Present Unit Restart Program 221224

The document outlines the current status of the NCTPS Stage III 1 X 800 MW restoration project, detailing completed and ongoing tasks with specific timeframes. Key activities include draining the boiler, welding leak joints, and preparing for trial operation. Additional notes indicate that the PA Fan A is ready for trial, while repairs on FD Fan B are in progress, with further actions scheduled for the following day.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views1 page

Present Unit Restart Program 221224

The document outlines the current status of the NCTPS Stage III 1 X 800 MW restoration project, detailing completed and ongoing tasks with specific timeframes. Key activities include draining the boiler, welding leak joints, and preparing for trial operation. Additional notes indicate that the PA Fan A is ready for trial, while repairs on FD Fan B are in progress, with further actions scheduled for the following day.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Present status of works

Schedule of NCTPS Stage III 1 X 800 MW restoration for Trial operation & C OD
Sl No. Description of Work Start time End time Remarks
1 Draining of boiler 14: 35 18: 35 Completed
2 Grinding of vent line leakage joints 19: 00 21:00 Completed
3 Welding of vent line Leak joints 22:00 23:00 Completed
4 SR of vent line leak joints 23:00 22.12.2024 Completed
15:00
5 Platform works for bottom ring header 21:00 22.12.2024 Completed
03:00
22.12.2024
6 Grinding of bottom ring header leakage 03:00 14:00 completed
joints
7 Welding of bottom ring header 14:30 18:00 Completed
8 SR of Bottom ring header joints 18:00 23.12.2024 In progress
14:00
9 Boiler water filling 17:30 20:00
10 Boiler hydro test and physical leak 20:00 21:00 Pressurising to
check 200 ksc and
physical checking
11 Boiler water draining to Normal level 21::00 21:15
12 De-aerator filling and aux boiler light up 21:00 24/12/202
and raising of de-aerator to 140 °C 4 02:00
24.12.2024
13 Hot water feed to boiler and light up 02:00 06:30
14 Vacuum pulling 06:00 07:00
15 Steam dumping 07:00 13:00
16 Synchronization/ Load rising to 280 MW 13:30 16:30 Check for silica
and iron values
to proceed to dry
mode
17 Load rise to 400- 450 MW 16:30 19:00
18 Further load rise Based on grid
clearance and
coal conditions

PA Fan A ready for trial

FD Fan B Blade fixing in progress (one number O ring and Teflon gasket damaged, spare expected by
10:00 hrs 23/12/2024

Tommorrow lowering of casing inspection and clearance for running.