GIS 22-101 Guidance On Industry Standard For ISO13705 Fired Heaters API 560
GIS 22-101 Guidance On Industry Standard For ISO13705 Fired Heaters API 560
GIS 22-101
Applicability Group
Date 30 December 2005
GIS 22-101
BP GROUP
ENGINEERING TECHNICAL PRACTICES
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Foreword
This is the first issue of Engineering Technical Practice (ETP) BP GIS 22-101. It is based on ISO
13705 and documents of three merged companies, BP, Amoco, and Arco listed below.
In addition, reference is made to other standards and reports that provide guidance in use of heritage
documents or similar documents.
Normative references are mandatory to extent that they are referenced and not superseded by this
guide.
British Petroleum
GS 122-1 Fired Heaters to API 560.
GS 122-2 Natural Drought Burners for Fired Process Heaters.
GS 122-3 Forced Draught Burners for Fired Process Heaters.
Amoco
A FE-FH 560-G Fabricated Equipment Fired Heaters Guide.
A FE-FH 560-E Fabricated Equipment Fired Heaters API 560 Engineering Specification.
ARCO
ES 30 Fired Process Heaters.
ES 110 Refractory Linings.
Page 2 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Table of Contents
Page
Foreword............................................................................................................................................2
Introduction ........................................................................................................................................6
1 Scope (1.1) ...............................................................................................................................6
1.1 Data sheets ...................................................................................................................7
1.2 Scope exclusions...........................................................................................................7
2 Normative references (1.6/1.7/1.3) ...........................................................................................7
2.1 Local codes ...................................................................................................................8
2.2 Compliance....................................................................................................................8
2.3 Precedence ...................................................................................................................8
3 Terms and definitions (1.4) .......................................................................................................9
4 General .....................................................................................................................................9
4.5 Alternative designs ........................................................................................................9
4.6 Material safety data sheets (MSDS) ..............................................................................9
5 Proposals (1.8) .......................................................................................................................10
5.1 Purchaser’s responsibilities .........................................................................................10
5.2 Vendor’s responsibilities (1.2 Alternative designs) ......................................................10
5.3 Documentation (1.9) ....................................................................................................12
5.3.1 Drawings for purchaser’s review .................................................................................12
6 Design considerations (2) .......................................................................................................12
6.1 Process design (2.1)....................................................................................................13
6.2 Combustion design (2.2) .............................................................................................15
6.3 Mechanical design (2.3 Mechanical) ...........................................................................15
7 Tubes (3) ................................................................................................................................16
7.1 General (3.1) ...............................................................................................................16
7.3 Materials (3.3)..............................................................................................................16
8 Headers (4).............................................................................................................................17
8.1 General (4.1) ...............................................................................................................17
8.2 Plug headers (4.2) .......................................................................................................17
8.3 Return bends (4.3).......................................................................................................17
8.4 Materials (4.4)..............................................................................................................17
9 Piping, terminals and manifolds (5) ........................................................................................18
9.1 General (5.1) ...............................................................................................................18
9.2.1 Allowable movement and loads...................................................................................18
9.3 Materials (5.3)..............................................................................................................18
10 Tube supports (6) ...................................................................................................................18
10.1 General (6.1) ...............................................................................................................18
10.3 Materials (6.3)..............................................................................................................19
Page 3 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Page 4 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
List of Tables
Page 5 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Introduction
a. Guidance for design, fabrication, erection, and testing of fired process heaters is based on
ISO 13705:2001.
b. Guidance statements of this GIS are modifications to ISO 13705.
c. Modifications to ISO 13705 are identified as Add, Modify to Read, or Delete.
d. Paragraph numbers in this specification correspond to ISO 13705.
e. Paragraphs of ISO 13705 that are not revised remain applicable.
f. Commentary additions to Paragraphs in this GIS are provided to further identify BP
practices with fired process heaters.
g. Due to a similarity between ISO 13705:2001 and API Std 560, API Std 560 may be used
as a base for process design and purchase of process fired heater. However, all Add,
Modify to Read, Delete, or Commentary from this GIS still apply.
h. Paragraph numbers in parenthesis provides reference to API Std 560 sections.
