Fidic Understanding by Yasser Shahin
Fidic Understanding by Yasser Shahin
… YASSER SHAHIN
Submission of L.O.A
Performance Security
Within 28-days after
receiving L.O.A
CL-4.2 EVENTS DIRECTIONS KEY PALN
Sign the
Contract Agreement Final
Within 28-days after Statement
receiving L.O.A Notice not less than 21-days As-Built Docs. + O & M
CL-1.6 to carry-out each test
Proposed Breakdown Prior to start tests on comp.
Of each Lump-sum price within CL-9.1 CL-4.1, lit.(d)
1st installment of 28-days after commencement
Advance Payment Date Tests on Completion
Within 42-days after CL-14.1 28-dayes after notice
issuing L.O.A CL-9.1
CL-14.7
Commencement Date Time for Completion of Works Application for T.O.C Taking Over Certificate
Completion Date
L.O.A Within 42-days after receiving L.O.A E.O.T “if delay is there” = Project duration + Extension of Time (E.O.T)
Not earlier 14-days The Engineer to reply within
28-days
CL-8.1 CL-8.2 CL-10.1
CL-10.1 CL-10.1
Notice of Commencement
Not less than 7-days
CL-8.1
Return of Performance
Engineer to certify 1st half
Security (50%) of Retention money.
Within 21-days of receiving Engineer to certify 2nd half CL-14.9
performance certificate (50%) of Retention money.
CL-4.2 CL-14.9
Statement at Completion
Within 84-days
Final Statement Draft of Final Statement CL-14.10
If Engineer agrees on draft Within 56-days of receiving
performance certificate
Final Statement CL-14.11
Insurance cover is no longer
CL-14.11
Engineer to issue within 28-days required
CL-14.13 Contractor to submit a CL-18.2
Discharge Letter
CL-14.12 Expiry of DLP
“Max. Extension of DLP
not more than 2-years”
CL-11.3
D.L.P)
Defects Liability Period (
CL-11.3
Tips
Programme
The Contractor (not Employer/Engineer) controls the method and sequence of the works. Therefore,
provided the contractor complies with the contract and applicable laws, The Contractor may perform the
works in the manner it think appropriate; subject to any Employer constraints identified in the contract. (CSL-
1.54)
Sub-Clause 8.3 does not empower The Engineer to give or withhold approval, only to notify if the Programme
The Contractor
does not comply with the contract.
The Contractor to submit a detailed programme to
the Engineer within 28-days from notice of
The contractor is obliged to proceed in accordance with the Programme he has submitted in the absence of
commencement. notice from the Engineer that is non-compliant.
CL-8.3 (Programme) The Contractor is under the express obligation to follow the programme, although this obligation is subject to
his other obligations. This role is clearly shown in the requirements of Sub-Clauses 8.3, 4.21(h) and 8.6.
The Engineer The Contractor is required to give notice of probable future events which may adversely affect or delay the
Unless The Engineer give notice to The Contractor actual execution of the works. “this means any event, not just events which may affect the contractual Time for
within 21-days
stating the extent to which the Programme does Completion”
not comply with the contract
programme. Sub-Clause 8.6 provides the basis for the Engineer to monitor progress and to require the Contractor who is in
delay “for reasons which are his responsibility under the contract”, to provide a Programme describing how he
CL-8.3 will accelerate to ensure completion within the time for completion (which to include any granted EOT). This
sub-clause 8.6 only operates when the cause of delay are not ones which fall within sub-clause 8.4.
If the Contractor decides himself to submit a revised Programme in order to comply with its primary
The Contractor obligation to complete the works within time for completion, he does nothing else than to comply with its
The Contractor shall proceed in accordance to obligation under sub-clause 8.3 and he is not in breach of contract. The Employer will then not be entitled to
the programme compensation. By contrast, a contractor who ignores that actual progress is too slow until the Employer
CL-8.3 instructs him to submit a revised Programme in accordance with sub-clause 8.6 must bear additional cost
Agreed upon programme / No incurred by the Employer.
Approved Programme
concerns for the Engineer
The Engineer
If (at any time) The Engineer gives notice (CL-8.3, last
nd
paragraph) or instruction (CL-8.6, 2 paragraph) to the
Contractor that the programme fails to comply with
the Contract or to be consistent with actual progress,
The contractor the Contractor shall submit a revised programme.
The Contractor might also submit a revised CL-8.3, last paragraph
programme whenever the previous programme is
CL-8.6, 2nd paragraph
inconsistent with actual progress or with the
Contractor's obligations. not
rd
CL-8.3, 3 line
The contractor Note: A problem for the Contractor is that if, claiming that the delay warrants further time for completion, he
The Contractor shall submit to the Engineer
refuses to act on the sub-clause 8.6 notice – he might put himself at risk of possible Employer termination under
a Revised Programme under same Sub-clause 15.2 “as having abandoned the works or otherwise plainly demonstrated the intention not to continue
process. performance….”
CL-8.3, CL-8.6
References:
Fidic Red Book 1999, Corbett & Co – Clause 08 and CSL 2002-2nd edition
Permanent work
definition as per
clause 1.1.5.4
The Engineer
Dispute20.2 Interference with tests on Consequences of Force Majeure
Completion CL-19.4
To proceed with determination in “Shall be followed” CL-10.3
accordance to sub-clause 3.5.
CL-20.1, 8th paragraph Contractor to Search
Optional Payment Termination
CL-19.6
CL-11.8
Payment
Where the Engineer has determined an Evaluation Contractor’s Claim (procedural)
amount to be due to the contractor The Engineer to consult with the The Engineer
under sub-clause 3.5, The Contractor is
Yes No Shall make fair determination on the
CL-12.3 CL-20.1
parties to achieve agreement.
entitled to apply for it by way of an matter and shall give notice to both
CL-3.5
interim payment certificate pursuant to parties for each determination/agreement.
sub-clauses 14.3 through 14.8. CL-3.5
CL-20.1, 7th paragraph
The suspended part to be omitted, If The suspended part affected the CL-16.1
and shall be treated under Cl-13 whole project, the Contractor to
“Variations & Adjustments”. give notice of termination under Cl-
CL-8.11 16.2 “Termination by Contractor”.
CL-8.11
+
Notice to Terminate effect after 28-days after the
works, as in Cl-8.11. with the contract agreement (Cl-
later dates of: 1.6) as regards signing of contact
CL-15.2 1. The Contractor receives
Or agreement and assignment of
the Notice; or contract (Cl-1.7).
2. The Employer returns the
The Contractor becomes
The Employer may by Notice Performance Security. Bankruptcy/insolvency
bankrupt or insolvent, etc.
terminate the Contract B. The Employer shall not
of the Employer or has
terminate the contract to
Immediately. gone into liquidation.
execute the works himself or
The Contractor gives or offers
by another contractor.
bribe, gift, etc. CL-15.2 C. After this termination Cl-16.3
& 19.6 shall be applied. If Notice
Takes effect
CL-15.5
Then and after terminating the contract; Then the Employer shall to:
1. The Employer may complete the works and/or any other entities to do so. 1. Return Performance Security
Cl-15.2 2. Pay the contractor according
2. The Employer shall give notice that contractor’s Equip. at or near site. Cl- to Cl-19.6 and,
15.2 3. Pay any amount of loss of
3. After Notification has been affected, The Engineer to proceed with his profit, loss or damages.
determination. Cl-15.3 Cl-16.4