Utilities
ADMINISTRATIVE REQUIREMENTS
01325 Construction Schedules and Monthly Progress Meetings
01328 Construction Surveying
01330 Submittal Procedures
QUALITY REQUIREMENTS
01422 Reference Technical Standards
01457 Construction Tests and Inspection
EXECUTION REQUIREMENTS
01785 Project Record Documents
SITE PREPARATION
02120 Material Disposal
02200 Site Preparation and Restoration
02232 Selective Clearing
02233 Clearing and Grubbing
02241 Care and Control of Water
02269 Trench Safety System
HARRIS COUNTY FLOOD CONTROL DISTRICT
STANDARD SPECIFICATIONS BOOK
TABLE OF CONTENTS
EARTHWORK
02314 Fill Material
02315 Excavating and Backfilling
02316 Structural Excavating and Backfilling
02317 Desilting Channels
02321 Cement Stabilized Sand
02322 Flowable Fill
02361 Reinforced Silt Fence
02364 Filter Dams
02365 Stabilized Construction Access
02376 Concrete Channel Lining and Concrete Interceptor Structures
02377 Rectangular Concrete Channel
02378 Riprap and Granular Fill
02379 Geotextiles for Erosion Control Systems
PLANTING
02911 Topsoil
02921 Turf Planting Zone Preparation
02922 Sod
02923 Broadcast Seeding
02925 Hydromulch-Hydroseeding
02936 Fertilizer and Soil Amendments
02938 Non-Cyclical Mowing
02940 Irrigation
HARRIS COUNTY FLOOD CONTROL DISTRICT
STANDARD SPECIFICATIONS BOOK
TABLE OF CONTENTS
PLANTING (CONTINUED)
02941 Herbicide Application
DIVISION 3 – CONCRETE
CAST-IN-PLACE CONCRETE
03310 Concrete
DETAIL SHEETS
SECTION 01181
PRIVATE UTILITIES
PART 1 – GENERAL
1.1 SUMMARY
1.2 NOTIFICATIONS
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 01181 - 1/1 Private Utilities
SECTION 01270
PART 1 – GENERAL
1.1 SUMMARY
1.2 MEASUREMENT
1.4 PAYMENT
06/09/2020
Harris County Flood Control District
Standard Specifications 01270 - 1/3 Measurement and Payment
C. Progress payments will be based on the Engineer’s observations and
evaluations of quantities incorporated in the work multiplied by the unit
price.
D. Final payment for pay items governed by unit prices will be made on the
basis of actual measurements and quantities, up to the lines and levels of
the required work, as determined by the Engineer, multiplied by the unit
price for the pay item which is incorporated in or made necessary by the
work.
E. Prepare and submit an Application for Payment for work completed and
not previously paid. The application at a minimum shall include the
following:
1. Application for Payment: The application will be in a form acceptable to
the Engineer. A sample form will be provided to the Contractor.
2. Construction Schedule: See Section 01325 - Construction Schedules,
Paragraph 1.3 General Form and Contents of Schedules.
3. Contractor Payroll Certificate: See Prevailing Wage Rates.
4. Pollution Prevention Plan (PPP) Reports: See Storm Water Pollution
Prevention Plan (if applicable). Inspection & Maintenance reports for
either SWPPP or BMP.
5. Quantity supporting documents include: plotted and tabulated cross-
sections, quantity calculations or suppliers’ invoices, etc.
6. Application supporting documents and submittal items are provided to
verify products, regulations and contract requirements are being met.
Application supporting documents include: signed daily work reports,
field obtained data, truck volume tickets, truck weight tickets, seed and
fertilizer tags, pesticide use records, etc. and other supporting
documents as they may be necessary or required by Contract
Documents.
7. When the project requires a Notice of Intent (NOI), a copy of the
submitted contractor’s Notice of Termination (NOT) to TCEQ is
required as support documentation for approval of final payment.
8. Progress Meetings: Meet with the Engineer 1 week prior to each
scheduled Application for Payment to discuss progress and corrective
action. Meetings are required, unless approved otherwise by the
Engineer
F. Incomplete Applications for Payment will not be processed and will be
returned to the Contractor.
A. Remove and replace the work, or portions of the work, not conforming to
the Contract Documents.
B. If, in the opinion of the Engineer, it is not practical to remove and replace
the work, the Engineer will direct one of the following remedies:
1. The nonconforming work will remain as is, but the unit price will be
adjusted to a lower price at the discretion of the Engineer.
06/09/2020
Harris County Flood Control District
Standard Specifications 01270 - 2/3 Measurement and Payment
2. The nonconforming work will be modified as authorized by the
Engineer, and the unit price will be adjusted to a lower price at the
discretion of the Engineer, if the modified work is deemed to be less
suitable than originally specified.
C. Individual Sections may modify these options or may identify a specific
formula or percentage price reduction.
D. The authority of the Engineer to assess the nonconforming work and
identify payment adjustment is final.
1.6 NONPAYMENT
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 01270 - 3/3 Measurement and Payment
SECTION 01292
MATERIAL ON HAND
PART 1 – GENERAL
1.1 SUMMARY
1.2 SUBMITTALS
A. Schedule of Values:
1. Contractor must make a separate request for each major pay item that
they would like to be paid for on a Schedule of Values basis.
B. Material on Hand:
1. For payments of Material on Hand, refer to the “Policy for Payment of
Material on Hand” as adopted by Harris County Commissioners Court
on December 6, 2005 or as amended.
END OF SECTION
06/09/2020
Harris County Flood Control District Schedule of Values and
Standard Specifications 01292 - 1/1 Material on Hand
SECTION 01325
PART 1 – GENERAL
1.1 SUMMARY
06/09/2020
Harris County Flood Control District Construction Schedules and
Standard Specifications 01325 - 1/2 Monthly Progress Meetings
E. Limit individual work activities to a 15 calendar day duration. Work
activities with duration longer than 15 calendar days should be segmented
into 15 calendar day increments.
1.4 SUBMITTALS
PART 3 – EXECUTION
A. Meet with the Engineer one week prior to each scheduled Application for
Payment to discuss progress and corrective action. Meetings are required
for contracts with 180 or more calendar days, if required by the Engineer,
or if contracts are behind schedule as determined by the Engineer.
END OF SECTION
06/09/2020
Harris County Flood Control District Construction Schedules and
Standard Specifications 01325 - 2/2 Monthly Progress Meetings
SECTION 01328
CONSTRUCTION SURVEYING
PART 1 – GENERAL
1.1 SUMMARY
1.3 STANDARDS
1.4 CONTROL
06/09/2020
Harris County Flood Control District
Standard Specifications 01328 - 1/2 Construction Surveying
1.6 DAMAGED MONUMENTS
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 01328 - 2/2 Construction Surveying
SECTION 01330
SUBMITTAL PROCEDURES
PART 1 – GENERAL
1.1 SUMMARY
06/09/2020
Harris County Flood Control District
Standard Specifications 01330 - 1/2 Submittal Procedures
4. Identify variations from requirements of Contract Documents and
identify product or system limitations.
G. Contractor’s Certification: Contractor shall certify the items have been
reviewed in detail and are correct and in accordance with Contract
Documents, except as noted by any requested variance.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 01330 - 2/2 Submittal Procedures
SECTION 01422
PART 1 – GENERAL
1.1 SUMMARY
1.2 ABBREVIATIONS
A. Most standards are the version included in the 2020 published volumes. If
no date is stated, the current version on January 1, 2019 is applicable.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 01422 - 1/1 Reference Technical Standards
SECTION 01457
PART 1 – GENERAL
1.1 SUMMARY
1.5 SUBMITTALS
END OF SECTION
06/09/2020
Harris County Flood Control District Construction Tests
Standard Specifications 01457 - 2/2 and Inspection
SECTION 01520
PART 1 – GENERAL
1.1 SUMMARY
1.3 FACILITIES
06/09/2020
Harris County Flood Control District Temporary Facilities
Standard Specifications 01520 - 1/2 for Engineer
PART 2 – PRODUCTS – Not used
END OF SECTION
06/09/2020
Harris County Flood Control District Temporary Facilities
Standard Specifications 01520 - 2/2 for Engineer
SECTION 01562
CONSTRUCTION FENCE
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
PART 2 – PRODUCTS
PART 3 – EXECUTION
3.1 INSTALLATION
A. Install the construction fence with posts of sufficient size and spacing to
insure that the construction fence remains upright throughout its installed
length and functions as an effective barrier for the areas designated for
protection.
B. Maintain and repair the construction fence throughout the duration of the
project, at no cost to the District, to insure that the barrier continuously
performs its intended function.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 01562 - 1/1 Construction Fence
SECTION 01565
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and Payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
1.3 DEFINITION
A. State Waters: The water of the ordinary flow, underflow, and tides of every
flowing river, natural stream, and lake, and of every bay or arm of the Gulf
of Mexico, and the stormwater, floodwater, and rainwater of every river,
natural stream, and watercourse in the state. State Waters do not include
percolating groundwater, diffuse surface rainfall runoff, groundwater
seepage or springwater before it reaches the watercourse.
06/09/2020
Harris County Flood Control District
Standard Specifications 01565 - 1/4 General Source Controls
B. Control dust blowing by utilizing one or more of the following:
1. Paper or wood mulches bound with natural or chemical binders.
2. Temporary vegetative cover.
3. Apply dust suppressants containing polyacrylamide (PAM) at
manufacturer’s recommended rate for duration required. Submit
manufacturer’s label identifying active ingredient.
4. Irrigation by water sprinkling.
5. Spreading hay.
C. Implement dust controls immediately whenever dust can be observed
blowing on the site or as directed by the Engineer.
D. Provide copy of Water Rights Permit from the Texas Commission on
Environmental Quality (TCEQ) prior to using State Water.
A. Wash concrete trucks only in a designated concrete truck wash out area.
Contain washed out materials in such a manner as to prevent discharges
directly into the receiving water(s). Excavated traps, earthen embankment
traps, or filter fabric fences may be used for containment. Stabilize
designated areas prior to project completion to prevent material from
entering the receiving water. For projects including a formal Notice of
Intent (NOI), refer to the SWPPP narrative for detailed information on
concrete wash out activities.
06/09/2020
Harris County Flood Control District
Standard Specifications 01565 - 3/4 General Source Controls
PART 2 – PRODUCTS – Not used
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 01565 - 4/4 General Source Controls
SECTION 01566
PART 1 – GENERAL
1.1 SUMMARY
A. When there is not a separate item listed for work in this section, no separate
measurement and payment is made. Include cost for work under this section
in the related unit price work.
B. Measurement and Payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 – Measurement and Payment for unit price
procedures.
1.3 REFERENCE
A. ANSI A300 - Part 1: Tree, Shrub, and Other Woody Plant Maintenance -
Standard Practices (Pruning)
B. ANSI A300 – Part 2: Tree, Shrub and Other Woody Plant Maintenance –
Standard Practices (Soil Management a. Modification, b. Fertilization, and c.
Drainage)
C. ANSI A300 - Part 5: Tree, Shrub and Other Woody Plant Maintenance –
Standard Practices (Management of Trees and Shrubs During Site Planning,
Site Development and Construction)
D. Best Management Practices – Managing Trees During Construction
E. Best Management Practices – Tree and Shrub Fertilization
F. Best Management Practices – Tree Pruning
G. Guide for Plant Appraisal, Latest Edition
H. Texas Supplement to the Guide for Plant Appraisal – Latest Edition
1.4 SUBMITTALS
A. Preserve and protect all trees and plants located in identified TPZ to prevent
foliage, branch, trunk, or root damage that could result from construction
operations.
B. Review of the installed TPZ’s, pruning work and any other tree care
operations, on-site with a Forester prior to the start of any clearing, grubbing,
or any other site prep or construction operations.
C. Provide 24-hour notice to Forester and Inspector for work that requires
review/meeting on site.
D. For further information on the execution of site protection refer to Part 3 of this
specification.
E. Prevent or minimize the following types of damage to trees and plants
designated for preservation:
1. Compaction of root zone by foot or vehicular traffic, or material storage.
2. Trunk or branch damage from equipment operations, material storage, or
from nailing or bolting.
3. Trunk or branch damage caused by ropes or guy wires.
4. Root poisoning from spilled solvents, gasoline, paint or other noxious
materials.
5. Branch damage due to improper pruning or trimming (See notes/details on
plans for tree pruning).
6. Alteration of soil pH factor caused by depositing lime, concrete, plaster or
other base materials near roots.
7. Cutting of roots larger than 1-1/2 inches in diameter without prior approval
from the Forester.
A. Protect designated trees for preservation using one or more of the following
methods:
06/09/2020
Harris County Flood Control District
Standard Specifications 01566 - 2/5 Tree and Plant Protection
1. Root Collar excavation
2. Air-Spading excavation
3. Root Pruning Trenches
B. Final grade adjacent to the tree shall be at the direction of the Forester and
shall match the surrounding proposed grading.
C. Monitor and assist with field layout of the tree protection zones before
demolition and construction operations begin. Ensure tree protection
procedures and techniques are practiced as specified and address conditions
specific to each site.
PART 3 – EXECUTION
A. Install tree protection fencing for all trees to be preserved and as specified in
the Best Management practices – Managing Trees During Construction.
B. Install tree protection fencing prior to site work or construction activity. Do not
remove or relocate tree protection fencing without direct approval of the
Forester.
C. Do not operate equipment within Tree Protection Zones (TPZ) or fenced
areas without approval of the Forester.
D. Prevent damage to or compaction of TPZ by construction activities.
06/09/2020
Harris County Flood Control District
Standard Specifications 01566 - 3/5 Tree and Plant Protection
E. Do not store equipment, construction materials, vehicles, topsoil or fill dirt
inside a fence or TPZ. Entryways and access into a protected area shall not
be provided unless approved by the Forester.
F. Where a fence is closer than four (4) feet to a trunk, protect the trunk with a
trunk protection structure.
G. Exercise caution when working near TPZ.
H. Repair damages to tree protection fencing at no additional cost to HCFCD.
I. Prevent scarring of trunks or limbs by equipment or other means.
J. Place six (6) to twelve (12) inches of mulch in the TPZ areas where
construction access extends into the TPZ of a tree designated to remain.
K. Ensure that mulch does not cover root collar or trunk. Place mulch in a
manner that does not compact the soil. Once access is no longer needed,
mulch shall be spread around the tree to a depth of no more than three (3)
inches.
L. Remove and dispose of tree protection fencing upon completion of all
construction activities in each work zone.
M. For additional information on TPZ fence material, and etc., see Section 3.6
Exhibits, included in this Specification.
06/09/2020
Harris County Flood Control District
Standard Specifications 01566 - 4/5 Tree and Plant Protection
work under the direct supervision of the Forester, unless otherwise directed
by the Forester.
B. Air Spading Excavation: Use a pneumatic excavation tool with a rated
operating pressure of 6.2-7.0 bar, air stream velocity at the cutting head of
2,200-2,500 km/hr. and an air displacement of 4,000-5,000 L/min. Use an air
compressor adequately sized as required to power the pneumatic excavation
tool in accordance with the manufacturers recommendations for the
pneumatic excavation tool.
C. Root Pruning Trenches: Install root pruning trenches prior to site work or
construction activity. Cut all roots by chainsaw, handsaw or loppers. Cut
roots cleanly, do not rip, tear, or chop roots. Backfill trench and compact
immediately after inspection for cleanly cut roots has been completed by a
Forester or an Inspector. (Refer to Damage Assessment, Section 3.5 of this
document).
1. Final grade adjacent to the tree shall be at the discretion of the Forester
and shall match the surrounding proposed grading.
2. Cover exposed roots to reduce damage caused by desiccation. Cover
roots with soil or mulch and water to help protect them from drying as a
result of the excavation process.
3. Use extreme care to prevent excessive damage to root systems.
3.5 Exhibits
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 01566 - 5/5 Tree and Plant Protection
TREE
PROTECTION DBH* MINIMUM
FENCING DISTANCE FROM
BASE OF TREE (FT)
<6" 3 FT.
AREA ENCLOSED BY
FENCE IS TREE
PROTECTION ZONE
8'-0"
FINISH GRADE
2'-0"
POLE
DEPTH
<6" 3 FT.
*
6" ≤ 20" 1 FT. PER INCH OF
TRUNK DIAMETER
@ DBH
>20" CONSULT
ARBORIST
SECTION VIEW
TRENCH EXCAVATION
N.T.S.
Exhibit B
N.T.S.
1'-0"
TREE PROTECTION
TREE AND ROOT PRUNING
Exhibit C
NOTE: APPLICABLE TO ROOT PRUNING ON ONE SIDE OF TREE ONLY. N.T.S.
CONSULT ARBORIST FOR MORE EXTENSIVE ROOT PRUNING.
8" INCHES OF
MULCH*
NOTES:
1. ONE COMPLETE WRAP OF BURLAP AROUND
TREE TRUNK.
2. STRAPS OR WIRE ARE USED ON OUTSIDE OF
PLANK TO BIND BOARDS IN PLACE.
