The document outlines the specifications for earthworks materials and construction for the Dolphin Project's Upstream and Compression Facilities in Ras Laffan, Qatar. It includes details on applicable codes, fill materials, construction requirements, and testing standards. The document is a revision history and serves as a guideline for ensuring compliance with local and international standards during the construction phase.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views12 pages

Dol 0000 CSP 00004

The document outlines the specifications for earthworks materials and construction for the Dolphin Project's Upstream and Compression Facilities in Ras Laffan, Qatar. It includes details on applicable codes, fill materials, construction requirements, and testing standards. The document is a revision history and serves as a guideline for ensuring compliance with local and international standards during the construction phase.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

DOLPHIN PROJECT Contractor’s Job Code:

0-3356-20

UPSTREAM AND COMPRESSION


FACILITIES
Contractor Document. No.
S-000-3112-002 <Z07>

Company Document No. DOL-0000-CSP-00004

Document Class. 2

Area: Multi Area

Discipline: CIVIL

Document Type: Specification

Commitment Number: UCB 15-01

Document Title:

EARTHWORKS MATERIALS AND CONSTRUCTION

As-Built

Issue
Rev. Purpose/Description of Revision Prepared Reviewed Approved Company
Date

C04 15MAY04 REVISED AS PER DEL-JGC-0050 AND R.Nishio M.Kitamura T.Mastuoka N/A
RELEASED FOR CONSTRUCTION
C05 14JUN04 RE-ISSUED AS PER DEL-JGC-0110 R.Nishio M.Kitamura T.Mastuoka N/A

C06 04APR05 ADDED SLOPE PROTECTION DETAILS R.Nishio M.Kitamura T.Mastuoka N/A

Z07 02JUN07 As-Built G. Vibar K. Kakuda Tsumuraya

_ __
__ RA| © This document is the property of Dolphin Energy Ltd. No part of this document may be reproduced or transmitted in any form or by any means, or used for any
purpose other than that which it is specifically furnished without the written consent of Dolphin Energy Ltd.

I N D __|
File Name:09004ed580465198_--_A4_--_.doc 1 of 12
||___ N-20
11-JUBUILT
AS
07
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

REVISION HISTORY

REV DATE DESCRIPTION

A01 25NOV02 ISSUED FOR REVIEW

N02 12MAR03 ISSUED FOR BID AFTER INTEGRATION OF DEL COMMENTS

R03 30MAR04 ISSUED FOR REVIEW (EPC PHASE)

REVISED AS PER DEL-JGC-0050 AND RELEASED FOR


C04 15MAY04
CONSTRUCTION

RE-ISSUED AS PER DISCUSSION REGARDING COMMENT ON


C05 14JUN04
DEL-JGC-0110

ADDED SLOPE PROTECTION DETAILS FOR EARTH MOUND UNDER


C06 04APR05
SLUG CATCHER

Z07 02JUN07 As-Built

Note:
A revision line in the right hand margin donates revisions.

_ __
__ RA|
I N D __| 2 of 12

||___ File
N
07 09004ed580465198_--_A4_--_.doc
-20Name:
11-JUBUILT
AS
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

Contents
1 SCOPE.................................................................................................................................................... 4

