h5h7-h7-Gp-cen-gen-gen-rfa-prg.2m-008-Rev01-2 Months Schedule - h7 (From 09 June 25 To 10 August 25)

The H5&H7 Condominium Project document outlines a request for approval regarding various project items, including drawings, samples, and documents, with a required response date of June 13, 2025. It details a two-month schedule from June 9, 2025, to August 10, 2025, including specific tasks and their durations. The document also includes comments from involved parties and a comprehensive timeline for construction activities.

Uploaded by

DUY DANG
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views8 pages

h5h7-h7-Gp-cen-gen-gen-rfa-prg.2m-008-Rev01-2 Months Schedule - h7 (From 09 June 25 To 10 August 25)

The H5&H7 Condominium Project document outlines a request for approval regarding various project items, including drawings, samples, and documents, with a required response date of June 13, 2025. It details a two-month schedule from June 9, 2025, to August 10, 2025, including specific tasks and their durations. The document also includes comments from involved parties and a comprehensive timeline for construction activities.

Uploaded by

DUY DANG
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

PROJECT NAME: H5&H7 CONDOMINIUM PROJECT

Submission Date: 09/06/2025 Email Date : 09/06/2025

Document Number: H5H7-H7-GP-CEN-GEN-GEN-RFA-PRG.2M-008 Rev. 01

REQUEST FOR APPROVAL NO 008

ITEM

Method Require date of reply :


Subject Material Drawing Subcontractor Other
statement 13/06/2025
We Enclose Records For The Items Described Below. We Kindly Suggest Parties To Comment Or
Approve The Items Mentioned:
EXPLANATION: 2 MONTHS SCHEDULE - H7 (FROM 09 JUNE 25 TO 10 AUGUST 25)
KẾ HOẠCH 2 THÁNG - H7 (TỪ 09/06/2025 ĐẾN 10/08/2025)

Item Description Approval status

Drawings A. Approve

Sample B. Approve subject to comments

Catalogues C. Revise and resubmit

Documents D. Reject

Distribute to:
BVV x CEN

BTC X

BVV comments:

BTC comments:

Prepared by: Checked by: Reviewed by:

CEN

Name: Võ Hoàng Ân Name: Dương Hồng Công Name: Hồ Đình Long


Date: 09/06/2025 Date: 09/06/2025 Date: 09/06/2025
Checked by: Checked by: Reviewed by:

BVV
Name: Lê Thanh Long Name: Ngô Văn Việt Name: GERALD C GARCIA
Date: Date: Date:
Checked by: Checked by: Reviewed by:

BTC

Name: Name: Name: RODEN MIRAMONTE


Date: Date: Date:
Stt Task Name Duration Start Finish June 2025 July 2025
07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08
1 2 MONTHS SCHEDULE - H7 134 d 16/05/25 26/09/25 2 MONTHS SCHEDULE - H7

2 A. PILING WORKS 54 d 16/05/25 08/07/25 A. PILING WORKS


08/07
3 DRIVING MASS PILES 54 d 16/05/25 08/07/25 54 d
08/07
4 Zone 1 (219 Piles) 44 d 16/05/25 28/06/25 44 d
28/06
5 Robot 3 44 d 16/05/25 28/06/25 44 d
28/06
6 Zone 2 (60 Piles) 18 d 05/06/25 22/06/25 18 d
22/06
7 Robot 2 18 d 05/06/25 22/06/25 18 d
22/06
8 Zone 3 (59 Piles) 10 d 29/06/25 08/07/25 10 d
29/06 08/07
9 Robot 3 10 d 29/06/25 08/07/25 10 d
29/06 08/07
10 Zone 4 (35 Piles) 7d 23/06/25 29/06/25 7d
23/06 29/06
11 Robot 2 7d 23/06/25 29/06/25 7d
23/06 29/06
12 B. EQUIPMENT 26 d 27/06/25 22/07/25 26 d
27/06 22/07
13 I. TOWER CRANE 26 d 27/06/25 22/07/25 26 d
27/06 22/07
14 Tower crane CT1 MCR160 (R50m Max L 22 d 27/06/25 18/07/25 22 d
=10 T) - Zone 1 27/06 18/07
15 Piling works 2d 27/06/25 28/06/25 2d
27/06 28/06
16 Excavation 3d 29/06/25 01/07/25 3d
29/06 01/07
17 Casting concrete for pile cage 2d 02/07/25 03/07/25 2d
02/07 03/07
18 Rebar, Formworks , Concrete for Foudation 4d 04/07/25 07/07/25 4d
04/07 07/07
19 Erection (including 3rd- party testing) 8d 11/07/25 18/07/25 8d
11/07 18/07
20 Tower crane CT2 - LLT 5020 (R50m Max L 25 d 28/06/25 22/07/25 25 d
=10 T) - Zone 4 28/06 22/07
21 Piling works 2d 28/06/25 29/06/25 2d
28/06 29/06
22 Excavation 3d 03/07/25 05/07/25 3d
03/07 05/07
23 Casting concrete for pile cage 2d 06/07/25 07/07/25 2d
06/07 07/07
24 Rebar, Formworks , Concrete for Foudation 4d 08/07/25 11/07/25 4d
08/07 11/07
25 Erection (including 3rd- party testing) 8d 15/07/25 22/07/25 8d
15/07 22/07
26 C. SUB-STRUCTURAL IN BUILDING 107 d 12/06/25 26/09/25 C. SUB-STRUCTURAL IN BUILDING
12/06
27 ZONE 1 90 d 29/06/25 26/09/25
29/06
28 DOMESTIC TANK, PUMP ROOM AND 80 d 29/06/25 16/09/25 80 d
PILE CAP 29/06

