26 Weeks RBP From 16-06-2025 To 14-12-2025 (West) GNT DIV
26 Weeks RBP From 16-06-2025 To 14-12-2025 (West) GNT DIV
16-06-2025 (Monday)
3 16-06-2025 GNT GNT-NDL NDL YARD SL 1 2 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL
4 16-06-2025 GNT GNT-NDL NDL YARD ST B/I Maintenance Shadow 2 Blocks of 30mins each ESM/NDL Assistant
2 Disconnection of each
5 16-06-2025 GNT GNT-NDL NDL YARD ST CH Maintenance Shadow ESM/NDL Assistant
30 min
execavation,Breaking drilling
6 16-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
execavation,Breaking drilling
7 16-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
11:30-
8 16-06-2025 GNT GNT-NDL DMT CMZ SL ENGG UTV MAIN 2 blocks of 90 min each 9:30-11:00 no 40 JE/P.Way/GID(G)
13:00
9 16-06-2025 GNT GNT-NDL GID YARD ST B/I Maintenance Shadow 2 Blocks of 30mins each ESM/GID Assistant
2 Disconnection of each
10 16-06-2025 GNT GNT-NDL GID YARD ST CH Maintenance MAIN ESM/GID Assistant
30 min
12 16-06-2025 GNT GNT-NDL JBK YARD ST Both B/I QTY/Inspection Shadow 2 Blocks of each 30min SSE/S/MRK ESM
14:00-
15 16-06-2025 GNT GNT-NDL CBM TLU UP/DN 164 169 TRD PTFE MANTENANCE MAIN 2 Blocks of 90 min each 10:30-12:00 SSE/TRD/GID TOWER CAR
15:30
16 16-06-2025 GNT GNT-NDL MRK YARD ST Both B/I M/I INSPECTION MAIN 2 Blocks of each 30min JE/S/CBM ESM
2 disconnection of each
17 16-06-2025 GNT GNT-NDL MRK YARD ST CH M/I INSPECTION Shadow JE/S/CBM ESM
30min
ENGG Staff
18 16-06-2025 GNT GNT-NDL KCD YARD ENGG & ST SSD Maintenance MAIN 2 Blocks of each 60min ESM/KCD
required.
19 16-06-2025 GNT GNT-NDL GKM KCD UP/DN 97 106 TRD PTFE MANTENANCE MAIN 120+120 MINUTES flexible slot SSE/TRD/MRK TOWER CAR
2 BLOCK OF 30MINS
20 16-06-2025 GNT GNT-NDL CEM YARD ST BOTH B/I Q.I Shadow SSE/S/VKN ESM
EACH
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
2 disconnection of each
21 16-06-2025 GNT GNT-NDL CEM YARD ST CH Q.I Shadow SSE/S/VKN ESM
30min
2 BLOCK OF 30MINS
23 16-06-2025 GNT GNT-NDL STUR YARD ST BOTH B/I MAINTENANCE MAIN ESM/STUR ASSISTANT
EACH
2 disconnection of each
24 16-06-2025 GNT GNT-NDL STUR YARD ST CH MAINTENANCE Shadow ESM/STUR ASSISTANT
30min
2 BLOCKS OF EACH 2
28 16-06-2025 GNT GNT-KCC NBR MAG UP ENGG WELDING OF RAIL JOINTS MAIN flexible slot no 4 SSE/P.WAY/GNT -
HOURS
17-06-2025 (Tuesday)
1 17-06-2025 GNT GNT-NDL NDL YA SL 1 2 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
execavation,Breaking drilling
4 17-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
5 17-06-2025 GNT GNT-NDL CMZ YARD ST B/I M.I Shadow 2 Blocks of 30mins each JE/S/NDL ESM
11:30-
6 17-06-2025 GNT GNT-NDL DMT CMZ SL ENGG UTV MAIN 2 blocks of 90 min each 9:30-11:00 no 40 JE/P.Way/GID(G)
13:00
execavation,Breaking drilling
7 17-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
OHE staff
10 17-06-2025 GNT GNT-NDL JBK SDV UP/DN ENGG TAMPING Shadow 2 block of 90 mins 11:00-14:00 km 1.6 SSE/P.Way/CBM
required
11 17-06-2025 GNT GNT-NDL JBK YARD ST Both B/I M.I Shadow 2 Blocks of each 30min JE/S/CBM ESM
2 disconnections of each
12 17-06-2025 GNT GNT-NDL JBK YARD ST CH TECH, M.I Shadow JE/S/CBM ESM
30min
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
14:00-
13 17-06-2025 GNT GNT-NDL CBM yard UP&DN 168 170 TRD CROSSOVERS MAINTENANCE MAIN 2 Blocks of 90 min each 10:30-12:00 SSE/TRD/GID TOWER CAR
15:30
16 17-06-2025 GNT GNT-NDL GKM YARD ST Cable meggering at GNT side MAIN 1 Disconection of 240mins NI wkg SSE/S/VKN ESMs & assistant
ESMs &
20 17-06-2025 GNT GNT-NDL GNT/S YARD ST 1 B/I M.I MAIN 1Blocks of 30min JE/S/GNT
assistants
ESMs &
21 17-06-2025 GNT GNT-NDL GNT/S YARD ST CH1-4 M.I Shadow 2 Disconection of 30mins JE/S/GNT
assistants
2 BLOCKS OF EACH 2
23 17-06-2025 GNT GNT-KCC NBR MAG UP ENGG WELDING OF RAIL JOINTS MAIN flexible slot no 4 SSE/P.WAY/GNT -
HOURS
18-06-2025 (Wednesday)
2 18-06-2025 GNT GNT-NDL GZL YARD SL 242 243 TRD T/O & SI MAINTENANCE MAIN 60+60 MINS SSE/TRD/NDL
execavation,Breaking drilling
3 18-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
execavation,Breaking drilling
5 18-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
11:30-
6 18-06-2025 GNT GNT-NDL DMT CMZ SL ENGG UTV MAIN 2 blocks of 90 min each 9:30-11:00 no 4 JE/P.Way/GID(G)
13:00
OHE staff
8 18-06-2025 GNT GNT-NDL JBK SDV UP/DN ENGG TAMPING Shadow 2 block of 90 mins 11:00-14:00 km 1.6 SSE/P.Way/CBM
required
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
14:00-
9 18-06-2025 GNT GNT-NDL CBM yard UP&DN 168 170 TRD CROSSOVERS MAINTENANCE MAIN 2 Blocks of 90 min each 10:30-12:00 SSE/TRD/GID TOWER CAR
15:30
11 18-06-2025 GNT GNT-NDL TLU YARD ST Both B/I MAINTENCE Shadow 2 Blocks of each 30min TECH/MRK ESM
2 disconnections of each
12 18-06-2025 GNT GNT-NDL TLU YARD ST CH TECH, MAINTENCE Shadow TECH/MRK ESM
30min
2 BLOCK OF 30MINS
14 18-06-2025 GNT GNT-NDL GKM YARD ST BOTH B/I M.I MAIN JE/S/KCD ESM
EACH
2 disconnection of each
15 18-06-2025 GNT GNT-NDL GKM YARD ST CH M.I Shadow JE/S/KCD ESM
30min
2 BLOCK OF 30MINS
16 18-06-2025 GNT GNT-NDL SAB YARD ST BOTH B/I Q.I Shadow SSE/S/VKN ESM
EACH
2 disconnection of each
17 18-06-2025 GNT GNT-NDL SAB YARD ST CH Q.I Shadow SSE/S/VKN ESM
30min
2 Disconnections of 30
19 18-06-2025 GNT GNT-NDL NDPU YARD ST ch 3,4 ekt maintenance Shadow ESM/PRCA assistant
mins each
19-06-2025 (Thursday)
2 19-06-2025 GNT GNT-NDL NDPL YARD ST B/I M.I Shadow 2 Blocks of 30mins each JE/S/NDL ESM
execavation,Breaking drilling
3 19-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
5 19-06-2025 GNT GNT-NDL SDV YARD ST B/I M.I Shadow 2 Blocks of 30mins each SE/S/GID ESM
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
11:30-
6 19-06-2025 GNT GNT-NDL DMT CMZ SL ENGG UTV MAIN 2 blocks of 90 min each 9:30-11:00 no 40 JE/P.Way/GID(G)
13:00
execavation,Breaking drilling
7 19-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
8 19-06-2025 GNT GNT-NDL JBK YARD ST Both B/I M/I INSPECTION Shadow 2 Blocks of each 30min JE/S/CBM ESM
2 Disconnections of each
9 19-06-2025 GNT GNT-NDL JBK YARD ST CH , M/I INSPECTION Shadow JE/S/CBM ESM
30min
14:00-
10 19-06-2025 GNT GNT-NDL JBK yard UP&DN 175 177 TRD CROSSOVERS MAINTENANCE MAIN 2 Blocks of 90 min each 11:00-12:30 SSE/TRD/GID TOWER CAR
15:30
19 19-06-2025 GNT GNT-NDL PPM YARD ST Both ufsbi monthly inspection Shadow 2 block 30 mins each JE/S/NLPD ESM
2 Disconnection 30 mins
20 19-06-2025 GNT GNT-NDL PPM YARD ST ch 1,2,3,4, monthly inspection Shadow JE/S/NLPD ESM
each
ESMs &
22 19-06-2025 GNT GNT-KCC NBR YARD ST BOTH B/I Qrtly inspection Shadow 2 block of 30mins SSE/S/GNT
Assistants
OHE Staff,
24 19-06-2025 GNT GNT-KCC NBR MAG DN ENGG TFTR WORK MAIN 1 BLOCKS OF 4 HOURS 6:30-9:30 km 0.2 SSE/P.WAY/GNT POWER BLOCK
Required
20-06-2025 (Friday)
1 20-06-2025 GNT GNT-NDL NDPL YARD SL 250 251 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
execavation,Breaking drilling
2 20-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
11:30-
4 20-06-2025 GNT GNT-NDL DMT CMZ SL ENGG UTV MAIN 2 blocks of 90 min each 9:30-11:00 no 40 JE/P.Way/GID(G)
13:00
execavation,Breaking drilling
5 20-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
14:00-
7 20-06-2025 GNT GNT-NDL JBK yard UP&DN 175 177 TRD CROSSOVERS MAINTENANCE Shadow 2 Blocks of 90 min each 11:00-12:30 SSE/TRD/GID TOWER CAR
15:30
12 20-06-2025 GNT GNT-NDL POO KCD UD ENGG Bri.413A Block Main 1 Block of 210 min SSE/Bri/GNT OHE with T/c
2 BLOCK OF 30MINS
13 20-06-2025 GNT GNT-NDL MUK YARD ST BOTH B/I Q.I Shadow SSE/S/VKN ESM
EACH
2 disconnection of each
14 20-06-2025 GNT GNT-NDL MUK YARD ST CH Q.I Shadow SSE/S/VKN ESM
30min
2 disconnection of each
19 20-06-2025 GNT GNT-NDL PRCA YARD ST ch 3,4 ekt maintenance. Shadow ESM/PRCA ASSISTANT
30min
21-06-2025 (Saturday)
execavation,Breaking drilling
2 21-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 SSE/S/NDL 09:00 17:00
blasting of rock
11:30-
4 21-06-2025 GNT GNT-NDL DMT CMZ SL ENGG UTV MAIN 2 blocks of 90 min each 9:30-11:00 no 40 JE/P.Way/GID(G)
13:00
execavation,Breaking drilling
5 21-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
7 21-06-2025 GNT GNT-NDL JBK yard UP/DN 175 177 TRD ATD & Isolators maintenance Shadow 3 Blocks of 60 min each SSE/TRD/GID
12 21-06-2025 GNT GNT-NDL POO KCD UD ENGG Bri.413A Block Main 1 Block of 180 min SSE/Bri/GNT OHE with T/c
