Internal 11 KV OH Line Method Statement

The document outlines the method statement for the installation of 11KV internal overhead transmission lines, detailing the purpose, responsible personnel, manpower, tools, and safety procedures. It specifies excavation dimensions, pole installation methods, and the importance of safety training and equipment. Additionally, it emphasizes the need for proper housekeeping and equipment inspection post-work completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
64 views2 pages

Internal 11 KV OH Line Method Statement

The document outlines the method statement for the installation of 11KV internal overhead transmission lines, detailing the purpose, responsible personnel, manpower, tools, and safety procedures. It specifies excavation dimensions, pole installation methods, and the importance of safety training and equipment. Additionally, it emphasizes the need for proper housekeeping and equipment inspection post-work completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

11KV Internal OHT Method Statement

Purpose:
The Purpose of Method Statement is define and Establish systematic and quality of Work.
Responsible persons :
Ram Mohan (PM)
Ramana Electrical Engineer
Raj Kumar (AGM)
Shareef (Safety Officer)
Man Power :
01 Operator
06 Helpers.
Reference :
Work will be executed according to approved Drawings.
Tools :
Auger
shovel
Spanners
Wrench
Axe
Ropes
Web Slings
Ladder.
PPES Used:
Helmet
Shoes
Reflective jacket
Hand Gloves
Procedure :

 List of Tools and Machinery : will be used Wrench, spanners, screw driver, cutting
player, Hammer, Hydra.
 Excavation manually will be done 05 feet, width 2.5 and pole to pole distance not
more than 50 meters ,length of poles 09.1 meters and 11 meters, weight 250 kgs.
 V” Cross arms are fixed with clamps and bolt nuts before pole erection and Pole laid
by hydra by using web slings.
 Back filling and compacting will be done manually.
 Tress trimming will be done were required and concern department permission will
be taken before commencing work.

 Pole climbing by using Ladder or manually for fixing the disc and pin type insulators
and aluminum conductor will be pulled by using ropes .
 For road crossing purpose 11 meters pole will be used.

Safety

 Induction training will be conducted to all staff and workforce


 Tool box meeting will be conducted and on hazards which are identified before starting
work.
 Personal protective equipment (PPE) to be used by the task force during site work.
 Obstacles should be cleared the from surrounding area to avoid accidents.
 While using power tools and hand Tools will be inspected and certified by HSE Officer .
 After Completing the work Housekeeping will be done and material will be stocked
properly

Contractor Signature of Project Manager PMC Project Engineer

Contractor Signature of Electrical Engineer