PA2402857 - 5575 South Gippsland Highway, Lang Lang - Ground Control Management Plan
PA2402857 - 5575 South Gippsland Highway, Lang Lang - Ground Control Management Plan
Management Plan
Lang Lang Sand Resources Pty Ltd
09 February 2023
Document status
© GHD 2023
This document is and shall remain the property of GHD. The document may only be used for the purpose for
which it was commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised
use of this document in any form whatsoever is prohibited.
1. Introduction 1
1.1 Purpose 1
1.2 Definitions 3
1.3 Scope and limitations 3
1.4 Legislative Environment 3
1.5 Stability and Ground Control Context 3
2. Quarry Setting 5
2.1 General 5
2.1.1 Development History 6
2.1.2 Proposed Quarry Development 6
2.2 Quarry Infrastructure and Local Surroundings 7
3. Geotechnical Performance and Considerations 8
3.1 Geotechnical Model Considerations 8
3.2 Regional and Site Geology 9
3.2.1 Regional Geology 9
3.2.2 Regional Structural Geology 9
3.2.3 Stratigraphy 9
3.2.4 Major Structures 12
3.2.5 Neotectonics 13
3.3 Hydrogeology 14
3.4 Material Strength Parameters 15
3.4.1 Material Strength Variability 16
3.5 Summary of Anticipated Failure Mechanisms 17
3.5.1 Circular Instability (Primary Mechanism) 17
3.5.2 Erosion and Piping (Secondary Mechanism) 18
3.6 Geotechnical Considerations 20
3.6.1 Seismic Loading 20
3.7 Data Uncertainty 20
3.8 Design Acceptance Criteria 21
3.9 Slope Design Geometry 21
3.10 Stability Performance 22
4. Geotechnical Management Process 24
4.1 General 24
4.2 Effective Slope Formation at WA7541 24
4.3 Slope Monitoring requirements 24
4.3.1 Overview 24
4.3.2 Visual Inspections 25
4.3.3 Crack Monitoring 25
4.3.4 Survey Monitoring 25
4.4 General Drainage Considerations 26
4.5 Temporary Stockpiles 26
4.6 Trigger Action Response Plan 26
4.6.1 General 26
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan i
5. Geotechnical Risk Assessment 30
5.1 General 30
5.2 Geotechnical Hazards Identification 30
5.3 Risk Management Framework 31
6. Geotechnical Hazard Management 32
6.1 Hazard Assessment Process 32
6.2 Geotechnical Hazard Awareness 32
6.3 Geotechnical Hazard Detection 32
6.4 Risk Matrix 32
6.5 Hazard Prevention 33
6.6 Geotechnical Hazard Mitigation 33
6.7 Risk Register – Site Geotechnical Log 34
6.8 Risk Assessment Results 39
7. Quarry Closure and Rehabilitation 40
7.1 Rehabilitation Strategy 40
7.2 Erosion Management 40
8. Review and Audit 42
8.1 Triggers For Geotechnical Review 42
9. References 43
9.1 Relevant Acts 43
9.2 Legislation and Guidance Documents 44
9.3 Relevant Site Documentation/Studies 44
Table index
Table 1 Summary of Mohr Coulomb Parameters 16
Table 2 Anticipated Instability Mechanisms Present 17
Table 3 FoS Guidelines after ERR (2020) 21
Table 4 Summary of Pit Wall Stability Monitoring Procedures 27
Table 5 TARP for Slope Condition 28
Table 6 Geotechnical Hazards at the WA7541 Site 30
Table 7 WA7541 Quarry Pit Risk Rating 35
Table 8 Proposed Erosion Monitoring Criteria 40
Figure index
Figure 1 Plan view of WA7541 Boundary and adjacent work authorities. 2
Figure 2 Design process flowchart 4
Figure 3 Site Location within the regional plan 5
Figure 4 Pit Development Plan 6
Figure 5 Plan View of the Proposed Quarry Location Depicting Nearby Receptors 7
Figure 6 Development of Geotechnical Domain Model after Read and Stacey (2009) 8
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan ii
Figure 7 Physiographic Sub-Divisions of Western Port (Carillo-Rivera, 1975, modified
from Jenkin, 1974). Proposed quarry shown in red. 9
Figure 8 Simplified Geological Map of the Lang Lang Region 10
Figure 9 Typical sub-surface profile at the site 12
Figure 10 Earthquake and Geological Map of the Lang Lang Area. Earthquake ≥
Magnitude 3.0 Shown 14
Figure 11 Depth to Groundwater at the WA7541 Site (VVG, 2021) 15
Figure 12 Summary of Effective Strength Distribution (Cohesion) 16
Figure 13 Summary of Effective Strength Distribution (Friction Angle) 17
Figure 14 Schematic of a circular failure 18
Figure 15 Example of Erosion of Exposed Sand Batters at Nearby Quarry 19
Figure 16 Subsurface Section Alignment A-A’. 19
Figure 17 Seismic Hazard Map of Victoria for 1/500 year Return Period 20
Figure 18 Section A-A’ – Critical Pit Geometry 22
Figure 19 Impact of plant off-set distance from crest on batter FoS 23
Figure 20 ERR Likelihood Descriptions (DJPR, 2020) 32
Figure 21 ERR Risk Matrix (DJPR, 2020) 33
Figure 22 Risk Rating Acceptability (DJPR, 2020) 33
Figure 23 Hierarchy of Controls 34
Appendices
Appendix A Quarry Inspection Sheet
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan iii
1. Introduction
1.1 Purpose
The purpose of this document is to provide a Ground Control Management Plan (GCMP) for Lang Lang Sand
Resources Pty Ltd (the Client), owned by Aurora Construction Materials (ACM), who wish to develop sand
resources at Work Authority 7541 (WA7541), located at 5575 South Gippsland Highway (SGH) in the Lang region
of Victoria (the site; see Figure 1. Primarily, the GCMP aims to identify the risks associated with quarrying
operations at the South Gippsland site and to provide a framework for risk management. It is understood the
Client’s work plan application must satisfy any requirements prescribed by the Department of Jobs, Precincts and
Regions (DJPR) - Earth Resources Regulation (ERR) division.
To assist the client with this application, GHD was engaged by Mr Kelvin Sargent of ACM to undertake a
geotechnical assessment of the site, with outcomes detailed in the GHD (2022) draft report ‘5575 South Gippsland
Highway Geotechnical Assessment’ dated 30 March 2022 (GHD Ref: 12527040-45542-13), and develop a ground
control management plan (GCMP) (this report) which identifies potential geotechnical risks and suitable risk
treatment protocols.