13 21-06-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 flexible slot 10
2 BLOCK OF 30MINS
14 21-06-2025 GNT GNT-NDL VKN YARD ST BOTH B/I M.I Shadow JE/S/VKN ESM
EACH
18 21-06-2025 GNT GNT-NDL PPM YARD ST LC 298 ekt maintenance Shadow 1 block of 30mins ESM/PRCA ASSISTANT
2 disconnections of each
19 21-06-2025 GNT GNT-NDL PPM YARD ST ch 3,4 ekt maintenance Shadow ESM/PRCA ASSISTANT
30min
22-06-2025 (Sunday)
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
execavation,Breaking drilling
1 22-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
11:30-
2 22-06-2025 GNT GNT-NDL DMT CMZ SL ENGG UTV MAIN 2 blocks of 90 min each 9:30-11:00 no 40 JE/P.Way/GID(G)
13:00
execavation,Breaking drilling
3 22-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
1 Disconnections of
7 22-06-2025 GNT GNT-NDL STUR YARD ST LC 291 EKT NM Shadow ESM/STUR Assistant
30mins
23-06-2025 (Monday)
1 23-06-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Shadow 60+60 4
2 23-06-2025 GNT GNT-NDL CMZ DMT SL 223 224 TRD PTFE MAINTENANCE MAIN 60+60 MINS SSE/TRD/NDL
3 23-06-2025 GNT GNT-NDL GZL YARD ST LC-192 EKT MAINTENANCE Shadow 1 BLCOK 30 MIN ESM/NDL
execavation,Breaking drilling
4 23-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
execavation,Breaking drilling
5 23-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
2 BLOCKS OF EACH 2 10:00- S&T, OHE Staff
6 23-06-2025 GNT GNT-KCC REP YARD UP/DN ENGG PCTM POINTS TAMPING MAIN 8:00-9:30 pt 1 SSE/P.WAY/GNT
HOURS 11:30 Required
S&T Staff
7 23-06-2025 GNT GNT-KCC GNT YARD UP/DN ENGG SSD MAINTENANCE MAIN 1 BLOCKS OF 60MIN SSE/P.WAY/GNT
Required
24-06-2025 (Tuesday)
1 24-06-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 24-06-2025 GNT GNT-NDL NDPL YARD SL 249 250 TRD ISOLATOR MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL TOWERCAR
S&T ,OHE
3 24-06-2025 GNT GNT-NDL GNT YARD SL ENGG Tamping MAIN 2 blocks of 120+120 min flexible slot km 1.6 SSE/PWAY/GNT
Required
required HQ s S&T,OHE with
4 24-06-2025 GNT GNT-NDL MRK GJJ UD ENGG Bri.387 Block Main 1 Block of 210 min SSE/Bri/GNT
permission T/c
execavation,Breaking drilling
5 24-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
execavation,Breaking drilling
6 24-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
S&T Staff
7 24-06-2025 GNT GNT-KCC REP YARD UP/DN ENGG SSD MAINTENANCE MAIN 1 BLOCKS OF 60MIN SSE/P.WAY/GNT
Required
25-06-2025 (Wednesday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 25-06-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
S&T ,OHE
2 25-06-2025 GNT GNT-NDL GNT YARD SL ENGG Tamping MAIN 2 blocks of 120+120 min flexible slot km 3 SSE/PWAY/GNT
Required
execavation,Breaking drilling
3 25-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
execavation,Breaking drilling
4 25-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
2 BLOCKS OF 60MIN S&T Staff
5 25-06-2025 GNT GNT-KCC NBR YARD UP/DN ENGG SSD MAINTENANCE MAIN SSE/P.WAY/GNT
EACH Required
26-06-2025 (Thursday)
1 26-06-2025 GNT GNT-NDL NDL NDPL ST LC-186 EKT MAINTENANCE Shadow 1 BLOCK 30 MIN ESM/NDL
2 26-06-2025 GNT GNT-NDL GZL YARD SL 241 243 TRD ISOLATOR MAINTENANCE MAIN 60+60 MINS SSE/TRD/NDL TOWER CAR
S&T ,OHE
3 26-06-2025 GNT GNT-NDL GNT YARD SL ENGG Tamping MAIN 2 blocks of 120+120 min flexible slot SSE/PWAY/GNT
Required
execavation,Breaking drilling
4 26-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each AXEN/C/MRK 09:00 17:00
blasting of rock
execavation,Breaking drilling
5 26-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
2 BLOCKS OF 60MIN S&T Staff
6 26-06-2025 GNT GNT-KCC MAG YARD UP/DN ENGG SSD MAINTENANCE MAIN SSE/P.WAY/GNT
EACH Required
GNT SOUTH S&T JOINT INSPECTION NOTES 2 BLOCKS OF 90MIN S&T Staff
7 26-06-2025 GNT GNT-NDL UP/DN ENGG MAIN SSE/P.WAY/GNT
YARD END ATTENTION EACH Required
27-06-2025 (Friday)
1 27-06-2025 GNT GNT-NDL CMZ YARD SL 230 2312 TRD T/O MAINTENANCE MAIN 60+60 MINS SSE/TRD/NDL TOWER CAR
14:45-
2 27-06-2025 GNT GNT-NDL VKN SYM DN 72 82 TRD AOH of CLs Main 75+75 12:30-13:45 10
16:00
3 27-06-2025 GNT GNT-NDL NDPU YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30" JE/S/PPM ESM
28-06-2025 (Saturday)
1 28-06-2025 GNT GNT-NDL GJJ YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
6 28-06-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD ISOLATOR MAINTENANCE MAIN 60+60 MINS
GNT SOUTH S&T JOINT INSPECTION NOTES 2 BLOCKS OF 90MIN S&T Staff
7 28-06-2025 GNT GNT-NDL UP/DN ENGG MAIN SSE/P.WAY/GNT
YARD END ATTENTION EACH Required
29-06-2025 (Sunday)
1 29-06-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
2 29-06-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
30-06-2025 (Monday)
1 30-06-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
CLS=
2 30-06-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
3 30-06-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
execavation,Breaking drilling
4 30-06-2025 GNT GNT-NDL DMT CMZ UP/DN 219/700 223/200 Engg-Con Shadow 2 blocks of 60 min each 10:00 12:00 AXEN/C/MRK 09:00 17:00
blasting of rock
execavation,Breaking drilling
5 30-06-2025 GNT GNT-NDL CMZ GZL UP/DN 232/650 233/400 Engg-Con Shadow 1 block of 90 mins 11:30-13:00 AXEN/C/MRK 09:00 17:00
blasting of rock
GNT NORTH S&T JOINT INSPECTION NOTES 2 BLOCKS OF 90MIN S&T Staff
6 30-06-2025 GNT GNT-KCC UP/DN ENGG MAIN SSE/P.WAY/GNT
YARD END ATTENTION EACH Required
01-07-2025 (Tuesday)
CLS=
1 01-07-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
2 01-07-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
GNT NORTH S&T JOINT INSPECTION NOTES 2 BLOCKS OF 90MIN S&T Staff
3 01-07-2025 GNT GNT-KCC UP/DN ENGG MAIN SSE/P.WAY/GNT
YARD END ATTENTION EACH Required
02-07-2025 (Wednesday)
1 02-07-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 02-07-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 02-07-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
GNT NORTH S&T JOINT INSPECTION NOTES 2 BLOCKS OF 90MIN S&T Staff
4 02-07-2025 GNT GNT-KCC UP/DN ENGG MAIN SSE/P.WAY/GNT
YARD END ATTENTION EACH Required
03-07-2025 (Thursday)
1 03-07-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
2 03-07-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Shadow 60+60 No. 4
UP and
3 03-07-2025 GNT GNT-KCC NBR YARD ST NBR-MAG,NBR-REP B/I M/I shadow 2 blocks of 30 min each JE/S/GNT ESM
DN
S&T JOINT INSPECTION NOTES 2 BLOCKS OF 90MIN S&T Staff
4 03-07-2025 GNT GNT-KCC MAG YARD UP/DN ENGG MAIN SSE/P.WAY/GNT
ATTENTION EACH Required
04-07-2025 (Friday)
1 04-07-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 60 MIN JE/SIG/NDL
2 04-07-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL
05-07-2025 (Saturday)
1 05-07-2025 GNT GNT-NDL GZL CMZ SL 238 239 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 05-07-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 05-07-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
S&T JOINT INSPECTION NOTES 2 BLOCKS OF 90MIN S&T Staff
4 05-07-2025 GNT GNT-KCC NBR YARD UP/DN ENGG MAIN SSE/P.WAY/GNT
ATTENTION EACH Required
06-07-2025 (Sunday)
1 06-07-2025 GNT GNT-NDL CMZ YARD SL 230 232 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 06-07-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 06-07-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
07-07-2025 (Monday)
TOWERCAR/PIC
1 07.07.2025 GNT GNT-NDL NDL YARD SL 256 257 TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
2 07.07.2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 07.07.2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 07.07.2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 10
08-07-2025 (Tuesday)
1 08-07-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD AOH OF ATD Shadow 90+90 MINS SSE/TRD/NDL
2 08-07-2025 GNT GNT-NDL GKM YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
C/o:1,
UP and AOH of T/os, Crossover and 14:45-
3 08-07-2025 GNT GNT-NDL VKN YARD 82 83 TRD Main 75+75 12:30-13:45 T/os:2
DN CLs. 16:00
,
14:00- S&T, OHE staff
4 08-07-2025 GNT GNT-NDL NDPU YARD ENGG & ST Redundant Glued Joint Renewal Main 2 Blocks of 90 min each 8:00-9:30 SSE/SW/NLPD
15:30 required
S&T JOINT INSPECTION NOTES 2 BLOCKS OF 90MIN S&T Staff
5 08-07-2025 GNT GNT-KCC NBR YARD UP/DN ENGG MAIN SSE/P.WAY/GNT
ATTENTION EACH Required
09-07-2025 (Wednesday)
