Present status of works
Schedule of NCTPS Stage III 1 X 800 MW restoration for Trial operation & C OD
Sl No. Description of Work Start time End time Remarks
1 Draining of boiler 14: 35 18: 35 Completed
2 Grinding of vent line leakage joints 19: 00 21:00 Completed
3 Welding of vent line Leak joints 22:00 23:00 Completed
4 SR of vent line leak joints 23:00 22.12.2024 Completed
15:00
5 Platform works for bottom ring header 21:00 22.12.2024 Completed
03:00
22.12.2024
6 Grinding of bottom ring header leakage 03:00 14:00 completed
joints
7 Welding of bottom ring header 14:30 18:00 Completed
8 SR of Bottom ring header joints 18:00 23.12.2024 In progress
14:00
9 Boiler water filling 17:30 20:00
10 Boiler hydro test and physical leak 20:00 21:00 Pressurising to
check 200 ksc and
physical checking
11 Boiler water draining to Normal level 21::00 21:15
12 De-aerator filling and aux boiler light up 21:00 24/12/202
and raising of de-aerator to 140 °C 4 02:00
24.12.2024
13 Hot water feed to boiler and light up 02:00 06:30
14 Vacuum pulling 06:00 07:00
15 Steam dumping 07:00 13:00
16 Synchronization/ Load rising to 280 MW 13:30 16:30 Check for silica
and iron values
to proceed to dry
mode
17 Load rise to 400- 450 MW 16:30 19:00
18 Further load rise Based on grid
clearance and
coal conditions
PA Fan A ready for trial
FD Fan B Blade fixing in progress (one number O ring and Teflon gasket damaged, spare expected by
10:00 hrs 23/12/2024
Tommorrow lowering of casing inspection and clearance for running.