GCMPs are a tool that provide the necessary framework to recognise, identify and address pertinent geotechnical
issues for the purpose of creating a safe, stable, and sustainable site, as defined in Section 1.2, during quarry
operations all the way through to closure and rehabilitation phases. Accordingly, a key part of the GCMP is the
geotechnical risk assessment. The risk assessment is used to identify and address any perceived or known
threats to the:
– Safety of people – including the public and site personnel
– Environment
– Risk to quarry employees
– Key infrastructure within and around the quarry
– Nearby public infrastructure (where applicable)
The findings of the risk assessment help tailor management protocols to the site for which the GCMP is being
developed with the aim of mitigating risks to tolerable thresholds.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 1
Figure 1 Plan view of WA7541 Boundary and adjacent work authorities.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 2
1.2 Definitions
Safe
The interim and final landforms should present the lowest reasonably achievable risk to public health and safety
and the environment, both within and beyond the quarry boundaries. A range of possible hazards will need to be
addressed including fire, dust, and contamination of air, soil, and water, and detrimental or uncontrolled water
flows or the development of weak or dangerous ground. Suitable controls which are necessary to maintain safe
conditions should be implemented, e.g., ground movement monitoring. This document focuses specifically on
stability related controls.
Stable
Anticipated ground movements should be minimised as far as reasonably practicable and those movements that
will occur should be understood, predictable and controllable. Controls necessary to maintain stability within and
beyond the site boundary should be in place with appropriate monitoring. The risk of rapid, adverse ground
movements leading to damage to infrastructure, property, or the environment should be as low as reasonably
achievable. Any risk to human life will also be identified and addressed.
Sustainable
The quarry pit geometry including any water bodies, should be feasible from long term stability, environmental,
social, and economic perspectives, and capable of beneficial use post quarrying.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 3
In developing the GCMP for WA7541 site, consideration is given to:
– The depth and operating life of the quarry
– The potential for changes in expected ground conditions associated with the expansion of the quarry (i.e.
groundwater fluctuations, bedding and planes of weakness)
– The location of working benches and transportation routes
– The potential for surface and ground water problems
– The equipment to be used, excavation methods, and handling of the resource and waste
– The presence of nearby surface features (e.g. public roads, railways, pipelines, natural drainage channels or
public buildings)
– The potential for the general public to inadvertently gain access to the quarry void during operation
– Geotechnical risk assessments and associated Trigger Action Response Plan (TARP)
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 4
2. Quarry Setting
2.1 General
The proposed quarry extraction site, WA7541, is situated in Lang Lang, Victoria, an area containing multiple sand
extraction quarries. The site is currently an undeveloped greenfield site, located approximately 7 km southeast of
the Lang Lang township, and 80 km southeast of Melbourne (Figure 3).
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 5
The WA7541 boundary covers an area of just under 118 Ha. The resource will likely be used for the production of
construction materials such as concrete and road surfacing material.
GHD understand that the client is proposing to excavate the resource using a sequenced process, as follows:
– Removal of overburden material (varies between 2 and 6 m in thickness)
– Dry extraction above the groundwater table
– Mechanical dredging to remove sand resources below the groundwater table
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 6
2.2 Quarry Infrastructure and Local Surroundings
This WA7541 site is bounded to the west and south by the South Gippsland Highway, to the northwest by WA1338
(Len Huxtable), to the northeast by Bass Gas Plant and to the east by private farmland. Four other existing WA
tenements can be found within 3 km of the proposed site: WA2 (Holcim), WA157 (Metro Quarry Group), WA1004
(Railway Sand Supplies) and WA1102 (Metro Quarry Group), as shown in Figure 5.
Figure 5 Plan View of the Proposed Quarry Location Depicting Nearby Receptors
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 7
3. Geotechnical Performance and
Considerations
3.1 Geotechnical Model Considerations
The geotechnical domain model forms the basis for any quarry pit slope design. The geotechnical domain model
facilitates the segregation of a quarry pit into sectors or zones which have similar geological, structural and
material property characteristics, thus modes of instability. In principle, the act of geotechnical domaining allows
for multiple optimisation techniques to apply, where the slope design is optimised, in terms of safety and
economics, for a given sector rather than applying a single slope design across the entire pit. In essence,
geotechnical domaining a quarry pit can be used inform quarry owners/operators where to focus their time and
effort.
The geotechnical domain model is compiled from four component models:
– Geological model
– Structural model
– Hydrogeological model
– Material properties model
Geotechnical domaining of the Client’s site has relied upon the philosophy set out by Read and Stacey (2009).
Outlined in the Figure 6 are the considerations that are taken into account when formulating site specific
geotechnical domains.
Figure 6 Development of Geotechnical Domain Model after Read and Stacey (2009)
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 8
3.2 Regional and Site Geology
3.2.1 Regional Geology
The proposed quarry site lies approximately 7 km inland from the eastern shores of Western Port Bay. The area is
situated within a tectonic depression, known as the Western Port Sunklands. The sunklands are bounded to the
west by the Tyabb Fault, and to the east by the Bass and Heath Hill Faults (GeoVic, 2014; Geoscience Australia,
2020), forming a horst (Mornington Peninsula bedrock ridge) and graben (Port Phillip Sunkland, Western Port
Sunkland) sequence (McAndrew & Marsden, 1968).
Figure 7 Physiographic Sub-Divisions of Western Port (Carillo-Rivera, 1975, modified from Jenkin, 1974). Proposed quarry
shown in red.
3.2.3 Stratigraphy
The area in the vicinity of the proposed quarry site consists of 3 main stratigraphic units Figure 8, as follows (from
oldest to youngest):
– Wonthaggi Formation (Ksw)
– Sandringham Sandstone, formerly known as Brighton Group (Nb)
– Unconsolidated Quaternary Deposits (Qg, Qa2 and Qa1)
A geological map of the proposed quarry site and the surrounding region is presented in Figure 8.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 9
Figure 8 Simplified Geological Map of the Lang Lang Region
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 10
Wonthaggi Formation (Ksw)
The oldest rocks found around the proposed quarry area is the sedimentary Wonthaggi Formation (Ksw). The
Wonthaggi Formation is part of the Strzelecki Group, which were the first sediments deposited within the
Gippsland Basin (Mehin & Bock, 1998). The overall thickness of the Strzelecki Group is at least 3000 m and
consists of interbedded non-marine greywackes, mudstones, sandstones, conglomerates, minor coals and
volcanics deposited in lacustrine, swamp or floodplain environments (Mehin & Bock, 1998). The Wonthaggi
Formation is defined by Welch et al. (2011) as a lithic volcaniclastic sandstone, arkose and siltstone, with minor
conglomerate and coal. Bryan et al. (1997) assigns an age of 129.5 – 100.5 Ma for the Wonthaggi Formation.
Sandringham Sandstone, formerly known as Brighton Group (Nb)
The Sandringham Sandstone (Nb) is a newly redescribed unit, grouping together the following units: Hanson Plain
Sand, Moorabool Viaduct Sands, Baxter Sandstone, Marina Cove Sand, Black Rock Sandstone, Red Bluff
Sandstone, Beaumaris Sandstone and the Brighton Group (VandenBerg, 2016).
Within the Port Phillip Bay region, exposures of Neogene sandstone are widely distributed and are often of
variable quality (VandenBerg, 2016). Therefore, these exposures have been studied in isolation from each other,
resulting in many outcrops being given their own rock unit name. VandenBerg (2016) conducted a re-examination
of the various type sections of these units and concluded that all name Neogene units in this region are shallow
marine in origin and contain sedimentary structures such as planar bedding and swaley cross-stratification. As
such, he interpreted that these units were deposited as a continuous sheet on an extensive strandplain, which has
been subsequently eroded into the scattered exposures that we see today. Because of these similarities,
VandenBerg (2016) proposes that these late-Neogene sediments be unified under the Sandringham Sandstone
name.