2 APPLICABLE CODES, SPECIFICATIONS AND STANDARDS .......................................................... 4


2.1 COMPANY General Specification................................................................................................... 4
2.2 DOLPHIN Project Documents ......................................................................................................... 4
2.3 Local National Standards and Regulations ..................................................................................... 5
2.4 International Standards (Major Codes and Standards)................................................................... 5
2.5 Order of Precedence ....................................................................................................................... 5
2.6 Site Conditions ................................................................................................................................ 6
3 FILL MATERIALS .................................................................................................................................. 6
3.1 Fill Type A........................................................................................................................................ 6
3.2 Fill Type B........................................................................................................................................ 7
3.3 Fill Type C ....................................................................................................................................... 7
4 WORKS .................................................................................................................................................. 8
4.1 Preliminary....................................................................................................................................... 8
4.2 Demolitions...................................................................................................................................... 8
4.3 Clearance of Vegetation.................................................................................................................. 8
4.4 Stripping of Topsoil.......................................................................................................................... 8
4.5 Excavation ....................................................................................................................................... 8
4.6 Soil Improvement ............................................................................................................................ 9
4.7 Stockpiling of Excavated Soil .......................................................................................................... 9
4.8 Disposal of Excavated Soil.............................................................................................................. 9
4.9 Management of Surface and Underground Water .......................................................................... 9
4.10 Fill .................................................................................................................................................... 9
5 SPECIFIC ITEMS ................................................................................................................................. 10
5.1 Earthworks for Fences .................................................................................................................. 10
5.2 Roads ............................................................................................................................................ 10
5.3 Underground Networks-Trenches ................................................................................................. 10
5.4 Foundations................................................................................................................................... 10
5.5 Tank Foundations and Dikes......................................................................................................... 10
5.6 Platform ......................................................................................................................................... 10
5.7 Protection of Slopes ...................................................................................................................... 10
5.8 Marine Works for LPG Tanks (out of Scope) ................................................................................ 11
6 CONTROLS AND TOLERANCES ....................................................................................................... 11
6.1 Tests on Fill Materials at Source ................................................................................................... 11
6.2 Methods......................................................................................................................................... 11
6.3 Frequency of Tests........................................................................................................................ 12
6.4 Earthwork Leveling Adjustment..................................................................................................... 12
7 MATERIAL TAKE OFF ........................................................................................................................ 12

_ __
__ RA|
I N D __| 3 of 12

||___ File
N
07 09004ed580465198_--_A4_--_.doc
-20Name:
11-JUBUILT
AS
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

1 SCOPE

This project design specification defines the materials, construction and testing requirements for the
earthworks to be carried out at the site preparation stage and during construction phase for all process
units and utilities for the DOLPHIN Project, Upstream & Compression Facilities located in Ras Laffan,
Qatar.

2 APPLICABLE CODES, SPECIFICATIONS AND STANDARDS

All design, engineering, materials and construction shall conform to the latest requirements of local
national standards and local regulations and to the following reference documents, codes and standards.
The latest edition of these documents at the time of contract award shall be applicable.

When these documents contain requirements conflicting with other documents / codes referred to here
after, this specification shall prevail.

However, any discrepancies shall be brought to the attention of the COMPANY.

2.1 COMPANY General Specification

2.1.1 Civil

GS CIV 101 General Earthworks


GS CIV 103 Fences
GS-CIV 201 Design and Construction of Roads and Stabilized Areas
GS CIV 202 Drainage and Underground Networks
GS CIV 300 Reinforced and Pre-stressed Concrete

2.1.2 Safety, Layout

GS SAF 021 Layout


GS SAF 216 Area classification
GS SAF 228 Liquid drainage

For a complete list of all applicable COMPANY general specifications, refer to document number:
‹ DOL-0000-GSP-01005 List of Applicable COMPANY Specifications

2.2 DOLPHIN Project Documents

2.2.1 General

‹ DOL-0000-GSP-01002 Geographic and Meteorological Data


‹ DOL-0000-GSP-01001 Basic Engineering Design Data
‹ Geotechnical Report As listed in DOL-0000-CSP-00051
‹ Topographical Report As listed in DOL-0000-CSP-00051
‹ Geotechnical and topographical documents of the new area of the Condensate Storage: As listed in
DOL-0000-CSP-00051

2.2.2 Layout

‹ RLO-0000-LPP-01000 Onshore Facilities – general Site Plan


‹ RLP-0000-LPP-02200 Ras Laffan Treatment Plant – Overall Plot Plan
‹ RLH-1430-LPP-03250 Ras Laffan Harbour Area – Condensate Storage and Export Plot
Plan – U143.
‹ RLH-1470-LPP-03450 Ras Laffan Harbour Area – Butane and Propane Storage – Plot
Plan U 147 & 148. (Out of Scope)