3. NO FASTENERS SHOULD BE DRIVEN INTO TREE.
4. TRUNK PROTECTION SHOULD BE ADJUSTED TO
ALLOW GROWTH IF TRUNK PROTECTION IS IN
PLACE DURING PERIODS OF TRUNK DIAMETER
GROWTH.
5. REMOVE TRUNK PROTECTION UPON PROJECT
COMPLETION.
INSTALL MATTING AS
DIRECTED BY ARBORIST
8" INCHES OF
MULCH*
S:\Operations\PROJECTS\PROJECT XY\PROJECT XY.dwg
Exhibit D N.T.S.
<6" 3 FT.
SEE TABLE
OPE
S:\Operations\PROJECTS\PROJECT XY\PROJECT XY.dwg
SL SEE TABLE
ED
H ER
AT
FE
6:1
O
4:1T
<6" 3 FT.
SEE TA
USE SMALL OR NO BLE
FOOTING TO DRAIN WATER
AVOID ROOT CUT DOWN SLOPE
NO GEOTEXTILE
OR GRAVEL
BELOW FILL
S:\Operations\PROJECTS\PROJECT XY\PROJECT XY.dwg
PROJECT SIGNS
PART 1 – GENERAL
1.1 SUMMARY
PART 2 – PRODUCTS
2.2 SUPPORTS
3.1 CONSTRUCTION
A. CSN Holder(s):
1. Construct notice CSN holder from 1.5 foot by 1.5 foot by ¾ inch thick
exterior grade (EXT BC) plywood. Paint white.
2. Bolt notice holder to 2 by 4 inch posts with 2 hot-dipped galvanized
screws per post. Paint posts white.
06/09/2020
Harris County Flood Control District
Standard Specifications 01580 - 1/2 Project Signs
3. Staple laminated Construction Site Notice to front of notice holder.
4. Place CSN holder at each entrance to the construction site.
A. Project Sign(s):
1. Install Project Identification sign(s) and Construction Site Notice holder(s)
prior to construction start.
2. Install, relocate when required, and maintain all project signs for duration
of Project.
B. Install sign(s) at location(s) designated by the Engineer or where shown on
the Plans. Position the sign(s) in such a manner as to be fully visible and
readable by the general public.
C. Install sign(s) level and plumb.
D. Project Identification Sign(s):
1. Mount each Project Identification sign on two 12 feet long 4 inch by 4 inch
posts; Install in the ground a minimum of 30 inches.
E. CSN Holder(s):
1. Drive supports a minimum of 1 foot into ground.
3.3 MAINTENANCE
3.4 REMOVAL
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 01580 - 2/2 Project Signs
SECTION 01785
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
A. Maintain at the job site, one hard copy of the following items.
1. Contract Documents to include a project manual and one complete
issued for construction set of plans with any issued revisions or
addendums to the contract.
2. Approved Shop Drawings.
3. Written directive for any changes in scope.
4. Contractor obtained permissions to perform the work. (i.e. access
agreements, temporary construction easement, parking, etc.)
5. TCEQ Notice of Intent (NOI) if applicable.
6. Construction Site Notice.
7. TPDES Stormwater Construction Permit.
8. Stormwater Pollution Prevention Plan (SWPPP)
9. TCEQ Notice of Termination (NOT) if applicable, as they are filed.
10. Other Environmental Permits, as required.
B. Store record documents apart from documents used for construction. Do
not use record documents for construction purposes. Maintain documents
in clean, dry, legible and orderly condition. Make documents and samples
available at all times for inspection by the Engineer.
C. For all projects, final deliverable record documents shall include:
1. Set of plans marked with field changes for use to create final Record
Drawings.
2. Notice of Termination (NOT) as required.
3. Warranty and Guaranty Affidavits
06/09/2020
Harris County Flood Control District
Standard Specifications 01785 - 1/2 Project Record Documents
4. Any Contractor obtained permits as required for the Work
5. Acceptance of any part of the Work done outside of HCFCD ROW.
1.4 RECORDING
1.5 SUBMITTALS
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 01785 - 2/2 Project Record Documents
SECTION 02120
MATERIAL DISPOSAL
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 – Measurement and Payment for unit price
procedures.
1.3 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02120 - 1/4 Material Disposal
e. Aerial map with boundary of fill location identified.
f. Physical address of the disposal location.
g. Estimated total number of cubic yards of excavated material to be
disposed at the location.
3. For disposal or recycling of concrete rubble, pipe or debris submit:
a. HCFCD project number and pay item number.
b. Physical address of disposal location.
c. Intended use of the material if not taken to a landfill or recycling
facility.
d. Estimated total quantity of material to be disposed at the location.
4. For disposal of tires submit:
a. HCFCD project number and pay item number.
b. Name and physical address of disposal or recycling location.
c. Estimated total quantity of material to be disposed at the location.
5. For burning of cleared vegetation submit:
a. HCFCD project number and pay item number.
b. Material intended to be burned.
c. Intended location of burn pit.
d. Copy of TCEQ burn permit.
e. List of notified local agencies and contact phone numbers.
6. Demonstration of compliance with any local jurisdictional requirements
for material disposal.
C. During construction, for material disposed in a landfill or at a recycling
facility submit the following pay application support documents. At the
direction of the Engineer provide one of the following;
1. One copy of the landfill operator’s ticket or receipt clearly showing the
truck load weight and/or cubic yards accepted by the landfill or
recycling facility.
2. Summary including the amount of material and disposal location for all
material removed from the site on a daily basis.
a. For disposal or recycling of concrete rubble, pipe or debris submit:
1. HCFCD project number and pay item number.
2. Physical address of disposal location.
3. Intended use of the material if not taken to a landfill or recycling
facility.
4. Estimated total quantity of material to be disposed at the
location.
b. For disposal of tires submit:
1. HCFCD project number and pay item number.
2. Name and physical address of disposal or recycling location.
3. Estimated total quantity of material to be disposed at the
location.
06/09/2020
Harris County Flood Control District
Standard Specifications 02120 - 2/4 Material Disposal
c. For burning of cleared vegetation submit:
1. HCFCD project number and pay item number.
2. Material intended to be burned.
3. Intended location of burn pit.
4. Copy of TCEQ burn permit.
5. List of notified local agencies and contact phone numbers.
d. Demonstration of compliance with any local jurisdictional
requirements for material disposal.
D. During construction, for material disposed in a landfill or at a recycling
facility submit the following pay application support documents. At the
direction of the Engineer provide one of the following;
1. One copy of the landfill operator’s ticket or receipt clearly showing the
truck load weight and/or cubic yards accepted by the landfill or
recycling facility.
2. Summary including the amount of material and disposal location for all
material removed from the site on a daily basis.
PART 3 – EXECUTION
3.1 GENERAL
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02120 - 4/4 Material Disposal
SECTION 02200
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item(s) listed on the
Unit Price Schedule.
B. Payment will be on the following schedule:
1. Payment of 70 percent of bid amount: When mobilization is complete,
including move-in of major equipment, installation of project signs,
sanitary facilities and, if required, accepted initial Construction
Schedule, temporary office and sanitary facilities for Engineer.
2. Payment of 30 percent of bid amount: When clean up/restoration of
project site is complete, including removal of construction debris,
temporary facilities, signs, any other related project appurtenances,
and delivery of final Project Record Documents.
C. Measurement and payment is as noted on the Unit Price Schedule.
D. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
PART 3 – EXECUTION
3.1 GENERAL
06/09/2020
Harris County Flood Control District Site Preparation
Standard Specifications 02200 - 1/3 And Restoration
National Weather Service Flood Watch or when directed by the Engineer
when needed to protect the public and public infrastructure.
H. Remove structures, abandoned utility lines and related obstructions to a
depth of 2 feet below the finished grade.
I. Collect tires, batteries, paint cans, oil cans and related items found on the
right-of-way in a location approved by the Engineer, for disposal by others.
Inform the Engineer of possibly hazardous material found on site for
assessment and handling/disposal by others.
J. Remove structures, outfall pipes, drainage facilities and other items that
may interfere with the construction work or as designated on the Plans.
K. Clean up and restore the site.
L. When Work is finished, remove existing HCFCD signs and reinstall in an
approved location or deliver the sign to an HCFCD facility when directed
by the Engineer.
3.3 ENCROACHMENTS
06/09/2020
Harris County Flood Control District Site Preparation
Standard Specifications 02200 - 2/3 And Restoration
3.7 BACKFILLING
3.8 DISPOSAL
3.10 SURVEYING
END OF SECTION
06/09/2020
Harris County Flood Control District Site Preparation
Standard Specifications 02200 - 3/3 And Restoration
SECTION 02232
SELECTIVE CLEARING
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
1.3 REFERENCE
A. ANSI A300 - Tree Care Operations - Tree, Shrub and Other Woody Plant
Maintenance - Standard Practices (includes supplements).
PART 3 – EXECUTION
3.1 GENERAL
06/09/2020
Harris County Flood Control District
Standard Specifications 02232 - 1/2 Selective Clearing
3. Chips larger than 6 inches are not permitted. Spread chips in a
uniform layer in a depth not to exceed 3 inches. Avoid placing chips
into waterways.
4. Tree limb and root pruning shall comply with ANSI A300.
5. Active Selective Clearing work limits shall not exceed 1,500 linear feet
at any given time, or as directed by the Engineer.
3.3 DISPOSAL
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02232 - 2/2 Selective Clearing
SECTION 02233
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
PART 3 – EXECUTION
A. Remove trees, woody vegetation and stumps from construction work limits
necessary for access, staging, excavation, fill, or other earthen work
activities from the work site.
B. Clearing and grubbing beyond construction limits for the Contractor’s
convenience is not to be permitted unless approved by the Engineer, and
shall be done at no cost to the District.
C. For clearing and grubbing on private property where the Contractor has
agreements, transmit written evidence to the Engineer that permission has
been obtained from the property owner prior to beginning work.
D. For linear projects, clearing and grubbing shall not exceed more than
1,500 linear feet ahead of the work completed and accepted by the
HCFCD Vegetation Management Department for turf establishment.
E. Engineer will designate and clearly mark trees to be saved. Protect
designated trees in accordance with Section 01565 - General Source
Controls, or Section 01566 - Tree and Plant Protection as they apply to
the contract.
F. Tree limbs extending over the project may be trimmed for access
purposes, or for execution of Work. Trim with a sharp saw or by-pass
pruner to produce a smooth cut, and execute evenly as not to harm the
structural stability of the tree.
06/09/2020
Harris County Flood Control District
Standard Specifications 02233 - 1/2 Clearing and Grubbing
G. For adjacent vegetation extending into the project site, refer to
Section 01566 - Tree and Plant Protection.
H. Remove stumps, roots and buried logs in areas of excavation or fill to a
depth of 1 foot below design or existing ground surface.
I. Grub trees and brush 2 feet below adjacent grades, in areas where
excavation or fill will not be performed, in a manner which permits smooth
grading.
3.3 DISPOSAL
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02233 - 2/2 Clearing and Grubbing
SECTION 02241
PART 1 – GENERAL
1.1 SUMMARY
A. Section includes requirements for the care and control of ground and
surface water.
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
D. Where paid for separately, payment is in accordance with Section 01292 -
Schedule of Values.
1.3 SUBMITTALS
PART 3 – EXECUTION
3.1 GENERAL
A. Select the means, methods and techniques to control ground water and
surface water.
B. Maintain the work reasonably free of water. Control shall be accomplished
in a manner that will preserve the strength of the subgrade and backfill,
06/09/2020
Harris County Flood Control District Care and
Standard Specifications 02241 - 1/2 Control of Water
not cause instability of slopes, will protect the proposed work and not
result in damage to existing facilities or contamination of water.
C. Lower the groundwater in advance of excavation utilizing wells, wellpoints
or similar methods, as necessary.
1. Open pumping with sumps and ditches is not permitted if it results in
boils, loss of fines, softening of the ground or instability, or erosion of
slopes.
2. Install wells and wellpoints with suitable screens and filters so that
continuous pumping of fines does not occur.
3. Arrange the discharge to facilitate collection of samples by the
Engineer and to prevent erosion at the outfall.
D. Remove care and control of water facilities in a manner as not to
contaminate water and restore channel area to a condition satisfactory to
the Engineer, after the work is complete.
3.2 REPAIR
END OF SECTION
06/09/2020
Harris County Flood Control District Care and
Standard Specifications 02241 - 2/2 Control of Water
SECTION 02269
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
1.4 SUBMITTALS
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02269 - 1/1 Trench Safety System
SECTION 02314
FILL MATERIAL
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
A. ASTM D 1140 - Amount of Material in Soil Finer Than the No. 200
(75 μm) Sieve.
B. ASTM D 2487 - Classification of Soils for Engineering Purposes
Unified Soil Classification System.
C. ASTM D 4647 - Identification and Classification of Dispersive Clay
Soils by the Pinhole Test.
D. ASTM D 4318 - Liquid Limit, Plastic Limit, and Plasticity Index of Soils.
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02314 - 1/3 Fill Material
4. Classification shall be reported in accordance with ASTM D 2487 and
include (as a minimum):
a. Group name.
b. Group symbol.
c. Soil color(s).
d. Results of the laboratory tests.
PART 2 – PRODUCTS
A. Use an approved material, free from roots, trash, organic matter and other
objectionable material where imported select fill material is shown on the
Plans or specified.
B. Where the imported select fill material is not specified elsewhere, the
material shall be a fine-grained lean clay with sand (CL) or sandy lean clay
(CL) soil material when classified in accordance with ASTM D 2487 and
conforming to the following criteria:
A. Where no other fill material is specified or shown, use inorganic soils from
the on-site excavation that are free from roots, trash, organic matter and
other objectionable material and classified by their group name and
symbol in accordance with ASTM D 2487 as follows:
06/09/2020
Harris County Flood Control District
Standard Specifications 02314 - 2/3 Fill Material
B. Do not use peat or other organic matter, muck, debris or similar materials.
The inorganic soils listed below may be used only with the approval of the
Engineer:
PART 3 – EXECUTION
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02314 - 3/3 Fill Material
SECTION 02315
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 – Measurement and Payment for unit price
procedures.
D. Measurement shall be based upon Registered Professional Land
Surveyor (RPLS) surveyed cross-sections or a digital terrain model, as
required and approved by the Engineer. See Paragraph 1.4 Definitions in
this Section.
1. Cross sections or survey data obtained by Contractor shall be tied to
the base line and, as a minimum, at the same locations and limits as
the design points/break points or every 100 Linear Feet (LF) whichever
is shorter.
2. Cross-sections or survey data obtained by Contractor shall be plotted
at the same scale as design cross-sections where available or to the
same horizontal and vertical scale where design cross-sections are not
available.
3. Plots of cross-sections or survey data shall include the
pre-construction, intermediate, final and design information.
E. Cross-sections in areas of buried riprap or protective linings, such as
riprap and concrete channel lining, shall be to the top of these materials.
Excavation required for placement of such protective lining is considered
structural excavation and incidental to the cost of related protective lining.
See Section 02316 – Structural Excavating and Backfilling.
F. For small areas or other areas where limits can readily be determined
visually, measurement may be by conventional taping and/or measuring
techniques, as approved by the Engineer. Measurement shall be
witnessed by the HCFCD site representative.
G. Where paid for separately, backslope swales shall be measured as noted
06/09/2020
Harris County Flood Control District
Standard Specifications 02315 - 1/5 Excavating and Backfilling
on the Unit Price Schedule.
H. Contractor shall perform all quantity calculations for approval by Engineer.
I. No payment will be made for over-excavation or over-filling beyond the
design cross-sections, except as directed by the Engineer.
J. Support partial pay application quantities with pre-construction and
intermediate cross-sections, Plan quantity calculations to-date or quantity
calculations determined from field measurement techniques previously
approved by the Engineer. Partial payment documented by field
measurement techniques other than approved survey submittals will
be limited to 90% of the plan quantity until a survey submittal is
approved.
K. Support final pay request quantities by using pre-construction,
intermediate and final cross-sections or final field measured quantity
calculations, as approved by the Engineer.
1.3 REFERENCES
1.4 DEFINITIONS
1.5 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02315 - 2/5 Excavating and Backfilling
files and report data used to calculate final quantities.
D. Survey information submittal shall include at a minimum: plan view
showing points taken with elevations, 1-ft contour lines, and baseline
corresponding with the design plan benchmark information, north arrow
and scale.
PART 2 – PRODUCTS
PART 3 – EXECUTION
A. Prepare the site for construction in accordance with Section 02200 – Site
Preparation and Restoration and Section 02233 – Clearing and Grubbing.
B. Remove grass and other vegetative cover from areas to be excavated or
filled.
C. Remove material that may interfere with the proposed work, including
unusable materials, disturbed soils and/or objectionable material as
directed by Engineer.
D. Engineer will inspect and approve foundation soil prior to placement of fill.
3.2 TOPSOIL
3.4 CONSTRUCTION
3.5 FILL
A. Maintain constant flow and drainage in the main and lateral channels,
backslope swales and off-site swales.