TOWERCAR/PIC
1 09-07-2025 GNT GNT-NDL NDL YA LINE SL 1KM 2 KM TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 09-07-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 09-07-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 09-07-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 No. 10
10-07-2025 (Thursday)
1 10-07-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 10-07-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 10-07-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 10-07-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
11-07-2025 (Friday)
TOWERCAR/PIC
1 11-07-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 11-07-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 11-07-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 11-07-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
12-07-2025 (Saturday)
1 12-07-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 12-07-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 12-07-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
13-07-2025 (Sunday)
1 13-07-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
2 13-07-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Shadow 60+60 No. 4
14-07-2025 (Monday)
TOWERCAR/PIC
1 14-07-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 14-07-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 14-07-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 14-07-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 10
15-07-2025 (Tuesday)
1 15-07-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD AOH OF ATD Shadow 90+90 MINS SSE/TRD/NDL
2 15-07-2025 GNT GNT-NDL GKM YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
C/o:1,
UP and AOH of T/os, Crossover and 14:45-
3 15-07-2025 GNT GNT-NDL VKN YARD 82 83 TRD Main 75+75 12:30-13:45 T/os:2
DN CLs. 16:00
,
14:00- S&T, OHE staff
4 15-07-2025 GNT GNT-NDL NDPU YARD ENGG & ST Redundant Glued Joint Renewal Main 2 Blocks of 90 min each 8:00-9:30 SSE/SW/NLPD
15:30 required
16-07-2025 (Wednesday)
TOWERCAR/PIC
1 16-07-2025 GNT GNT-NDL NDL YA LINE SL 1KM 2 KM TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 16-07-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 16-07-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 16-07-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 No. 10
17-07-2025 (Thursday)
1 17-07-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 17-07-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 17-07-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 17-07-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
18-07-2025 (Friday)
TOWERCAR/PIC
1 18-07-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 18-07-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
3 18-07-2025 GNT GNT-NDL NLPD YARD ENGG TWS block Main 1 block of 180 min SSE/PWAY/NLPD
CLS=
4 18-07-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
5 18-07-2025 GNT GNT-NDL STUR NRT DN ENGG TRR block MAIN 1 block of 180 min -- -- SSE/PWAY/NLPD
19-07-2025 (Saturday)
1 19-07-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 19-07-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 19-07-2025 GNT GNT-NDL STUR NRT DN ENGG TRR block MAIN 1 block of 180 min -- -- SSE/PWAY/NLPD
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 19-07-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
20-07-2025 (Sunday)
1 20-07-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
2 20-07-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Shadow 60+60 No. 4
3 20-07-2025 GNT GNT-NDL STUR NRT DN ENGG TRR block MAIN 1 block of 180 min -- -- SSE/PWAY/NLPD
UP and
3 20-07-2025 GNT GNT-KCC NBR YARD ST NBR-MAG,NBR-REP B/I M/I shadow 2 blocks of 30 min each JE/S/GNT ESM
DN
21-07-2025 (Monday)
1 21-07-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD ISOLATORMAINTENANCE Shadow 60 MINS SSE/TRD/NDL
3 21-07-2025 GNT GNT-NDL STUR NRT DN ENGG TRR block MAIN 1 block of 180 min -- -- SSE/PWAY/NLPD
22-07-2025 (Tuesday)
1 22-07-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 60 MIN JE/SIG/NDL
2 22-07-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL
3 22-07-2025 GNT GNT-NDL STUR NRT DN ENGG TRR block MAIN 1 block of 180 min -- -- SSE/PWAY/NLPD
3 22-07-2025 GNT GNT-NDL SYM YARD DN ENGG TWS block MAIN 1 block of 180 min -- -- SSE/PWAY/VKN
23-07-2025 (Wednesday)
1 23-07-2025 GNT GNT-NDL GZL CMZ SL 238 239 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 23-07-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 23-07-2025 GNT GNT-NDL STUR NRT DN ENGG TRR block MAIN 1 block of 180 min -- -- SSE/PWAY/NLPD
3 23-07-2025 GNT GNT-NDL VKN SYM UP ENGG LC 287 block MAIN 1 block of 180 min -- -- SSE/PWAY/VKN
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 23-07-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 22-07-2025 GNT GNT-NDL SYM YARD DN ENGG TWS block MAIN 1 block of 180 min -- -- SSE/PWAY/VKN
24-07-2025 (Thursday)
1 24-07-2025 GNT GNT-NDL CMZ YARD SL 230 232 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 24-07-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 24-07-2025 GNT GNT-NDL SYM YARD DN ENGG TWS block MAIN 1 block of 180 min -- -- SSE/PWAY/VKN
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 24-07-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
25-07-2025 (Friday)
1 25-07-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD AOH OF ATD Shadow SSE/TRD/NDL
2 25-07-2025 GNT GNT-NDL GZL YARD ST LC-192 EKT MAINTENANCE Shadow 1 BLCOK 30 MIN ESM/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 25-07-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 25-07-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
5 25-07-2025 GNT GNT-NDL GJJ YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
26-07-2025 (Saturday)
1 26-07-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 26-07-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 26-07-2025 GNT GNT-NDL DMT YARD ST LC-197 EKT MANTENANCE Shadow 1 BLCOK 30 MIN ESM/GID
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 26-07-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
27-07-2025 (Sunday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 27-07-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 27-07-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 27-07-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 flexible slot 10
28-07-2025 (Monday)
TOWERCAR/PIC
1 28-07-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 28-07-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 28-07-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 28-07-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 10
29-07-2025 (Tuesday)
1 29-07-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD AOH OF ATD Shadow 90+90 MINS SSE/TRD/NDL
2 29-07-2025 GNT GNT-NDL GKM YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
3 29-07-2025 GNT GNT-NDL SYM YARD DN ENGG TWS block MAIN 1 block of 180 min -- -- SSE/PWAY/VKN
C/o:1,
UP and AOH of T/os, Crossover and 14:45-
3 29-07-2025 GNT GNT-NDL VKN YARD 82 83 TRD Main 75+75 12:30-13:45 T/os:2
DN CLs. 16:00
,
30-07-2025 (Wednesday)
TOWERCAR/PIC
1 30-07-2025 GNT GNT-NDL NDL YA LINE SL 1KM 2 KM TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 30-07-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 30-07-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 30-07-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 No. 10
31-07-2025 (Thursday)
1 31-07-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 31-07-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
3 31-07-2025 GNT GNT-NDL SYM YARD DN ENGG TWS block MAIN 1 block of 180 min -- -- SSE/PWAY/VKN
CLS=
3 31-07-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 31-07-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
01-08-2025 (Friday)
TOWERCAR/PIC
1 01-08-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 01-08-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 01-08-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 01-08-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
02-08-2025 (Saturday)
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