1/ 6
Stt Task Name Duration Start Finish June 2025 July 2025
07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08
29 1. Excavation work (Team A) 9d 29/06/25 07/07/25 9d
29/06 07/07
30 2. Pile cap 7d 08/07/25 14/07/25 7d
08/07 14/07
31 3. Backfill for Pile cap 3d 15/07/25 17/07/25 3d
15/07 17/07
32 4. Waterproofing and protection screed 4d 18/07/25 21/07/25 4d
18/07 21/07
33 5. Bottom Slab 7d 22/07/25 28/07/25 7d
22/07 28/07
34 6. Wall, Mep Work 7d 29/07/25 04/08/25 7d
29/07 04/08
44 SPECTIC TANK 2 81 d 29/06/25 17/09/25 81 d
29/06
45 1. Excavation work (Team B) 5d 29/06/25 03/07/25 5d
29/06 03/07
46 2. Lean concrete, Waterproofing and 5d 21/07/25 25/07/25 5d
protection screed 21/07 25/07
47 3. Bottom Slab 7d 26/07/25 01/08/25 7d
26/07 01/08
48 4. Wall, Mep Work 7d 02/08/25 08/08/25 7d
02/08
58 GREASE TRAP 2 69 d 11/07/25 17/09/25
11/07
59 1. Excavation work (Team B) 5d 11/07/25 15/07/25 5d
11/07 15/07
60 2. Lean concrete, Waterproofing and 4d 21/07/25 24/07/25 4d
protection screed 21/07 24/07
61 3. Bottom Slab 5d 25/07/25 29/07/25 5d
25/07 29/07
62 4. Wall, Mep Work 5d 30/07/25 03/08/25 5d
30/07 03/08
72 FIRE FIGHTING TANK AND PILE CAP 76 d 04/07/25 17/09/25
04/07
73 1. Excavation work (Team B) 7d 04/07/25 10/07/25 7d
04/07 10/07
74 2. Pile cap 7d 11/07/25 17/07/25 7d
11/07 17/07
75 3. Backfill for Pile cap 3d 18/07/25 20/07/25 3d
18/07 20/07
76 4. Waterproofing and protection screed 4d 21/07/25 24/07/25 4d
21/07 24/07
77 5. Bottom Slab 7d 25/07/25 31/07/25 7d
25/07 31/07
78 6. Wall, Mep Work 7d 01/08/25 07/08/25 7d
01/08 07/08
88 OIL TANK 1 59 d 22/07/25 18/09/25
22/07
89 1. Excavation work (Team A) 4d 22/07/25 25/07/25 4d
22/07 25/07
90 2. Waterproofing and protection screed 3d 26/07/25 28/07/25 3d
26/07 28/07
91 3. Bottom Slab 7d 29/07/25 04/08/25 7d
29/07 04/08
102 PILE CAP, CONNECTION BEAM AND 81 d 08/07/25 26/09/25
STUMP 08/07