By necessity, ISO 13705:2001 and API Std 560 provide more flexibility than
required by BP. These two documents do not include specific BP experience. This
GIS adds requirements that BP has found necessary for safe and cost effective
operation.
From experience of the industry as a whole, the ISO and API standards are a
distillation of general experience. Individual companies have different cultures and
operating procedures (again learned from experience). BP requirements in this GIS
fit with the BP operating and design philosophy.
This GIS may refer to certain local, national, or international regulations, but the
responsibility to ensure compliance with legislation and any other statutory
requirements lies with the user. The user should adapt or supplement this GIS to
ensure compliance for the specific application.
1 Scope (1.1)
Add
This GIS provides guidance on industry standard for the design, materials, fabrication,
inspection, testing, documentation, and preparation for shipment of fired process heaters based
on ISO 13705:2001.
Engineers should be acquainted with BP and Industry requirements for fired heater
services and ensure appropriate requirements are applied to the specific fired
heater application. BP Process Hazard Analyses and siting studies are important
sources for both input and review of the engineering of fired heaters. BP experts in
applicable areas of heater design should be consulted on new heater designs that
have not been previously reviewed.
Page 6 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Add
Add
BP
DS 22-100 Data Sheet for Fired Heaters.
GIS 12-201 Guidance on Industry Standard for Low Voltage Induction Motors (IEC).
GIS 12-202 Guidance on Industry Standard for Low Voltage Motors (IEEE 841).
GIS 12-203 Guidance on Industry Standard for High Voltage Induction Motors (IEC).
GIS 12-204 Guidance on Industry Standard for Medium Voltage Motors (API 541).
GIS 72-001 Guidance on Industry Standard for Procurement of Refractory (Including
Material Performance Requirements).
GIS 72-002 Guidance on Industry Standard for Refractory Installation.
GIS 72-003 Guidance on Industry Standard for Refractory Dry-out.
GIS 72-004 Guidance on Industry Standard for Refractory Inspection.
GIS-72-102 Guidance on industry Standard for Vee Anchoring Systems.
GIS 72-103 Guidance on Industry Standard for Hex-mesh Anchoring Details.
GIS 72-104 Guidance on Industry Standard for Independent Anchor Systems –
Corner Tabs, U-Tabs and Ring Tabs.
GIS 72-105 Guidance on Industry Standard for Refractory Construction Details.
GIS 72-106 Guidance on Industry Standard for Independent Anchor Systems – Hex
Cells, S-Bars and Curl Anchors.
GIS 72-108 Guidance on Industry Standard for Miscellaneous Refractory
Construction Details.
Page 7 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
2.2 Compliance
BP and Vendor shall mutually determine measures that must be taken to comply with federal,
state, or local codes, regulations, ordinances, or rules that may be applicable to equipment.
As an example, Material Safety Data Sheet is required for all chemicals received at
BP Company facilities within the United States (refer to Section 4.6 for more
details)
2.3 Precedence
a. Order of application of the specification shall be:
1. Statutory or local regulations.
2. Equipment requisition and data sheets.
3. BP specifications.
Page 8 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
4. ISO 13705.
b. In absence of specified order of precedence, Vendor shall obtain written approval from BP
before proceeding with work.
Add
3.82
3.83
3.84
3.85
4 General
Add
Page 9 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
c. MSDSs shall fully comply with regulations for MSDS preparation specified by entity that
has jurisdiction and shall include a statement that the substance is considered hazardous by
regulation.
d. If any substance is exempt from regulation, a statement to that effect shall be included.
e. Before shipment, MSDSs shall be forwarded to receiving facility.
f. At shipment, MSDSs in protective envelopes shall be affixed to the outside of the
shipment.