1 02-08-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 02-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 02-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
03-08-2025 (Sunday)
1 03-08-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
2 03-08-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Shadow 60+60 No. 4
UP and
3 03-08-2025 GNT GNT-KCC NBR YARD ST NBR-MAG,NBR-REP B/I M/I shadow 2 blocks of 30 min each JE/S/GNT ESM
DN
04-08-2025 (Monday)
1 04-08-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD ISOLATOR MAINTENANCE Shadow 60+60
S&T ,OHE
2 04-08-2025 GNT GNT-NDL NLPD YARD SL ENGG Tamping Shadow 2 blocks of 120+120 min SSE/PWAY/NLPD
Required
05-08-2025 (Tuesday)
1 05-08-2025 GNT GNT-NDL NDL YARD SL 257 256 TRD ISOLATOR MAINTENANCE Shadow 60+60 SSE/TRD/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 05-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 05-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
06-08-2025 (Wednesday)
1 06-08-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD ISOLATOR MAINTENANCE Shadow 60 MINS
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 06-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
2 06-08-2025 GNT GNT-NDL NLPD YARD ENGG TWS block Main 1 block of 180 min SSE/PWAY/NLPD
3 06-08-2025 GNT GNT-NDL DMT YARD ST BOTH B/I & CH MAINTENANCE Shadow 4 BLOCKS 30 MIN ESM/GID
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 06-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
6 06-08-2025 GNT GNT-NDL PRCA YARD ST Both B/I Monthly Inspection Main 2 Blocks of each 30" JE/S/PPM ESM
07-08-2025 (Thursday)
1 07-08-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD ISOLATOR MAINTENANCE Shadow 60 MINS
2 07-08-2025 GNT GNT-NDL GZL YARD SL ST BOTH B/I & CH MAINTENANCE Shadow 3 BLCOKS 30 MIN EACH ESM/NDL
3 07-08-2025 GNT GNT-NDL GID YARD ST BOTH B/I & CH MAINTENANCE Shadow 4 BLCOKS 30 MIN EACH ESM/GID
08-08-2025 (Friday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 08-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 08-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 08-08-2025 GNT GNT-NDL DKD YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30" JE/S/KCD ESM
UP and
4 08-08-2025 GNT GNT-NDL SYM YARD 72 73 TRD SYM TRANSFORMER mAIN 60+60 1
DN
09-08-2025 (Saturday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 09-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 09-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 09-08-2025 GNT GNT-NDL POO YARD UP ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30" JE/S/KCD ESM
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
10-08-2025 (Sunday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 10-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 10-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
11-08-2025 (Monday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 11-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 11-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
12-08-2025 (Tuesday)
1 12-08-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD ISOLATOR MAINTENANCE Shadow 60 MINS
2 12-08-2025 GNT GNT-NDL GZL YARD SL ST BOTH B/I & CH MAINTENANCE Shadow 3 BLCOKS 30 MIN EACH ESM/NDL
3 12-08-2025 GNT GNT-NDL GID YARD ST BOTH B/I & CH MAINTENANCE Shadow 4 BLCOKS 30 MIN EACH ESM/GID
13-08-2025 (Wednesday)
1 13-08-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 13-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 13-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
14-08-2025 (Thursday)
TOWERCAR/PIC
1 14-08-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 14-08-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
2 14-08-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 14-08-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 14-08-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
15-08-2025 (Friday)
1 15-08-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD ISOLATOR MAINTENANCE Shadow 60+60
S&T ,OHE
2 15-08-2025 GNT GNT-NDL NLPD YARD SL ENGG Tamping Shadow 2 blocks of 120+120 min SSE/PWAY/NLPD
Required
16-08-2025 (Saturday)
TOWERCAR/PIC
1 16-08-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 16-08-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 16-08-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 16-08-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
17-08-2025 (Sunday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 17-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 17-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 17-08-2025 GNT GNT-NDL DKD YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30" JE/S/KCD ESM
UP and
4 17-08-2025 GNT GNT-NDL SYM YARD 72 73 TRD SYM TRANSFORMER mAIN 60+60 1
DN
18-08-2025 (Monday)
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 18-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 18-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 18-08-2025 GNT GNT-NDL DKD YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30" JE/S/KCD ESM
UP and
4 18-08-2025 GNT GNT-NDL SYM YARD 72 73 TRD SYM TRANSFORMER mAIN 60+60 1
DN
19-08-2025 (Tuesday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 19-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 19-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
20-08-2025 (Wednesday)
1 20-08-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 20-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 20-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
21-08-2025 (Thursday)
1 21-08-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD ISOLATOR MAINTENANCE Shadow 60 MINS
2 21-08-2025 GNT GNT-NDL GZL YARD SL ST BOTH B/I & CH MAINTENANCE Shadow 3 BLCOKS 30 MIN EACH ESM/NDL
3 21-08-2025 GNT GNT-NDL GID YARD ST BOTH B/I & CH MAINTENANCE Shadow 4 BLCOKS 30 MIN EACH ESM/GID
22-08-2025 (Friday)
1 22-08-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD ISOLATOR MAINTENANCE Shadow 60 MINS
2 22-08-2025 GNT GNT-NDL GZL YARD SL ST BOTH B/I & CH MAINTENANCE Shadow 3 BLCOKS 30 MIN EACH ESM/NDL
3 22-08-2025 GNT GNT-NDL GID YARD ST BOTH B/I & CH MAINTENANCE Shadow 4 BLCOKS 30 MIN EACH ESM/GID
23-08-2025 (Saturday)
1 23-08-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 23-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 23-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
24-08-2025 (Sunday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 24-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 24-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
25-08-2025 (Monday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 25-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 25-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 25-08-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 flexible slot 10
26-08-2025 (Tuesday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 26-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 26-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 26-08-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 flexible slot 10
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 26-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
27-08-2025 (Wednesday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 27-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 27-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 27-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 27-08-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 flexible slot 10
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 27-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
28-08-2025 (Thursday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 28-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 28-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 28-08-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 flexible slot 10
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 28-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
29-08-2025 (Friday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 29-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 29-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 29-08-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 flexible slot 10
