0% found this document useful (0 votes)
415 views3 pages

Earned Value Management (EVM) - Solved Examples in USD

The document provides examples of Earned Value Management (EVM) calculations, including Estimate at Completion (EAC) and Variance at Completion (VAC), showing how to assess project performance in terms of schedule and budget. It includes detailed calculations for three different scenarios, indicating whether projects are ahead or behind schedule and over or under budget. Key metrics such as Schedule Performance Index (SPI) and Cost Performance Index (CPI) are used to evaluate project status.

Uploaded by

azad01.nga
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
415 views3 pages

Earned Value Management (EVM) - Solved Examples in USD

The document provides examples of Earned Value Management (EVM) calculations, including Estimate at Completion (EAC) and Variance at Completion (VAC), showing how to assess project performance in terms of schedule and budget. It includes detailed calculations for three different scenarios, indicating whether projects are ahead or behind schedule and over or under budget. Key metrics such as Schedule Performance Index (SPI) and Cost Performance Index (CPI) are used to evaluate project status.

Uploaded by

azad01.nga
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

📘 Earned Value Management (EVM) – Solved Examples in USD

🧮 Example 1: Estimate at Completion (EAC) and Variance at Completion (VAC)

Given:

• Budget at Completion (BAC) = 22,000


• Earned Value (EV) = 13,000
• Planned Value (PV) = 14,000
• Actual Cost (AC) = 15,000

Solution:

1. Schedule Performance Index (SPI) = EV / PV = 13,000 / 14,000 = 0.93

→ Project is behind schedule

2. Cost Performance Index (CPI) = EV / AC = 13,000 / 15,000 = 0.87

→ Project is over budget

3. Estimate at Completion (EAC) = AC + [(BAC − EV) / (CPI × SPI)]

= 15,000 + [(22,000 − 13,000) / (0.87 × 0.93)] ≈ 26,123

4. Variance at Completion (VAC) = BAC − EAC = 22,000 − 26,123 = −4,123

The project is expected to exceed the budget by 4,123 and is also behind schedule

Element Value (USD) Formula / Note


BAC (Budget at Completion) 22,000 Total planned budget
EV (Earned Value) 13,000 Work actually completed
PV (Planned Value) 14,000 Work planned to be
completed
AC (Actual Cost) 15,000 Actual cost incurred
SPI (Schedule Performance 0.93 EV / PV = 13,000 / 14,000
Index)
CPI (Cost Performance Index) 0.87 EV / AC = 13,000 / 15,000
EAC (Estimate at Completion) ≈ 26,123 AC + [(BAC − EV) / (CPI ×
SPI)]
VAC (Variance at Completion) −4,123 BAC − EAC = 22,000 − 26,123
Conclusion The project is expected to be
over budget by 4,123 and
behind schedule
🧮 Example 2: Performance Analysis After Month 2

Planned Value by Month:

• Month 1: 13,373
• Month 2: 7,229
• Month 3: 30,120
• Month 4: 9,639

Earned Value:

• Month 1: 12,048
• Month 2: 9,036

Actual Cost:

• Month 1: 15,060
• Month 2: 6,024

Cumulative Totals After Month 2:

• Planned Value (PV) = 13,373 + 7,229 = 20,602


• Earned Value (EV) = 12,048 + 9,036 = 21,084
• Actual Cost (AC) = 15,060 + 6,024 = 21,084

Calculations:

• Schedule Variance (SV) = EV − PV = 21,084 − 20,602 = 482


• Schedule Performance Index (SPI) = EV / PV = 21,084 / 20,602 = 1.02
• Cost Variance (CV) = EV − AC = 21,084 − 21,084 = 0
• Cost Performance Index (CPI) = EV / AC = 21,084 / 21,084 = 1.00

The project is slightly ahead of schedule and exactly on budget.

Element Value (USD) Formula / Note


PV (Cumulative) 20,602 Month 1 + Month 2 = 13,373 + 7,229
EV (Cumulative) 21,084 Month 1 + Month 2 = 12,048 + 9,036
AC (Cumulative) 21,084 Month 1 + Month 2 = 15,060 + 6,024
SV (Schedule Variance) +482 EV − PV = 21,084 − 20,602
SPI (Schedule Performance 1.02 EV / PV = 21,084 / 20,602
Index)
CV (Cost Variance) 0 EV − AC = 21,084 − 21,084
CPI (Cost Performance Index) 1.00 EV / AC = 21,084 / 21,084
Conclusion The project is slightly ahead of
schedule and exactly on budget
🧮 Example 3: Activity-Based SPI and CPI Calculation

Activity A:

• Planned Value (PV): 2,169


• Actual Cost (AC): 2,410
• % Complete: 100%
• Earned Value (EV): 2,169

Activity B:

• Planned Value (PV): 964


• Actual Cost (AC): 1,205
• % Complete: 75%
• Earned Value (EV): 723

Cumulative Totals:

• Planned Value (PV) = 2,169 + 964 = 3,133


• Actual Cost (AC) = 2,410 + 1,205 = 3,614
• Earned Value (EV) = 2,169 + 723 = 2,892

Calculations:

• Schedule Performance Index (SPI) = EV / PV = 2,892 / 3,133 = 0.92


• Cost Performance Index (CPI) = EV / AC = 2,892 / 3,614 = 0.80

The project is both behind schedule and over budget.

Element Activity A Activity B Total Formula / Note


Planned Value 2,169 964 3,133 Total planned
(PV) value for both
tasks
Actual Cost (AC) 2,410 1,205 3,614 Total actual cost
incurred
Earned Value (EV) 2,169 (100%) 723 (75%) 2,892 Total earned
value based on
% done
SPI — — 0.92 EV / PV = 2,892
/ 3,133
CPI — — 0.80 EV / AC = 2,892
/ 3,614
Conclusion The project is
behind schedule
and over budget

You might also like