In the Lang Lang area, the Sandringham Sandstone is described as a paralic (interbedded marine and non-
marine) silt, sand and gravel deposit. The unit is variably calcareous and ferruginised, with sections of limestone
(GeoVic, 2014). Elsewhere, the Sandringham Sandstone also exists as sandy silt, fine sandstone, sandy
conglomerate to pebbly sandstone and clayey sand. The sandstone also contains carbonaceous bands (with plant
fossils), lag deposits, horizontal and swaley cross-lamination, and preserved burrows (VandenBerg, 2016).
The Sandringham Sandstone has been dated as Pliocene to Miocene in age, with a minimum age of 4.6 Ma
constrained by the overlying basalts of the Newer Volcanic Group and a maximum age of 5.8 (±0.2) Ma
determined by Sr/Sr isotope ratios within mollusc fossils (Hare et al., 2005; Wallace et al., 2005).
Due to its widespread distribution, the Sandringham Sandstone is overlain by multiple units. In the Lang Lang
Lowlands area, the Sandringham Sandstone is overlain by unconsolidated Quaternary sediments.
Unconsolidated Quaternary Deposits (Qa2, Qa1, Qg)
The youngest units found within the proposed quarry area are a series of Quaternary aged unconsolidated
sediments (GeoVic, 2014). There are two distinct phases of alluvial sedimentation (Qa2 and Qa1) and a series of
coastal lagoon deposits (Qg). Both phases of alluvial sedimentation are defined as generally unconsolidated,
variably sorted silt, sand and gravel, with Qa2 dissected to form terraces higher than Qa1 (GeoVic, 2014). The
coastal lagoon deposits can be found on the coast of Western Port Bay, to the southwest of the proposed quarry
site (GeoVic, 2014). Qg consists of variably consolidated, dark grey to black silt and clays.
In this region, these Quaternary sediments directly overlie the Sandringham Sandstone. A stratigraphy column is
presented in Figure 9.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 11
Figure 9 Typical sub-surface profile at the site
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 12
Heath Hill Fault
The Heath Hill Fault is a known fault in the Lang Lang area. The Heath Hill Fault is a NE-SW trending reverse fault
represented as a topographical scarp, with the Cretaceous Wonthaggi Formation upthrown relative to the Western
Port Sunklands. Geoscience Australia (2020) measures the Heath Hill Fault at 50.3 km, with a location precision of
250 m resulting from small-scale mapping from the 90 m resolution SRTM DEM. It is probable that the Heath Hills
Fault has experienced “recent” activity, with the Neogene-aged Haunted Hills Formation displaced across the fault
trace, evidence of Pliocene or younger movement.
Lang Lang Fault
The complex Lang Lang Fault is a fault which acts as the northern/western boundary of the Lang Lang Lowlands.
The Lang Lang Fault is an approximately 20 km long fault splaying off the Heath Hill Fault just northeast of Heath
Hill. The easternmost extent of the Lang Lang Fault has an almost E-W strike, which transitions to NE-SW from
around Caldermeade (GeoVic, 2014).
Like the Wellington Fault, the Lang Lang Fault is not listed as a neotectonic feature (Geoscience Australia, 2020).
However, topographical analysis of the region show that the Lang Lang Lowlands have been elevated relative to
the Western Port Sunklands. Remnants of the Sandringham Sandstone have been preserved on the Lang Lang
Lowlands block, in contrast to the purely Quaternary nature of the deposits within the northern sunklands.
Therefore, it is likely that the Lang Lang Fault has experienced post-Neogene activity to some degree. However, a
combination of the lack of surface expression, the absence of recorded earthquake activity along the fault and the
less than optimal orientation of the fault trace suggest that future activity along this fault is unlikely, but not
impossible.
Bass Fault/Almurta Fault
The Bass Fault is a NE-SW trending reverse fault located to the east of the Heath Hill Fault. Geoscience Australia
(2020) lists the fault as 57.6 km in length, dipping to the southeast. The fault trace is mapped based on its
topographic expression, with an estimated vertical displacement across the fault of 45 m. This fault is suggested to
be neotectonically active based on displaced Neogene fluvial deposits across the fault scarp. One single
earthquake has been recorded in proximity to the Bass Fault, with a magnitude 3.1 recorded in 1987 (discussed
further in Section 3.2.5 ).
The Almurta Fault (located further east) is often considered as continuous with the Bass Fault, however
Geoscience Australia (2020) does not consider this to be the case. The 1:250 000 geological map for Warragul
(VandenBerg, 1997) also maps these two structures as separate faults.
Other than the fault trace, not much else is known about the Almurta Fault, which is not classified as a neotectonic
feature on the Neotectonic Features database (Geoscience Australia, 2020).
3.2.5 Neotectonics
In a search of Geoscience Australia’s Earthquakes@GA database (2021), only two earthquakes with a magnitude
greater than 3.0 have been recorded in the 10 km surrounding the proposed quarry site (Figure 10). The most
recent of those was a magnitude 3.3 which occurred on 20 December 1987, approximately 600 m from the
proposed quarry. Another earthquake was recorded on 18 September 1980, this time 8.5 km to the southeast of
the proposed site (magnitude 3.1).
Due to the age of these events, the records for these earthquakes are incomprehensive, recording only the time
and location, and not attributed to a specific fault. Based on location alone, it is likely that the 1980 event occurred
on the Bass Fault, while the 1987 event occurred in between the Wellington Fault and the Heath Hill Fault.
Based on the earthquake record, large earthquakes are uncommon in the area, with a magnitude 5.0 at the mouth
of Western Port Bay being the largest recorded in 1971. However, the area remains seismically active in the
Australian context, with smaller earthquakes recorded every few years, the majority recorded within the South
Gippsland Highlands. Given the present-day stress field of Australia (Rajabi et al., 2017) and the strike of the
mapped faults in the immediate area, the Heath Hill Fault and the Bass Fault are the most likely faults near the
proposed quarry location to experience a future fault rupture.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 13
Figure 10 Earthquake and Geological Map of the Lang Lang Area. Earthquake ≥ Magnitude 3.0 Shown
3.3 Hydrogeology
The groundwater table at the WA7541 proposed quarry site was interpreted using Visualising Victoria’s
Groundwater (VVG), a web based software that federates groundwater data from disparate sources. The depth to
water table is depicted in Figure 11. It is noted that this depth to groundwater is generally consistent with the
information recorded on the provided lithology logs.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 14
Figure 11 Depth to Groundwater at the WA7541 Site (VVG, 2021)
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 15
and as such, a range in typical effective strengths has been outlined in Table 1, which is based on the batter
stability observations including measurements of stable batter profile, slope analyses and follow-up geotechnical
reviews performed for proximate sand quarries.
