Scaffolding Required Material
Height Dia / width Length in Feet Volume f3
2*pi*r
Volume of Scaffolding Req FFL ATA 32019 20,000
20,000
One Cube of Scaffolding Volume 10 10 6 600
Required Number of Cubes 33.333
One Cube of Scaffolding Contains
Number in one Total Material Required Number of Total Total Scff incl
Factoe Of Internal Rental per
SR# Description Scaffolding
cube for one column Columns Requirement non usage Percentage day rate
Pipe 1 1 15%
1 6' Pipe 1 33.33 33.33 33.00 38 5
2 8' Pipe 1 33.33 33.33 33.00 38 5
3 10 ' Pipe 6 200.00 200.00 200.00 230 5
4 20' Pipe 6 200.00 200.00 200.00 35 10
5 12' Cross Bars 2 66.67 66.67 67.00 77 6
Planks - - - -
6 Metallic Plank 6 200.00 200.00 200.00 230 30
7 Toe Boards 4 133.33 133.33 133.00 153 20
8 Base Plate 4 133.33 133.33 133.00 153 2
Joints - - - -
9 Universal Joint 7 233.33 233.33 233.00 268 1.50
10 Pin Joint 7 233.33 233.33 233.00 268 1.50
11 Fixed Joint 6 200.00 200.00 200.00 230 1.00
103.62 37.68
65.94
37.68
1 4
OPTION-I OPTION-II OPTION-III
25% NEW 75% New purchase total price new RENTAL UNIT RATE 25% NEW PURCHASE
Rental unit rate total price Rental
PURCHASE RENTAL unit rate purchase FOR 4 MONTHS 75% RENTAL
9 28 1678.571428571 63,701.79 150.00 5,692.50 600.00 33,002.95
9 28 150.00 5,692.50 600.00 17,077.50
58 173 2785.714285714 640,714.29 150.00 34,500.00 600.00 263,678.57
9 26 5585.714285714 192,707.14 300.00 10,350.00 1,200.00 79,226.79
19 58 3350 258,117.50 180.00 13,869.00 720.00 106,136.38
- - - - - - -
58 173 4564.285714286 1,049,785.71 900.00 207,000.00 3,600.00 883,446.43
38 115 500 76,475.00 600.00 91,770.00 2,400.00 294,428.75
38 115 100 15,295.00 45.00 6,882.75 180.00 24,472.00
- - - - - - -
67 201 274.2857142857 73,494.86 45.00 12,057.75 180.00 54,546.96
67 201 180 48,231.00 45.00 12,057.75 180.00 48,231.00
58 173 190 43,700.00 30.00 6,900.00 120.00 31,625.00