_ __
__ RA|
I N D __| 4 of 12

||___ File
N
07 09004ed580465198_--_A4_--_.doc
-20Name:
11-JUBUILT
AS
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

2.2.3 Civil

‹ DOL-0000-CSP-00001 Site Preparation Specification


‹ DOL-0000-CSP-00002 Roads and Fencing
‹ DOL-0000-CSP-00003 Underground Installation Networks
‹ DOL-0000-CSP-00051 Civil and Structural Design Specification
‹ DOL-0000-CSP-00052 Reinforced Concrete Materials and Construction
‹ DOL-0000-CST-00051 Concrete Work Standards
‹ DOL-0000-CST-00001 Underground Installation Networks Standards
‹ DOL-0000-CSP-00053 Tank Foundations and Dikes
‹ RLH-1430-CGA-00001 Site Preparation - Condensate Storage - Plan view
‹ RLH-1430-CGA-00002 Site Preparation - Condensate Storage – Sections
‹ RLP-0000-CGA-00001 Site Preparation Plan view.
‹ RLP-0000-CGA-00002 Site Preparation Sections

2.2.4 Buildings

‹ DOL-0000-BSP-00001 Building Programme

2.2.5 Electrical

‹ RL0-1200-ESD-01040 Earthing, Power, Lighting Standards

2.2.6 Safety, Environment and Fireproofing / Corrosion

‹ RL0-0000-FPY-01200 Safety Concept (Onshore)


‹ RL0-0000-FPY-01230 Environmental & Waste Protection Philosophy
‹ RL0-0000-FPY-01450 Active Fire Fighting Philosophy
‹ RL0-0000-FSP-01550 Fire Fighting and Life Saving Equipment

2.3 Local National Standards and Regulations

‹ QNBS
‹ Environmental Protections Standards – State of Qatar
‹ Environmental Guidelines & Environmental Protection Criteria for Ras Laffan Industrial City

2.4 International Standards (Major Codes and Standards)

British Standards
‹ BS
American Standards
‹ ASTM American Society for Testing and Materials
‹ AASHTO Guide to design of pavement structures
‹ API 650 Appendix E Seismic Design of Storage Tanks

For a complete list of all applicable Codes and Standards, refer to document number :
‹ DOL-0000-GSP-01003 Applicable Codes and Standards

2.5 Order of Precedence

Prevailing order, in case of conflict the governing order of priority shall be :

(i) Qatar Statutory Regulations


(ii) Safety Concept – Onshore
(iii) Project specification
(iv) COMPANY general specifications
(v) Codes, Standards & Recommended Practices listed in documents mentioned above.

_ __
__ RA|
I N D __| 5 of 12

||___ File
N
07 09004ed580465198_--_A4_--_.doc
-20Name:
11-JUBUILT
AS
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

2.6 Site Conditions

2.6.1 Preliminary

For soil geo-technical and topographical conditions refer to latest issue of Fugro Soil Consultant
Geo-technical and Topographical reports as listed in document N° DOL-0000-CSP-00051 Civil and
Structural Design Specification.

Note: The Condensate Storage Plot has been relocated since the time when the scope of works for the Geotechnical and
Topographical Survey was specified.

As a consequence, the information relative to this area contained in the Final Soil Report in this document is not applicable
anymore.

The soil geotechnical and topographical reports of the new location of the Condensate Storage area is to be determined during the
detailed engineering phase. (Relevant data was updated)

2.6.2 Reference Topographic Level

Refer to document N° DOL-0000-CSP-00051

2.6.3 Soil Conditions

Refer to Section 2.6.1 of the present document.

2.6.4 Ground Water

Refer to Section 2.6.1 of the present document.

2.6.5 Allowable Soil Bearing Pressure

As per Document no DOL-0000-CSP-00051 Civil and Structural Design Specification.

3 FILL MATERIALS

According to the Soil Geotechnical Report issued by Fugro, the following materials shall be used :

3.1 Fill Type A

Fill Type A shall be used when necessary under all foundations.