06/09/2020
Harris County Flood Control District
Standard Specifications 02315 - 4/5 Excavating and Backfilling
3.8 EROSION AND SEDIMENT CONTROL
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02315 - 5/5 Excavating and Backfilling
SECTION 02316
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
PART 2 – PRODUCTS
06/09/2020
Harris County Flood Control District Structural Excavating
Standard Specifications 02316 - 1/5 and Backfilling
2.5 SUBGRADE STABILIZATION
2.8 TOPSOIL
PART 3 – EXECUTION
3.2 EXCAVATION
06/09/2020
Harris County Flood Control District Structural Excavating
Standard Specifications 02316 - 3/5 and Backfilling
shown on the Plans. A plan for early placement of backfill must be
submitted by the Contractor and approved by the Engineer. Any
additional material testing required for early placement of backfill will be
the responsibility of the Contractor.
D. Do not backfill where the top of walls are supported by slabs or
intermediate walls until the slab or intermediate walls have been placed
and cured. Do not backfill until the minimum curing requirement and
minimum design compressive strength have been met unless otherwise
shown on the Plans.
E. Prevent any wedging action of backfill against the structure. Step cut
(bench) the slopes bounding the excavation, as required, to prevent
wedging.
F. Use sand or gravel backfill for backfilling behind sheet pile walls,
wingwalls, retaining walls, rectangular concrete channel walls or other
retaining structures. Backfill in the zone for a distance of 3 feet from the
wall to 1.5 foot below the top of the wall, unless shown otherwise on the
Plans. Backfill the 1.5 foot zone with 1 foot of clay soil conforming to Part
2 of this Section and backfill the top 6 inches with topsoil conforming to
Section 02911 - Topsoil.
G. Excavate a minimum of 3 feet around abutment backwalls, inlets, junction
boxes, and manholes and fill with cement stabilized sand, unless shown
otherwise on the Plans.
06/09/2020
Harris County Flood Control District Structural Excavating
Standard Specifications 02316 - 4/5 and Backfilling
7. Consolidate concrete backfill in accordance with Section 03310 -
Concrete.
B. Prevent damage to structures caused by backfilling or other construction
operations.
END OF SECTION
06/09/2020
Harris County Flood Control District Structural Excavating
Standard Specifications 02316 - 5/5 and Backfilling
SECTION 02317
DESILTING CHANNELS
PART 1 – GENERAL
1.1 SUMMARY
PART 3 – EXECUTION
3.1 DESILTING
A. Excavate and grade the flowline of the channel bottom to the lines and
grades noted on the Plans or as directed by the Engineer, to restore
positive drainage during base flow conditions.
B. Desilting the channel bottom is intended to restore the channel to its
original design configuration. Do not excavate beyond the design grade to
deepen the channel or undermine/disturb the adjacent channel banks,
unless directed by the Engineer.
C. When desilting concrete lined channel sections, remove all sediment
within the channel through the concrete lined channel section reach.
D. Clear and remove all sediment from culverts, pipes, and drainage conduits
outfalling into the project reach to the limits of the Districts right-of-way.
E. Clear and remove all sediment from culverts, pipes, and underneath
bridges that serve as a crossing structure to allow for positive drainage
during base flow conditions in the channel.
F. Remove and dispose of sediment accumulations located in the channel
bottom not shown on the plans to restore positive drainage during base
flow conditions.
06/09/2020
Harris County Flood Control District
Standard Specifications 02317 - 1/2 Desilting Channels
3.2 EQUIPMENT
A. Provide equipment with rubber tracks or tires for sediment removal from
concrete lined channels, and protect existing concrete features as
approved by the Engineer.
3.4 REPAIRS
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02317 - 2/2 Desilting Channels
SECTION 02321
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
1.3 REFERENCES
A. ASTM C 40 -
Organic Impurities in Fine Aggregates for Concrete.
B. ASTM C 94 -
Ready-Mixed Concrete.
C. ASTM C 123 -
Lightweight Pieces in Aggregate.
D. ASTM C 142 -
Clay Lumps and Friable Particles in Aggregates.
E. ASTM C 150 -
Portland Cement.
F. ASTM D 558 -
Moisture-Density Relations of Soil-Cement-Mixtures.
G. ASTM D698 -
Laboratory Compaction Characteristics of Soils Using
Standard Effort (12,400 ft-lb/ft3 (600kN-m/m³)).
H. ASTM D 1633 - Compressive Strength of Molded Soil-Cement
Cylinders.
I. ASTM D 2487 - Classification of Soils for Engineering Purposes (Unified
Soil Classification System).
J. ASTM D 4318 - Liquid Limit, Plastic Limit and Plasticity Index of Soils.
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02321 - 1/4 Cement Stabilized Sand
PART 2 – PRODUCTS
2.1 MATERIALS
PART 3 – EXECUTION
3.2 PLACEMENT
06/09/2020
Harris County Flood Control District
Standard Specifications 02321 - 2/4 Cement Stabilized Sand
B. Perform and complete compaction of sand/cement mixture within 4 hours
after addition of water to mix at the plant.
C. Do not place or compact sand/cement mixture in standing or free water.
3.4 ACCEPTANCE
06/09/2020
Harris County Flood Control District
Standard Specifications 02321 - 3/4 Cement Stabilized Sand
B. When mixture produces 7-day compressive strength less than 200 psi and
greater than or equal to 140 psi, material shall be accepted contingent on
credit in payment. Compute credit by the following formula:
Credit per Pay Item = $(Bid Amount) x [(2 (200 psi - actual psi at 48
hours)) / 200]
1. To use this formula, Bid Amount refers to the unit price of the related
Pay Item (CMP, RCP, RCB, etc.)
2. Credit per Pay Item refer to the amount to be deducted, per unit from
the unit price of the related Pay Item.
C. When mixture produces 2-day compressive strength less than 140 pounds
per square inch, then remove and replace cement-sand mixture and
paving and other necessary work at no cost to the District.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02321 - 4/4 Cement Stabilized Sand
SECTION 02322
FLOWABLE FILL
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02322 - 1/3 Flowable Fill
PART 2 – PRODUCTS
2.1 MATERIALS
PART 3 – EXECUTION
A. Batch, mix and transport flowable fill in accordance with ASTM C 94,
except when directed otherwise by the Engineer.
06/09/2020
Harris County Flood Control District
Standard Specifications 02322 - 2/3 Flowable Fill
B. Mix flowable fill in quantities required for immediate use. Do not use
portions which have developed initial set or which are not in place within
90 minutes after the initial water has been added.
C. Do not mix flowable fill while the air temperature is at or below 35 degrees
F. without prior approval of the Engineer.
3.2 PLACEMENT
3.4 CLEAN UP
A. Clean up excess flowable fill discharged from the work area and remove
excess flowable fill from pipes at no cost to the District.
B. Refer to Section 02120 - Material Disposal.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02322 - 3/3 Flowable Fill
SECTION 02361
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
1.4 SUBMITTALS
PART 2 – PRODUCTS
06/09/2020
Harris County Flood Control District
Standard Specifications 02361 - 1/2 Reinforced Silt Fence
C. Geotextile fabric shall be free of defects or flaws that affect its physical
properties.
D. Provide a geotextile fabric with a minimum grab strength of 100 lbs (ASTM
D 4632).
E. Provide reinforced silt fence with properties in accordance with AASHTO
M 288 Geotextile Specification for Highway Applications Table 6.
2.2 SUPPORTS
PART 3 – EXECUTION
3.1 GENERAL
3.2 MAINTENANCE
A. Inspect reinforced silt fence after each rainfall, daily during periods of daily
rainfall, and, at a minimum, once every week. Repair and/or replace any
component of the reinforced silt fence that becomes defective from
intended use.
B. Remove sediment deposits when the deposit reaches 1/3 the height of the
fence. Dispose of sediment properly.
C. Remove reinforced silt fence and dispose of any sediment accumulations
promptly when directed by Engineer.
3.4 DISPOSAL
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02361 - 2/2 Reinforced Silt Fence
SECTION 02364
FILTER DAMS
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
1.4 SUBMITTALS
PART 2 – PRODUCTS
A. Style 1 - zinc coated prior to being double twisted into mesh in accordance
with ASTM A 975.
06/09/2020
Harris County Flood Control District
Standard Specifications 02364 - 1/3 Filter Dams
2.3 WIRE MESH FOR REINFORCEMENT
A. Provide spiral binders, lacing wire and stiffeners made of wire having the
same coating material and same wire size as the wire mesh for
reinforcement.
PART 3 – EXECUTION
3.1 INSTALLATION
3.2 MAINTENANCE
A. Sediment Accumulation.
1. Remove accumulated sediment as needed or when directed by the
Engineer.
2. Reshape the filter dam as needed or when directed by the Engineer.
3.3 REMOVAL
A. Maintain the filter dam, in place, throughout the duration of the Project.
Remove when directed by the Engineer. Sod the exposed earth
beneath the filter dam and areas damaged by the removal process in
accordance with Section 02921 - Turf Establishment.
06/09/2020
Harris County Flood Control District
Standard Specifications 02364 - 2/3 Filter Dams
3.4 SEDIMENT DISPOSAL
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02364 - 3/3 Filter Dams
SECTION 02365
PART 1 – GENERAL
1.1 SUMMARY
1.3 SUBMITTALS
PART 2 – PRODUCTS
06/09/2020
Harris County Flood Control District Stabilized
Standard Specifications 02365 - 1/2 Construction Access
2.2 GRANULAR FILL
PART 3 – EXECUTION
3.1 GENERAL
3.2 MAINTENANCE
A. Inspect and maintain stabilized areas daily. Provide periodic top dressing
with additional granular fill as necessary.
B. Repair or replace components of stabilized access areas that become
defective from intended use.
C. Maintain stabilized access areas until acceptance of the Project or as
directed by Engineer.
D. Remove stabilized access promptly when directed by Engineer. Restore
areas where stabilized construction access was removed to final project
grade in preparation of turf establishment by others.
3.3 DISPOSAL
END OF SECTION
06/09/2020
Harris County Flood Control District Stabilized
Standard Specifications 02365 - 2/2 Construction Access
SECTION 02376
PART 1 – GENERAL
1.1 SUMMARY
1.3 SUBMITTALS
PART 2 – PRODUCTS
2.1 CONCRETE
06/09/2020
Harris County Flood Control District Concrete Channel Lining And
Standard Specifications 02376 - 1/2 Concrete Interceptor Structures
PART 3 – EXECUTION
A. The prepared subgrade or seal slab which forms the base of a concrete
placement area should normally be dry at the time of concreting. If the
concrete is placed in hot, dry conditions, the base should be lightly
dampened with water in advance of concreting. There should be no free
water standing on the base, nor water seeping into the placement area,
nor should there be any muddy or soft spots when the concrete is placed.
END OF SECTION
06/09/2020
Harris County Flood Control District Concrete Channel Lining And
Standard Specifications 02376 - 2/2 Concrete Interceptor Structures
SECTION 02377
PART 1 – GENERAL
1.1 SUMMARY
1.3 SUBMITTALS
PART 2 – PRODUCT
2.1 CONCRETE
PART 3 – EXECUTION
3.1 INSTALLATION
06/09/2020
Harris County Flood Control District
Standard Specifications 02377 - 1/2 Rectangular Concrete Channel
B. Excavate the Channel. Refer to Section 02315 - Excavating and
Backfilling.
C. Excavate for concrete. Refer to Section 02316 - Structural Excavating and
Backfilling.
D. Refer to Section 03310 - Concrete.
E. For concrete designed without retarding agents and placed in ambient
temperatures above 50 degrees F., leave rectangular concrete channel
wall forms in a minimum of 24 hours after the concrete is placed.
F. For concrete designed with retarding agents and/or placed in ambient
temperatures below 50 degrees F., remove forms when approved by the
Engineer.
G. Tolerances:
1. Screed the concrete surface to be true within 1/4 inch in 10 feet.
2. Plumb walls to within 1/8 inch from top to bottom.
A. The prepared subgrade or seal slab which forms the base of a concrete
placement area should normally be dry at the time of concreting. If the
concrete is placed in hot, dry conditions, the base should be lightly
dampened with water in advance or concreting. There should be no free
water standing on the base, nor water seeping into the placement area,
nor should there be any muddy or soft spots when the concrete is placed.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02377 - 2/2 Rectangular Concrete Channel
SECTION 02378
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
D. Excavation for gravel, granular fill, riprap and buried riprap, and boulders
is measured from finished grade, and will not be measured separately, but
is incidental to riprap unit price measurement.
E. Riprap and granular fill used in toe walls, grade beams or termination
trenches are incidental to unit price measurement.
F. Excavation for rock trenches will not be measured separately, but is
incidental to the unit price measurement of Riprap and Granular Fill.
G. The excavated volume of material displaced for the installation of rock
mats will not be measured separately, but is incidental to the unit price
measurement of Riprap and Granular Fill. Payment for fill material placed
above the rock mat will be made under the appropriate fill unit item.
H. On-site topsoil will not be measured and paid separately, but is incidental
to riprap surface measurement.
I. Imported topsoil will be paid for as noted on the Unit Price Schedule.
1.3 REFERENCES
06/09/2020
Harris County Flood Control District
Standard Specifications 02378 - 1/5 Riprap and Granular Fill
1.4 SUBMITTALS
A. Keep the storage area clean, firm, smooth and well drained in order that
the product can be placed with a minimum of foreign matter.
B. Stockpile and handle gravel, granular fill, riprap and boulders to minimize
segregation of particle sizes either in the stockpile or while loading,
hauling and handling.
PART 2 – PRODUCTS
2.1 RIPRAP
06/09/2020
Harris County Flood Control District
Standard Specifications 02378 - 2/5 Riprap and Granular Fill
TABLE 1
RIPRAP GRADATION NO. 1
Stone Weight Volume Cubical Shape Spherical
Shape
Percent Lbs. Cubic Ft (2) Ft (Each Side) Ft (Dia.)
Lighter Lower Upper Lower Upper Lower Upper Lower Upper
by Weight Limit Limit Limit Limit Limit Limit Limit Limit
100 180 265 1.20 1.77 1.06 1.21 1.31 1.50
50 80 110 0.53 0.73 0.81 0.90 1.01 1.12
15 40 60 0.27 0.40 0.64 0.74 0.80 0.91
Notes:
The theoretical cube and sphere size is presented for guidance only.
1. Paragraph 2.1 shall control riprap shape and dimensions.
2. Volume is based on 150 pcf, unit weight.
Riprap Gradation No. 1 is to be used where an 18 inch thick riprap mat is
3. noted on the Plans.
TABLE 2
RIPRAP GRADATION NO. 2
Spherical
Stone Weight Volume Cubical Shape
Shape
Percent Lbs. Cubic Ft (2) Ft (Each Side) Ft (Dia.)
Lighter Lower Upper Lower Upper Lower Upper Lower Upper
by Weight Limit Limit Limit Limit Limit Limit Limit Limit
100 260 640 1.73 4.27 1.20 1.62 1.49 2.01
50 130 200 0.87 1.33 0.95 1.10 1.18 1.37
15 40 150 0.27 1.00 0.64 1.00 0.80 1.24
Notes:
The theoretical cube and sphere size is presented for guidance only.
1. Paragraph 2.1 shall control riprap shape and dimensions.
2. Volume is based on 150 pcf, unit weight.
Riprap Gradation No. 2 is to be used where a 24 inch thick riprap mat is
3. noted on the Plans.
2.4 BOULDERS
2.5 GEOTEXTILE
06/09/2020
Harris County Flood Control District
Standard Specifications 02378 - 4/5 Riprap and Granular Fill
PART 3 – EXECUTION
A. Place the gravel, granular fill, riprap or boulders to the slopes, lines and
grades as shown on the Plans.
B. To establish a well-graded mass of riprap with minimal voids, fill voids
between larger riprap blocks with spalls and smaller blocks of the largest
feasible size to form a compact mass. Do not place spalls and small
blocks in place of larger size riprap or granular fill.
C. Install riprap and granular fill mat to the thickness as shown on the Plans.
Riprap shall have minimum mat thickness as shown on the gradation
tables.
D. Install gravel and boulders to the thickness as shown on the Plans.
E. Place the gravel, granular fill, riprap and boulders to avoid displacement or
damage to the prepared surface or geotextile and in a manner to avoid
segregation of particle sizes.
F. Fill riprap voids and bury riprap a minimum of 6 inches with topsoil on side
slopes as directed by the Engineer.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02378 - 5/5 Riprap and Granular Fill
SECTION 02379
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 – Measurement and Payment for unit price
procedures.
D. Staples and termination trenches are incidental to the geotextile installation
and will not be paid for separately.
E. Geotextile used in termination trenches and overlaps is incidental to surface
measurement.
1.3 REFERENCES
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District Geotextiles for
Standard Specifications 02379 - 1/3 Erosion Control Systems
C. Submit manufacturer’s recommended installation method for geotextile
installation based on its designated use.
A. Inspect geotextile filter fabric delivered to the site for damage. Protect the
geotextile from construction traffic damage.
B. Store the geotextile in accordance with the manufacturer’s
recommendations for outdoor storage.