For the proposed 5575 South Gippsland Highway quarry, GHD is of the opinion that suitable and appropriate
geotechnical information is available to reasonably undertake slope stability modelling. Accordingly, GHD
considers that the material parameters (including Mohr-Coulomb strength parameters) in Table 1 are suitable for
use in slope stability calculations.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 16
Figure 13 Summary of Effective Strength Distribution (Friction Angle)
As depicted in Figure 15, GHD notes that the material strength parameters adopted for WA7541 are conservative
(lower bound) in comparison to the spectrum of typical friction angles (after Terzaghi and Peck, 1967).
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 17
Figure 14 Schematic of a circular failure
Circular failure is dependent upon the shear strength characteristics of the soil materials (e.g., sand resources),
the slope angle of the cut face and the phreatic conditions within the soil materials.
Circular failure occurring as a potential failure mechanism has been identified primarily for the overburden and
resource units at the site. This failure mechanism is not considered to pose any significant risk, providing adequate
surface water management measures are coupled with a suitable pit geometry.
The typical subsurface profile of the proposed development is shown below in Figure 16, which includes cohesive
soils (i.e., clays and silts) overly mostly sand resources, with discontinuous and relatively thin layers of interburden
(i.e., clays and silts).
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 18
Figure 15 Example of Erosion of Exposed Sand Batters at Nearby Quarry
Piping can occur as water infiltration or perched water may drain via weak zones in the in-situ materials causing
the soil to wash out and undercut overlying batters. This can potentially lead to batter instability if not suitably
managed. Based on the encountered materials, it is likely that the primary mechanism of failure is circular failure.
Circular failure can also result, particularly where the standing groundwater level interfaces with the exposed sand
batters above pond level. Undercutting of the base/foundation could potentially increase the likelihood of circular
failure of the overlying batter slope. This instability mechanism can be managed with suitable batter design
(including offset from base of slope) and surface water management. The secondary mechanism of potential
instability can occur from erosion of exposed batters, as the initiation of instabilities within exposed soil units are
usually governed by build of pore water pressures as a result of uncontrolled / excessive surface water ingress.
This can lead to a decrease in material strength and eventuate as slumping and / or sloughing of batters.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 19
3.6 Geotechnical Considerations
3.6.1 Seismic Loading
The Melbourne area inclusive of the WA 7541 site is within a relatively intermediate to high risk seismic zone.
GHD has undertaken additional stability assessments on the critical slope profiles to determine the sensitivity of
the proposed pit to seismic events.
According to the ‘Atlas of Seismic Hazard Maps of Australia’ 2013, Melbourne and surrounding areas have among
the highest Peak Ground Acceleration (PGA) compared to the rest of the nation. The Spectral Acceleration (SA)
hazard value at 500 and 2500 year return periods (ARI) are PGA 0.0627 g (refer to Figure 17) and PGA 0.1704 g
respectively. Stability assessments have been done in accordance with the CSIRO (2009) guidelines for a 1 in 500
ARI.
Figure 17 Seismic Hazard Map of Victoria for 1/500 year Return Period
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 20
3.8 Design Acceptance Criteria
The nomination of suitable acceptance criteria is a key part of the design and development of stability
management protocols. It provides a basis to evaluate the calculated stability performance (e.g. deterministic
Factor of Safety (FoS) of batters against the nominated criteria, with due consideration of the likely scale of the
potential instability and the associated consequences posed by it. Design acceptance criteria for the proposed site
have been nominated in line with accepted industry practice as outlined by DJPR (2020) Geotechnical guideline
for terminal and rehabilitated slopes for the extractives industry projects, and published precedents as outlined in
CSIRO’s ‘Guidelines for Open Pit Slope Design’, (Stacey and Read, 2009).
Based on above outlined aspects, and in light of the anticipated risk of instability within the confines of the site, the
following design acceptance criteria has been nominated:
– A Factor of Safety of 2.0 is proposed for all Rehabilitated batters
– A Factor of Safety of 1.6 is proposed for Terminal batters
– A Factor of Safety of 1.3 is proposed for Operating batters
– A Factor of Safety of 1.1 for seismic conditions
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 21
Figure 18 Section A-A’ – Critical Pit Geometry
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 22
Dredging Off-set Distance
1.32
1.30
1.28
Factor of Safety (FoS)
1.26
1.24
1.22
1.20
1.18
1.16
0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0
Off-set distance (m)
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 23
4. Geotechnical Management Process
4.1 General
Outlined within this section are the respective geotechnical and ground stability management protocols that will be
implemented at the WA7541 site to ensure that worker safety and risk to external receptors are not compromised.
The overall geotechnical risk management framework within sand quarries such as the ACM Lang Lang site
consists of the following considerations:
– Employment of suitable slope formation techniques
– Robust geotechnical monitoring protocols
– Appropriate response approaches to potential geotechnical hazards
Outlined below are the requirements for these considerations within the WA7541 Site.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 24
– Risk assessments contained within this document
– Stability assessments – including the development of trigger levels
– Actual field conditions and stability performance history (noting the rehabilitated areas will allow more stable
conditions to be achieved, reduced ground movement and optimisation of monitoring requirements in the form
of monitoring network intensities and frequencies)
The proposed monitoring system for the WA7541 site will involve the systematic recording of regular visual
inspections supplemented with periodic collection of data obtained from a network of survey monitoring points
distributed at a relatively wide spacing around the planned pit crest. Refer to Table 4 for timeframes and roles and
responsibilities.
If movement is indicated, a more extensive and possibly more sophisticated program can be implemented building
upon the initially proposed system.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 25
The stability of instrument stations can be checked by resurveying the control network or reference stations each
time the instrument station is used. Care must be taken to ensure sufficient observations are made to all reference
stations on a regular basis.
Data from the survey monitoring should be plotted and assessed after each set of reading. If movement is
detected, monitoring frequency of secondary points will depend on the size of the potential block dimension and
movement rates. These protocols are further reflected in the stability management TARP (Trigger Action
Response Plan) outlined in Section 4.5.
If instability is detected, additional secondary monitoring points may be established in the area to determine the
size, failure geometry and movement rates, and to assist in the planning of remedial measures.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 26
Table 4 Summary of Pit Wall Stability Monitoring Procedures
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 27
Table 5 TARP for Slope Condition
Potential for actual Potential or actual fretting/erosion Potential or actual fretting/erosion of batter Potential or actual fretting/erosion of batter
fretting, erosion, of batter face involving ≥ 25 m3 face involving ≥ 25 m³ volume (and < 100 face involving ≥ 100 m³ volume.
minor cracks, volume (and < 100 m³); ground m³).
seepage or ground movement / displacement with Ground movement / displacement with
displacement. (< 25 cracks dilated >5 mm and over Ground movement / displacement with Cracks dilated > 50 mm and over 10 m
Condition of m3 in volume). 10 m length. cracks dilated >20 mm and over 10 m length.
quarry slopes length.
Cracks dilated ≤ 20 mm and up to Uncontrolled water flow.
20 m length. Cracks dilated ≤ 40 mm and up to 20 m
length.
Pooled water ≤ 25 m2 area.