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 29-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
30-08-2025 (Saturday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 30-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 30-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 30-08-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 flexible slot 10
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 30-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
31-08-2025 (Sunday)
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
1 31-08-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 31-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
3 31-08-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 flexible slot 10
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 31-08-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
01-09-2025 (Monday)
1 01-09-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Shadow 60+60 4
2 01-09-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD AOH OF ATD Shadow SSE/TRD/NDL
3 01-09-2025 GNT GNT-NDL GZL YARD ST LC-192 EKT MAINTENANCE Shadow 1 BLCOK 30 MIN ESM/NDL
02-09-2025 (Tuesday)
1 02-09-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 02-09-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
03-09-2025 (Wednesday)
1 03-09-2025 GNT GNT-NDL CMZ GZL SL 238 239 TRD CL'S MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL TOWER CAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 03-09-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
04-09-2025 (Thursday)
1 04-09-2025 GNT GNT-NDL NDL NDPL ST LC-186 EKT MAINTENANCE Shadow 1 BLOCK 30 MIN ESM/NDL
2 04-09-2025 GNT GNT-NDL NDPL YARD SL 253 255 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL TOWER CAR
05-09-2025 (Friday)
1 05-09-2025 GNT GNT-NDL GZL NDPL SL 246 247 TRD CLS MAINTENACE Shadow 60+60 MINS SSE/TRD/NDL TOWER CAR
14:45-
2 05-09-2025 GNT GNT-NDL VKN SYM DN 72 82 TRD AOH of CLs Main 75+75 12:30-13:45 10
16:00
3 05-09-2025 GNT GNT-NDL NDPU YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30" JE/S/PPM ESM
06-09-2025 (Saturday)
1 06-09-2025 GNT GNT-NDL GJJ YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
07-09-2025 (Sunday)
2 07-09-2025 GNT GNT-NDL KCD YARD UP 106 108 TRD AOH of Turnouts and Crossoves Shadow 2 blocks of 75 min each flexible slot
08-09-2025 (Monday)
TOWERCAR/PIC
1 08-09-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 08-09-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 08-09-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 08-09-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 10
09-09-2025 (Tuesday)
1 09-09-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD AOH OF ATD Shadow 90+90 MINS SSE/TRD/NDL
2 09-09-2025 GNT GNT-NDL GKM YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
2 09-09-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
2 09-09-2025 GNT GNT-NDL NLPD YARD SL ENGG TWS block Main 1 block of 180 min SSE/PWAY/NLPD TOWERCAR
C/o:1,
UP and AOH of T/os, Crossover and 14:45-
3 09-09-2025 GNT GNT-NDL VKN YARD 82 83 TRD Main 75+75 12:30-13:45 T/os:2
DN CLs. 16:00
,
14:00- S&T, OHE staff
4 09-09-2025 GNT GNT-NDL NDPU YARD ENGG & ST Redundant Glued Joint Renewal Main 2 Blocks of 90 min each 8:00-9:30 SSE/SW/NLPD
15:30 required
10-09-2025 (Wednesday)
TOWERCAR/PIC
1 10-09-2025 GNT GNT-NDL NDL YA LINE SL 1KM 2 KM TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 10-09-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 10-09-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 10-09-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 No. 10
11-09-2025 (Thursday)
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
1 11-09-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 11-09-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 11-09-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 11-09-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
12-09-2025 (Friday)
TOWERCAR/PIC
1 12-09-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 12-09-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 12-09-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 12-09-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
13-09-2025 (Saturday)
1 13-09-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 13-09-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 13-09-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
14-09-2025 (Sunday)
1 14-09-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
3 14-09-2025 GNT GNT-NDL VKN YARD DN ENGG TWS block MAIN 1 block of 180 min -- -- SSE/PWAY/VKN
2 14-09-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Shadow 60+60 No. 4
UP and
3 14-09-2025 GNT GNT-KCC NBR YARD ST NBR-MAG,NBR-REP B/I M/I shadow 2 blocks of 30 min each JE/S/GNT ESM
DN
15-09-2025 (Monday)
1 15-09-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD ISOLATORMAINTENANCE Shadow 60 MINS SSE/TRD/NDL
3 15-09-2025 GNT GNT-NDL VKN YARD DN ENGG TWS block MAIN 1 block of 180 min -- -- SSE/PWAY/VKN
S&T, OHE staff
3 15-09-2025 GNT GNT-NDL PRCA YARD ENGG & ST Redundant Glued Joint Renewal Main 2 Blocks of 90 min each flexible slot SSE/SW/NLPD
required
16-09-2025 (Tuesday)
1 16-09-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 60 MIN JE/SIG/NDL
2 16-09-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL
17-09-2025 (Wednesday)
1 17-09-2025 GNT GNT-NDL GZL CMZ SL 238 239 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 17-09-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
3 17-09-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
18-09-2025 (Thursday)
1 18-09-2025 GNT GNT-NDL CMZ YARD SL 230 232 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 18-09-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
3 18-09-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
19-09-2025 (Friday)
1 19-09-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD AOH OF ATD Shadow SSE/TRD/NDL
2 19-09-2025 GNT GNT-NDL GZL YARD ST LC-192 EKT MAINTENANCE Shadow 1 BLCOK 30 MIN ESM/NDL
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
3 19-09-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
4 19-09-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
5 19-09-2025 GNT GNT-NDL GJJ YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
20-09-2025 (Saturday)
1 20-09-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 20-09-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
3 20-09-2025 GNT GNT-NDL DMT YARD ST LC-197 EKT MANTENANCE Shadow 1 BLCOK 30 MIN ESM/GID
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
4 20-09-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
21-09-2025 (Sunday)
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
1 21-09-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
9.00 17.00h Tower car, Rail
1 21-09-2025 GNT GNT-NDL DMT YARD ENGG TWS block Main 1 block of 180 min SSE/PWAY/GID
hrs rs crane & OHE
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 21-09-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
3 21-09-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 10
22-09-2025 (Monday)
TOWERCAR/PIC
1 22-09-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 22-09-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 22-09-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 22-09-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 10
23-09-2025 (Tuesday)
1 23-09-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD AOH OF ATD Shadow 90+90 MINS SSE/TRD/NDL
2 23-09-2025 GNT GNT-NDL GKM YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
UP and AOH of T/os, Crossover and 14:45-
3 23-09-2025 GNT GNT-NDL VKN YARD 82 83 TRD Main 75+75 12:30-13:45
DN CLs. 16:00
24-09-2025 (Wednesday)
TOWERCAR/PIC
1 24-09-2025 GNT GNT-NDL NDL YA LINE SL 1KM 2 KM TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 24-09-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 24-09-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 24-09-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 No. 10
25-09-2025 (Thursday)
1 25-09-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 25-09-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 25-09-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. SSE/TRD/VKN
