Instrument Transformer Specification
Instrument Transformer Specification
NO: VOLUME II
JSW.MH/UT- JSW NEO ENERGY LIMITED
SECTION C 7
1-200 MW- 200 MW WIND FARM POWER PROJECT
SHEET 1
001
SCHEDULE 2
INSTRUMENT TRANSFORMERS
INSTRUMENT TRANSFORMERS
1.0 GENERAL:
1.1 The instrument transformers and accessories shall conform to the latest
version of the standards specified below except to the extent explicitly modified in the
specification and shall be in accordance with the requirements in Chapter-GTR.
Current transformers IEC: 60044-1 (or IS:2705)
Capacitive Voltage transformers IEC:60044-5 / IEC-60358
Inductive Voltage Transformers IEC:60044-2
1.2 The instrument transformers shall be complete with its terminal box and a common
marshalling box for a set of 3 instrument transformers.
1.3 The instrument transformer tank along with top metallics shall be hot dip galvanized.
Spray galvanisation as per IS-5905 with 250 micron thickness of Zinc followed by finishing
coats of a suitable primer with sealer is also acceptable with approval of owner.
1.4 The impregnation details along with tests/checks to ensure successful completion
of impregnation cycle shall be furnished for approval.
1.5 The instrument transformers shall be designed for use in geographic and meteorological
conditions as given in Chapter-GTR.
2.0 CONSTRUCTION FEATURES :
The features and constructional details of instrument transformers shall be in accordance
with requirements stipulated here under :
2.1 Bushing/Insulators:
a) Instrument transformers shall be of 245 kV class, oil filled with shedded
porcelain/composite bushings / Insulators suitable for outdoor service and upright
mounting on steel structures.
b) Bushings/Insulators shall conform to requirements stipulated in Chapter-GTR. The
bushing/insulator for CT shall be one piece without any metallic flange joint.
c) The Instrument transformer shall have cantilever strength of not less than (800kg
is mentioned elsewhere) kg, and 350 kg for 420/245 kV Instrument transformers
respectively or as per the value obtained vide Chapter-GTR, whichever is higher.
d) Instruments transformers shall be hermetically sealed units. Bidder/ Manufacturer
shall furnish details of the arrangements made for the sealing of instrument
transformers during detailed engineering.
Bidder/Manufacturer shall also furnish the details of site tests to check the
effectiveness of hermetic sealing for approval.
e) Polarity marks shall indelibly be marked on each instrument transformer and at the
lead terminals at the associated terminal block.
SPEC. NO: VOLUME II
JSW.MH/UT- JSW NEO ENERGY LIMITED
SECTION C 7
1-200 MW- 200 MW WIND FARM POWER PROJECT
SHEET 2
001
SCHEDULE 2
INSTRUMENT TRANSFORMERS
SCHEDULE 2
INSTRUMENT TRANSFORMERS
c) Core lamination shall be of cold rolled grain oriented silicon steel or other equivalent
alloys.The cores used for protection shall produce undistorted secondary current
under transient conditions at all ratios with specified CT parameters.
d) The expansion chamber at the top of the porcelain insulators should be suitable for
expansion of oil.
e) Facilities shall be provided at terminal blocks in the marshalling box for star delta
formation, short circuiting and grounding of CT secondary terminals.
f) Current transform guaranteed burdens and accuracy class are to be intended
as simultaneous for all cores.
h) For 420/245/145 kV current transformer, characteristics shall be such as to provide
satisfactory performance of burdens ranging from 25% to 100% of rated burden over
a range of 10% to 100% of rated current in case of metering CTs and up to the
accuracy limit factor/knee point voltage in case of relaying CTs. However, the CT
construction / metering core accuracy must meet the CEA guidelines on Metering,
with the latest amendments as on date of manufacturing, compulsorily.
i) The current transformer shall be suitable for horizontal transportation.
It shall be ensured that the CT is able to withstand all the stresses imposed on
it while transporting and there shall be no damage in transit. The Contractor shall
submit the details of packing design to the Purchaser for review.
j) For 420/245 kV CTs the instrument security factor at all ratios shall be less than five
(5) for metering core. If any auxiliary CTs/reactor are used in the current transformers
then all parameters specified shall have to be met treating auxiliary CTs as an
integral part of the current transformer. The au xiliary CTs/reactor sh all
preferably be inbuilt construction of the CTs. In case these are to be mounted
separately these shall be mounted in the central marshalling box suitably wired upto
the terminal blocks. Tan-delta point shall be brought out near bottom terminal box for
measurement during routine maintenance, with Bay de-energised & suitably isolated.
k) The wiring diagram plate for the interconnections of the three single phase CTs
shall be provided inside the marshalling box.
l) The current transformers should be suitable for mounting on lattice support
structure to be provided by the Contractor in accordance with stipulations of
Chapter-GTR.
m) The CT shall be designed as to achieve the minimum risks of explosion in
s e r v i c e .Bidder/Manufacturer s h a l l bring out in his offer, the measures taken
to achieve this.
n) 420/245/145 kV current transformers shall be suitable for high speed auto reclosing.
4.0 VOLTAGE TRANSFORMERS:
SPEC. NO: VOLUME II
JSW.MH/UT- JSW NEO ENERGY LIMITED
SECTION C 7
1-200 MW- 200 MW WIND FARM POWER PROJECT
SHEET 4
001
SCHEDULE 2
INSTRUMENT TRANSFORMERS
SCHEDULE 2
INSTRUMENT TRANSFORMERS
6.0 TESTS :
6.1 In accordance with the requirements in Chapter-GTR, Current and Voltage Transformers
should have been type tested and shall be subjected to routine tests in accordance with
IEC:60044-1/IS:2705 and IEC: 60044-5/60044-2 respectively.