5 Proposals (1.8)
Add
Page 10 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
5.2.4 Exceptions
a. BP approval of Vendor of design and drawings for construction or release of equipment by
authorized inspector shall not relieve Vendor of responsibility for heater and does not alter
conditions of guarantee.
b. At bid submittal stage, all exceptions taken to these specifications, all variances from these
specifications, and all substitutions of operating capabilities or equipment called for in
these specifications shall be listed in writing and forwarded to BP or its designated
representative. Any such exceptions, variances, or substitutions that are not listed at time
of bid and which subsequently are identified by BP or its representative in the submittal
shall be grounds for immediate disapproval without comment.
c. Fabrication shall not begin until drawings have been stamped approved for construction by
BP or their designated representative.
Page 11 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Add
Add
Fired heaters and their auxiliary equipment covered by this GIS shall be suitable for all
specified operating conditions and shall be designed and constructed to operate for at least 4
years of uninterrupted continuous service periods between shutdowns, unless otherwise
approved by BP.
Page 12 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
If the heater is expected to run longer between shutdowns, that timeframe should be
specified to replace the “4 years”.
The 4 years operational requirement shall consider the following:
a. Design should take into consideration component design and selection of materials of
construction to ensure thermal and hydraulic performance is maintained during this period.
b. If 4 years of continuous operation requirement cannot be met, Vendor should specify:
1. Why this requirement cannot be met (this could be for process and/or economic
reasons).
2. Which operating periods can be guaranteed.
Page 13 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Avoiding pass splitting may not be possible in all applications, such as vacuum
heaters and ethylene crackers.
c. If convection sections of process heater are either wholly or partially used to generate
steam, following requirements shall be met:
1. If steam superheater coils are used, these shall not form part of first three rows of
convection shield sections. This requirement shall also apply to stripping steam coils
located in convection section of process heater.
Preferably, this coil should be “sandwiched-in” within steam generation tubes. This
assures that superheater tubes can be operated, particularly during the heater/unit
start-up, in “dry” or without flow through conditions without risk of heat damage to
the tubes.
2. Design of steam generator shall be subject to BP approval.
The allowable water-steam circulation rates, the minimum allowable tube side
velocities and the maximum allowable heat fluxes for steam generations are a
function of steam pressure and water quality.
3. Proposed steam generation operation should not prejudice process operation and this
shall be taken into account if steam generation coil is proposed.
Possible problems shall be addressed, including:
• Statutory authorities’ requirements for boiler inspections that are more frequent
than heater inspections.
• Loss of boiler feed water requiring heater shutdown.
• High superheated steam temperatures requiring either heater to be shut down or
heater operation limited by steam temperatures.
• Loss of any section of steam generation (boiler feed water coil, steam generation
coil or steam superheat coil) may result in heater shutdown.
d. Helical or circular coil configurations shall not be used for two phase flow applications
unless approved by BP.
6.1.3
Add
Page 14 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Page 15 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
7. Header box covers shall be gasketed and bolted tightly all around.
Keeping the air-in leaks to the minimum is very important for heater performance.
b. If steam air decoking is specified, coil material together with provisions for thermal
expansion shall be suitable for short term tube metal temperature of at least 675°C
(1250°F).
7 Tubes (3)
Add
Page 16 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
8 Headers (4)
Page 17 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Add
9.1.9 a. Unless approved by BP in writing, manifolds shall have extruded instead of welded in
stubs.
b. If extruded manifolds are carbon steel, stress relieving shall be used.
c. If manifolds are stainless steel, solution annealing shall be used.
Add
Page 18 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
10.1.8 Sleeves
a. Stainless steel sleeves shall be attached and filled with refractory for the provision of the
two additional tube rows stated in section 10.1.7.
b. Structural end wall plate shall be partially cut to indicate position of sleeves.
Page 19 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
normal operation, then this casing temperature can be increased provided there is
economic justification for the increased heat losses, e.g. the ducting downstream of
the heater or air preheater to the stack.