10,
Crank handle 1,2,3&4 No
4 25-09-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
26-09-2025 (Friday)
TOWERCAR/PIC
1 26-09-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 26-09-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
2 26-09-2025 GNT GNT-NDL NLPD YARD SL ENGG TWS block Main 1 block of 180 min SSE/PWAY/NLPD TOWERCAR
CLS=
3 26-09-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. SSE/TRD/VKN
10,
Crank handle 1,2,3&4 No
4 26-09-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
27-09-2025 (Saturday)
1 27-09-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 27-09-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
3 27-09-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
28-09-2025 (Sunday)
1 28-09-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
2 28-09-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Shadow 60+60 No. 4
2 28-09-2025 GNT GNT-NDL GID DMT DN ENGG PQRS block Main 1 block of 180 min SSE/PWAY/GID
UP and
3 28-09-2025 GNT GNT-KCC NBR YARD ST NBR-MAG,NBR-REP B/I M/I shadow 2 blocks of 30 min each JE/S/GNT ESM
DN
29-09-2025 (Monday)
TOWERCAR/PIC
1 29-09-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 29-09-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 29-09-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 29-09-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 10
30-09-2025 (Tuesday)
1 30-09-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD AOH OF ATD Shadow 90+90 MINS SSE/TRD/NDL
2 30-09-2025 GNT GNT-NDL GKM YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
2 30-09-2025 GNT GNT-NDL GID DMT DN ENGG PQRS block Main 1 block of 180 min SSE/PWAY/GID
UP and AOH of T/os, Crossover and 14:45- C/o:1,
3 30-09-2025 GNT GNT-NDL VKN YARD 82 83 TRD Main 75+75 12:30-13:45
DN CLs. 16:00 T/os:2
14:00- S&T, OHE staff
4 30-09-2025 GNT GNT-NDL NDPU YARD ENGG & ST Redundant Glued Joint Renewal Main 2 Blocks of 90 min each 8:00-9:30 SSE/SW/NLPD
15:30 required
01-10-2025 (Wednesday)
TOWERCAR/PIC
1 01-10-2025 GNT GNT-NDL NDL YA LINE SL 1KM 2 KM TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 01-10-2025 GNT GNT-NDL GID DMT DN ENGG PQRS block Main 1 block of 180 min SSE/PWAY/GID
2 01-10-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 01-10-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 01-10-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Shadow 75+75 No. 10
02-10-2025 (Thursday)
1 02-10-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 02-10-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
2 02-10-2025 GNT GNT-NDL GID DMT DN ENGG PQRS block Main 1 block of 180 min SSE/PWAY/GID
CLS=
3 02-10-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE MAIN 60+60 No. SSE/TRD/VKN
10,
Crank handle 1,2,3&4 No
4 02-10-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
03-10-2025 (Friday)
TOWERCAR/PIC
1 03-10-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 03-10-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
2 03-10-2025 GNT GNT-NDL GID DMT DN ENGG PQRS block Main 1 block of 180 min SSE/PWAY/GID
CLS=
3 03-10-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE MAIN 60+60 No. SSE/TRD/VKN
10,
Crank handle 1,2,3&4 No
4 03-10-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
04-10-2025 (Saturday)
1 04-10-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
1 04-10-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 04-10-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
3 04-10-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
05-10-2025 (Sunday)
1 05-10-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
2 05-10-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Main 60+60 No. 4
2 05-10-2025 GNT GNT-NDL GID DMT DN ENGG PQRS block Main 1 block of 180 min SSE/PWAY/GID
UP and
3 05-10-2025 GNT GNT-KCC NBR YARD ST NBR-MAG,NBR-REP B/I M/I shadow 2 blocks of 30 min each JE/S/GNT ESM
DN
06-10-2025 (Monday)
1 06-10-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Main 60+60 4
2 06-10-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD AOH OF ATD Shadow SSE/TRD/NDL
3 06-10-2025 GNT GNT-NDL GZL YARD ST LC-192 EKT MAINTENANCE Shadow 1 BLCOK 30 MIN ESM/NDL
07-10-2025 (Tuesday)
1 07-10-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER MAIN 1 BLOCK 30 MIN JE/SIG/NDL
2 07-10-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE MAIN 60+60+60 MINS SSE/TRD/NDL TOWERCAR
S&T ,OHE
3 07-10-2025 GNT GNT-NDL GNT YARD SL ENGG Tamping MAIN 2 blocks of 120+120 min flexible slot SSE/PWAY/GNT
Required
08-10-2025 (Wednesday)
1 08-10-2025 GNT GNT-NDL CMZ GZL SL 238 239 TRD CL'S MAINTENANCE MAIN 60+60 MINS SSE/TRD/NDL TOWER CAR
1 08-10-2025 GNT GNT-NDL NDL YARD SL ENGG TWS block MAIN 1 block of 180 min SSE/PWAY/NDL TOWER CAR
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 08-10-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
S&T ,OHE
3 08-10-2025 GNT GNT-NDL GNT YARD SL ENGG Tamping MAIN 2 blocks of 120+120 min flexible slot SSE/PWAY/GNT
Required
09-10-2025 (Thursday)
1 09-10-2025 GNT GNT-NDL NDL NDPL ST LC-186 EKT MAINTENANCE MAIN 1 BLOCK 30 MIN ESM/NDL
2 09-10-2025 GNT GNT-NDL NDPL YARD SL 253 255 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL TOWER CAR
S&T ,OHE
3 09-10-2025 GNT GNT-NDL GNT YARD SL ENGG Tamping MAIN 2 blocks of 120+120 min flexible slot SSE/PWAY/GNT
Required
10-10-2025 (Friday)
1 10-10-2025 GNT GNT-NDL GZL NDPL SL 246 247 TRD CLS MAINTENACE Shadow 60+60 MINS SSE/TRD/NDL TOWER CAR
2 26-09-2025 GNT GNT-NDL NLPD YARD SL ENGG TWS block Main 1 block of 180 min SSE/PWAY/NLPD TOWERCAR
14:45-
2 10-10-2025 GNT GNT-NDL VKN SYM DN 72 82 TRD AOH of CLs Main 75+75 12:30-13:45 10
16:00
3 10-10-2025 GNT GNT-NDL NDPU YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30" JE/S/PPM ESM
S&T ,OHE
4 10-10-2025 GNT GNT-NDL GNT YARD SL ENGG Tamping MAIN 2 blocks of 120+120 min flexible slot SSE/PWAY/GNT
Required
11-10-2025 (Saturday)
1 11-10-2025 GNT GNT-NDL GJJ YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
S&T, OHE staff
2 11-10-2025 GNT GNT-NDL PRCA YARD ENGG & ST Rail Renewal Main 2 Blocks of 90 min each flexible slot SSE/SW/NLPD
required
Crank handle 5,6,7&8 No
3 11-10-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 blocks each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
12-10-2025 (Sunday)
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
13-10-2025 (Monday)
1 13-10-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD ISOLATORMAINTENANCE Shadow 60 MINS SSE/TRD/NDL
S&T, OHE staff
3 13-10-2025 GNT GNT-NDL PRCA YARD ENGG & ST Redundant Glued Joint Renewal Main 2 Blocks of 90 min each flexible slot SSE/SW/NLPD
required
14-10-2025 (Tuesday)
1 14-10-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 60 MIN JE/SIG/NDL
2 14-10-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL
S&T, OHE staff
3 14-10-2025 GNT GNT-NDL PRCA YARD ENGG & ST Redundant Glued Joint Renewal Main 2 Blocks of 90 min each flexible slot SSE/SW/NLPD
required
15-10-2025 (Wednesday)
1 15-10-2025 GNT GNT-NDL GZL CMZ SL 238 239 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
S&T, OHE staff
3 15-10-2025 GNT GNT-NDL PRCA YARD ENGG & ST Redundant Glued Joint Renewal Main 2 Blocks of 90 min each flexible slot SSE/SW/NLPD
required
16-10-2025 (Thursday)
1 16-10-2025 GNT GNT-NDL CMZ YARD SL 230 232 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
17-10-2025 (Friday)
1 17-10-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD AOH OF ATD Shadow SSE/TRD/NDL
2 17-10-2025 GNT GNT-NDL GZL YARD ST LC-192 EKT MAINTENANCE Shadow 1 BLCOK 30 MIN ESM/NDL
3 17-10-2025 GNT GNT-NDL GJJ YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
18-10-2025 (Saturday)
1 18-10-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 18-10-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
3 18-10-2025 GNT GNT-NDL DMT YARD ST LC-197 EKT MANTENANCE Shadow 1 BLCOK 30 MIN ESM/GID
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
4 18-10-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
19-10-2025 (Sunday)
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
1 19-10-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 19-10-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