6.2 The test reports of the type tests and the following additional type tests (additional
type tests are required for Instrument Transformers, rated above 72.5 kV only)shall also
be subm view.
a) Current transformers :
i) Radio interference test as per Annexure-A of Chapter-GTR.
ii) Seismic withstand test as per Annexure-B of Chapter-GTR.
iii) Thermal stability test, i.e. application of rated voltage and rated extended
thermal current simultaneously by synthetic test circuit.
iv) Thermal c o -efficient t e s t i . e . measurement o f t a n d e l t a a s a function of
temperature (at ambient and between 80oC & 90oC) and voltage (at 0.3, 0.7,
1.0 and 1.1 Um/
v) The current transformer shall be subjected to Fast Transient test by any one
of the following two methods given below to assess the CT performance in
service to withstand the high frequency over voltage generated due to closing
& opening operation of isolators.
Alternatively, m e t h o d as per IEC:44-1 may be followed:
Method I : 600 negative polarity lightning impulses chopped on crest will be applied to
current transformer. The opposite polarity amplitude must be limited to 50% of crest
value when the wave is chopped. Impulse crest values will be 1000 kVp for 420 kV CTs.
One impulse per minute shall be applied and every 50 impulse high frequency currents
form the windings and total current to earth will be recorded and be compared with
reference currents recorded applying one or more (max 20) reduced chopped impulses of
50% of test value.
Oil samples will be taken before and 3 days after the test. Gas analysis must not show
appreciable rate of increase in various gases related with the results of the analysis
performed before test.
Total sum of crest values of current through secondaries must not exceed 5% of the crest
value of total current to earth.CT must ithstand dielectric tests after this test to pass the test.
SPEC. NO: VOLUME II
JSW.MH/UT- JSW NEO ENERGY LIMITED
SECTION C 7
1-200 MW- 200 MW WIND FARM POWER PROJECT
SHEET 6
001
SCHEDULE 2
INSTRUMENT TRANSFORMERS
Method II : 100 negative polarity impulses with a rise and fall time of less than 0.25
microsecond having 950 kV for 420 kV CT corrected to atmospheric condition shall
be applied at one minute interval and total current through insulation of earth will be
recorded. The amplitude of first opposite polarity should be limited to 50% of the chopped
impulse crest value. Voltage and total current wave shapes shall be recorded after every
10 impulses, and will be compared with reference wave shapes recorded before test at
50% of test values.
Oil sample shall be taken before and 3 days after the test and CT shall be deemed to
have passed the test if the increase in gas content before and after test is not appreciable.
b) Voltage transformers:
i) High f r e q u e n c y c a p a c i t a n c e a n d equivalent series resistance
measurement (as per IEC-358).
ii) Seismic withstand test (as per Annexure-B of Chapter-GTR).
iii) Stray capacitance and stray conductance measurement of the low voltage
terminal (as per IEC-358).
iv) Determination of temperature coefficient test (as per IEC-358).
v) Radio interference test as per IEC-60044-5 or as per Annexure- A of Chapter-
GTR. However the RIV level shall be as specified in clause Major technical
parameters in Chapter-GTR. The Ferro-resonance type test shall be
carried out on the complete CVT.
vi) Apart from the above, report of all special tests mentioned in IEC-60044-5
for Capacitive voltage transformer shall also be submitted for approval.
6.3 The current and voltage transformer shall be subjected to the following routine/site
tests in addition to routine tests as per IEC/IS.
a) CURRENT TRANSFORMERS:
ROUTINE TESTS :
i) Measurement of Capacitance.
ii) High voltage power frequency withstand test on Secondary Winding.
iii) Over-voltage inter turn test (as per BS:3938).
iv) Oil leakage test.
v) Measurement of tan delta at 0.3, 0.7, 1.0 and 1.1 Um
vi) Measurement of partial discharge shall be carried out as per IEC.
b) VOLTAGE TRANSFORMERS:
Routine tests on Capacitive voltage transformer shall be done in line with IEC-60044-5.
SPEC. NO: VOLUME II
JSW.MH/UT- JSW NEO ENERGY LIMITED
SECTION C 7
1-200 MW- 200 MW WIND FARM POWER PROJECT
SHEET 7
001
SCHEDULE 2
INSTRUMENT TRANSFORMERS
SCHEDULE 2
INSTRUMENT TRANSFORMERS
G.8.2. Standard reference range of frequencies 96% to 102% for protection and
for which the accuracies are valid 99.5 to 101% for measurement
G.8.5. Number of terminals in control cabinet All terminals of control circuits are wired upto
marshalling box plus 20% spare terminals evenly
distributed on all TBs
E8.3 High frequency capacitance for entire Within 80% to 150% of rated
carrier frequency capacitance
range
E8.4 Equivalent series resistance Less than 40 ohms.
over the entire carrier frequency
range
E8.5 Stray capacitance and stray As per IEC:358
conductance of the
LV terminal over entire
carrier frequency range
SPEC. NO: VOLUME II
JSW.MH/UT- JSW NEO ENERGY LIMITED
SECTION C 7
1-200 MW- 200 MW WIND FARM POWER PROJECT
SHEET 9
001
SCHEDULE 2
INSTRUMENT TRANSFORMERS
burden (VA)
Voltage Transformers shall also comply with the requirements of Table-IB of this Chapter.
SCHEDULE 2
INSTRUMENT TRANSFORMERS
TABLE - IB
REQUIREMENTS OF 245 KV CAPACITIVE VOLTAGE TRANSFORMERS
1. Rated primary voltage (kV rms) 245
3. No. of secondaries 3
1.5 - 30 seconds
5. Phase angle error + 10 minutes (For metering core)
9. Accuracy 3P 3P 0.2
10. Output burden (VA) (minimum) 50 50 50