For most of the heater casings the 65°C (149°F) temperature limitation is not a
problem but there could be difficulties on the roof and floor. Obviously the casing
temperature can be increased downstream of the heat exchanger where the furnace
efficiency is not affected, provided the casing cannot be touched during normal
operation.
The Vendor/Contractor should ensure that the paintwork on the casing is suitable
for the maximum temperature that the casing can attain (with still air and the
maximum ambient air temperature).
Add
11.1.11 Dry-out
Heater lining dry-out procedure shall be per GIS 72-003.
Vendor may propose an alternate dry-out procedure if the requirements of GIS 72-003 cannot be
met. Alternate refractory dry-out procedure shall be subject to BP approval.
Add
Page 20 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
d. For furnaces, fired heaters, stacks, and ducting, categories selected shall be AC-10, AC-11,
AC-14, or AC-15.
e. For Reforming furnaces categories selected shall be AC-18 or AC-19.
11.3.9 Add
Stainless steel fibres shall be type 304 unless BP approval for substitute materials is obtained.
The stainless steel fibres provide an element of structural integrity to thin layer
linings where independent anchoring is utilized. The fibres act as reinforcing that
improves mechanical integrity when cracking is evident. The fibres do not improve
other physical properties of the refractory lining. In most instances the compressive
strength is slightly reduced when stainless steel fibres are used.
Use of premix castables with metallic fibres should be avoided. Metallic fibres tend
to segregate within the mix before use. Adding fibre to premix castable prior
application is preferred option.
Add
11.3.11
a. Impervious organic coating shall be applied immediately after castable placement and
reapplication of same coating shortly after 24 hr cure to reduce tendency of hydraulic
setting castables to develop alkaline hydrolysis.
b. If alkaline hydrolysis has occurred, loss in refractory thickness is usually less than 10 mm
(3/8 in). If this occurs, loose material shall be brushed off and impervious organic coating
applied.
Hydraulic setting castables, in particular lightweight and medium weight insulating
castables, are susceptible to development of alkaline hydrolysis (carbonization) if
placed under high ambient temperatures and/or high humidity conditions shortly
after placement.
Use of forced drying by air movement or low temperature to remove a percent of
mechanical water prior to application of impervious coating can further reduce
possibility of development of alkaline hydrolysis. Alkaline hydrolysis is a naturally
occurring phenomenon such that use of either or both of above procedures may not
entirely prevent formation.
Hot Face
Product Form Manufacturer’s Fiber Temperature Rating
2 300°F 2 600°F
Blanket 1 400°F N/A
3
Module, not folded, 10 lb/ft min. 1 800°F 2 000°F
3
Module, folded, 9,3 lb/ft min. 1 900°F 2 200°F
Page 21 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
c. Soluble ceramic fibre, also known as Alkaline Earth Silicate Wool, linings shall be
selected from Table 3B of GIS 72-001.
Manufacturers of RCF have developed an alternative to refractory ceramic fibres
called soluble ceramic fibre linings. This fibrous product, which is made with
alkaline earth silicates, does not contain aluminium oxide and has proved to
dissolve in body fluids of the lung. This fibre material is considered safer for use
than RCF materials and each facility is encouraged to research this material with
the manufacturers, for possible applications, to ensure that the work force is
adequately protected.
d. Soluble ceramic fibre linings shall be limited to the temperatures shown in Table 2.
Hot Face
Product Form Manufacturer’s Fiber Temperature
Rating
980°C (1 800°F)
Blanket 760°C (1 400°F)
Module, not folded N/A
Module, folded or stacked 815°C (1 500°F)
e. Soluble ceramic fibre products should not be exposed to long term flame impingement.
Very short flame impingement will not cause significant damage, but long term
flame impingement will cause sufficient damage that could lead to hot spots and
maintenance requirements.
11.4.3 Add
Ceramic fibre exposed to direct heat shall be rated for 1 200°C (2 200°F) service, minimum.
11.4.17 Modify to read
When the fuel contains ≥ 0,5% (mass) sulfur, the following applies:
a. A protective coating to prevent acid corrosion shall to be applied to the casing.