C. Protect the geotextile from direct sunlight and ultraviolet radiation. Keep the
fabric wrapped in its protective covering during shipping and storage. The
label affixed to each roll should state manufacturer’s name, geotextile
name (product designation) and type, lot number, roll number and roll
dimensions including length, width and gross weight. Replace or repair
damaged geotextile or protective covering as directed by the Engineer.
D. Do not use hooks or other sharp objects to handle the geotextile. Do not
drag the geotextile on the ground.
PART 2 – PRODUCTS
2.1 MATERIALS
PART 3 – EXECUTION
06/09/2020
Harris County Flood Control District Geotextiles for
Standard Specifications 02379 - 2/3 Erosion Control Systems
D. Immediately prior to placing the geotextile, the Engineer shall inspect and
approve the prepared section.
A. Do not leave the geotextile exposed to the sun longer than the
manufacturer recommends to minimize damage due to ultraviolet radiation.
Do not install a geotextile if it has been removed from its protective
covering longer than the manufacturer recommends.
B. For placement of geotextile, follow manufacturer’s installation instructions
and at a minimum:
1. Place the geotextile directly on the prepared area. Lay the geotextile
smoothly on the subgrade to minimize tension, stress, folds and
wrinkles.
2. After placement, do not unnecessarily walk on or disturb the geotextile
unless required to preserve contact with the subgrade. Equipment is
not allowed on the unprotected geotextile. Protect the geotextile from
clogging, penetrations, tears and other damage during installation.
3. Place the geotextile strips from downstream to upstream. Overlap
successive geotextile sheets such that the upstream sheet is placed
over the downstream sheet and/or the upslope over the downslope.
4. Overlap adjoining geotextile sections a minimum of 2 feet.
5. Replace or repair any geotextile damaged during the placement of
riprap or other materials at no additional cost to the District. Place a
geotextile patch of the same material over the area and extend a
minimum of 3 feet beyond the perimeter of the tear and/or damage.
Orient the patch material so that its fibers are aligned with the
damaged geotextile fibers.
C. Placements under water are not permitted without Engineer’s approval.
END OF SECTION
06/09/2020
Harris County Flood Control District Geotextiles for
Standard Specifications 02379 - 3/3 Erosion Control Systems
SECTION 02462
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
06/09/2020
Harris County Flood Control District
Standard Specifications 02462 - 1/7 Steel Sheet Piling
1.4 SUBMITTALS
A. Store sheet piles and accessories in an area free of standing water and
elevated off the ground.
B. Keep pile interlocks clean and free of sand, gravel, mud and other
potential obstructions.
C. Prevent damage to sheet piling, protective coating and accessories during
handling.
A. Existing Facilities.
1. Before the start of construction, adequately protect any existing
structures from damage. Repair damage to permanent facilities due to
negligence or lack of adequate protection at no cost to the District.
Prior to beginning of the project, a joint inspection will be made by the
Contractor and Engineer to determine the condition of the existing
structures.
06/09/2020
Harris County Flood Control District
Standard Specifications 02462 - 2/7 Steel Sheet Piling
B. New Concrete Work.
1. Schedule concrete placement operations so that pile driving will be
complete before any concrete is placed within 50 feet of sheet piling.
1.7 COORDINATION
PART 2 – PRODUCTS
A. Provide hot rolled steel sheet piling which meets the requirements of
ASTM A 328, ASTM A 572 or ASTM A 690. ASTM A 690 sheet piling, or
piling with protective coating, is required in marine environments or as
shown on the Plans.
B. Structural property requirements are shown on the Plans. Select the grade
of steel and sheet pile section that meets or exceeds these requirements.
C. Provide steel sheet piles and special fabricated shapes having a
continuous jaw interlock joint throughout the entire length of the sheet.
D. Provide handling holes located in the sheet pile web.
E. Provide sheet piles and interlocks free of excessive kinks, camber or twist
that would interfere with reasonably free sliding in the joint.
F. Provide square and blunt shaped pile ends.
G. Provide new sheet piles. Used sheet piling will not be accepted.
H. Provide steel sheet piling products from a single manufacturer.
2.2 ACCESSORIES
2.3 FABRICATION
A. Fabricate items such as wale beams, struts, closure sections and special
sections in accordance with the requirements of the AISC Specifications
for the Design, Fabrication and Erection of Structural Steel for Buildings.
B. Perform welding in accordance with the requirements of AWS D1.1
Structural Welding Code - Steel.
06/09/2020
Harris County Flood Control District
Standard Specifications 02462 - 3/7 Steel Sheet Piling
2.4 FABRICATED CONNECTIONS
A. Where tie rods are required for an anchored wall system, use either
ASTM A 36 or ASTM A 615 tie rods, as noted on the Plans. The
ASTM A 615 tie rods shall be equal to the grade 60 Dywidag Threadbar
Reinforcing System.
PART 3 – EXECUTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02462 - 4/7 Steel Sheet Piling
2) Where a steel cap will be placed on the top of the wall, trim
sheet piling as necessary to have level bearing of the cap on the
sheet pile.
3) Where the sheet pile tops will be exposed, trim the tops of piling
as necessary to the same level to provide a uniform
appearance.
4) Where the sheet pile wall functions in a hydraulic structure, such
as a drop structure or weir structure, all sheet pile tops shall be
accurately driven to or cut off at the design elevation.
b. Variation from vertical (plumb) shall not exceed 1 inch in 10 feet.
3. Horizontal Tolerances.
a. Walls shall be straight and uniform in appearance. Maintain a
tolerance of 2 inches from the Plan layout. In sheet pile lined
channels, the face to face distance between the walls shown on the
Plans shall be maintained, as a minimum.
C. Setting Sheet Piling.
1. If necessary to comply with the above tolerances, use a guide frame or
template to start piling.
2. Set and drive ball and socket joint piling with the ball end leading.
When the socket joint must lead, place a bolt or similar object in the
bottom end to minimize socket clogging.
3. Guide each sheet pile into the interlocking joint of the previously placed
pile.
4. Gradually lower pile after being threaded. Do not drop the pile into
place.
5. Interlock piles in accordance with the manufacturer’s printed literature.
Incorrect interlocking to make angles or bends will not be acceptable.
D. Pile Driving.
1. Drive piles vertically and in correct alignment so that the tops of the
piles lie on a straight line and to insure a proper interlocking of joints
throughout the pile length.
2. Drive piles with a hammer of a size and weight appropriate for the pile
and conditions encountered. A drop hammer will not be allowed.
However, a hairpin stabbing hammer will be permitted to start the
sheet pile, provided the piling is protected from damage.
3. Drive piles to required full Plan penetration using only the hammer.
4. Drive the piles in an acceptable manner to prevent the pile bottom from
drifting, becoming misaligned or loosing interlocking of sheets.
Remove and replace any pile ruptured at the interlock or damaged in
any other way at no additional cost to the District.
5. Water jetting is not permitted.
6. Do not overdrive piles, lift driven piles or jack driven piles.
06/09/2020
Harris County Flood Control District
Standard Specifications 02462 - 5/7 Steel Sheet Piling
3.2 FIELD CUTTING AND CONNECTING
A. Comply with the AISC Specification for the Design, Fabrication and
Erection of Structural Steel for Buildings in the fabrication and erection of
such items as wale beams, tie rods and special sections.
B. Drill bolt holes in order to obtain smooth, uniform holes of the proper
diameter. Making bolt holes with a cutting torch is not permitted.
C. Splices.
1. Avoid splices of sheet piles and obtain approval of the Engineer prior
to using.
a. Where allowed, the number of splices per pile shall be limited to 2
splices.
2. The piling to be spliced shall be ordered full length from the mill.
Match-mark and cut the pile at splice locations. As pile driving
proceeds, splice the match-marked pieces to reconstruct the original
sheet pile shipped from the mill. Splicing randomly selected sections is
not permitted.
3. Provide splice plates on the flanges to compensate for not welding the
interlocks where full section modulus is required in the region of the
splice.
4. Stagger splices on adjacent piles by at least 2 feet.
D. Cut off and replace, using full strength welds, the damaged portion of the
top of the piling if it is appreciably damaged during driving or by other
means.
E. Perform welding in accordance with the requirements of AWS D1.1
Structural Welding Code - Steel.
A. Place weep holes, where shown on the Plans, in the web of the sheet pile,
not in the flange.
B. Provide weep holes with a filtration system of graded gravel and
geotextile, as shown on the Plans.
A. Seal handling holes and holes for structural items such as bolts and tie
rods with similar materials. Similar materials shall be welded in place.
06/09/2020
Harris County Flood Control District
Standard Specifications 02462 - 6/7 Steel Sheet Piling
3.6 TIE RODS
A. Tighten anchor rod nuts to remove all slack in the system before
backfilling and installing the retaining wall cap.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02462 - 7/7 Steel Sheet Piling
SECTION 02464
TIMBER BENTS
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
1.4 SUBMITTALS
PART 2 – PRODUCTS
A. Provide southern pine wood poles for use as timber bent piles that meet
the requirements of ANSI O5.1.
1. Provide minimum diameter of 8 inches at the pile tip.
B. Provide southern pine wood poles that are pressure preservative treated
in accordance with AWPA C4 using one of the following methods:
06/09/2020
Harris County Flood Control District
Standard Specifications 02464 - 1/2 Timber Bents
1. Creosote conforming to AWPA P1/P13 to 9.0 pounds per cubic foot
(pcf) by assay.
2. Chromated copper arsenate (CCA - Type C) oxide preservative to
produce a retention assay of 0.6 pounds per cubic foot.
2.3 HARDWARE
PART 3 – EXECUTION
3.1 INSTALLATION
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02464 - 2/2 Timber Bents
SECTION 02505
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
A. ASTM D 3212 - Joints for Drain and Sewer Plastic Pipes Using Flexible
Elastomeric Seals
B. ASTM D 3350 - Polyethylene Plastics Pipe and Fittings Materials.
C. ASTM D 4976 - Polyethylene Plastics Molding and Extrusion Materials.
D. ASTM F 477 - Elastomeric Seals (Gaskets) for Joining Plastic Pipe.
E. AASTO M294 - Corrugated Polyethylene Pipe, 300- to 1500-mm
Diameter.
1.4 SUBMITTALS
PART 2 – PRODUCTS
06/09/2020
Harris County Flood Control District
Standard Specifications 02505 - 1/2 High Density Polyethylene Pipe
PART 3 – EXECUTION
3.1 INSTALLATION
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02505 - 2/2 High Density Polyethylene Pipe
SECTION 02611
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
A. ASTM A 506 - Reinforced Concrete Arch Culvert, Storm Drain, and
Sewer Pipe.
B. ASTM A 507 - Reinforced Concrete Elliptical Culvert, Storm Drain,
and Sewer Pipe.
C. ASTM C 76 - Reinforced Concrete Culvert, Storm Drain, and Sewer
Pipe.
D. ASTM C 443 - Joints for Concrete Pipe and Manholes, Using Rubber
Gaskets.
E. ASTM C 655 - Reinforced Concrete D-Load Culvert, Storm Drain,
and Sewer Pipe.
F. ASTM C 877 - External Sealing Bands for Non-circular Concrete
Sewer, Storm Drain, and Culvert Pipe.
G. ASTM C990 - Standard Specification for Joints for Concrete Pipe,
Manholes, and Precast Box Sections Using
Preformed Flexible Joint Sealants
H. ASTM C1619 - Standard Specification for Elastomeric Seals for
Joining Concrete Structures
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02611 - 1/2 Reinforced Concrete Pipe
PART 2 – PRODUCTS
PART 3 – EXECUTION
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02611 - 2/2 Reinforced Concrete Pipe
SECTION 02612
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCE
1.4 SUBMITTALS
PART 2 – PRODUCTS
06/09/2020
Harris County Flood Control District Precast Reinforced
Standard Specifications 02612 - 1/2 Concrete Box
D. Provide joints comprised of preformed flexible joints sealants conforming
to ASTM C990.
PART 3 – EXECUTION
END OF SECTION
06/09/2020
Harris County Flood Control District Precast Reinforced
Standard Specifications 02612 - 2/2 Concrete Box
SECTION 02630
CONCRETE MANHOLES
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02630 - 1/3 Concrete Manholes
PART 2 – PRODUCTS
2.2 CONCRETE
2.4 MORTAR
A. Provide cast-iron frames, grates, rings and covers as shown on the Plans.
Refer to City of Houston Department of Public Works and Engineering -
Standard Construction Details and Section 02084 -Frames, Grates, Rings
and Covers.
06/09/2020
Harris County Flood Control District
Standard Specifications 02630 - 2/3 Concrete Manholes
2.6 PIPE CONNECTIONS TO MANHOLES
A. Storm sewer pipe connection should meet ASTM C923 and ASTM F2510
for flexible CMP and HDPE pipe. Rigid (concrete) pipe connections to
manholes do not have to comply with ASTM C923, and may be grouted
instead.
PART 3 – EXECUTION
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02630 - 3/3 Concrete Manholes
SECTION 02631
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
1.3 REFERENCE
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District Storm Sewers
Standard Specifications 02631 - 1/6 and Outfalls
B. Handle pipe, box, precast manholes, fittings and accessories carefully with
approved handling devices. Materials cracked, gouged, chipped, dented
or otherwise damaged will be considered nonconforming.
C. Store pipe, box, precast manholes and fittings on heavy timbers or
platforms to avoid contact with the ground.
D. Unload pipe and box, precast manholes, fittings and accessories as close
as practical to the location of installation to avoid unnecessary handling.
E. Keep interiors of pipe, box, precast manholes and fittings free of dirt and
foreign matter.
F. Rotate HDPE pipe in storage during periods of extreme heat to prevent
deflection.
PART 2 – PRODUCTS
PART 3 – EXECUTION
06/09/2020
Harris County Flood Control District Storm Sewers
Standard Specifications 02631 - 2/6 and Outfalls
3.2 HIGH DENSITY POLYETHYLENE (HDPE) PIPES
A. Install concrete pipe per ASTM C1479 and concrete box per ASTM C1675
and in accordance with AASHTO Section 27, the manufacturer’s
recommendations and as specified in this Section. Where these
standards conflict, the more stringent standard shall govern.
B. Install pipe and box only after excavation is completed, the bottom of the
trench is shaped, bedding material is installed and all are approved by the
Engineer.
C. Install pipe and box to the line and grade indicated on the Plans. Place
pipe and box so that they have continuous bearing of barrel-bottom on
bedding material and the pipe is laid in the trench so the interior surfaces
of the pipe follow the grades and alignments indicated.
06/09/2020
Harris County Flood Control District Storm Sewers
Standard Specifications 02631 - 3/6 and Outfalls
D. Use cement stabilized sand for backfill for storm sewers being constructed
under roadways from the top of the pipe to the underside of the subgrade,
unless otherwise shown on the Plans.
3.5 MANHOLES
06/09/2020
Harris County Flood Control District Storm Sewers
Standard Specifications 02631 - 4/6 and Outfalls
2. Pipes 15 to 24 inches: three-fourths of largest pipe diameter.
3. Pipes larger than 24 inches: equal to largest pipe diameter.
c. Invert slope through manhole: 0.10 foot drop across manhole with
smooth transition of invert through manhole unless otherwise
shown on Plans.
2. Form invert channels with structural concrete if not integral with
manhole base section. Provide curves for side inlets and smooth invert
fillets for flow transition between pipe inverts. Refer to Section 03310 -
Concrete.
E. Manhole Frame and Adjustment Rings.
1. Combine precast concrete or HDPE adjustment rings so elevation of
installed casting cover matches pavement surface. Seal between
concrete adjustment ring and precast top section with non-shrink grout;
do not use mortar between adjustment rings. Apply latex-based
bonding agent to precast concrete surfaces joined with non-shrink
grout. Set cast iron frame on adjustment ring in bed of approved
sealant material. Install sealant bed consisting of two beads of sealant,
each bead at least 0.5 inch high and 0.5 inch wide.
2. For manholes in unpaved areas, set top ring of frame a minimum of 6
inches above existing ground unless shown otherwise on Plans. In
unpaved areas, encase manhole frame in mortar or non-shrink grout
placed flush with face of manhole ring and top edge of frame. Provide
rounded corner around perimeter.
F. Where rigid joints are used for connecting existing sewers to the manhole,
backfill under the existing sewer up to the springline of the pipe with
nonstructural concrete or flowable fill.
G. In unpaved areas, provide positive drainage away from manhole frame to
natural grade.
3.5 APPURTENANCES
A. Construct manholes and install frames, grates, rings and covers. Refer to
Section 02630 - Concrete Manholes.
B. Plaster brick inlets with 1/2 inch mortar on the inside. The walls for brick
inlets shall be a minimum of 8 inches thick.
C. Provide forms for both the outside and inside faces of concrete inlet walls.
If the material excavated for the inlet can be hand trimmed to a smooth
vertical face, the outside forms may be omitted with approval of Engineer.
D. Connect inlet leads to the inlet.
E. Cut off inlet leads neatly at the inside face of inlet wall. Point up with
mortar.
F. When the box section of the inlet has been completed, shape the floor of
the inlet to drain.