Pooled water > 25 m2 area.
Person
Responses
Responsible
Monitor production Monitor production activities. Liaise with shift supervisor, assess situation Inspect area from outside the failure zone
activities. Communicate with quarry and inspect as required. Communicate with and report to quarry manager. Implement
geotechnical engineer. geotechnical consultant. Notify stakeholders recovery plan once formulated (risk
as required. assessment required).
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 28
Alert Green Yellow Orange Red
Shift / Report with daily Monitor slope conditions Communicate with workforce that an orange Communicate with workforce that a red
Production production plan throughout shift. Report any level has been reached. Closely monitor level has been reached and withdraw
noticeable change in conditions to slope conditions throughout shift. Report personnel and equipment to a safe
Supervisor Routine mapping and the quarry geotechnical engineer. any noticeable change in conditions to the location. Secure to prevent entry. Inspect
monitoring. Report any change of conditions quarry manager. Report any change of area from outside the failure zone and
or change in TARP level to the conditions or change in TARP level to the report to superintendent and quarry
next shift. next shift. Engage with a geotechnical manager immediately. Implement recovery
consultant, as required. plan once formulated (risk assessment
required).
Assess area. Determine Evaluate the monitoring data and provide Inspect, investigate and formulate recovery
frequency of inspections, recommendation for TARP level advance. plan (formal risk assessment required).
monitoring and remedial work. Assess area. Determine frequency of Report findings to quarry management.
Notify management of any inspections, increased monitoring and
change. Communicate with quarry remedial work. Notify management of any
workers the location, nature and change.
expected conditions associated
with the failure.
Quarry worker Report with daily Become familiar with location and Elevate level of awareness and monitor pit Comply with emergency evacuation
production plan potential change in pit slope slope conditions during shift and provide procedures and withdraw to a safe location.
condition during shift. Report any feedback on pit slope conditions.
significant change in conditions to
shift supervisor. Report with daily
production plan.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 29
5. Geotechnical Risk Assessment
5.1 General
The geotechnical risk assessment is a quantitative assessment based on the ‘likelihood’ and ‘consequence’ of a
major geotechnical hazard occurring.
The qualitative risk assessment process has been utilised, as outlined in the risk assessment matrix presented in
Table 7 which aligns with the Australian Standard for Risk Management AS/NZ Standard 4360 (Standards
Australia 2004). Table 35 outlines the risk rating acceptability.
Mechanism Description
Hazard 1 Potential for small scale circular instability, as a result of
Slumping/erosion of sand batters, slumping of internal slumping and / or sloughing of the any operating, terminal or
stockpiles (including any stacked consolidated slimes remediated sand batter faces and any (temporary)
stockpiles) stockpiles, where applicable.
Potential causes for slumping include, but are not limited to:
– Highly disturbed materials and/or weak planes
encountered during excavation of sand resources.
– Improper surface and groundwater management during
underwater extraction around the batter faces or
periphery of stockpiles
– Inappropriate construction geometry.
Could occur due to groundwater drawdown in the region
surrounding the quarry. Suitable construction of the lower
slopes would be required if groundwater levels drop below
current levels (i.e., 5 m bgsl).
Hazard 2 Larger scale slope volume movements that are governed by
Deep seated circular instability the soil shear strength characteristics.
– Slope instability occurs when the driving forces are
greater than the resisting forces.
– Movement of this hazard occurs in a circular/rotational
manner and is dependent upon the slope geometry,
material strength and groundwater conditions.
– Consequences of this type of hazard can include partial
or full loss of pit crests and impacting working benches /
crane pads.
– Could occur due to groundwater drawdown in the region
surrounding the quarry. Suitable construction of the
lower slopes would be required if groundwater levels
drop below current levels (i.e., 5 m bgsl).
In extreme cases the failure zone may migrate some
distance from the pit crest which may exceed the work
authority boundary.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 30
Mechanism Description
Hazard 3 Represented by small to large volumes of inflow into the
Erosion or piping between nearby quarries. excavation.
– The failure mechanism (i.e., erosion or piping) could
manifest from water flow in the sand between nearby
quarries.
The consequence of this may range from a minor to full loss
of the overlying pit crest but is dependent on volume of flow
between the two pits.
Hazard 4a Potential for small scale circular instability to occur above
Slumping of sand batters above beaching zone. the water line (or beaching point).
– This mechanism may be exacerbated due to
undercutting of the submerged slopes, highly disturbed
(very loose) materials, weak planes encountered during
excavation of sand resources.
This mechanism may also result due to improper surface
and groundwater management during underwater extraction
or inappropriate construction geometry.
Hazard 4b Potential for medium to large scale circular instability to
Slumping of sand batters below beaching zone. occur due to slumping of batter below the water line, leading
to propagation of a failure above the water line.
– This mechanism may be exacerbated due to
undercutting of the submerged slopes, highly disturbed
(very loose) materials, weak planes encountered during
excavation of sand resources.
This mechanism may also result due to improper surface
and groundwater management during underwater extraction
or inappropriate construction geometry.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 31
6. Geotechnical Hazard Management
6.1 Hazard Assessment Process
An ongoing hazard assessment process is applied at the WA7541 Quarry, resulting in risk-based decision-making
at all stages of quarry planning, design, development / construction / operations, and progressive rehabilitation /
closure. The previous section summarised the anticipated instability mechanisms that pose potential threats to
stable ground conditions in the proposed sand quarry. These hazards have been further evaluated as part of the
geotechnical risk assessment process, using the risk rating matrix outlined in Appendix A3 of the ‘Preparation of
Work Plans and Work Plan Variations – Guideline for Extractive Industry Projects’, dated December 2020,
prepared by DJPR.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 32
Figure 21 ERR Risk Matrix (DJPR, 2020)
Figure 21 must be applied to each identified hazard, by selecting a consequence and likelihood according to the
guidelines. The risk matrix is designed to work in conjunction with the site geotechnical log. The log is designed to
identify the risk, classify the risk and describe the actions required to minimise the risk.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 33
Figure 23 Hierarchy of Controls
– Elimination - The hazard can be quarried out or removed from the site.
– Substitution – Modifications to the quarry design and operational procedures.
– Isolation – Delineating the area of concern to restrict access (e.g. bunding, windrows, fencing etc.).
– Engineering Controls – Revised slope design to improve stability (e.g. buttressing and safety berms etc.) or
improving knowledge of slope responses using additional monitoring equipment.
– Administrative – Communication of geotechnical hazards, geotechnical reporting and safety documentation
(e.g. safe work method statements (SWMS).