When sulfur containing fuel is used to fire the heater the casing surface beneath the
fire protection material may be less than the condensation temperature of sulfuric
acid, a byproduct of the combustion process. Acid corrosion of the steel heater
casing will be the result. An appropriate coating can eliminate this threat.
b. Castable materials shall have a total concentration of free alkali, MgO, and iron in the
aggregate of less than 15%.
c. The “facing” of a castable or brick lining shall be “medium weight” or heavier.
d. Block insulation shall not be used when fuel sulphur content exceeds 1%.
e. When a ceramic fiber blanket is used with fuel with sulphur contents exceeding 10 ppm a
casing coating shall be applied to prevent corrosion.
f. When a ceramic fibre lining is used, fuel with ≥ 0,5% sulfur/H2S shall have a stainless
vapour barrier, 50 µm (2 mil), and casing coating. The vapour barrier shall be located
between blanket layers. The foil interface temperature shall be 55°C (100°F) above the gas
condensation temperature.
g. Surfaces to which a shell coating is to be applied for corrosion protection shall be grit
blasted to a near-white finish (SSPC-SP10).
Page 22 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
h. Acceptable shell coatings are coal tar epoxy or silicone acrylic copolymer. Shell coatings
service temperatures shall be a minimum of 28°C (50°F) above the calculated temperature
of the shell.
Table 3 below summarizes casing coating requirements.
11.4.20 Add
a. If high velocity jets are used, 14 gage 300 series SS blast shields shall be used over fibre
linings exposed to jets.
b. Shield design shall be of specified construction of 460 mm (18 in) by 460 mm (18 in)
panels with 4 anchors each.
c. If sootblowers or other high velocity jets are used in convection section and blast shields
cannot be used over fibre linings, castables shall be specified for entire convection section.
Page 23 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Page 24 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
temperature, whichever is greater, and of being raised from cold to design operating
temperature at rate of 55°C (100°F) per hr.
3. Specific attention shall also be given to possibility of low temperature conditions, in
particular, below acid dew point level, and possible effects of resultant condensation
within stack.
b. If operating conditions are such that unlined stack appears suitable, proposals may be
submitted and shall be subject to BP approval.
c. Unlined stacks should only be considered/installed if:
1. Process in tubes is noncombustible (e.g., steam superheaters or inert gas heaters).
2. Stacks are very short and easily replaced, e.g., grade mounted stacks about 15 m
(50 ft) high.
3. Reason for internally lining stack is in response to possibility of damage from heater
fire.
13.2.12 Modify to read
Breeching located over horizontal convection zones shall have at least 1 take-off for every 9,1 m
(30 ft) length of convection section.
13.2.15 Add
Steel stacks shall have corrosion allowance appropriate to 20 yr design life.
Page 25 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
14.1.19
BP may specify use of fuel gas or compressed air as substitute for steam as an
atomizing medium.
14.1.20 Add
If liquid fuels are specified to be burned, use of safety interlocking mechanism shall be
considered to ensure that:
a. Liquid fuel gun cannot be withdrawn until supply of liquid fuel and atomizing medium
have been turned off.
b. Liquid fuel and atomizing medium cannot be turned on with liquid gun withdrawn.
c. Liquid fuel cannot be turned on before atomizing medium.
d. Atomizing medium cannot be turned off before liquid fuel.
14.1.22 Add
a. Burner, but excluding any refractory parts located in or attached to heater floor or wall,
shall be suitable for being removed and replaced on process heater while other burners
remain in operation.
b. For dual fuel burners, burner shall be suitable for firing on one fuel with liquid fuel gun or
gas guns for other fuel removed.
Add
14.1.24 Louvers
a. Combustion air louvers in burner register shall have control handle and be capable of being
locked in position.
b. Louver (damper) spindle bearings shall be capable of being lubricated to ensure continuing
operation.
Page 26 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
2. For forced draught burner application, combustion air ducting arrangement drawings
and calculations to confirm that not more than 10% combustion air misdistribution,
measured within burner throat shall be present.