G. Finish concrete surfaces. Refer to Section 03310 - Concrete.
06/09/2020
Harris County Flood Control District Storm Sewers
Standard Specifications 02631 - 5/6 and Outfalls
3.6 PROTECTION
3.7 INSPECTION
A. Leakage Inspection.
1. Visually inspect for leaks and repair in a manner approved by the
Engineer.
B. CMP and HDPE Pipe Deflection Inspection.
1. The internal diameter of the barrel shall not be reduced more than
7.5% for CMP and 5% for HDPE of its base diameter when measured
no less than days following completion of installation.
2. Check pipes for deflection using a mandrel, as directed by the
Engineer.
3. Provide odd numbered mandrel with no less than 9 arms. Provide
properly sized proving ring to allow verification of the mandrel’s
accuracy.
4. Replace the pipe where pipe deflection exceeds 7.5 percent of the
inside diameter.
3.8 DISPOSAL
END OF SECTION
06/09/2020
Harris County Flood Control District Storm Sewers
Standard Specifications 02631 - 6/6 and Outfalls
SECTION 02632
PART 1 – GENERAL
1.1. SUMMARY
1.3. REFERENCE
1.4. SUBMITTALS
PART 2 – PRODUCTS
06/09/2020
Harris County Flood Control District Inlets, Headwalls
Standard Specifications 02632 - 1/3 and Wingwalls
D. Precast Concrete Base: Provide suitable cutouts or holes to receive pipe
and connections.
2.2 CONCRETE
A. Storm sewer pipe connection should meet ASTM C923 and ASTM F2510
for flexible CMP and HDPE pipe. Rigid (concrete) pipe connections to
manholes do not have to comply with ASTM C923, and may be grouted
instead.
2.5 CONCRETE
2.7 MORTAR
06/09/2020
Harris County Flood Control District Inlets, Headwalls
Standard Specifications 02632 - 2/3 and Wingwalls
2.8 MISCELLANEOUS METALS
A. Provide cast iron frames, grates, rings, covers and handrails conforming to
the Plans.
PART 3 – EXECUTION
END OF SECTION
06/09/2020
Harris County Flood Control District Inlets, Headwalls
Standard Specifications 02632 - 3/3 and Wingwalls
SECTION 02642
PART 1 – GENERAL
1.1 SUMMARY
A. Section includes requirements for corrugated metal pipe (CMP) for gravity
sewers and drains, including fittings and appurtenances.
1.3 REFERENCE
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02642 - 1/3 Corrugated Metal Pipe
PART 2 – PRODUCTS
A. Steel Pipe:
1. Galvanized pipe conforming to AASHTO M 36 shall be full circle
Type I, Type IA or Type IR; or pipe arch Type II or Type IIR.
2. Fabrication with circumferential corrugations, lap joint construction with
riveted or spot welded seams, helical corrugations with continuous
helical lock seam or ultra-high frequency resistance butt-welded seams
are acceptable.
B. Polymer Precoated Galvanized Steel Pipe:
1. Pipe conforming to the requirements of AASHTO M 245 shall be full
circle Type I, Type IA or Type IR; or pipe arch Type II or Type IIR.
06/09/2020
Harris County Flood Control District
Standard Specifications 02642 - 2/3 Corrugated Metal Pipe
2. Fabrication with circumferential corrugations, lap joint construction with
riveted seams or helical lock seams is acceptable.
3. Inside and outside coating shall be a minimum of 10 mils.
PART 3 – EXECUTION
3.1 PREPARATION
3.2 INSTALLATION
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02642 - 3/3 Corrugated Metal Pipe
SECTION 02911
TOPSOIL
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02911 - 1/3 Topsoil
iii. if the source site was previously fertilized
b. Routine Analysis (Macronutrients) - N, P, K, Ca, Mg, Na, pH
and conductivity (Ec).
c. Micronutrients - S, Zn, Fe, Cu, B, Mo and Mn.
d. Organic matter.
e. Textural analysis.
C. Imported topsoil samples.
1. When requested by the Engineer, submit sufficient samples of topsoil
for additional testing by the District.
2. When additional samples are required, submit samples at least 60
days prior to delivery or placement of topsoil.
3. Supply samples from the same source and stockpile as the topsoil for
the project.
PART 2 – PRODUCTS
2.1 MATERIALS
PART 3 – EXECUTION
A. Stripped topsoil generated on-site shall include fine roots and herbaceous
vegetation as specified on the Plans or as directed by the Engineer.
Stockpile topsoil generated on-site for use on the side slopes, berms, dry
bottoms, wetland shelves and any other area directed by the Engineer.
3.4 DISPOSAL
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02911 - 3/3 Topsoil
SECTION 02921
PART 1 – GENERAL
1.1 SUMMARY
PART 2 – PRODUCTS
2.1 Topsoil
2.2 SOD
2.3 SEED
06/09/2020
Harris County Flood Control District
Standard Specifications 02921 - 1/4 Turf Planting Zone Preparation
2.4 HYDROMULCH-HYDROSEEDING
PART 3 – EXECUTION
3.1 GENERAL
A. Prepare the seedbed to support turf grass and/or sod placement prior to
broadcast seeding or sodding activities.
B. Seedbed preparation will include soil cultivation throughout a minimum of
four (4) inches of the final graded surface or as directed by HCFCD
representative.
C. Apply fertilizer or soil amendment to seedbed as directed by a HCFCD
representative. The HCFCD representative will determine which soil
amendment will be used.
1. Refer to Fertilizer and Soil Amendment Specification.
D. Remove all roots and woody plants over three (3) inches in diameter.
E. Seedbed must be uniform in tilth and free of clods larger than two (2)
inches. The use of a penetrometer may be used as a gauge to determine
seedbed depth and tilth.
06/09/2020
Harris County Flood Control District
Standard Specifications 02921 - 2/4 Turf Planting Zone Preparation
F. Disk, harrow, or rake seedbed to loosen soil surface if rainfall or
compaction occur prior to seeding.
G. Grade seedbed(s) adjacent to turfed areas or pavement to permit the sod
to be placed flush with adjacent surfaces.
H. Lightly compact the seedbed(s) with a roller such as a Culti-packer.
I. Protect prepared seedbed(s) from damage by pedestrians or vehicular
traffic until final inspection and acceptance by the HCFCD representative.
J. Correct irregularities in finished seedbed surfaces to eliminate
depressions.
3.5 HYDROMULCH-HYDROSEEDING
3.6 SODDING
3.8 DISPOSAL
06/09/2020
Harris County Flood Control District
Standard Specifications 02921 - 3/4 Turf Planting Zone Preparation
3.10 PENALTIES
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02921 - 4/4 Turf Planting Zone Preparation
SECTION 02922
SOD
PART 1 – GENERAL
1.1 SUMMARY
1.3 SUBMITTALS
PART 2 – PRODUCTS
2.1 SOD
A. Staples used for anchored sod shall be 4 X 1/8 inch or 11 gauge steel
staples.
PART 3 – EXECUTION
3.1 GENERAL
A. Harvest, deliver, and install sod within a 36 hour period. Sod not planted
within this time period will be inspected and approved by HCFCD prior to
installation.
B. Sod that has been allowed to dry out by exposure to the sun and air is
unacceptable and will be rejected.
C. Sod shall be placed in areas as shown on the site plans or as directed by
HCFCD.
D. HCFCD reserves the right to reject any unacceptable sod.
06/09/2020
Harris County Flood Control District
Standard Specifications 02922 - 2/3 Sod
F. Lightly water sod during placement to prevent excessive moisture loss.
G. Immediately after installation of sod, remove extraneous clumps of sod or
plant remnants from adjacent pavement and the finished sod surface.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02922 - 3/3 Sod
SECTION 02923
BROADCAST SEEDING
PART 1 – GENERAL
1.1 SUMMARY
A. When there is not a separate item listed for work in this Section, no
separate measurement and payment is made. Include cost for work under
this Section in the related unit price work.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
1.3 REFERENCES
A. Texas Seed and Plant Certification Act and Standards, Section 62.
B. U.S. Department of Agriculture Rules and Regulations - Federal Seed Act.
1.4 SUBMITTALS
PART 2 – PRODUCTS
2.1 MATERIAL
06/09/2020
Harris County Flood Control District
Standard Specifications 02923 - 1/3 Broadcast Seeding
E. Provide Certified Bermuda grass tested by an accredited seed testing
lab. Only bags with blue tags affixed will be accepted.
PART 3 – EXECUTION
A. HCFCD may not require all of the species listed in each of the seed
plans, some species may be excluded based on site conditions or other
factors.
B. Seed shall be applied in accordance with the following seed plan:
C. Planting dates are approximate, HCFCD will determine which seed to use
prior to start of seeding.
D. Seeding rate for Pure Live Seed (PLS) is used to determine the actual
application rate of bulk seed to apply.
E. To determine PLS- (% germination X % purity/100) ex. 95 X 85 /100=
80.75% PLS
06/09/2020
Harris County Flood Control District
Standard Specifications 02923 - 2/3 Broadcast Seeding
F. To determine quantity of PLS needed per acre (seeding rate / %PLS) =
lbs. of seed needed for application. Ex. 60 lbs. /0.807PLS = 74.34 lbs. of
seed needed per acre.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02923 - 3/3 Broadcast Seeding
SECTION 02925
HYDROMULCH-HYDROSEEDING
PART 1 - GENERAL
1.1 SUMMARY
A. When there is not a separate item listed in the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related unit price work.
B. Measurement and Payment is as noted on the Unit Price Schedule.
1.3 SUBMITTALS
A. Submit, prior to the start of work, the product and manufacturer’s name of
hydro-mulch/soil binder/tackifier to be used.
B. Submit a delivery ticket showing quantity of hydro-mulch/soil
binder/tackifier delivered to each turf establishment project site.
PART 2 - PRODUCTS
2.1 HYDROMULCH
A. Provide mulch that is an Engineered Fiber Matrix (EFM) and conforms to
the following property values when uniformly applied at a rate of 3500
pounds per acre under laboratory conditions.
Property Test Req. Value Req. Value
(physical) Method (English) (SI)
Mass Per Unit ASTM D6566a 11.6 oz./yd² (min.) 393 g/m² (min.)
Thickness ASTM D6525a 0.16 inch (min.) 4 mm (min.)
Ground Cover ASTM D6567a 98% (min.) 98% (min.)
Water Holding ASTM D7367 1100% (min.) 1100% (min.)
Material Color Observed Green Green
Cover Factorb Large Scale 0.05 (max.) 0.05 (max.)
% Effectivenessc Large Scale 95% (min.) 95% (min)
Cure Time Observed 24-48 hrs. 24-48 hrs.
Vegetation ASTM D7322 600% (min) 600% (min)
Yield Calculated 1.82 (min.) 1541 (min.)
Functional Observed Up to 12 months Up to 12 months
Ecotoxicity EPA 2021.0 96-hr. LC50 > 100% 96- hr. LC50> 100%
Biodegradability ASTM D5338 100% (min.) 100% (min.)
06/09/2020
Harris County Flood Control District
Standard Specifications 02925 - 1/2 Hydromulch-Hydroseeding
1. ASTM test methods developed for Rolled Erosion Control Products
and have been modified to accommodate Hydraulically-Applied
Erosion Control Products.
2. Cover Factor is calculated as soil loss ratio of treated surface versus
an untreated control surface.
3. % Effectiveness= One minus Cover Factor multiplied by 100%.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02925 - 2/2 Hydromulch-Hydroseeding
SECTION 02936
PART 1 – GENERAL
1.1 SUMMARY
1.3 REFERENCES
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02936 - 1/3 Fertilizer and Soil Amendments
B. Deliver fertilizer in clean, unopened and undamaged bags.
PART 2 – PRODUCTS
2.1 FERTILIZER
PART 3 – EXECUTION
3.1 GENERAL
3.2 FERTILIZER
06/09/2020
Harris County Flood Control District
Standard Specifications 02936 - 2/3 Fertilizer and Soil Amendments
B. Apply soil amendments/conditioners at the maximum rates listed below for
each product.
1. Gypsum - 2,500 lbs. per acre
2. Sulfur - 300 lbs. per acre
3. Lime - 2,500 lbs. per acre
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02936 - 3/3 Fertilizer and Soil Amendments
SECTION 02938
NON-CYCLICAL MOWING
PART 1 – GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work of this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
PART 3 – EXECUTION
3.1 GENERAL
A. Mow areas including the top of berm, from right-of-way to top of slope,
channel side slopes and channel bottom.
B. Cut grass to a minimum of two (2) inches and not greater than four (4)
inches in height.
C. For mowing prior to seeding, mowers shall be adjusted to the minimum
cutting height of the equipment.
D. Cutting of heavy brush with stems up to three (3) inches in diameter may
be required in areas of dense vegetation.
E. Establish a cutting path to traverse 100 percent of the designated area.
Mowing of any site will not be considered complete for payment until the
entire area has been uniformly cut, including all handwork. It is strongly
recommended that all handwork be completed within three (3) days of
mowing. Recut missed strands of vegetation or areas not uniformly cut at
no additional cost.
F. Cut all vegetation in the bottom of the channel or basin in dry conditions.
Cut vegetation adjacent to wet areas from the toe line extending a
minimum of two (2) feet into the channel or basin bottom, as determined
by the Engineer or his designee. Cut only vegetation growing above the
water surface level.
06/09/2020
Harris County Flood Control District
Standard Specifications 02938 - 1/2 Non-Cyclical Mowing
G. Do not mow when soil conditions cannot support the weight of the
equipment and mowing causes rutting of the soil or slope instability.
H. To avoid damage caused by mowers, leave a six (6) inch vegetated
buffer zone along fence lines and around trees. Use hand trimmers to
clear buffer zones of all undesirable vegetation along fence lines,
drainage interceptor structures, and outfall pipes, adjacent to bridge
guardrails, pilings and other obstructions where mowers are unable to
cut.
I. Use mowing equipment in good operating condition and maintained to
provide a clean cut of vegetation.
J. Equip mower decks with safety chains to prevent damage to property
from flying debris.
K. Do not store equipment within 30 feet of streets during non-working hours.
Store materials and/or equipment on-site in an orderly manner.
L. Repair damage caused by the mowing operation at no additional cost
to the District.
A. Notify the Engineer or his designee, in writing, five (5) working days prior
to the starting of mowing.
B. Notify the Engineer or his designee at the completion of each mowing
activity for an inspection of the finished site.
C. Repair damage caused by mowing operations at no additional cost to the
District.
3.4 CLEANUP
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02938 - 2/2 Non-Cyclical Mowing
SECTION 02940
IRRIGATION
PART 1 – GENERAL
1.1 SUMMARY
1.3 SUBMITTALS
PART 3 – EXECUTION
3.1 GENERAL
06/09/2020
Harris County Flood Control District
Standard Specifications 02940 - 1/2 Irrigation
B. Install the irrigation system per manufacturer’s recommendations.
C. For projects less than five (5) acres, the use of a water truck or
hydromulching equipment, rather than a temporary stationary irrigation
system, is acceptable when approved by the Engineer.
D. Irrigate at intervals to promote and sustain vegetation. Prevent wilting of
vegetation through proper water application frequency and quantity.
E. Implement frequent, shorter applications of water immediately following
seeding and germination to ensure growth.
F. Distribute irrigation water evenly across the irrigated area.
G. Utilize sprinkler heads that apply a fine, even spray over irrigated area.
H. Avoid watering impervious surfaces, including but not limited to, concrete
paving, roadways and buildings.
I. Avoid irrigation practices that create run-off, build-up of hydrostatic
pressures behind structures or ponding of water.
A. Maintain vehicular access throughout the site during progress of the work.
Protect irrigation pipes crossing top of berms and access roads.
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02940 - 2/2 Irrigation
SECTION 02941
HERBICIDE APPLICATION
PART 1 - GENERAL
1.1 SUMMARY
A. Where there is not a separate item listed on the Unit Price Schedule for
work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on the
Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit price
procedures.
1.3 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 02941 - 1/5 Herbicide Application
1.4 APPLICATOR QUALIFICATIONS
PART 2 – PRODUCTS
2.1 MATERIAL
PART 3 – EXECUTION
3.1 GENERAL
A. Notify the District, in writing or via e-mail two (2) business days prior to
applying herbicides.
B. Apply herbicide in accordance with requirements established by:
1. Texas Department of Agriculture
2. United States Environmental Protection Agency (EPA)
3. Harris County General Use Permit requirements
4. In accordance with manufacturer’s label.
C. Follow safety procedures and use safety equipment required by regulatory
agencies and as stated on manufacturer’s product label.
D. Apply herbicide only to areas as shown on the Plans or designated by
the District to control undesirable vegetation, including aquatic areas.
Areas of application may include parts or all the Right-of-Way.
E. Prepare herbicide mixtures with clean, potable water. Do not use water
from channel or basins.
F. Undesirable vegetation will be defined by the District representative and
may include but is not limited to, Alligator weed, Willow, Cattail, Chinese
Tallow, McCartney Rose, Johnson grass, Ragweed, Baccharis, Torpedo
grass, and or other native, invasive species.
G. Make broadcast applications over the top of targeted vegetation per the
manufacturer’s recommended rate needed to provide proper coverage of
treatment area.