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 34
Table 7 WA7541 Quarry Pit Risk Rating
Element at Quarry Hazard type Likelihood Consequence Risk Corrective / Likelihood Consequence Residual Comments
risk Boundary Category1 Rating Management Category1 Risk Rating
Action(s)
Internal All batters Hazard Type 1 – Possible Moderate Medium GPS monitoring Unlikely Moderate Medium – Establish exclusion zone(s) for pedestrian i.e., on-site personnel
Batters - Small scale (movement); – Regular visual observations/monitoring undertaken
Personnel slumping/erosion of Regular inspections
safety and sand batters for signs of – Avoid quarry activities that would knowingly decrease the stability of batters and stockpiles,
Quarry Mobile instability; i.e., undercutting. These stockpiles (including any temporary stacked consolidated slimes
Plant Monitoring of stockpiles) will be maintained in accordance with the ACT EPA (2019) guidelines.
groundwater; – Ensure surface water drainage systems are adequately maintained to reduce water ingress
Geotechnical into slope material.
excavation control; – Pond water levels should be maintained to minimise the potential for instability of
Surface water submerged batters, as lowering of the pond may result in instabilities occurring in
managed in previously submerged batters.
accordance with site
– Suitable stand-off distances for haul trucks and vehicles will be maintained from the crest
instituted
of the underside batter and from the toe of excavated batters.
management plan.
– Bunding will be constructed to reduce the risk of vehicle roll-overs.
Hazard Type 2 – Rare Major Medium GPS monitoring Rare Moderate Medium – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel.
Deep seated circular (movement); – Regular visual observations/monitoring undertaken.
instability Regular inspections
for signs of – Avoid quarry activities that would knowingly decrease the stability of batters and stockpiles,
instability; i.e., undercutting. These stockpiles (including any temporary stacked consolidated slimes
Monitoring of stockpiles) will be maintained in accordance with the ACT EPA (2019) guidelines.
groundwater; – Ensure surface water drainage systems are adequately maintained to reduce water ingress
Geotechnical into slope material.
excavation control; – Pond water levels should be maintained to minimise the potential for instability of
Surface water submerged batters, as lowering of the pond may result in instabilities occurring in
managed in previously submerged batters.
accordance with site
– Groundwater monitoring data will be collected regularly to identify any adverse trends (if
instituted
any).
management plan.
Hazard Type 3 – Rare Moderate Medium GPS monitoring Rare Minor Low – Regular visual observations/monitoring undertaken
Erosion or piping (movement); – Ensure surface water drainage systems are adequately maintained to reduce water ingress
between nearby Regular inspections into slope material.
quarries. for signs of
instability; – Pond water levels should be maintained to minimise the potential for instability of
Monitoring of submerged batters, as lowering of the pond may result in instabilities occurring in
groundwater and previously submerged batters.
pond levels;
Geotechnical
excavation control;
Surface water
managed in
accordance with site
instituted
management plan
Hazard Type 4a– Possible Minor Medium Daily inspections; Unlikely Minor Low – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel
Slumping of sand Suitable as- – Regular visual observations/monitoring undertaken
batters above constructed
beaching zone. geometry; Erosion – Avoid quarry activities that would knowingly decrease the stability of batters and stockpiles,
control measures; i.e., undercutting. These stockpiles (including any temporary stacked consolidated slimes
Hazard Type 4b– stockpiles) will be maintained in accordance with the ACT EPA (2019) guidelines.
Slumping of sand Dedicated site
batters water level surface water – Ensure surface water drainage systems are adequately maintained.
leading to instability management plans – Where ‘soft’ ground conditions are encountered at the waterline interface, a geotechnical
of above water level will be implemented; engineer should inspect the area to ensure stability related risks are minimised.
GPS monitoring and
batters. – Any plant (fixed or mobile) should be located at a safe standoff distance from the crest of
/ or prisms and pins
the interface. A field bearing capacity assessment, using Dynamic Cone Penetrometers,
should be installed.
should be undertaken within these locations, prior to undertaking any underwater extraction
(min. blow count 6 per 100 mm of penetration).
1
Determined on the basis of the critical credible or reasonable outcome, which takes into consideration the temporal exposure of at-risk elements.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 35
Element at Quarry Hazard type Likelihood Consequence Risk Corrective / Likelihood Consequence Residual Comments
risk Boundary Category1 Rating Management Category1 Risk Rating
Action(s)
Quarry Internal Hazard Type 1 – Possible Moderate Medium GPS monitoring Unlikely Minor Low – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel.
infrastructure Small scale (movement); – Regular visual observations/monitoring undertaken
slumping/erosion of Regular inspections
sand batters for signs of – Avoid quarry activities that would knowingly decrease the stability of batters and stockpiles,
instability; i.e., undercutting. These stockpiles (including any temporary stacked consolidated slimes
Monitoring of stockpiles) will be maintained in accordance with the ACT EPA (2019) guidelines.
groundwater; – Ensure surface water drainage systems are adequately maintained to reduce water ingress
Geotechnical into slope material.
excavation control; – Pond water levels should be maintained to minimise the potential for instability of
Surface water submerged batters, as lowering of the pond may result in instabilities occurring in
managed in previously submerged batters.
accordance with site
– Suitable stand-off distances for haul trucks and vehicles will be maintained from the crest
instituted
of the underside batter and from the toe of excavated batters.
management plan.
– Bunding will be constructed to reduce the risk of vehicle roll-overs.
Hazard Type 2 – Possible Minor Medium GPS monitoring Unlikely Minor Low – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel.
Deep seated circular (movement); – Regular visual observations/monitoring undertaken.
instability Regular inspections
for signs of – Avoid quarry activities that would knowingly decrease the stability of batters and stockpiles,
instability; i.e., undercutting. These stockpiles (including any temporary stacked consolidated slimes
Monitoring of stockpiles) will be maintained in accordance with the ACT EPA (2019) guidelines.
groundwater; – Ensure surface water drainage systems are adequately maintained to reduce water ingress
Geotechnical into slope material.
excavation control; – Pond water levels should be maintained to minimise the potential for instability of
Surface water submerged batters, as lowering of the pond may result in instabilities occurring in
managed in previously submerged batters.
accordance with site
– Groundwater monitoring data will be collected regularly to identify any adverse trends (if
instituted
any).
management plan.
Hazard Type 4a – Possible Moderate Moderate Daily inspections; Unlikely Minor Low – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel
Slumping of sand Suitable as- – Regular visual observations/monitoring undertaken
batters above constructed
beaching zone. geometry; Erosion – Avoid quarry activities that would knowingly decrease the stability of batters and stockpiles,
control measures; i.e., undercutting. These stockpiles (including any temporary stacked consolidated slimes
Hazard Type 4b– stockpiles) will be maintained in accordance with the ACT EPA (2019) guidelines.
Slumping of sand Dedicated site
batters water level surface water – Ensure surface water drainage systems are adequately maintained.
leading to instability management plans – Where ‘soft’ ground conditions are encountered at the waterline interface, a geotechnical
of above water level will be implemented; engineer should inspect the area to ensure stability related risks are minimised.
GPS monitoring and
batters. – Any plant (fixed or mobile) should be located at a safe standoff distance from the crest of
/ or prisms and pins
the interface. A field bearing capacity assessment, using Dynamic Cone Penetrometers,
should be installed.
should be undertaken within these locations, prior to undertaking any underwater extraction
(min blow count 6 per 100 mm of penetration).