It shall comply with the following specifications :

1 Type of soil inorganic and free draining with no more than trace
amounts of organic matter, gypsum or salts
2 Particle size 50 mm max
3 Fines content 15% max
4 Gradation Well graded
5 Liquid limit 25 max

Fill shall be placed in loose layers not exceeding 225 mm thickness, and each layer shall be compacted
with suitable equipment to a minimum of 95 % of its Proctor maximum density.

Test : fill density testing at a frequency of one test per 300 m² layer.

Desert fill may be considered as Fill Type A, if site trials demonstrate that it presents the following
minimal properties when compacted:

_ __
__ RA|
I N D __| 6 of 12

||___ File
N
07 09004ed580465198_--_A4_--_.doc
-20Name:
11-JUBUILT
AS
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

Property Typical value


Bulk density (Mg/m3) 1.8 to 1.9
Angle of internal friction (degrees) 33
Young’s modulus of elasticity (Pa) 50
Poisson’s ratio 0.3
Maximum dry density (Mg/m3) 1.95 to 2.0
Optimum moisture content % 10-12
Design CBR value % 25

3.2 Fill Type B

Fill Type B shall be used for the following :


• Roadway and paving sub grades
• Embankment
• Grading of general area to be used by construction or plant operation

It shall comply with the following specifications:

1 Type of soil inorganic and free draining with no more than trace
amounts of organic matter, gypsum or salts
2 Particle size 75 mm max
3 Fines content 30% max
4 Gradation Well graded
5 Liquid limit 40 max

Fill shall be placed in loose layers not exceeding 250 mm thickness, and each layer shall be compacted
with suitable equipment to a minimum of 90 % of its Proctor maximum density, except for the top 300 mm
that shall be compacted to a minimum of 95%.

Test : fill density testing at a frequency of one test per 1000 m² layer.

Dune sand may be considered as Fill Type B, if site trials demonstrate that it presents the following
minimal properties when compacted:

Property Typical value


Bulk density (Mg/m3) 1.75
Angle of internal friction (degrees) 30
Young’s modulus of elasticity (Pa) 25
Poisson’s ratio 0.25
Maximum dry density (Mg/m3) 1.7 to 1.8
Optimum moisture content % 12-14
Design CBR value % 10

3.3 Fill Type C

Fill Type C shall be used only at locations where installation of structure or equipment is not planned, as
well as in open areas where only grading is required.

It shall comply with the following specifications :

1 Type of soil Inorganic granular or silt soil with a low to negligible


gypsum/salt content
2 Particle size 100 mm max
3 Fines content 50% max
4 Gradation Well graded
5 Liquid limit 40 max

_ __
__ RA|
I N D __| 7 of 12

||___ File
N
07 09004ed580465198_--_A4_--_.doc
-20Name:
11-JUBUILT
AS
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

Fill shall be placed in loose layers not exceeding 600 mm thickness, and be compacted using bulldozers
and or other types of grading equipment.

Test : fill density testing at a frequency of one test per 1000 m² layer.

4 WORKS

4.1 Preliminary

• All works shall be in compliance with Earthworks Design Study, that specifies the balance of fill and
excavation, as well as all trucking of earth on site and out of site.
• If tests performed on soil in situ demonstrate that some of the conclusions of the Earthwork Design
Study are not applicable (excavation material not meeting requirements to be used as fill, bottom of
excavation not meeting the requirements for foundation subgrade …), the Contractor shall inform
the Company. The Contractor shall in no circumstance take the initiative to modify the sequences,
timing and quantities specified in the Earthworks Design Study without the approval of the Company

4.2 Demolitions

All rough tracks, paved or unpaved roads and more generally all existing buildings, paving, sewerage etc
shall be demolished, and the resulting debris shall be disposed of to a dump located out of construction
site.

4.3 Clearance of Vegetation

All trees, shrubs and vegetation, including roots present on construction site shall be removed and flora
shall be subject to joint inspection by the Ras Laffan Authorities and the Contractor representatives prior
to the beginning of works and shall be relocated at a location identified by the Ras Laffan Authorities’
representative. They shall be either burned on site if safety conditions allow it, or disposed of to a dump
located out of construction site.