06/09/2020
Harris County Flood Control District
Standard Specifications 02941 - 2/5 Herbicide Application
H. Do not apply herbicide if rain is imminent within two (2) hours of
application.
I. Avoid applications of herbicide to areas where desirable vegetation is
established where applicable. Replace desirable vegetation killed by
misapplication or overspray of herbicide at no cost to the District.
J. When clearing sites, achieve 100 percent control of target species, and
re-cut and re-treat target species if new growth appears within 60 days of
first application at no additional cost to the District.
K. For general herbicide applications achieve at least 90 percent control of
target species.
L. Control of target species shall be visible within 14 days after application. If
control has not been achieved, make additional application within 14 days
of notification, or based on manufacturer’s label recommendations.
Additional applications will be made at no additional cost to the District.
M. When clearing sites, or for cut stump applications, apply herbicide within
two (2) hours of cutting tree and brush stumps. Re-cut stumps if
application of herbicide is more than two (2) hours after initial cutting.
1. Treat each stump individually to ensure proper application and dosage
to control the target plant.
2. General area spraying of herbicides is not permitted.
3.2 EQUIPMENT
A. Woody Species
1. Category 1 (HD, LG). High Density, Primarily Large Trees - Areas with
an undesirable species density greater than 60% vegetative cover with
more than 50% of those species being large trees that require the cut
stump method of treatment. Large trees are defined as those greater
than five (5) inches diameter at breast height (dbh). Although these
areas contain primarily large trees, all undesirable species present in
the area shall be treated with appropriate methods as described in Part
3.1, General Execution of this Specification.
2. Category 2 (HD,SM). High Density, Primarily Smaller Trees and
Saplings - Areas with an undesirable species density greater than 60%
vegetative cover with more than 50% of those species being less than
five inches dbh. Although these areas contain primarily smaller trees
and saplings, all undesirable species present in the area shall be
treated with appropriate methods as described in Part 3.1, General
Execution of this Specification.
06/09/2020
Harris County Flood Control District
Standard Specifications 02941 - 3/5 Herbicide Application
3. Category 3 (MD, LG). Medium Density, Primarily Large Trees - Areas
with an undesirable species density greater than 25%, but less than
60%, vegetative cover with more than 50% of those species present
being mature trees. Although these areas contain primarily large trees,
all undesirable species present in the area shall be treated with
appropriate methods as described in Part 3.1, General Execution of
this Specification.
4. Category 4 (MD, SM). Medium Density, Primarily Smaller Trees and
Saplings - Areas with an undesirable species density greater than
25%, but less than 60%, vegetative cover with more than 50% of those
species present being saplings. Although these areas contain primarily
smaller trees and saplings, all undesirable species present in the area
shall be treated with appropriate methods as described in Part 3.1,
General Execution of this Specification.
5. Category 5 (LD, LG). Low Density, Primarily Large Trees - Areas with
an undesirable species density greater than 5%, but less than 25%,
vegetative cover with more than 50% of those species present being
mature trees. Although these areas contain primarily large trees, all
undesirable species present in the area shall be treated with
appropriate methods as described in Part 3.1, General Execution of
this Specification.
6. Category 6 (LD, SM). Low Density, Primarily Smaller Trees and
Saplings - Areas with an undesirable species density greater than 5%,
but less than 25%, vegetative cover with more than 50% of those
species present being saplings. Although these areas contain primarily
smaller trees and saplings, all undesirable species present in the area
shall be treated with appropriate methods as described in Part 3.1,
General Execution of this Specification.
7. Category 7 (Water-based) Areas with undesirable woody species in
standing water or submerged conditions.
8. Category 8 (Tree-Planting Sites) Areas where seedlings have been
planted and require ongoing suppression of competing vegetation
during the tree establishment period.
B. Grass Species Applications
1. Category 1 (Broadcast applications) Open right-of-way with good
access; can be covered with wheeled vehicles for application.
2. Category 2 (Spot applications) Locations with limited access and
right-of-way where wheeled vehicles cannot safely traverse will be
treated by hand applicators.
C. Aquatic Applications
1. Category 1 (Water Based) are applications applied from watercraft
purposed for herbicide applications.
2. Category 2 (Land Based) are applications applied from the bank to
vegetation on the water surface.
06/09/2020
Harris County Flood Control District
Standard Specifications 02941 - 4/5 Herbicide Application
3.4 CLEAN UP AND DISPOSAL
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 02941 - 5/5 Herbicide Application
SECTION 03310
CONCRETE
PART 1 – GENERAL
1.1 SUMMARY
A. Section includes requirements for cast-in-place concrete.
A. Where there is not a separate item listed on the Unit Price Schedule
for work in this Section, no separate measurement and payment is made.
Include cost for work under this Section in the related item listed on
the Unit Price Schedule.
B. Measurement and payment is as noted on the Unit Price Schedule.
C. Refer to Section 01270 - Measurement and Payment for unit
price procedures.
1.3 REFERENCE
06/09/2020
Harris County Flood Control District
Standard Specifications 03310 - 1/10 Concrete
S. ASTM C 39 - Standard Test Method for Compressive Strength of
Cylindrical Concrete Specimens
T. ASTM C 94 - Ready-Mixed Concrete.
U. ASTM C 138 - Unit Weight, Yield, and Air Content (Gravimetric) of
Concrete.
V. ASTM C 143 - Slump of Hydraulic-Cement Concrete.
W. ASTM C 150 - Portland Cement.
X. ASTM C 172 - Sampling Freshly Mixed Concrete.
Y. ASTM C 173 - Air Content of Freshly Mixed Concrete by Volumetric
Method.
Z. ASTM C 231 - Air Content of Freshly Mixed Concrete by Pressure
Method.
AA. ASTM C 260 - Air-Entraining Admixtures for Concrete.
BB. ASTM C 309 - Liquid Membrane-Forming Compounds for Curing
Concrete.
CC. ASTM C 494 - Chemical Admixtures for Concrete.
DD. ASTM C 595 - Blended Hydraulic Cements.
EE. ASTM C 618 - Coal Fly Ash and Raw or Calcined Natural Pozzolan
for Use as a Mineral Admixture in Concrete
FF. ASTM C 685 - Concrete Made by Volumetric Batching and
Continuous Mixing.
GG. ASTM C 1077 - Laboratories Testing Concrete and Concrete
Aggregates f o r Use in Construction and Criteria for
Laboratory Evaluation.
HH. CPMB-100 - Concrete Plant Standards, Part 2 – Plant Control
Systems.
II. CRSI - Placing Reinforcing Bars.
JJ. CRSI MSP-1 - Manual of Standard Practice.
1.4 SUBMITTALS
06/09/2020
Harris County Flood Control District
Standard Specifications 03310 - 2/10 Concrete
F. If requested submit certification from concrete supplier that materials and
equipment used to produce and deliver concrete comply with this Section.
G. Submit Shop Drawings in accordance with ACI 315 and ACI 318, when
required, showing reinforcement type, quantity, size, length, location,
spacing, bending, splicing, support, fabrication details and other pertinent
information.
H. For waterstops, submit product information, including manufacturer’s
description literature, installation instructions and specifications.
I. Submit curing procedures including materials and equipment to be used.
PART 2 – PRODUCTS
A. Cementitious Material:
1. Portland Cement: ASTM C 150, Type I/II or II, unless the use of Type
III is authorized by Engineer; or ASTM C 595, Type IP. For concrete in
contact with sewage, use Type II cement.
2. When aggregates are potentially reactive with alkalis in cement, use
cement not exceeding 0.6 percent alkali content in the form of Na2O +
0.658 K2O.
3. Type “F” fly ash meeting requirements of ASTM C 618 may be used as
mineral admixture in concrete mixture. When fly ash mineral filler is
used, store and inspect in accordance with ASTM C 618. Do not use
fly ash in amounts to exceed 25 percent by weight of cementitious
material in mix design. Cement content may be reduced when strength
requirements can be met. When fly ash is used, “cement” is defined as
cement plus fly ash.
B. Water: Clean, free from harmful amounts of oils, acids, alkalis or
other deleterious substances and meeting requirements of ASTM C 94.
C. Aggregate:
1. Coarse Aggregate: ASTM C 33. Unless otherwise indicated, use the
following ASTM standard sizes: No. 357 or No. 467; No. 57 or No. 67,
No. 7. Maximum size: Not larger than 1/5 of the minimum dimension
between sides of forms nor larger than 3/4 of minimum clear spacing
between reinforcing bars.
2. Fine Aggregate: ASTM C 33.
3. Determine the potential reactivity of fine and coarse aggregate in
accordance with the Appendix to ASTM C 33.
06/09/2020
Harris County Flood Control District
Standard Specifications 03310 - 3/10 Concrete
D. Air Entraining Admixtures: ASTM C 260.
E. Chemical Admixtures:
1. Water Reducers: ASTM C 494, Type A.
2. Water Reducer and Retarder: ASTM C 494, Type D.
3. High Range Water Reducer (Superplasticizer): ASTM C 494, Types F
and G.
F. Prohibited Admixtures: Admixtures containing calcium chloride,
thiocyanate, or materials that contribute free chlorine ions in excess of
0.1 percent by weight of cement.
G. Reinforcing Steel:
1. Use new billet steel bars conforming to ASTM A 615, ASTM A 767,
or ASTM A 775, grade 60 unless otherwise shown on Plans. Use
deformed bars except where smooth bars are specified. When placed
in work, keep steel free of dirt, scale, loose or flaky rust, paint, oil or
other harmful materials.
2. Tie Wire: ASTM A 82. Use 16-1/2 gauge minimum for tie wire unless
otherwise shown on the Plans.
H. Curing Compounds: Liquid membrane-forming compounds conforming to
ASTM C 309, with white or other heat reflecting pigment.
A. Lumber and Plywood: Seasoned and of good quality, free from loose
or unsound knots, knot holes, twists, shakes, decay and other
imperfections, which would affect strength or impair the finished surface of
concrete. Use S4S lumber for facing and sheathing.
B. Formwork: For exposed concrete indicated to receive rubbed finish,
provide form or form- lining surfaces free of irregularities.
C. Form Ties: Metal or fiberglass of approved type with tie holes not larger
than 7/8 inch in diameter.
D. Metal Forms: Clean and in good condition, free from dents and rust,
grease or other foreign material that tend to mar or discolor concrete, in a
gauge and condition capable of supporting concrete and construction
loads without significant distortion. Countersink bolt and rivet heads on
facing sides. Use only metal forms which present a smooth surface and
which line up properly.
06/09/2020
Harris County Flood Control District
Standard Specifications 03310 - 4/10 Concrete
2.4 MEASUREMENT OF MATERIALS
PART 3 – EXECUTION
06/09/2020
Harris County Flood Control District
Standard Specifications 03310 - 5/10 Concrete
concrete. Provide adequate cleanout openings. Before placing concrete,
remove extraneous matter from within forms.
C. Unless otherwise indicated, form outside corners and edges with
triangular 3/4 inch chamfer strips (measured on sides).
D. Remove metal form ties to depth of at least 3/4 inch from surface of
concrete. Do not use pipe spreaders. Remove spreaders which are
separate from forms as concrete is being placed.
E. Immediately before the concrete is placed, wet surface of
forms which will come in contact with concrete.
A. Install conduit and piping as shown on the Plans. Locate and fasten
conduit, piping and other embedded items in forms.
A. Place and consolidate in accordance with ACI 304R and ACI 309R.
B. Give at least 24 hours advance notice to Engineer to permit inspection of
forms, reinforcing steel, embedded items and other preparations for
placing concrete. Place no concrete prior to Engineer’s inspection.
C. Schedule concrete placing to permit completion of finishing operations
in daylight hours. However, if necessary to continue after daylight
hours, light the site as required. If rainfall occurs after placing operations
are started, provide covering to protect the work.
D. Use troughs, pipes and chutes lined with approved metal or
synthetic material. Place concrete without allowing segregation. Keep
chutes, troughs and pipes clean and free from coatings of hardened
concrete. Do not allow aluminum material to be in contact with concrete.
E. Limit free fall of concrete to prevent segregation. Do not deposit large
quantities of concrete at one location so that running or working concrete
along forms is required. Do not jar forms after concrete has taken on initial
set; do not place any strain on projecting reinforcement or anchor bolts.
F. Use tremies for placing concrete in walls and similar narrow or
restricted locations. Use tremies made in sections, provide in several
lengths, so that outlet may be adjusted to proper height during
placement operations.
G. When the weather is hot enough to cause the concrete
temperature to exceed 90 degrees F, employ means, such as
pre-cooling aggregates and mixing water, using ice or placing at night, to
maintain concrete temperature below 90 degrees F.
H. Consolidate each layer of concrete with concrete spading implements
and mechanical vibrators of type and adequate number for the size of
06/09/2020
Harris County Flood Control District
Standard Specifications 03310 - 7/10 Concrete
placement. Apply vibrators to concrete immediately after depositing. Do
not use vibrators to aid lateral flow of concrete. Do not over-
consolidate concrete.
I. When placement of concrete flatwork is stopped unexpectedly, install a
rigid transverse bulkhead, accurately notched for the reinforcing steel and
shaped accurately to the cross section.
J. Handling and Placing Concrete: Conform to ACI 302.1R, ACI 304R and
ACI 309R.
A. Comply with ACI 308. Cure by preventing loss of moisture and rapid
temperature change for a period of seven (7) days when Type I/II, II or IP
cement has been used and for three (3) curing days when Type III cement
has been used.
B. Start curing as soon as free water has disappeared from the concrete
surface after placing and finishing.
C. A curing day is any calendar day in which the temperature is above
50 degrees F for at least 19 hours. Colder days may be counted if air
temperature adjacent to concrete is maintained above 50 degrees F. In
continued cold weather, when artificial heat is not provided, removal of
forms and shoring may be permitted at the end of calendar days equal to
twice the required number of curing days.
D. Formed surfaces not requiring rubbed-finished surface:
1. Cure by leaving forms in place for the full cure period or forms may
be removed after two (2) days and curing compound applied. Keep
wood forms wet during the curing period. Add water as needed for
other types of forms.
2. Soffit Forms: Leave soffit forms and shores in place until concrete
has reached the specified design strength unless a plan for early
removal of forms is submitted by the Contractor and approved by the
Engineer. Any additional material testing required for the early
removal of forms will be responsibility of the Contractor.
E. Rubbed Finish:
1. At formed surfaces requiring rubbed finish, remove forms as soon as
practicable without damaging the surface. Remove forms from
surfaces requiring rubbing only as rapidly as rubbing operation
progresses.
2. After rubbed-finish operations are complete, continue curing formed
surfaces by using either approved curing/sealing compounds or moist
cotton mats until normal curing period is complete.
F. Unformed Surfaces: Cure with approved membrane curing compound
method in accordance with ASTM C 309.
1. After concrete has received a final finish and surplus water sheen
has disappeared, immediately seal surface with a uniform coating of
approved curing compound, applied at the rate of coverage
06/09/2020
Harris County Flood Control District
Standard Specifications 03310 - 8/10 Concrete
recommended by manufacturer or as directed by Engineer. Provide
uniform coverage at a minimum rate of one (1) gallon per 180 square
feet of area.
2. Thoroughly agitate the compound during use and apply by means of
approved mechanical power pressure sprayers equipped with
atomizing nozzles. For application on small miscellaneous items,
hand-powered spray equipment may be used. Prevent loss of
compound between nozzle and concrete surface during spraying
operations.
3. Do not apply compound to a dry surface. If concrete surface has
become dry, thoroughly moisten surface immediately prior to
application. At locations where coating shows discontinuities,
pinholes or other defects, or if rain falls on a newly coated
surface before film has dried sufficiently to resist damage, apply an
additional coat of compound at the specified rate of coverage.
3.7 FINISHING
A. Patch honeycomb, minor defects and form tie holes in concrete surfaces
with cement mortar mixed one (1) part cement to two (2) parts fine
aggregate. Repair defects by removing unsatisfactory material and
replacing with new concrete, keyed and bonded to existing concrete.
Finish to provide a uniform surface between patches and existing
concrete.
B. Apply a broomed finish to all exposed surfaces of interceptor structure
inlets and channel lining. Apply broomed finish in a single, continuous
stroke perpendicular to the channel flow to produce a uniform surface
Apply a rubbed finish to all o t h e r exposed surfaces unless directed
otherwise on the Plans or by the Engineer. After pointing has set
sufficiently, wet the surface and perform first surface rubbing with No. 16
carborundum stone or approved equal. Do not add cement to form surface
paste. Rub sufficiently to bring surface to paste; to remove form marks
and projections; and to produce a smooth, dense surface. Spread or brush
material, which has been ground to paste, uniformly over surface and
allow to reset. In preparation for final acceptance, clean surfaces and
perform final finish rubbing with No. 30 carborundum stone or
approved equal. After rubbing, allow paste on the surface to re-set; then
wash surface with clean water. Leave structure with a clean, neat and
uniform finish.