3 19-10-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 10
20-10-2025 (Monday)
TOWERCAR/PIC
1 20-10-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 20-10-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 20-10-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 20-10-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Main 75+75 10
21-10-2025 (Tuesday)
1 21-10-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD AOH OF ATD Shadow 90+90 MINS SSE/TRD/NDL
2 21-10-2025 GNT GNT-NDL GKM YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
UP and AOH of T/os, Crossover and 14:45- C/o:1,
3 21-10-2025 GNT GNT-NDL VKN YARD 82 83 TRD Main 75+75 12:30-13:45
DN CLs. 16:00 T/os:2
22-10-2025 (Wednesday)
TOWERCAR/PIC
1 22-10-2025 GNT GNT-NDL NDL YA LINE SL 1KM 2 KM TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 22-10-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
3 22-10-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 22-10-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Main 75+75 No. 10
23-10-2025 (Thursday)
1 23-10-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 23-10-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 23-10-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE MAIN 60+60 No. SSE/TRD/VKN
10,
Crank handle 1,2,3&4 No
4 23-10-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
24-10-2025 (Friday)
TOWERCAR/PIC
1 24-10-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 24-10-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 24-10-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE MAIN 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 24-10-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
25-10-2025 (Saturday)
1 25-10-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 25-10-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 25-10-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
26-10-2025 (Sunday)
1 26-10-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
2 26-10-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Main 60+60 No. 4
UP and
3 26-10-2025 GNT GNT-KCC NBR YARD ST NBR-MAG,NBR-REP B/I M/I shadow 2 blocks of 30 min each JE/S/GNT ESM
DN
27-10-2025 (Monday)
TOWERCAR/PIC
1 27-10-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 27-10-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 27-10-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 27-10-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Main 75+75 10
28-10-2025 (Tuesday)
1 28-10-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD AOH OF ATD Shadow 90+90 MINS SSE/TRD/NDL
2 28-10-2025 GNT GNT-NDL GKM YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
2 28-10-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
2 28-10-2025 GNT GNT-NDL NLPD YARD SL ENGG TWS block Main 1 block of 180 min SSE/PWAY/NLPD TOWERCAR
C/o:1,
UP and AOH of T/os, Crossover and 14:45-
3 28-10-2025 GNT GNT-NDL VKN YARD 82 83 TRD Main 75+75 12:30-13:45 T/os:2
DN CLs. 16:00
,
14:00- S&T, OHE staff
4 28-10-2025 GNT GNT-NDL NDPU YARD ENGG & ST Redundant Glued Joint Renewal Main 2 Blocks of 90 min each 8:00-9:30 SSE/SW/NLPD
15:30 required
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
29-10-2025 (Wednesday)
TOWERCAR/PIC
1 29-10-2025 GNT GNT-NDL NDL YA LINE SL 1KM 2 KM TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 29-10-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 29-10-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 29-10-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Main 75+75 No. 10
30-10-2025 (Thursday)
1 30-10-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 30-10-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 30-10-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE MAIN 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 30-10-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
31-10-2025 (Friday)
TOWERCAR/PIC
1 31-10-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 31-10-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 31-10-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE MAIN 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 31-10-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
01-11-2025 (Saturday)
1 01-11-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
1 02-11-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
2 02-11-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Main 60+60 No. 4
UP and
3 02-11-2025 GNT GNT-KCC NBR YARD ST NBR-MAG,NBR-REP B/I M/I shadow 2 blocks of 30 min each JE/S/GNT ESM
DN
03-11-2025 (Monday)
1 03-11-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD ISOLATORMAINTENANCE Shadow 60 MINS SSE/TRD/NDL
04-11-2025 (Tuesday)
1 04-11-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 60 MIN JE/SIG/NDL
2 04-11-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL
05-11-2025 (Wednesday)
1 05-11-2025 GNT GNT-NDL GZL CMZ SL 238 239 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
06-11-2025 (Thursday)
1 06-11-2025 GNT GNT-NDL CMZ YARD SL 230 232 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
1 07-11-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD AOH OF ATD Shadow SSE/TRD/NDL
2 07-11-2025 GNT GNT-NDL GZL YARD ST LC-192 EKT MAINTENANCE Shadow 1 BLCOK 30 MIN ESM/NDL
5 07-11-2025 GNT GNT-NDL GJJ YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
08-11-2025 (Saturday)
1 08-11-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
3 08-11-2025 GNT GNT-NDL DMT YARD ST LC-197 EKT MANTENANCE Shadow 1 BLCOK 30 MIN ESM/GID
3 09-11-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 flexible slot 10
10-11-2025 (Monday)
TOWERCAR/PIC
1 10-11-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 10-11-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
3 10-11-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 10-11-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Main 75+75 10
11-11-2025 (Tuesday)
1 11-11-2025 GNT GNT-NDL NDL YARD SL 256 257 TRD AOH OF ATD Shadow 90+90 MINS SSE/TRD/NDL
2 11-11-2025 GNT GNT-NDL GKM YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
UP and AOH of T/os, Crossover and 14:45-
3 11-11-2025 GNT GNT-NDL VKN YARD 82 83 TRD Main 75+75 12:30-13:45
DN CLs. 16:00
12-11-2025 (Wednesday)
TOWERCAR/PIC
1 12-11-2025 GNT GNT-NDL NDL YA LINE SL 1KM 2 KM TRD POH OF ATD Shadow 60+60 SSE/TRD/NDL
KUP
2 12-11-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLCOK 60 MIN JE/SIG/NDL
3 12-11-2025 GNT GNT-NDL GZL CMZ SL 240 242 TRD AOH OF ATD Shadow 60+60 MINS
4 12-11-2025 GNT GNT-NDL CEM VKN DN 88 82 TRD AOH of CLs Main 75+75 No. 10
13-11-2025 (Thursday)
1 13-11-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 13-11-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 13-11-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE MAIN 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 13-11-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
14-11-2025 (Friday)
TOWERCAR/PIC
1 14-11-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
2 14-11-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 14-11-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE MAIN 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 14-11-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
15-11-2025 (Saturday)
1 15-11-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 15-11-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 15-11-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
16-11-2025 (Sunday)
1 16-11-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
2 16-11-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Main 60+60 No. 4
UP and
3 16-11-2025 GNT GNT-KCC NBR YARD ST NBR-MAG,NBR-REP B/I M/I shadow 2 blocks of 30 min each JE/S/GNT ESM
DN
17-11-2025 (Monday)
1 17-11-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 17-11-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 17-11-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 17-11-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
18-11-2025 (Tuesday)
TOWERCAR/PIC
1 18-11-2025 GNT GNT-NDL NDL NDPL SL 256 257 TRD SCL MAINTENANCE WORK Shadow 60+60 SSE/TRD/NDL
KUP
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
2 18-11-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