Stockpiles Internal Hazard Type 4a: Unlikely Minor Low Stockpiles designed Unlikely Minor Low – Establish exclusion zone(s) for pedestrian i.e., on-site personnel
Slumping of in accordance with – Regular visual observations/monitoring undertaken
stockpiles DPI (2010); Surface
water managed in – Avoid quarry activities that would knowingly decrease the stability of stockpiles, i.e.,
accordance with site undercutting. These stockpiles (including any temporary stacked consolidated slimes
instituted surface stockpiles) will be maintained in accordance with the ACT EPA (2019) guidelines.
water management – Ensure surface water drainage systems are adequately maintained.
plan; Avoid – Ensure that foundation area of stockpiles is suitable prior to placement.
saturation of the
– Suitable stand-off distances for haul trucks and vehicles will be maintained from the toe of
stockpiled material.
any stockpiled material.
South West and Hazard Type 2 – Rare Moderate Medium GPS monitoring Rare Moderate Medium – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel.
Gippsland South Deep seated circular (movement); – Regular visual observations/monitoring undertaken.
Highway instability Regular inspections
for signs of – Avoid quarry activities that would knowingly decrease the stability of batters and stockpiles,
instability; i.e., undercutting. These stockpiles (including any temporary stacked consolidated slimes
Monitoring of stockpiles) will be maintained in accordance with the ACT EPA (2019) guidelines.
groundwater; – Ensure surface water drainage systems are adequately maintained to reduce water ingress
Geotechnical into slope material.
excavation control;
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 36
Element at Quarry Hazard type Likelihood Consequence Risk Corrective / Likelihood Consequence Residual Comments
risk Boundary Category1 Rating Management Category1 Risk Rating
Action(s)
Surface water – Pond water levels should be maintained to minimise the potential for instability of
managed in submerged batters, as lowering of the pond may result in instabilities occurring in
accordance with site previously submerged batters.
instituted – Groundwater monitoring data will be collected regularly to identify any adverse trends (if
management plan. any).
Noise/ West and Hazard Type 2 – Unlikely Moderate Medium Regular inspections Unlikely Minor Low – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel.
screening South Deep seated circular for signs of – Regular visual observations/monitoring undertaken.
bund instability instability;
Monitoring of – Avoid quarry activities that would knowingly decrease the stability of batters and stockpiles,
groundwater; i.e., undercutting. These stockpiles (including any temporary stacked consolidated slimes
Geotechnical stockpiles) will be maintained in accordance with the ACT EPA (2019) guidelines.
excavation control; – Ensure surface water drainage systems are adequately maintained to reduce water ingress
Surface water into slope material.
managed in – Pond water levels should be maintained to minimise the potential for instability of
accordance with site submerged batters, as lowering of the pond may result in instabilities occurring in
instituted previously submerged batters.
management plan.
– Groundwater monitoring data will be collected regularly to identify any adverse trends (if
any).
Beach Energy East / North Hazard Type 2 – Rare Major Medium GPS monitoring Rare Moderate Medium – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel.
(Bass Gas) Eastern Deep seated circular (movement); – Regular visual observations/monitoring undertaken.
Plant instability Regular inspections
for signs of – Ensure surface water drainage systems are adequately maintained to reduce water ingress
instability; into slope material.
Monitoring of – Pond water levels should be maintained to minimise the potential for instability of
groundwater; submerged batters, as lowering of the pond may result in instabilities occurring in
Geotechnical previously submerged batters.
excavation control; – Groundwater monitoring data will be collected regularly to identify any adverse trends (if
Surface water any).
managed in
accordance with site
instituted
management plan.
Residential West, East Hazard Type 2 – Rare Moderate Medium GPS monitoring Unlikely Minor Low – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel.
Property and South Deep seated circular (movement); – Regular visual observations/monitoring undertaken.
instability Regular inspections
for signs of – Ensure surface water drainage systems are adequately maintained to reduce water ingress
instability; into slope material.
Monitoring of – Pond water levels should be maintained to minimise the potential for instability of
groundwater; submerged batters, as lowering of the pond may result in instabilities occurring in
Geotechnical previously submerged batters.
excavation control; – Groundwater monitoring data will be collected regularly to identify any adverse trends (if
Surface water any).
managed in
accordance with site
instituted
management plan.
Realigned North and Hazard Type 2 – Rare Major Medium GPS monitoring Rare Moderate Medium – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel.
waterway North East Deep seated circular (movement); – Regular visual observations/monitoring undertaken.
(MW asset instability Regular inspections
RD2504) for signs of – Avoid quarry activities that would knowingly decrease the stability of batters and stockpiles,
instability; i.e., undercutting. These stockpiles (including any temporary stacked consolidated slimes
Monitoring of stockpiles) will be maintained in accordance with the ACT EPA (2019) guidelines.
groundwater; – Ensure surface water drainage systems are adequately maintained to reduce water ingress
Geotechnical into slope material.
excavation control; – Pond water levels should be maintained to minimise the potential for instability of
Surface water submerged batters, as lowering of the pond may result in instabilities occurring in
managed in previously submerged batters.
accordance with site
– Groundwater monitoring data will be collected regularly to identify any adverse trends (if
instituted
any).
management plan.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 37
Element at Quarry Hazard type Likelihood Consequence Risk Corrective / Likelihood Consequence Residual Comments
risk Boundary Category1 Rating Management Category1 Risk Rating
Action(s)
Access Road East Hazard Type 2 – Rare Major Medium GPS monitoring Rare Minor Low – Establish exclusion zone(s) for pedestrian, i.e., on-site personnel.
Deep seated circular (movement); – Regular visual observations/monitoring undertaken.
instability Regular inspections
for signs of – Ensure surface water drainage systems are adequately maintained to reduce water ingress
instability; into slope material.
Monitoring of – Pond water levels should be maintained to minimise the potential for instability of
groundwater; submerged batters, as lowering of the pond may result in instabilities occurring in
Geotechnical previously submerged batters.
excavation control; – Groundwater monitoring data will be collected regularly to identify any adverse trends (if
Surface water any).
managed in
accordance with site
instituted
management plan.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 38
6.8 Risk Assessment Results
The geotechnical risk assessment for WA7541 site is summarised in Table 7.
Based on the risk assessment presented below, the residual risk to external receptors has been assessed to be
“Low”.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 39
7. Quarry Closure and Rehabilitation
7.1 Rehabilitation Strategy
The following progressive rehabilitation strategies are recommended for the WA7541 Quarry site:
– Store all topsoil for use on site that can later be used to cover and revegetate disturbed land, and thereby
reducing surface erosion and improving slope stability. Where possible topsoil will be used in the creation of
‘self-sustaining’ landforms that are vegetated with indigenous flora sourced from the local area, be of local
provenance, and be appropriate to the site’s Ecological Vegetation class.
– Store overburden in stockpiles for future use e.g. select back fill material. These stockpiles will be constructed
and maintained in line with the EPA publication ‘Construction Techniques for Sediment Pollution Control’, to
ensure the likelihood of erosion related instabilities (slumping / sloughing etc.) are mitigated.
As far as practicable, progressive rehabilitation should be incorporated into daily operations to achieve the best
outcome.