06/09/2020
Harris County Flood Control District
Standard Specifications 03310 - 9/10 Concrete
3.8 DEFECTIVE WORK
3.10 PROTECTION
END OF SECTION
06/09/2020
Harris County Flood Control District
Standard Specifications 03310 - 10/10 Concrete
2020 Detail Sheets
3 MIN FT. SEE NOTES
DATE APPR
SEE STORM SEWER & 1 AND 2. 3 FT. HARDWARE 15 # ROOFING FELT
2M
RIPRAP DETAIL SHEET CLOTH T.
1F
IN.
5 MIN. IN. FILTER FABRIC
1 FT. HARDWARE 4 IN.
4 IN.
1 FT.
CLOTH
FT
TOP OF CHANNEL LINING IN.
IN.
.
MA
1 FT.
8M 4 IN. DIA. PVC
2 FT. ~
3 FT.
1 FT.
STAIRS TO BE INSTALLED ~ TRIM PVC FLUSH
~
SEE NOTES
~
T
AT LOCATIONS SHOWN 1 AND 2. ~ TO FINISH CONCRETE
CH
ON PLANS. SEE DETAIL.
FT.
1 FT.
T.
1 FT.
1 A. 1F DRAIN GRAVEL
L INE
2 MIN
MA
1 A.
DRAIN GRAVEL 15 # ROOFING FELT
15 # ROOFING FELT
T
"A"
DESCRIPTION
5 MIN. IN.
SECTION
FT.
PLAN
CH
FT. GRADE BEAM-SEE DETAIL
BOTTOM
WIDTH
MID-SLOPE LINING
L
A
INE
TYPE "A" 4 IN. DIA. PVC
HARDWARE CLOTH 4 IN. PVC PIPE
WEEP HOLE (TYP.)
4 IN.
~ 8 MIN. IN. CONC. CHANNEL 15 # ROOFING FELT W/HARDWARE CLOTH
15 # ROOFING FELT
"A"
OVER END.
FT.
~ ~
TOEWALL UPSTREAM ~
~
3 MIN
TOEWALL AT UPSTREAM AND TOEWALL UPSTREAM & DOWNSTREAM.
1 FT.
TYPE "B"
1 FT.
DOWNSTREAM ENDS OF FT. & DOWNSTREAM TYPE "B" WEEP HOLE. FILTER FABRIC SEAL SLAB
~
WEEP HOLE
~
LINING. (SEE TYP. CHANNEL SEE WEEP HOLE DETAILS.
(TYP.)
LINING DETAIL). CL FILTER FABRIC
DRAIN GRAVEL
8 IN X 3 FT MIN
4 IN
.
TOP OF CHANNEL LINING 10 1 FT. 1 FT. DRAIN GRAVEL
FT.
E /
OT SPECIFY REINFORCING
EN
REV
SE STEEL, SEE NOTE 11. 6 IN. 6 IN.
3 MIN
1 FT. 2 FT. 1 FT.
3 FT.
TOEWALL AT TOP OF CHANNEL
A TOP OF BANK LINING
MA
5 MIN INCHES SEE TYP. CONCRETE CHANNEL 3/4" GAP
T
CHANNEL LINING DETAIL. 9 3/4" CONTINUOUS DRAINAGE
(ALLOWS DOWEL GEOTEXTILE TYP.
CH
BOTTOM DOWEL AT GEOCOMPOSITE WITH 8 OZ
C CHANNEL BAR TO MOVE)
L 12" C-C NON-WOVEN GEOTEXTILE.
4 IN
4 IN
FT FT
LIN
SEE NOTES
PROJECT TITLE
PROJECT ID#
BOTTOM WIDTH 1 AND 2.
D/2
4 IN. DIA.
E"
1 A. PVC PIPE 4 IN. DIA. PVC PIPE
20 IN
12 IN
20 IN
12 IN
SMOOTH BAR
D
A"
PILOT CHANNEL ~
1 A. ~ SEAL SLAB
(SEE TABLE C
L
D/2
SEE NOTE 5. 1 FT-6 IN. MIN.
14 IN
12 IN
ONE BELOW)
FT
4 IN
4 IN
1 MIN FT. MATERIAL 1 FT. OR STEEL TUBE
8 MIN IN.
TOP OF CHANNEL
LINING
CONTINUOUS STEEL WEEP HOLE DETAILS
PREPARED:
DETAIL A
APPROVED:
NOTES:
CHECKED:
1. STRUCTURAL CONCRETE FOR CONCRETE CHANNEL LINING AND NONSTRUCTURAL CONCRETE FOR SEAL SLAB SHALL BE IN
ACCORDANCE WITH SPECIFICATION SECTION NO. 03310-CONCRETE.
TYPICAL TRAPEZOIDAL CHANNEL LINING SPECIFY REINFORCING
6 IN. 2. REINFORCING STEEL SHALL BE IN ACCORDANCE WITH SPECIFICATION SECTION NO. 03310-CONCRETE.
STEEL, SEE NOTE 11. 3. EXCAVATION AND BACKFILL FOR CONCRETE CHANNEL LINING SHALL BE IN ACCORDANCE WITH SPECIFICATION SECTION NO.
FILTER FABRIC
CONCRETE LINING 1 FT. 02316-STRUCTURAL EXCAVATING AND BACKFILLING.
SEE WEEPHOLE
THICKNESS 5 MIN IN. 4. RIPRAP SHALL BE IN ACCORDANCE WITH SPECIFICATION SECTION NO. 02378-RIPRAP AND GRANULAR FILL.
NOTE d.
5 MIN IN. SEE TYP. STAIR DETAIL 5. A NON-REINFORCED 4 INCH MINIMUM NONSTRUCTURAL CONCRETE SEAL SLAB IS REQUIRED BENEATH THE BOTTOM OF
MA
RE
CHANNEL LINING DETAIL. CONSTRUCTION JOINT CONCRETE CHANNELS.
HE
TC
BOTTOM WIDTH PILOT CHANNEL WIDTH 6. STRUCTURAL CONCRETE GRADE BEAMS SHALL BE INSTALLED TRANSVERSELY AT 20 FOOT MAX. CENTERS ON CONCRETE
ES
HL
BW < 12 FT FLAT BOTTOM LINED CHANNELS WITH BOTTOM WIDTHS EQUAL TO OR GREATER THAN 20 FEET.
GO
BW = 12 FT - 20 FT 6 FT REINF. STEEL 4 FT. MIN. 7. JOINTS:
1 A. CL 5 BARS 5 INCHES
GO
INE
BW > 20 FT 8 FT SYMMETRICAL ALL AROUND A. PLACE CONSTRUCTION JOINT IN CONCRETE LOW-FLOW, TRAPEZOIDAL BOTTOM SECTIONS AND SLOPES AT 20 FOOT
2 IN. ABOUT CL O.C. (EACH LAYER)
FT
LO
1 A. ~
MIN., SPACING CONTINUOUSLY THROUGH CHANNEL LINING.
TYP.
"A
6 IN.
FT.
D
TRIM PIPE FLUSH
IN
B. PLACE EXPANSION JOINT IN CONCRETE LOW-FLOW, TRAPEZOIDAL BOTTOM SECTIONS, AND SLOPES AT 60 FOOT MAX.
AN
"
CL CHANNEL
2M
N
VARI FT. TYPE B WEEP HOLE
IO
LINING
TY
8. CEMENT STABILIZED SAND SHALL BE PROVIDED AND PLACED IN ACCORDANCE WITH SPECIFICATION SECTION NO. 02321
4 MIN FT
4
AT
BOTTOM WIDTH AT 3 IN. FT. O.C. -CEMENT STABILIZED SAND.
RM
SEE WEEP HOLE 9. DELETE 2 FT FLAT EDGE WHEN LINING IS BELOW TOP OF BANK. SEE MID-SLOPE LINING DETAIL.
5 IN
SEE NOTE 12
FO
DETAILS. 10. UPSTREAM AND DOWNSTREAM TOE WALL 3 FOOT MIN. DEPTH AT BOTTOM OF SLOPE AND 8 INCHES THICK.
PILOT CHANNEL
.
IN
SEE DETAIL B. 11. MINIMUM #4 BARS (GRADE 60) AT 12 INCHES ON CENTER EACH WAY.
NY
(SEE TABLE ABOVE) ~
12. VARIES BASED ON SIDE SLOPE. MINIMUM 1 FOOT VERTICAL AT TOE OF SLOPE.
PA
8 MIN IN. 8 IN. 13. FOR RCP OUTFALLS 48 INCHES DIA. AND LARGER, USE HEADWALL/WINGWALL DETAIL ON SHEET
M
CO
SEE NOTE 8. 14. FOR STRUCTURAL BACKFILL MATERIAL PER SPECIFICATION SECTION 2316, USE CONCRETE COARSE AGGREGATE ASTM C33
DETAIL B EXTENT OF SPECIFY REINFORCING SIZE NO. 467. LIMESTONE AND RECYCLED CONCRETE NOT ALLOWED.
4 FE FT.
OPTIONAL 8 MIN IN. USE IN THE END PRODUCT IN ACCORDANCE WITH RULE 137.33 (b) AND (c) OF THE TEXAS BOARD OF PROFESSIONAL ENGINEERS.
6 IN.
6"
SEE NOTE 5.
~
DATE APPR
10 FT. TYP. 12 FT. TYP. 10 FT. TYP.
OR MATCH
1 FT.
8 IN.
8 IN. 8 IN. 5 FT. 1 FT. OFFSITE SWALE 3 FT. 4 FT. 3 FT.
8 IN.
8 IN. 8 IN. SLOPE 8 IN. 1 FT.
4 FT. 6 IN.
SEE NOTE 10.
1.5:1
8 IN.
SEE NOTE 10.
1.5 :1
SEE NOTE 10.
VARIES
10 FT. TYP.
10 FT. TYP.
VARIES
11 FT. TYP.
VARIES
10 FT. TYP.
DESCRIPTION
SLOPE
AS
NECESSARY
A 2:1 A B 2:1
B C C
D D
1.5:1
4 FT. 6 IN.
1.5 :1
#4 BARS 3:1 3:1
8 IN.
ON 8 IN
CENTERS VARIES
1 FT. #4 BARS
1 FT. 8 IN.
8 IN.
ON 8 IN.
8 IN.
#4 BARS 1 FT. 1 FT.
CENTERS
ON 8 IN. SEE NOTE 7.
1 FT. 8 IN.
8 IN.
CENTERS 5 FT. TYP. 6 FT. TYP.
OR MATCH
OFFSITE SWALE
PLAN PLAN PLAN SLOPE PLAN
ROW
10 FT. TYP. 6 IN.
REV
ROW
SEE NOTE 10 SEE NOTE 10 SEE NOTE 10 SEE NOTE 10 3 FT. 4 FT. 3 FT.
ROW
12 FT. TYP. 12 FT. TYP.
10 FT. TYP. 1 FT. 1 FT.
ROW
2 FT.
TYP.
MAX.
1 FT. 4 FT. 6 IN.
1 FT.
5 FT.
TYP.
2 FT.
SEE NOTE 5. 6 IN. SEE NOTE 5. SEE NOTE 5. 5 IN.
1 FT.
2 FT.
TYP.
SLOPE SLOPE
VARIES
TYP.
2 FT.
VARIES
5 FT.
MAX
MAX.
3 FT.
OFFSITE DITCH
2 FT. 6 IN.
8 IN.
FLOWLINE
MAX.
8 IN.
4 FT.
8 IN. 2 FT.
8 IN. 6 IN.
2 FT.
TYP.
TYP.
2 FT.
PROJECT TITLE
8 IN.
PROJECT ID#
IN. ER
5 IN.
DETAILS
5 IN.
2 F COU 8 IN. IN. ER 8 IN. 2 F COU SAND (3 FT AROUND BOX)
ND SEE NOTE 2. T. M PL A ND 8 IN.
BA 2 F COU B
N D SEE NOTE 2. GROUT
BA
6 IN.
SEE NOTE 2. SEE NOTE 2. NOTE:
12 IN.
N. SECTION SECTION SECTION SECTION WALLS AND FLOOR SHALL BE
MI
5F
T. A M IN. B T.
MI
N. C D 6 IN. REINFORCED STRUCTURAL
T. 5F CONCRETE OR WALLS MAY BE
5F
8 IN. CONCRETE BRICK
TYPICAL OFFSITE DITCH TYPICAL BACKSLOPE COMBINATION BACKSLOPE & URBAN BACKSLOPE CONSTRUCTION
INTERCEPTOR STRUCTURE INTERCEPTOR STRUCTURE OFFSITE DITCH INTERCEPTOR STRUCTURE INTERCEPTOR STRUCTURE
(42 INCH MAX.) (24 INCH & 30 INCH ONLY) (42 INCH MAX.) (24 INCH ONLY)
USE BELL & SPIGOT JOINT NOTES:
CHANNEL 5 FT. MIN. SOIL AND WATER TIGHT
BACKSLOPE 5 FT. MIN.
BOTTOM SWALE INTO SLOPE
2 FT. MIN. 1. INTERCEPTOR OUTFALL PIPES WITHIN THE HCFCD RIGHT-OF-WAY SHALL BE CMP OR HDPE PIPE IN
INTO SLOPE ACCORDANCE WITH SPECIFICATION SECTION 02642- CORRUGATED METAL PIPE, HIGH DENSITY
BAND 1.5 O.D. + 12 IN. MIN.
COUPLER POLYETHYLENE (HDPE) PIPE IN ACCORDANCE WITH SPECIFICATION SECTION 2505-HIGH DENSITY
POLYETHYLENE, OR APPROVED EQUAL. USE TABLE ON STORM SEWER AND RIPRAP DETAILS SHEET FOR
CORRUGATED GALVANIZED STEEL PIPE THICKNESS.
12 IN.
MIN.
INTERCEPTOR
2. PROVIDE AND PLACE CEMENT STABILIZED SAND IN ACCORDANCE WITH SPECIFICATION SECTION
E STRUCTURE
ROW
6 IN.
CL 03310-CONCRETE.
PREPARED:
APPROVED:
CHECKED:
NEW PIPE 1'-3" 1'-3" 5. INTERCEPTOR STRUCTURES:
6 IN.
MIN. MIN. a. ADJUST LENGTH AND WIDTH IN FIELD AS NECESSARY.
b. 2-FEET DEEP X 8-INCH WIDE TOE ALL AROUND THE STRUCTURE.
CMP OR HDPE PIPE
SEE NOTE 1. E SEE NOTE 2. c. STEEL REINFORCING-#4 BARS (GRADE 60) AT 12 INCHES ON CENTER
CEMENT STABILIZED EACH WAY.
10° - OUTFALL
TO CHANNEL
CMP BAND HIGH DENSITY CORRUGATED
POLYETHYLENE (HDPE) SMOOTH SEE NOTE 2. SAND ALL AROUND PIPE. d. ANY INTERCEPTOR OUTFALL PIPE LARGER THAN MAXIMUM SIZE
SEE NOTE 2. INDICATED REQUIRES A SEPARATE DETAIL.
0° - OUTFALL TO COUPLER DETAIL SEE
LINED PIPE.
e. MATCH TOP OF CONCRETE WITH NATURAL GROUND.
RE
DETENTION BASIN 6. CONCRETE PILOT CHANNEL
NOTE 9.
HDPE PIPE
HE
SEE NOTE 8.
BEDDING HDPE a. 1.5 FEET DEEP X 8-INCH WIDE TOE ALL AROUND THE STRUCTURE.
ES
b. STEEL REINFORCING - #4 BARS (GRADE 60) AT 12 INCHES ON CENTER EACH WAY.
COUPLER DETAIL
GO
PLAN EXISTING PIPE PIPE DETAIL c. MATCH TOP OF CONCRETE WITH BOTTOM OF DETENTION BASIN.
ROW
1/2 IN.
O
5 FT. 6 IN. (CMP, RCP, OR 7. CONCRETE PAD AROUND URBAN BACKSLOPE INTERCEPTOR: PAID FOR AS CONCRETE INTERCEPTOR
G
6 IN.
MIN.
MAX.
LO
HDPE) STRUCTURE PER UNIT PRICE SCHEDULE. TYPE "A" INLET BOX, COH DWG. NO. 2084-08 WITH GRATE TOP,
CL BACKSLOPE SWALE 12 IN.
D
VULCAN FOUNDRY COMPANY, V-4880-1 OR APPROVED EQUAL, APPROX. 473 SQ.IN. OPENING. PAID 2632-05
AN
6 IN. FELT
10 FT. TYP. 8. BACKSLOPE SWALE AND INTERCEPTOR STRUCTURE ELEVATIONS AND LOCATIONS SHOWN ON THE PLANS
N
ARE APPROXIMATE. FINAL ELEVATIONS AND LOCATIONS SHALL BE FIELD VERIFIED BY THE ENGINEER
TIO
3 FT. 4 FT. 3 FT.
PRIOR TO INSTALLATION.
A
8 IN.
RM
FABRICATED 9. STRUCTURAL CONCRETE WITH #4 BARS (GRADE 60) 12 INCH O.C. EACH WAY, 3 ROWS MIN. EACH WAY. -
8 IN. 1 FT.
ELBOW
FO
FOR COLLARS ONLY. WAIT A MINIMUM OF 24 HOURS AFTER PLACING CONCRETE TO BACKFILL.