4.4 Stripping of Topsoil

Unless otherwise specified, the first 0.20m of topsoil shall be stripped. The valuable topsoil shall be
stripped and stockpiled in a designated area by Ras Laffan Authorities. Otherwise, the topsoil shall be
dumped at the location identified by the Company.

4.5 Excavation

• Excavations shall be performed with appropriate equipment, bulldozer most often and locally,
hydraulic breaker when necessary.
• Temporary excavations in soil with low cohesion, above groundwater shall be either supported or
sloped to a rate of 1 vertical to 1.5 horizontal.
• Excavations shall be kept free from water in compliance with chapter Management of Surface and
Underground Water.
• Bottom of excavated areas shall be sloped to avoid water gathering (ponding), and water shall be
evacuated as per chapter Management of Surface and Underground Water.
• Contractor’s attention is drawn to the potential existence of underground services, drains, cables,
pipes. When obstructions are discovered during excavations, whether they were known to exist or
not, the Contractor shall take all measures to prevent both damage to live networks, and accidents
on site. Excavation shall then be performed by approved methods, including excavations by hand,
protection and diversion of services.
• Use of explosive shall be strictly in accordance with laws and regulations and subject to the
approval of Ras Laffan Authorities.

_ __
__ RA|
I N D __| 8 of 12

||___ File
N
07 09004ed580465198_--_A4_--_.doc
-20Name:
11-JUBUILT
AS
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

4.6 Soil Improvement

Where unsuitable material is encountered at the bottom of an excavated area, it shall be removed and
disposed of to a dump located out of site.

Such unsuitable materials may be represented by :


• Soft clay or silt layers or pockets
• High sulfate content layers or pockets
• Boulders size ≥0.5 m3
• Layers of loose materials not meeting the requirements of soil characteristics listed in Section 6 of
the specification n° DOL-0000-CSP-00051 ‘Civil and Structural Design Specification’, in general, or
the requirements of document N° DOL-0000-CSP-00053 ‘Tank Foundations and Dikes’ for Tanks.
• Any other foreign material discovered by the Contractor or pointed out to by the Company

The resultant excavation shall be back filled with suitable fill materials following the requirements of
paragraph Fill Materials.

4.7 Stockpiling of Excavated Soil

Excavated soil and crushed rock suitable for fill purposes shall be selected, transported and stockpiled at
locations approved by the Company. The stockpiled soil shall be subjected to sieve analysis and
approval. If the excavated soil is unsuitable for fill material, the next stipulation shall be followed.

4.8 Disposal of Excavated Soil

Excavated soil and rock unsuitable for fill purposes (not meeting the requirements of Document n°
DOL-0000-CSP-00051 Civil and Structural Design Specification in general and DOL-0000-CSP-00053
Tank Foundations and Dikes for Tanks) shall be disposed of to an approved dump located out of site.

4.9 Management of Surface and Underground Water

In consultation with the geotechnical consultant, and with the Company’s approval, the Contractor shall
design, provide, install, operate and maintain
• all necessary systems to lower the water table 300mm below the excavation or foundation formation
level
• sumps, temporary or permanent ditches, culverts, trenches, drains, pumps, pipes and all other
necessary equipment of sufficient capacity to evacuate all surface and underground water

The groundwater level shall be continuously maintained below the excavation level until the filling or
foundation construction and back filling are completed.

4.10 Fill

• Fill and back fill shall be performed with approved materials as specified in paragraph Fill above.
Placement of fill Types A, B, and C according to same paragraph.
• Ground water from site may be used for moisture conditioning of soils for compaction if its
properties allow it. If ground water is aggressive against concrete, it shall not be used. In this case,
water shall be brought to site for compaction purposes.
• Use of seawater for fill around concrete constructions shall be forbidden – not allowed by any
means.