– The following long-term rehabilitation strategies are recommended for the WA7541 Quarry site:
– Undertake final landform slope stability and erosion assessments to understand the nature of the final
rehabilitation concept.
– Undertake ground movement and groundwater monitoring at regular intervals until revegetation has
established and rehabilitated batters are ‘self-sustaining’, safe and stable as defined in Section 1.2.
– Should there be any material changes to the stability conditions at the site, the stability assessment and the
long-term rehabilitation plan should be reviewed accordingly.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 40
Item Rehabilitation / Closure Criteria Elements to be Monitored Frequency
No erosion channels greater than 50 Y4 - 12 Monthly
mm deep and/or wide: remedial action Additional inspections after
initiated immediately significant rainfall events.
No more than 5 erosion channels
greater than 20 mm deep and/or wide
within a 20 m wide area remedial
action initiated immediately
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 41
8. Review and Audit
This GCMP is considered to be ‘live’ document, i.e. requires continual review and is to be updated as required. In
general, updates to this GCMP should include, at a minimum, the following:
Site geotechnical conditions and hazard management
– Review of ground control management.
– Review of data collection and monitoring.
– Stability and suitability (i.e. safe and stable) of quarry pit design
• The outcomes of the geotechnical inspections undertaken of the excavated batters can assist with
assessing stability performance and subsequently verify/refine the material characteristics adopted for
the site. This observational approach is considered suitable for the site and the outcomes of which can
be utilised to update this GCMP, as required.
– Implementation of the GCMP.
– Compliance with this GCMP.
– Effectiveness and validity of this GCMP.
– Responsibilities and accountabilities are being met.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 42
9. References
ACT Environment Protection Authority (2019), Guideline for Stockpile Management, ACT Government, November
2019.
Australian Standards 1726 (2017) – ‘Geotechnical Site Investigations’.
Carillo-Rivera, J. J. (1975). Hydrogeology of Western Port, Geological Survey of Victoria Survey Report, 1.
Casagrande, A., 1948. Classification and identification of soils. Transactions, ASCE, vol. 113, pp901-930.
CMPA, 2016, ‘Working Safely with Geotechnical Risks in Quarries’, Guideline prepared by the Construction
Material Processors Association (CMPA), February, 2016, Issue 1.
DJPR, 2020, ‘Preparation of Works and Work Plan Variations – Guideline for Extractive Industry Projects’,
Department of Jobs, Precincts and Regions, December 2020.
DJPR, 2020, ‘Geotechnical Guidelines for Terminal and Rehabilitated Slopes: Extractives Industry Projects,
Department of Jobs, Precincts and Regions, September 2020.
DPI, 2010, ‘Code of Practice for Small Quarries’, Department of Primary Industries (DPI), Earth Resources
Regulation (ERR)
DELWP, 2019, Water Management Information System (WMIS), Department of Environment, Land, Water &
Planning, Online Access - http://data.water.vic.gov.au/. Last accessed: 15 October 2019.
Geoscience Australia (2021). Earthquakes@GA Database, Geoscience Australia, Canberra, accessed 15
February 2021.
Geoscience Australia (2020). Australian Neotectonics Database, Geoscience Australia, accessed 30 November
2020.
GeoVic (2014). Victorian Surface Geology (Seamless Geology 2007-2014) database. Retrieved from: http://er-
info.dpi.vic.gov.au/sd_weave/anonymous.html on 19 August 2020.
GHD (2022). 5575 South Gippsland Highway Geotechnical Assessment, GHD Ref: 12527040-45542-13, dated 30
March 2022. (GHD, 2022)
Mark. L., Burbidge, D. R., Edwards, M., 2013. Atlas of Seismic Hazard Maps of Australia: Seismic Hazard Maps
and Hazard Spectra. Record 2013/41: Geoscience Australia: Canberra.
McAndrew, J. & Marsden, M. A. H. (1973). Regional guide to Victorian geology. [Melbourne] School of Geology,
University of Melbourne.
Read, J., Stacey, P., 2009. Guidelines for Open Pit Slope Design, first edition, CRC Press, published 18
November 2009.
Standards Australia and Standards New Zealand (2004) – AS/NZS 4360:2004 – ‘Risk Management’, Sydney,
NSW.
VandenBerg, A.H.M., 1997. Warragul SJ 55-10 Edition 2, 1:250 000 scale Geological Map Series, Geological
Survey of Victoria.
VandenBerg, A. H. M. (2016). Depositional Facies and Extent of the Late Neogene Sandringham Sandstone in
Southern Victoria, Australia, Proceedings of the Royal Society of Victoria, 128, 7-24.
Wallace, M. W., Dickinson, J. A., Moore, D. H. & Sandiford, M. (2005). Late Neogene strandlines of southern
Victoria: a unique record of eustasy and tectonics in southeast Australia, Australian Journal of Earth Sciences, 52,
279-297.
Welch, S. I., Higgins, D. V. & Gallaway, G. A. (2011) eds. Surface Geology of Victoria 1:250 000, Geological
Survey of Victoria, Department of Primary Industries.
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 43
– Environmental Protection and Biodiversity Conservation Act (1999) Cth
– Flora and Fauna Guarantee Act (1988) (Vic)
– Mineral Resources (Sustainable Development) Act 1990 (Vic)
– Mineral Resources (Sustainable Development) (Extractive Industries) Regulations 2019.
– Occupational Health and Safety Act 2004 (Vic)
– Occupational Health and Safety Regulations (2017) (Vic)
– Planning and Environment Act 1987 (Vic)
– State Planning Policy Framework (SPPF, Vic)
– Water Act 1989 (Vic)
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 44
Appendices
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 45
Appendix A
Quarry Inspection Sheet
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 46
General Slope Stability Checklist
General Slope Stability Checklist
Date of Inspected
Inspection by
Benches and haul roads stable and without signs of failure (e.g.,
significant cracking, slumping)
Wide enough for vehicles and suitable rockfall protection and sufficient
toe/ bench catch capacity, debris build-up on benches, loss of bench
width (e.g., from erosion or underlying batter instability)
Access and haul roads in good condition, free draining and without signs
of movement (e.g., cracking, slumping)
Cracking on the surface and crest of the stockpile, heave at the toe of
the stockpile or surface water pooling/ponding
Pit Surrounds
Drainage away from pit, including storm water and surface water
Signage
Crests
Tension cracks increasing in size and/or offsets, sliding of one face of the
crack
Edge Protection Berm (windrows) in place and in order
Faces
Date of Inspected
Inspection by
Crests Yes No
Tension cracks increasing in size and/or offsets, sliding of one face of the
crack
Open structural features inclined steeply > 70 degrees out of the face
Toe
Other observations
ghd.com The Power of Commitment
GHD | Lang Lang Sand Resources Pty Ltd | 12527040 | Ground Control Management Plan 47
This document is in draft form. The contents, including any opinions, conclusions or recommendations contained in, or which may be implied from, this draft document
must not be relied upon. GHD reserves the right, at any time, without notice, to modify or retract any part or all of the draft document. To the maximum extent permitted
by law, GHD disclaims any responsibility or liability arising from or in connection with this draft document.