IN
10. EPOXY "CLEAN WATER CLEAR CHOICE" LOGO BUTTON ON INTERCEPTORS. LOCATION TO BE DETERMINED
G
NY
BY THE ENGINEER.
PA
6 IN. MIN.
M
SEE NOTE 2.
CO
ALL AROUND
BACKSLOPE (TYP.)
INTERCEPTOR
EXISTING PIPE THIS DETAIL SHEET HAS BEEN PREPARED FOR USE ON HCFCD PROJECTS OR PROJECTS TO BE
SHOWN. SEE
SLOPE 6 IN.
PLANS FOR
6 IN. MIN.
D D MAINTAINED BY THE HCFCD WHEN COMPLETED BY OTHERS. AN ENGINEER WHO INCORPORATES THE
BAND COUPLER. DESIGNATED 2:1 2:1 DETAILS ON THIS SHEET BECOMES RESPONSIBLE FOR ITS USE IN THE END PRODUCT IN ACCORDANCE
20 FT. (MIN.) SEE BAND STRUCTURE OR WITH RULE 137.33 (b) AND (c) OF THE TEXAS BOARD OF PROFESSIONAL ENGINEERS.
SEE TABLE
G COUPLER DETAILS. AS DIRECTED BY
ENGINEER.
CMP OR HDPE PIPE
BELOW SECTION
E SEE NOTE 1.
1 FT. 8 IN.
8 IN.
PLAN
6 IN.
MIN.
1 FT.
DATE APPR
TOPSOIL OVER RIPRAP BEND COUPLER TOP OF TIMBER BENT
10 FT. MIN. INTO SLOPE
5 FT. 2 FT. MIN.
BAND
EXPOSED ABOVE SLOPE
A 4 IN. X 8 IN.
TIMBER
MIN. INTO SLOPE 6 FT. 3/4" DIA. GALVANIZED
TIMBER BENT FOR OUTFALLS 48 IN. DIA. COUPLER SEE TYPICAL
CONCRETE MAX. 1 FT. MIN. OF RIPRAP BOLTS WITH OVERSIZE
AND LARGER. SEE NOTE 4 AND
2D
~ A
CMP SEE NOTE 2.
1D
PIPE DIA.
VARIES
DESCRIPTION
1D
4 IN. X 12 IN.
ROW
SEE NOTE 7. ~ EXISTING PIPE SEE NOTE 7. TIMBER
~
D/2 (TYP.) SEE NOTE 3.
SEE NOTE 3. ~ ~
SEE NOTES
1 & 6. CMP OR HDPE
CMP BAND A
12 FT.
SEE NOTE 2.
SLOPE 6 IN. SEE NOTE 3. A
8 IN. DIA. PILE GALVANIZED
12O° COUPLER DETAIL 20 FT. (MIN.)
FABRICATED
8 IN. DIA. PILE BOLT
CHANNEL D EXISTING ELBOW
PIPE 6 IN. SEE NOTE 6. TYPICAL SECTION SEE NOTE 4.
BOTTOM
MIN. SECTION ELEVATION
TIMBER BENT DETAIL FOR 48-INCH CMP;
PIPE ADJUSTMENT DETAIL 36-INCH HDPE AND LARGER OUTFALLS
24-INCH TO 42-INCH DIAMETER
REV
30° - OUTFALL MANHOLE
6 IN.
MIN.
TO CHANNEL
0° - OUTFALL TO WRAP JOINT WITH 1'-3" 1'-3"
6 IN.
PLAN DETENTION BASIN 30# X 12 IN.
~
MIN. MIN.
3 FT. MIN. REMOVE EXISTING PIPE ASPHALT FELT. USE BELL & SPIGOT
MAINTENANCE BERM SEE NOTE 3. JOINT SOIL AND WATER
10 FT. MIN. INTO SLOPE
NEW PIPE
~ TIGHT
CEMENT STABILIZED SAND
ROW
RIPRAP DETAILS
48 IN. DIA. AND LARGER. SEE 1.5 O.D + 12 IN. MIN.
PROJECT TITLE
PROJECT ID#
TIMBER BENT DETAIL. SEE NOTE 4.
BEDDING RCP FABRICATED
1/2 IN.
12 IN.
SEE NOTE 9. ELBOW EXISTING PIPE
A
MIN.
2 FT.
MAX.
MIN & CMP DETAIL (CMP, RCP, OR
6 IN.
MIN.
1 FT. HDPE)
SEE NOTE 6. EXISTING PIPE
A 12 IN.
FELT
SEE NOTE 7. CMP OR HDPE
6 IN. MIN. ALL AROUND
SEE NOTE 2.
6 IN.
(TYP.)
~ SEE NOTE 7. ~
~ EXISTING PIPE
SEE NOTE 3. D
CONCRETE EXISTING
SEE NOTE 3. SEE TYPICAL CONCRETE
T A ~
COLLAR DETAIL.
PIPE
SEE NOTE 3. CEMENT STABILIZED SAND
6D OR TOP OF SLOPE 6 IN.
20 FT. (MIN.) SLOPE 6 IN.
A HIGH DENSITY CORRUGATED
ALL AROUND PIPE SEE NOTE 3.
PIPE ELEVATION ON
OPPOSITE BANK, 20 FT. (MIN.) ~ POLYETHYLENE (HDPE)
SEE NOTE 6. FABRICATED ELBOW SMOOTH LINED PIPE.
WHICHEVER IS SMALLER.
SECTION
TIMBER BENT FOR OUTFALLS 48 IN.
SECTION SEE NOTE 8. HDPE PIPE BEDDING HDPE
DIA. AND LARGER. SEE TIMBER
COUPLER DETAIL PIPE DETAIL
TYPICAL STORM SEWER OUTFALL BENT DETAIL. PIPE ADJUSTMENT DETAIL CONCRETE COLLAR
STRUCTURE LAYOUT 48-INCH AND LARGER DIAMETER DETAIL
NOTES:
1. INSTALL RIPRAP EROSION PROTECTION IN GRASS LINED CHANNELS AND DETENTION BASINS FOR
20 MIN. FT. ANY SIZE STORM SEWER PIPE AND TREATMENT PLANT OUTFALL, DIMENSIONED AS SHOWN IN
SLOPE MIN.
SEE NOTE 6. 2. STORM SEWER OUTFALL PIPES WITHIN THE HCFCD RIGHT-OF-WAY SHALL BE CMP OR HDPE IN
PREPARED:
FT.
APPROVED:
C CHANNEL
CHECKED:
L ACCORDANCE WITH SPECIFICATION SECTION 02642-CORRUGATED METAL PIPE, HIGH DENSITY
SLOPE MIN.
T
1/3 UP
POLYETHYLENE PIPE, OR APPROVED EQUAL. USE TABLE BELOW FOR CORRUGATED GALVANIZED
FT.
STEEL PIPE.
~ C CHANNEL
L
PIPE OUTFALL IN CHANNELS 3. PROVIDE AND PLACE CEMENT STABILIZED SAND IN ACCORDANCE WITH SPECIFICATION SECTION
NO. 02321-CEMENT STABILIZED SAND.
B 4. TIMBER BENTS SHALL BE IN ACCORDANCE WITH SPECIFICATION SECTION 02464-TIMBER BENTS.
BOTTOM WIDTH PIPE OUTLET INVERT 5. EXCAVATION, FILL, AND BACKFILL FOR STORM SEWER OUTFALLS SHALL BE IN ACCORDANCE WITH
2T
RE
SPECIFICATION SECTION 02316- STRUCTURAL EXCAVATING AND BACKFILLING.
6 FEET ≤ BW ≤ 20 FT 1 FOOT ABOVE FLOWLINE *
HE
6. RIPRAP SHALL BE PLACED IN ACCORDANCE WITH SPECIFICATION SECTION 02378-RIPRAP AND
C C
ES
GRANULAR FILL. FILL RIPRAP VOIDS AND BURY RIPRAP A MINIMUM OF 6 INCHES WITH TOPSOIL ON
20 FEET < BW ≤ 60 FT AT TOE OF SLOPE *
GO
T SIDE SLOPE AS DIRECTED BY THE ENGINEER.
7. IN DETENTION BASINS, SET FLOWLINE OF OUTFALL AT TOE OF THE SLOPE OR FLOWLINE OF PILOT
GO
BW > 60 FT AT TOE OF SLOPE *
~ CHANNEL. IN CHANNEL, USE ELEVATION INDICATED IN THE PIPE OUTFALL IN CHANNELS TABLE.
LO
2T STRUCTURAL CONCRETE #4 BARS (GRADE 40) 12 INCH O.C. EACH WAY - FOR COLLARS ONLY. WAIT
* OR 1 FOOT ABOVE NORMAL 8.
D
AN
WATER LEVEL, WHICHEVER IS A MINIMUM OF 24 HOURS AFTER PLACING CONCRETE TO BACKFILL.
N
HIGHER 9. FOR RCP OUTFALL IN GRASS LINED CHANNELS AND DETENTION BASINS, USE HEADWALL/
IO
SLOPE MIN.
AT
1/3 UP
RM
AND DETENTION BASINS , SEE HCFCD CONCRETE CHANNEL LINING DETAILS.
FT.
FO
IN
Y
AN
THIS DETAIL SHEET HAS BEEN PREPARED FOR USE ON HCFCD PROJECTS OR PROJECTS TO
CORRUGATED GALVANIZED STEEL PIPE (TYPE I)
MP
B BE MAINTAINED BY THE HCFCD WHEN COMPLETED BY OTHERS. AN ENGINEER WHO
CO
2-2/3" X 1/2" CORRUGATION 3" X 1" & 5" X 1" CORRUGATION INCORPORATES THE DETAILS ON THIS SHEET BECOMES RESPONSIBLE FOR ITS USE IN THE
T PIPE DIA. MIN. FILL * SHEET THICKNESS MIN. FILL* SHEET THICKNESS END PRODUCT IN ACCORDANCE WITH RULE 137.33 (b) AND (c) OF THE TEXAS BOARD OF
NOTE: C CHANNEL
TOPSOIL OVER RIPRAP L PROFESSIONAL ENGINEERS.
T (MAT THICKNESS) (in.) (in.) gage (in.) (mm) (in.) gage (in.) (mm)
PLAN 18" MIN. GRADE 1 SEE NOTE 6.
24 12 16 .064 1.63 - - - -
24" MIN. GRADE 2
T
20 MIN. FT.
- - - -
SLOPE MIN.
30 12 16 .064 1.63
1/3 UP
36 12 16 .064 1.63 - - - -
FT.
T
42 12 16 .064 1.63 12 16 .064 1.63
48 12 16 .064 1.63 12 16 .064 1.63
2T
24 IN.
MIN.
NOTE: PROP. TOP
CSN
1'-6"
2. PROVIDE STAPLES PER SPECIFICATION
CONSTRUCT IN ACCORDANCE WITH OF SLOPE
SECTION NO. 02922-SOD.
HCFCD SPECIFICATION SECTION
DESCRIPTION
OW 01580 - PROJECT SIGNS. SEE DETAIL "A"
FL 3. SOD ROLL AS SHOWN IN DETAIL "C"
OW
SPACING FL EQUIVALENT TO TWO ROWS OF SOD
6 FT. MAX FOR REINFORCED FENCE. PROP. TOE PANELS.
OF SLOPE
STAGGERED MIN. TWO ROWS 4. PLACE TWO ROWS OF SOD PANELS ALONG
3. ATTACH SILT FENCE FABRIC TO
WIRE FENCE AND EXTEND INTO
4. BACKFILL AND COMPACT THE
EXCAVATED SOIL.
D SOD PANELS (TYP.) EDGES OF CONCRETE PAVING AND
STRUCTURES WHERE SOIL IS DISTURBED
THE TRENCH. PLAN EXCEPT BELOW THE NORMAL WATER SURFACE.
STAGGERED SOD
A PANELS (2 MIN.) 48 IN. SOD
MIN.
1'-0"
ROLLS
SOD SOD
SOD SOD
24 IN.
24 IN.
MIN.
REV
STAPLES "U" STAPLES
SEE DETAIL "B".
FL
OW O W CSN HOLDER DETAIL "A" DETAIL "B" 45°
FL 24 IN. 48 IN.
"U" STAPLES
PROP. TOE OF X.
. MA
A SWPPP / BMP SIGN AND CONSTRUCTION SLOPE OR NORMAL
20 F
T
PROP. TOP OF SLOPE DETAIL "C"
STORMWATER POLLUTION
WATER SURFACE
EXTEND SILT FENCE FABRIC .M AX.
SITE NOTICE HOLDER DETAILS 2 0 FT
PREVENTION DETAILS
INTO TRENCH. FOUR ROWS
WIRE OR PLASTIC X.
. MA STAGGERED
PROJECT TITLE
T SOD
20 F
PROJECT ID#
GRID MESH SOD PANELS
4 IN.
6 IN.
ROADWAY
12 IN.
R R
TU TO
EXISTING
SOD
SOD
U EP
FLOW FLOW
SOD
SOD
SOD
50 FT. MAX.
SOD
GROUND 50 FT. MAX.
R C
SOD
SOD
ST TER
C
SILT FENCE FABRIC WHERE NO BACKSLOPE SWALE
IN
EXISTS OR FOR PAVED CHANNEL,
PLACE A DOUBLE ROW OF SOD
SECTION
ROADWAY
SOD
PANELS AT TOP OF SLOPE.
VARIES
A 20 FT. SOD
APPROVED:
PREPARED:
FLOWLINE
S:\Operations\PROJECTS\2020 Standard Detail Sheets\STORMWATER POPULATION PREVENTION DETAILS\Stormwater Pollution Prevention Details.dwg
TOE OF SLOPE
CHECKED:
4. TYPE 4 (GABION)
a. HEIGHT - 30 INCHES (MINIMUM). MEASURE VERTICALLY FROM EXISTING GROUND TO TOP OF FILTER DAM.
b. TOP WIDTH - 2 FEET (MINIMUM).
5. TYPE 5. AS SHOWN ON THE PLANS.
B. CONSTRUCT FILTER DAMS ACCORDING TO THE FOLLOWING CRITERIA UNLESS SHOWN OTHERWISE ON THE PLANS.
TOE OF SLOPE
B 3 FT. 4 FT. 3 FT.
1. TYPE 2 AND 3 FILTER DAMS: SECURE WITH 20 GAUGE GALVANIZED WOVEN WIRE MESH WITH 1 INCH
C SEE NOTE B.6. 6 IN.
DEPRESS CENTER AREA WIRE MESH
DIAMETER HEXAGONAL OPENINGS.
(SEE NOTE B.1.) 2. GRANULAR FILL:
a. PLACE ON MESH TO HEIGHT AND SLOPES SHOWN ON PLANS OR AS SPECIFIED BY THE ENGINEER.
MIN.
1 FT
6 6
C 1 1 b. 3-5 INCHES FOR ROCK FILTER DAM TYPES 2, AND 4.
REFER TO GRANULAR FILL IN SPECIFICATION SECTION NO. 02378-RIPRAP AND GRANULAR FILL.
ILE
TEXT 3. WIRE MESH: FOLD AT UPSTREAM SIDE OVER GRANULAR FILL AND TIGHTLY SECURE TO ITSELF ON THE
GEO SEE NOTE B.6. DOWNSTREAM SIDE USING WIRE TIES OR HOG RINGS.
GRANULAR FILL 4. IN STREAMS: SECURE OR STAKE MESH TO STREAM BED PRIOR TO AGGREGATE PLACEMENT.
B 5.
6.
SEE SPECIFICATION SECTION NO. 02364-FILTER DAMS.
EMBED ONE FOOT MINIMUM INTO SLOPE AND AT SLOPE RAISE ONE FOOT HIGHER THAN CENTER OF
DEPRESSED AREA.
PLAN
GEOTEXTILE NOTES: SEE GEOTEXTILE
NOTES
IN-CHANNEL FILTER DAM MIN. AOS SIEVE NO. 120 MIN SECTION
MAX. AOS SIEVE NO. 50 MAX C
WEIGHT OZ/SY 4 0Z. MIN
B PROJECT
FLOWLINE
2 FT. MIN. THIS DETAIL SHEET HAS BEEN PREPARED FOR USE ON HCFCD PROJECTS OR PROJECTS TO BE MAINTAINED BY THE
HCFCD WHEN COMPLETED BY OTHERS. AN ENGINEER WHO INCORPORATES THE DETAILS ON THIS SHEET BECOMES
RESPONSIBLE FOR ITS USE IN THE END PRODUCT IN ACCORDANCE WITH RULE 137.33 (b) AND (c) OF THE TEXAS
WIRE MESH BOARD OF PROFESSIONAL ENGINEERS.
PROPOSED
OUTFALL GRANULAR FILL OR EXISTING
FLOWLINE
E E
6 IN.
TIL IL
X XT
TOE OF SLOPE TE E SEE NOTE B.6.
O OT
GE GE
PIPE
9900 Northwest Freeway
Houston, Texas 77092
PLAN
ONLY APPLIES FOR
DETENTION BASIN
B
FD-TYPE SHEET NUMBER
OUTFALL PIPE