Before any filling begins, the site to be filled shall be cleared. If natural existing soil is to be kept in place,
the first 200 mm of its surface shall be scraped, moisture conditioned, and compacted to an average
density of 95% of MDD, with no individual test result less than 90%, as per ASTM D1557.

_ __
__ RA|
I N D __| 9 of 12

||___ File
N
07 09004ed580465198_--_A4_--_.doc
-20Name:
11-JUBUILT
AS
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

5 SPECIFIC ITEMS

5.1 Earthworks for Fences

• Security Fence and Internal Fence as per drawings and n° DOL-0000-CSP-00002 Roads and
Fencing
• Temporary fence as per document n° DOL-0000-CSP-00001 Site Preparation

5.2 Roads

Earthworks for roads shall be as per document n° DOL-0000-CSP-00002 Roads and Fencing.
Depending on results of tests performed in situ after leveling, subgrade shall be either

‹ Fill type B if natural soil does not match the requirements listed in document n°
DOL-0000-CSP-00002 Roads and Fencing Section 3.3.
‹ Or natural soil properly compacted in accordance with document n° DOL-0000-CSP-00002 Roads
and Fencing Section 3.3.

NB: For roads Types I and II, ditches may not receive the concrete lining during construction phase.
Therefore, ditches shall be protected against erosion for the time of construction if deemed necessary, or
if they are damaged during construction, they shall be reconditioned, right before concrete lining is
placed.

5.3 Underground Networks-Trenches

• Excavation for trenches shall include shoring of faces if soil requires it


• Backfill shall be according to document n° DOL-0000-CSP-00003 Underground Installation
Networks, including implementation of warning mesh and protective tiles when required
• Hand back fill may be required locally
• Unsuitable material detected at design level of trench bottom shall be removed and replaced with
suitable material

5.4 Foundations

Backfill of excavations after construction of foundations shall be performed :


• after foundations have cured and protection has been placed as per document n°
DOL-0000-CSP-00052 Reinforced Concrete Materials and Construction Section 7.5
• in such a way that does not generate efforts for which the foundation was not designed (i.e. lateral
efforts on one side only …etc)

5.5 Tank Foundations and Dikes

Tank Pads shall comply with document n° DOL-0000-CSP-00053 Tank Foundations and Dikes.

5.6 Platform

Platform shall be realized horizontally up to finish level specified on drawings. Slopes and other details
shall be done after the platform is delivered and accepted, according to specific details of design.

5.7 Protection of Slopes

‹ During intermediary stages of construction, slopes shall be protected against wind and water
erosion according to specific drawings. The Contractor shall provide temporary water drainage
accordingly
‹ Permanent slopes that are going to exist all along plant life shall be provided with adequate
protection which could typically be by stone/ cobble, or by suitable vegetation. For relatively steep
slopes, various types of geo-textiles may be considered to provide soil reinforcement or assist slope
face protection.

_ __
__ RA|
I N D __| 10 of 12

||___ File
N
07 09004ed580465198_--_A4_--_.doc
-20Name:
11-JUBUILT
AS
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

5.7.1 Slope Protection for Earth Mound under Slug Catcher

(1) SCOPE
This paragraph specifies the details of permanent slope protection for the earth mound under slug
catcher 100-0X0100-A/B.

(2) MATERIAL
Stone shall be limestone or sandstone comprise sound, dense, hard and durable rock free from
weathering, the individual pieces being clean and angular and neither elongated nor flat. Color should be
white, yellow and the texture should be rough.

Water, sand, reinforcement steel bars, welded wire mesh or likes used for concrete and mortar works
shall be in accordance with DOL-0000-CSP-00052.

Concrete for toe beams, verges and stair cases shall be structural concrete Type-A.

(3) WORKMANSHIP
Stones for random rubble facing shall consist of random (irregular) stone whose dimension on the
exposed face shall be from 150mm to 400mm and whose average thickness shall be 200mm.

Stones shall be carefully shaped to obtain as close a fit as possible at beds and joints and sufficient
space shall be left between stones to allow the joints to be filled completely with cement sand mortar to
prevent infiltration. No cavities shall be left under or between the stones.

