Outline King Post
・Number: 78nos
・Weight: 9.8 - 31ton
(Ave. 17.4ton)
Capitol Theatre
・Length: 26.5 – 29.2m
(Ave. 27.3m)
・Steel: S355
North Bridge Road
Foundation Pile
・Number: 78nos
・Diameter: 1.8 – 2.3m
・Depth: 43.7 – 68.7m
・Concrete: G40
Peninsula Plaza
Section
Delivery
4-6nos at one time
With police escourt
Comet trailer
1. Preparation
Bed must be perfectly flat. Adjust by filler plate.
(To make straight marking line on side of KP)
2. Delivery
2 men for road, 2men for pedestrian when sending out
trailer
OK No good
3. Lay KP on the bed
・Major axis to be vertical
・Put filler plate into gap
(some KP has different section of its upper & lower
portion)
・KP must be put horizontally
・Cantilever should be less than 3m
4. Hoisting KP
・Only for shifting KP, use red color lifting lug
・Must use proper equipment for hoisting even if it’s
stopper pin
・25mm thk steel plate must be spread all over the
working area of crane without gap
・Once stop hoisting at 50mm height to check the
ground under the crane
5. Visual check
- Welding portion
-- Under cut, blow hole, overlap, slag, discontinuity
- Dimension of KP
-- Length, section
- Number of shear stud
6. Joint dolly
・Provide center marking on top and side of KP
・Adjust dolly center to KP center with jack support
※Do not tighten bolt
・Calculation of corbel bracket level:
A = GL-104.95+1.30+0.10 (m)
A
③ 7. Order of tightening bolts
①
After adjustment of center line to KP,
②
insert bolt following order shown in
the left figure.
Tightening should be from inside
towards outside.
4
2 bolts indicated with △ must be
2 tightened to prevent backling of
8 9 10 erection plate.
1
3 5 6 7
8. Welding case of the little dipper
・Avoid short bead (Min. 40mm)
1m
9. Frame setting
・Bore hole must be covered with steel mesh
・Guard rail must be fixed on frame
・Make ground flat and tighten before putting steel plate
・Steel plate must be parallel with grid line and 4 corner
of frame must be on doubled steel plate
10. Adjust level using water level
・Confirm the frame is stable
11. Marking X-Y on frame
Cylinder jack
Marking
11. Marking X-Y on frame
Tremie pipe Y ・Put tape on frame and then mark on it to prevent
8 inch dia confuse with previous one
・Mark location of I-beam on frame
11. Marking X-Y on frame
・Put tape on frame and then mark on it to prevent
confuse with previous one
・Mark location of I-beam on frame
12. Installation of cylinder jack on 4 directions
・Fix extension piece on the cylinder jack if the stroke
(Max. 750mm) is not enough to push KP
・Must check if it works every time before its installation
13. Rebar cage installation
・No. of spacer
・φ1800: 8pcs ・φ2000: 9pcs ・φ2300: 10pcs
・The required length of hook to suspend cage must be
calculated in advance to installation
14. Erection of KP
・250t + 100t double crane lifting
15. Installation of little dipper
16. Set I beams to
prepare for zero reading
17. Set KP vertical
・Check marking on KP from X and Y axis by theodolite
・Set little dipper zero
・Record value of scale on top of dolly
Theodolite
reading
Put tape
and mark
18. Release I beams and sink KP down to designated level
Jack ※To consider the way to sink KP down without
releasing I beams
19. Set I beams again and adjust level by 2 jacks under the
corbel bracket
20. Adjust location and verticality
・Reading laser point on scale on dolly referring
recorded value
tolerance is ±0mm
・Reading value of little dipper referring recorded value
tolerance is ±0.115°(1/500) (50mm/25m)
21. Insert 8 inches tremie pipes
・Desanding
22. Cast concrete
・Suspend tremie pipes with jig shown in the left figure
and shake 2 pipes at the same time.
23. Curing
・Duration of curing is 12 hours
※Don’t release I beams and jacks while curing
24. Remove I beams and jacks then fix L frame
25. Pump out bentonite
26. Backfill with sand
・Backfill around KP equally to avoid loading horizontal
force to KP
27. Put flag beside KP
28. KP infill concreting
G40 High flow concrete (600-700mm)
Casting speed = 1m/min
Concrete
Min.
2m
Cycle schedule of piling work
250t crawler crane 70t crawler crane BG36-1 BG36-2 Installation frame Dolly L-frame for backfilling
1st day 2nd day 3rd day
19 20 21 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Unloading rebar cage & Pre join rebar cage
Desanding Tremie pipe Backfilling
Pile 1 Casing Boring Rebar caging Setting frame KP installation Concreting Changing frame for backfilling Removing frame
Joint dolly
Desanding Tremie pipe Backfilling
Pile 2 Casing Boring Rebar caging Setting frame KP installation Concreting Changing frame for backfilling Removing frame
Joint dolly Unloading rebar cage & Pre join rebar cage
Tremie pipe Backfilling Desanding
Pile3 Setting frame KP installation Concreting Changing frame for backfilling Removing frame Pile 9 Casing Boring Rebar caging
lei
p
n Joint dolly
iot Tremie pipe Backfilling Desanding
a Pile4 Setting frame KP installation Concreting Changing frame for backfilling Removing frame Pile 10 Casing Boring Rebar caging
d
n
u
o
F
Joint dolly
Unloading rebar cage & Pre join rebar cage
Backfilling Desanding Tremie pipe
Pile 5 Changing frame for backfilling Removing frame Pile 7 Casing Boring Rebar caging Setting frame KP installation Concreting
Joint dolly
Backfilling Desanding Tremie pipe
Pile 6 Changing frame for backfilling Removing frame Pile 8 Casing Boring Rebar caging Setting frame KP installation Concreting
Joint dolly
CBP HP1 Install casing Boring Hard Pile Rebar Caging Casting Install casing Boring Hard Pile Rebar Caging Casting Install casing Boring Hard Pile Rebar Caging Casting
BG28 Desand Desand Desand
CBP HP2 Boring Hard Pile Rebar Caging Concreting Install casing Boring Hard Pile Rebar Caging Concreting Install casing Boring Hard Pile Rebar Caging Concreting Install casing
BG28 Desand Desand Desand
CBP HP3 Install casing Boring Hard Pile Rebar Caging Casting Install casing Boring Hard Pile Rebar Caging Casting Install casing Boring Hard Pile Rebar Caging Casting
P BG25 Desand Desand Desand
B
C
CBP SP Boring Soft Pile Take out Casing 1, 2, 3 Boring Soft Pile Take out Casing 1, 2, 3 Boring Soft Pile Take out Casing 1, 2, 3
BG25
Service casing installation Service casing installation
Pre join rebar cage Pre join rebar Pre join rebar cage Pre join rebar Pre join rebar cage
70t crawler crane A 70t crawler crane B BG28 BG25 A BG25 B