CLS=
3 18-11-2025 GNT GNT-NDL CEM YARD UP&DN 88 90 TRD T/OS MAINTENANCE Shadow 60+60 No. 10, SSE/TRD/VKN
T/O=2
Crank handle 1,2,3&4 No
4 18-11-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 block each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
19-11-2025 (Wednesday)
1 19-11-2025 GNT GNT-NDL CMZ DMT SL 221 223 TRD TUNNEL SCL MAINTENANCE Shadow 60+60 SSE/TRD/NDL TOWERCAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 19-11-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 19-11-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
20-11-2025 (Thursday)
1 20-11-2025 GNT GNT-NDL DMT CMZ SL 220 221 TRD AOH of ATD Shadow 60+60 MINS SSE/TRD/NDL
2 20-11-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Shadow 60+60 No. 4
UP and
3 20-11-2025 GNT GNT-KCC NBR YARD ST NBR-MAG,NBR-REP B/I M/I shadow 2 blocks of 30 min each JE/S/GNT ESM
DN
21-11-2025 (Friday)
1 21-11-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 60 MIN JE/SIG/NDL
2 21-11-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL
22-11-2025 (Saturday)
1 22-11-2025 GNT GNT-NDL GZL CMZ SL 238 239 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 22-11-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 22-11-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
23-11-2025 (Sunday)
1 23-11-2025 GNT GNT-NDL CMZ YARD SL 230 232 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 23-11-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 23-11-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
24-11-2025 (Monday)
1 24-11-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD ISOLATORMAINTENANCE Shadow 60 MINS SSE/TRD/NDL
S&T, OHE staff
2 24-11-2025 GNT GNT-NDL PRCA YARD ENGG & ST Redundant Glued Joint Renewal Main 2 Blocks of 90 min each flexible slot SSE/SW/NLPD
required
25-11-2025 (Tuesday)
1 25-11-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 60 MIN JE/SIG/NDL
2 25-11-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL
26-11-2025 (Wednesday)
1 26-11-2025 GNT GNT-NDL GZL CMZ SL 238 239 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 26-11-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 26-11-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
27-11-2025 (Thursday)
1 27-11-2025 GNT GNT-NDL CMZ YARD SL 230 232 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 27-11-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 27-11-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
28-11-2025 (Friday)
1 28-11-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD AOH OF ATD Shadow SSE/TRD/NDL
2 28-11-2025 GNT GNT-NDL GZL YARD ST LC-192 EKT MAINTENANCE Shadow 1 BLCOK 30 MIN ESM/NDL
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
3 28-11-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
Towerstaff
car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
4 28-11-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
5 28-11-2025 GNT GNT-NDL GJJ YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
29-11-2025 (Saturday)
1 29-11-2025 GNT GNT-NDL GZL CMZ SL 233 234 TRD AOH OF ATD Shadow 60+60 MINS SSE/TRD/NDL
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 29-11-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
3 29-11-2025 GNT GNT-NDL DMT YARD ST LC-197 EKT MANTENANCE Shadow 1 BLCOK 30 MIN ESM/GID
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
4 29-11-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
30-11-2025 (Sunday)
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
1 30-11-2025 GNT GNT-NDL CMZ JBK DL 231 177 OHE - CON Shadow 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
Pending works/ Remarks block may be planed as 9.00 17.00h Tower car, Rail
2 30-11-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA
attention per B/S hrs rs crane & OHE
3 30-11-2025 GNT GNT-NDL GKM CEM UP 89 95 TRD AOH of CLs Shadow 75+75 10
01-12-2025 (Monday)
1 01-12-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Shadow 60+60 4
2 01-12-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD AOH OF ATD Shadow SSE/TRD/NDL
3 01-12-2025 GNT GNT-NDL GZL YARD ST LC-192 EKT MAINTENANCE Shadow 1 BLCOK 30 MIN ESM/NDL
02-12-2025 (Tuesday)
1 02-12-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER Shadow 1 BLOCK 30 MIN JE/SIG/NDL
2 02-12-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE Shadow 60+60+60 MINS SSE/TRD/NDL TOWERCAR
03-12-2025 (Wednesday)
1 03-12-2025 GNT GNT-NDL CMZ GZL SL 238 239 TRD CL'S MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL TOWER CAR
Tower car, Rail
Pending works/ Remarks block may be planed as 9.00 17.00h
2 03-12-2025 GNT GNT-NDL MRK STUR DL 143 32 OHE - CON Main 2 Blocks of each 120min SSE/TrD/C/BZA crane & OHE
attention per B/S hrs rs
staff
04-12-2025 (Thursday)
1 04-12-2025 GNT GNT-NDL NDL NDPL ST LC-186 EKT MAINTENANCE Shadow 1 BLOCK 30 MIN ESM/NDL
2 04-12-2025 GNT GNT-NDL NDPL YARD SL 253 255 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL TOWER CAR
05-12-2025 (Friday)
1 05-12-2025 GNT GNT-NDL GZL NDPL SL 246 247 TRD CLS MAINTENACE Shadow 60+60 MINS SSE/TRD/NDL TOWER CAR
14:45-
2 05-12-2025 GNT GNT-NDL VKN SYM DN 72 82 TRD AOH of CLs Main 75+75 12:30-13:45 10
16:00
3 05-12-2025 GNT GNT-NDL NDPU YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30" JE/S/PPM ESM
06-12-2025 (Saturday)
1 06-12-2025 GNT GNT-NDL GJJ YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
Block Planned Demanded On Date
Sub KM Planned block Timings Train
Major Station/Station Main or Planned Block Duration Output Supervisor Block Timings Remarks (S&T, Caution Order
S.No Date Div Secti Direction Dept Type of Work Repercu (HH:MM) OHE, Tower Car,
Section Shadow (in mins) From To Deputed Impositions/
on From To From To Unit Quantity sions Power block, etc)
(HH:MM) (HH:MM) From To Alterations
S&T, OHE staff
2 06-12-2025 GNT GNT-NDL PRCA YARD ENGG & ST Rail Renewal Main 2 Blocks of 90 min each flexible slot SSE/SW/NLPD
required
Crank handle 5,6,7&8 No
3 06-12-2025 GNT GNT-NDL NLPD Yard ST Shadow 4 blocks each 30 minutes JE /SIGNAL /NLPD ESM
M/Inspection Train
07-12-2025 (Sunday)
1 07-12-2025 GNT GNT-NDL KCD YARD UP 106 108 TRD AOH of Turnouts and Crossoves Shadow 2 blocks of 75 min each flexible slot
08-12-2025 (Monday)
1 08-12-2025 GNT GNT-NDL CEM VKN UP 82 88 TRD AOH of ATDs Main 60+60 4
2 08-12-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD AOH OF ATD Shadow SSE/TRD/NDL
3 08-12-2025 GNT GNT-NDL GZL YARD ST LC-192 EKT MAINTENANCE Shadow 1 BLCOK 30 MIN ESM/NDL
09-12-2025 (Tuesday)
1 09-12-2025 GNT GNT-NDL NDL YARD ST EI CHANGE OVER MAIN 1 BLOCK 30 MIN JE/SIG/NDL
2 09-12-2025 GNT GNT-NDL CMZ DMT SL 218 219 TRD CL'S MAINTENANCE MAIN 60+60+60 MINS SSE/TRD/NDL TOWERCAR
S&T ,OHE
3 09-12-2025 GNT GNT-NDL GNT YARD SL ENGG Tamping MAIN 2 blocks of 120+120 min flexible slot SSE/PWAY/GNT
Required
10-12-2025 (Wednesday)
1 10-12-2025 GNT GNT-NDL CMZ GZL SL 238 239 TRD CL'S MAINTENANCE MAIN 60+60 MINS SSE/TRD/NDL TOWER CAR
11-12-2025 (Thursday)
1 11-12-2025 GNT GNT-NDL NDL NDPL ST LC-186 EKT MAINTENANCE MAIN 1 BLOCK 30 MIN ESM/NDL
2 11-12-2025 GNT GNT-NDL NDPL YARD SL 253 255 TRD UIOL MAINTENANCE Shadow 60+60 MINS SSE/TRD/NDL TOWER CAR
S&T ,OHE
3 11-12-2025 GNT GNT-NDL GNT YARD SL ENGG Tamping MAIN 2 blocks of 120+120 min flexible slot SSE/PWAY/GNT
Required
12-12-2025 (Friday)
1 12-12-2025 GNT GNT-NDL GZL NDPL SL 246 247 TRD CLS MAINTENACE Shadow 60+60 MINS SSE/TRD/NDL TOWER CAR
14:45-
2 12-12-2025 GNT GNT-NDL VKN SYM DN 72 82 TRD AOH of CLs Main 75+75 12:30-13:45 10
16:00
3 12-12-2025 GNT GNT-NDL NDPU YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30" JE/S/PPM ESM
S&T ,OHE
4 12-12-2025 GNT GNT-NDL GNT YARD SL ENGG Tamping MAIN 2 blocks of 120+120 min flexible slot SSE/PWAY/GNT
Required
13-12-2025 (Saturday)
1 13-12-2025 GNT GNT-NDL GJJ YARD ST Both B/I Monthly Inspection Shadow 2 Blocks of each 30MIN. JE/S/KCD ESM
14-12-2025 (Sunday)
1 14-12-2025 GNT GNT-NDL NDL YARD SL 256 256 TRD ISOLATORMAINTENANCE Shadow 60 MINS SSE/TRD/NDL
AKULA Digitally
by AKULA
signed
Digitally signed by
BHARA BHARATH
KUMAR
SRINATH JAGIRDAR
TH Date:
Digitally signed by Date: 2025.06.13
2025.06.14 SYED VAZEER PENUMUD Digitally signed by
17:54:21 +05'30'
SYED VAZEER BABU PENUMUDI RAVITEJA