When placed on the sloped ground the stones shall be placed on material trimmed and compacted to
make a firm bed.

Toe beams, verges, stair cases and weep holes shall be provided in accordance with the detail
drawings.

5.8 Marine Works for LPG Tanks (out of Scope)

Marine works for LPG tanks area shall be according to document n° RLH-1470-CGA-00001.

6 CONTROLS AND TOLERANCES

6.1 Tests on Fill Materials at Source

Tests shall be carried out on each source of material to be used as fill, whether from excavations, site
stockpiles or borrow pits, to establish the following properties:

• Natural Water Content


• Maximum Dry Density and Optimum Moisture Content
• Particle size distribution, including hygrometer analysis
• Liquid Limit
• Plasticity Index

These tests shall be repeated if the source of material changes or if the material itself changes. A
sufficient number of tests shall be performed to establish representative average and range of properties
(approximately one set of tests per 5 000 m3 : the number of tests shall vary depending on the quantity of
material and the consistency of results).

6.2 Methods

Sampling and testing shall be made in accordance with the following standards :

_ __ • Classification (sieve) test : ASTM D 422 or British equivalent


__ RA|
I N D __| 11 of 12

||___ File
N
07 09004ed580465198_--_A4_--_.doc
-20Name:
11-JUBUILT
AS
DOLPHIN PROJECT Company Doc. No.: DOL-0000-CSP-00004
UPSTREAM AND COMPRESSION FACILITIES Contractor Job Code: 0-3356-20
(Doc.Title Earthworks material and construction Contractor Doc. No.: S-000-3112-002 <Z07>

• Liquid limit, plastic limit, plasticity : ASTM D 4318 or British equivalent


• Moisture-density (compaction) test : ASTM D 1557 or British equivalent
• Field density :ASTM D 1556 or D 2922 or British equivalent
• Moisture content :ASTM D2216 or D3017 or British equivalent
• Sulfate content :BS 1377 Part 3 or equivalent ASTM
• Gypsum content :To be identified by Laboratory

6.3 Frequency of Tests

6.3.1 General Earthworks

• Test on fill

Field density / Moisture content :


a minimum of 2 tests per compacted layer, and every 300 m² for Fill A, 1000 m² for Fills B and C
according to Chapter 3 of the present document.

Additional tests will be required by Company when the quality of moisture control or compaction appears
incorrect.
The compacted layer submitted to test shall not be covered until Company has approved the test results.

• Test on earthworks for foundation

Field density : one test every 100m² of foundations

6.3.2 Laboratory

As per GS CIV 101 Chapter 4.2.2, the Contractor shall install his own laboratory on site, which shall allow
him to check the quality of equipment and materials in use. It will allow him to propose adjustments to the
Company with respect to quality and use.
The site laboratory shall be run at the Contractor’s expenses and include :
• The installation, fitting, maintenance and dismantling of a building on an area suitable for laboratory
use
• The laboratory operation and personnel required to perform tests

6.4 Earthwork Leveling Adjustment

Dimension checking shall be made by Contractor from benchmarks and stakes in compliance with layout
plans.

• Actual position shall be within ± 2 cm of theoretical position.


• Unless otherwise specified on the drawings, maximal deflection over a 3 m ruler shall be no more
than 3 cm, tolerance from true line ± 7.5 cm

If during 2 consecutive days of work, more than 10% of the points that have been checked do not
correspond with the tolerances specified above, the Company reserves the right to stop works, to
examine the methods and equipment utilized, and to revise or replace them.

7 MATERIAL TAKE OFF

Measurement methods of earth works shall be referred to the following construction subcontract
documents:

z RL0-0000-GIQ-14102 (E-1430-102): Inquiry Package for Site Preparation


z RL0-0000-GIQ-14201 (E-1430-201): Inquiry Package for Industrial Civil Works

_ __
__ RA| ========= End of Specification ==========

I N D __| 12 of 12