3. Pilot drawing.
4. Materials of construction.
5. Performance curves showing burner heat liberation for all specified fuels as function
of fuel pressure, atomizing medium pressure, and atomizing medium consumption.
6. Estimate for particulates, NOx, SOx, CO, and hydrocarbons emissions in products of
combustion for specified fuels.
7. Estimate on burner noise levels.
b. Data to be provided as part of burner supply include:
1. Final dimensioned general arrangement drawings with details on vital components,
materials of construction, and burner tip drilling information.
2. Test certificates for materials of construction for burner components.
3. Report on burner acceptance test.
4. Final burner heat release curve for specified fuel(s).
5. Installation, operating, and maintenance instructions.
6. Recommended spare parts with price list.
Page 27 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
a) Range 33% to 60% of design heat liberation at 30% and 50% excess air (all
fuels).
b) Range 60% to 110% of burner design heat liberation at 15% excess air (oil
firing), 10% excess air (gas firing), 15% excess air (all fuels), and 50% excess
air (all fuels).
c) Test to be performed on each fuel burned to determine maximum turndown that
can be achieved with satisfactory and stable combustion.
d) Test to be performed using combustion air at ambient temperature and
additionally, if BP specified, air preheated to nominated temperature.
5. Flame envelope
a) Flame envelope shall be determined during test.
b) Envelope limits could be judged by visual inspection (as minimum) or by
performing CO test by inserting sample probe along flame height and width.
c) CO content of less than 100 ppm is considered as boundary of flame envelope.
6. Stack emissions test of particulates, NOx, SOx, CO, and hydrocarbons shall be within
BP specified limits.
7. Gas pilot test shall be performed during main burner test. Pilot should exhibit stable
flame at gas design operating pressure ±40%, and over entire main burner operating
test range.
8. Pilot shall be able to ignite main burner smoothly and safely for all specified fuels at
all design heat releases and design draught conditions.
9. Burner shall be tested for out of ratio turndown flame stability on all fuels to
determine maximum safe turndown of a fuel with draught at burner remaining
constant. The following test procedure conditions may be considered:
a) Burner air louvers set fully open and drought set to provide 45% excess air at
110% of burner design heat liberation.
b) With same drought maintained at burner, flow of selected fuel to be reduced
until first signs of flame instability occur. This fuel flow and corresponding
excess air shall be recorded.
c) If testing flame stability for combination burners firing fuel gas only, test should
be performed with atomizing medium for liquid fuel gun both “on” and “off”.
d) To ensure flame remains stable at full liberation and at turndown, test to reduce
combustion air until burner is firing close to or substoichiometric should be
conducted or considered.
e. Limitation of burner as determined by test shall be included in burner operating instruction
(operating envelopes) and setting burner operating limits, trips, and alarms.
Add
Page 28 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Page 29 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
3. Operating mechanism shall give positive drive in both opening and closing directions
but shall be counterbalanced to fail in open position.
4. Cable operated mechanisms shall have adequate tensioning devices.
b. Limit stops shall be installed on all control dampers. These stops shall:
1. Prevent complete closure of dampers.
2. Prevent damper blades exceeding their fully open positions.
c. Type (fixed or variable) and position of these stops shall be agreed upon with BP.
Add
a. Instruments may be from Vendor or BP.
b. Data sheet for mechanical design of heater shall provide Vendor with list of instruments
meeting project requirements.
15.1.1.5 Add
Connections shall be provided in common burner ducting of each burner group.
Add
15.3.2.4 If reverse steam air decoking is intended, additional skin thermocouples shall be installed in
each pass on one of the shock tubes.
Page 30 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Page 31 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
o. Extent of skidding, boxing, crating, or coating for export shipment will be specified by BP.
p. Long term storage requirements will be specified by BP.
q. Vendor shall be solely responsible for adequacy of equipment preservation provision
employed with respect to materials application.
r. Equipment preservation shall be suitable for at least 18 months of outdoor storage.
