Tender Summary (RAW)

The document outlines the tender for a 5 MW, 10 MWh Battery Energy Storage System (BESS) plant at Nachna, Rajasthan, with a bid submission deadline of June 23, 2025. It includes details on project scope, financial and technical qualifying criteria, and performance guarantees. The tender is open for consortium bids and specifies conditions for project completion and payment terms.

Uploaded by

himm31177
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views3 pages

Tender Summary (RAW)

The document outlines the tender for a 5 MW, 10 MWh Battery Energy Storage System (BESS) plant at Nachna, Rajasthan, with a bid submission deadline of June 23, 2025. It includes details on project scope, financial and technical qualifying criteria, and performance guarantees. The tender is open for consortium bids and specifies conditions for project completion and payment terms.

Uploaded by

himm31177
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Tender Summary

Version 1 Date: 18.06.2025


Page No.
1 Project scope EPC 5 MW 10MWh BESS PLANT AT NACHNA , COMC Post Defect 15
Liability Period for 1st Year , COMC Post Defect Liability Period for
2nd Year , COMC Post Defect Liability Period for 3rd Year , COMC
Post Defect Liability Period for 4th Year , COMC Post Defect
Liability Period for 5th Year , COMC Post Defect Liability Period
for 6th Year , COMC Post Defect Liability Period for 7th Year ,
COMC Post Defect Liability Period for 8th Year , COMC Post
Defect Liability Period for 9th Year , COMC Post Defect Liability
Period for 10th Year , COMC Post Defect Liability Period for 11th
Year
2 Tender No GEM/2025/B/6299098
3 Location latitude 27°27'21.4"N, longitude 71°43'59.0"E in Nachna 10
reservoir; District: Jaisalmer; State: Rajasthan
4 MSME Exemption for No
Document Fee and EMD
5 Document Fee No
6 Processing Fee No
7 Cost of EMD 10,00,000
8 Date and time of bid 23rd June 2025
submission
9 Date and time of bid Not applicable
submission (Hard Copy)
10 Date and time of bid Same day i.e. 23rd June 2025
opening
11 Mode of Submission Online 554
12 Date and time of Pre bid _
meeting
13 JV/ Consortium Yes, A consortium including an unincorporated JV 489
14 Performance Bank 5% of EPC Contract value with validity of 24 months 566
Guarantee (PBG)
15 Tender Type EPC
16 Qualifying Criteria 1. Financial criteria: The Average Annual Financial Turn over 487
during the last three (3) years ending on ending 31st March
2025 should be at least Rs. 405 Lakhs. While computing the
annual turnover, other income shall not be considered.
2. Technical criteria: Design, Engineering, Supply, Construction,
Erection, Testing and Commissioning on turnkey basis of
BESS (Battery Energy Storage System) Power Systems/ Solar
PV-BESS Hybrid Projects with EMS (Energy Management
System) of minimum capacity of 1 MWh or above at single
location, and with Comprehensive Operation & Maintenance
for at least (1) year period.

17 Qualifying Criteria in Case  Technical qualification criteria shall be fulfilled by at least 489
of Consortium one constituent member of Consortium/ JV
 Financial qualification criteria shall be fulfilled by at least
one constituent member of Consortium/ JV
18 Use of Financial Strength NA
of Affiliate
19 PPA NA
20 Project Bid Size 5 MW/ 10 MWh BESS
21 Grid Connectivity Bidder shall also submit detailed grid compliance study with 44
Power Plant Controller as per CEA technical standards to grid
connectivity standard to grid connectivity and latest guideline of
SLDC first charging clearance.

22 Project completion (SCOD) After the successful completion of the trial run 37
23 Criteria for Power Supply Self-arrangement except for storage yard 16
24 Reverse Auction NA
25 Implementation Schedule 496

26 LD on project delay 0.5% (half percent) of the total contract value for every week of 497
the delay subject to a maximum of 5% of the total contract value.
27 Bid Validity -
28 LOI/LOA Date not specified
29 Important Points to be  Floating Solar Project of 9MW/11.5MWp is in progress at 15,
considered Nachna and power evacuation is via behind the meter 26,
552
mechanism at 33KV level.
 Construction of interconnection between Plant
equipment or Floating Solar Plant System with separate
metering, panels and safety tripping as per standard
norms (approved by HPRGE)
30 Payment Terms 507
0.5 %: On submission of Electrical SLD (Single Line Diagram), BESS
Design with EMS Integration, Elevation Plan, Structural Drawings
– Certified by Chartered Structural Engineer etc
80 %: On receipt of the Material on Site and all verification by
HPRGE/ Consultant. 1)BESS, 2) Inverter/PCU, 3) Structures, 4)
Balance of System. 5)Transformer

9.5%: Installation &Commissioning of BESS facility with EMS

10%: After Completion of Performance ratio test and operational


acceptance of plant by HPRGE, completion of Project
Documentation and Project Closeout.