Add
16.1.6
a. Materials furnished shall comply with materials requirements, including tolerances (if
any), and shown in specification documents.
b. If BP inspector finds materials or finished product in which materials used or work
performed is not in compliance with specifications, work or materials shall be removed or
otherwise corrected by Vendor at Vendor’s expense.
Page 32 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
d. Adequate safety measures shall be provided and maintained at all times during
development and execution of project.
e. BP shall be notified 7 working days prior to hydrotesting and functional testing.
Add
17.2.6 a. BP reserves right to require Vendor to remove sections containing completed welds or any
portion of finished weld and prepare specimens and deliver such specimens to BP for
testing.
b. Costs in a. will be borne by BP.
c. Repairs required by test results not meeting specifications shall be charged to Vendor
account.
d. BP reserves right to use destructive testing methods.
Page 33 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
4. ASTM E 186 shall be used for heavy walled castings from 50 mm (2 in) to 115 mm
(4-1/2 in) thick.
f. Severity level for each category shall be as follows:
1. Category A - Gas porosity: level 3.
2. Category B - Sand and slag inclusions: level 3.
3. Category C - Shrinkage, all four types: level 2.
4. Category D - Crack: none.
5. Category E - Hot tear: none.
g. Defects may be repaired by welding. Weld repairs shall be made using welding procedures
approved by BP and operators qualified in accordance with ASME BPVC Sec IX.
Add
17.4.7 Lifting lug welds shall be examined 100% by liquid penetration and magnetic particle test.
Page 34 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
17.5.1.4 Add
Heating shall not be used to evaporate water from austenitic stainless steel tubes.
Page 35 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Annex A (Appendix A)
(Informative)
Equipment data sheets
Modify to read
Data sheets and instructions for use of data sheets are in DS 22-100.
Page 36 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Annex B (Appendix B)
(Informative)
Purchaser’s checklist
Modify to read
Purchaser’s checklist is in DS 22-100.
Page 37 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Annex C (Appendix C)
(Informative)
Proposed shop assembly conditions
Modify to read
Proposed shop assembly conditions section is in DS 22-100.
Page 38 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Annex E
(Normative)
Centrifugal fans for fired heater systems
E.2. Design
E.2.1. General
E.2.1.2. Add
c. Fans shall be designed for optimum efficiency at normal heat release and design excess air
(normal operating points).
d. Forced draught (FD) fans shall be sized on combustion air flow requirements as defined in
6 of this GIS.
e. Induced draught (ID) fans shall be sized on flue gas quantities produced from combustion
airflow requirements as defined in 6 of this GIS.
f. Static head required for FD and ID fans shall be consistent with system losses at
combustion and flue gas quantities as defined above.
g. FD fans shall be capable of supplying sufficient air to burners such that heater can operate
at 100% design duty and design excess air with one burner not functioning.
h. Mechanical design temperature for ID fans shall be at least 56°C (100°F) above maximum
expected operating temperature under all conditions of furnace operation.
E.2.1.3. Add
Unless otherwise approved by BP, induced and forced draught fans and their drivers shall be
freely accessible for maintenance and mounted on foundation blocks separate from heater at or
near ground level.
E.2.1.15. Add
If forced draught is used, each heater shall have one forced draught fan with shutoff damper
downstream of fan.
E.3.2. Drivers
E.3.2.7. Add
Electric motor drivers shall comply with relevant requirements of GIS 12-201, GIS 12-202,
GIS 12-203 or GIS 12-204.
Page 39 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Page 40 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
The contents of ISO 13705 Annex G and API Std 560 Appendix F.A-F.F cover the
same subjects. However, the subjects are differently organized in these documents.
User has an option to use methodology for measuring of thermal efficiency of fired
process heaters from either of these two documents
Page 41 of 42
30 December 2005 GIS 22-101
Guidance on Industry Standard for ISO 13705 Fired Heaters (API 560)
Bibliography
Page 42 of 42