2/ 6
Stt Task Name Duration Start Finish June 2025 July 2025
07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08
103 1. Excavation work (Team A) 14 d 08/07/25 21/07/25 14 d
08/07 21/07
104 2. Pile cap and Connection Beam 10 d 22/07/25 31/07/25 10 d
22/07 31/07
105 3. Backfill for Pile cap and Connection Beam 14 d 01/08/25 14/08/25 14 d
01/08
111 ZONE 2 100 d 12/06/25 19/09/25 ZONE 2
12/06
112 SPECTIC TANK 1, GREASE TRAP 1 91 d 12/06/25 10/09/25 91 d
12/06
113 1. Pressing sheet Pile L=9m 4d 12/06/25 15/06/25 4d
12/06 15/06
114 2. Excavation work (Team B) 4d 16/07/25 19/07/25 4d
16/07 19/07
115 3. Waterproofing and protection screed 3d 20/07/25 22/07/25 3d
20/07 22/07
116 4. Bottom Slab 5d 23/07/25 27/07/25 5d
23/07 27/07
117 5. Wall, Mep Work 6d 28/07/25 02/08/25 6d
28/07 02/08
127 PILE CAP AND STUMP 62 d 20/07/25 19/09/25
20/07
128 1. Excavation work (Team B) 7d 20/07/25 26/07/25 7d
20/07 26/07
129 2. Pile cap 10 d 27/07/25 05/08/25 10 d
27/07 05/08
136 ZONE 3 57 d 26/07/25 20/09/25
26/07
137 PILE CAP, CONNECTION BEAM AND 57 d 26/07/25 20/09/25
STUMP 26/07
138 1. Excavation work (Team A) 7d 26/07/25 01/08/25 7d
26/07 01/08
139 2. Pile cap and Connection Beam 10 d 02/08/25 11/08/25 10 d
02/08
146 ZONE 4 77 d 02/07/25 16/09/25 ZONE 4
02/07
147 OIL TANK 2 63 d 02/07/25 02/09/25 63 d
02/07
148 1. Excavation work (Team C - Backup) 4d 02/07/25 05/07/25 4d
02/07 05/07
149 2. Waterproofing and protection screed 3d 06/07/25 08/07/25 3d
06/07 08/07
150 3. Bottom Slab 7d 09/07/25 15/07/25 7d
09/07 15/07
151 4. Wall, Mep Work 7d 16/07/25 22/07/25 7d
16/07 22/07
152 5. Top slab 7d 23/07/25 29/07/25 7d
23/07 29/07
153 6. Waiting concrete strenthenging 7d 30/07/25 05/08/25 7d
30/07 05/08
161 PILE CAP AND STUMP 52 d 27/07/25 16/09/25
27/07
162 1. Excavation work (Team B) 7d 27/07/25 02/08/25 7d
27/07 02/08

3/ 6
2-MONTHS MANPOWER DEPLOYMENT
From 08/06/25 to 14/06/25 From 15/06/25 to 21/06/25 From 22/06/25 to 28/06/25 From 29/06/25 to 05/07/25 From 06/07/25 to 12/07/25 From 13/07/25 to 19/07/25 From 20/07/25 to 26/07/25 From 27/07/25 to 02/08/25 From 03/08/25 to 09/08/25
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
AREA CONSTRUCTION / TASK

10/6/25

11/6/25

12/6/25

13/6/25

14/6/25

15/6/25

16/6/25

17/6/25

18/6/25

19/6/25

20/6/25

21/6/25

22/6/25

23/6/25

24/6/25

25/6/25

26/6/25

27/6/25

28/6/25

29/6/25

30/6/25

10/7/25

11/7/25

12/7/25

13/7/25

14/7/25

15/7/25

16/7/25

17/7/25

18/7/25

19/7/25

20/7/25

21/7/25

22/7/25

23/7/25

24/7/25

25/7/25

26/7/25

27/7/25

28/7/25

29/7/25

30/7/25

31/7/25
8/6/25

9/6/25

1/7/25

2/7/25

3/7/25

4/7/25

5/7/25

6/7/25

7/7/25

8/7/25

9/7/25

1/8/25

2/8/25

3/8/25

4/8/25

5/8/25

6/8/25

7/8/25

8/8/25

9/8/25
Piling Work 10 10 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 10 10 10 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Pre-boring driver and signal man 3 3 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 3 3 3 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Pressing driver and signal man 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Welder 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Crawler crane driver 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Surveyer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Excavation - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Team A - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Team B - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Substructure - - - - - - - - - - - - - - - - - - - - - - - - - - 3 4 5 8 14 25 25 25 30 35 35 35 35 30 30 30 40 50 50 60 60 65 65 70 70 85 85 85 90 95 100 90 80 80 70 60 60
Team 1 - Domestic Tank & Pile Cap- - - - - - - - - - - - - - - - - - - - - - - - - - 3 4 5 5 10 10 10 10 10 10 10 10 10 5 5 5 5 5 5 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10

Rebar - - - - - - - - - - - - - - - - - - - - - - - - - - 3 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Formwork - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Team 2 - FF Tank & Pile Cap - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 3 4 10 10 10 10 10 10 5 5 5 5 5 5 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10

Rebar - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 3 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Formwork - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Team 3 - Spectic Tank 2, Grease Trap


- 2 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 10 10 10 10 10 10 10 10 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 10 10 10 - - -

Rebar - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 5 5 5 - - -

Formwork - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 5 5 5 - - -

Team 4 - Spectic Tank 1, Grease Trap


- 1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10

Rebar - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Formwork - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Team 5 - Oil Tank 1, 2 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 10 10 10 10 10 10 10 10 10 10 10 10 10 10 20 20 20 20 20 20 20 10 10 10 10 10

Rebar - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 10 10 10 10 10 10 10 5 5 5 5 5

Formwork - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 10 10 10 10 10 10 10 5 5 5 5 5

Team 6 - Pile cap Zone 2 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 10 10 10 10 10 10 10 10 10 10 10 10 - -

Rebar - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 - -

Formwork - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 - -

Team 7 - Pile cap Zone 3 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 10 10 10 10 10 10 10 10

Rebar - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5

Formwork - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5

Team 8 - Pile cap Zone 4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 10 10 10 10 10 10 10

Rebar - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5

Formwork - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5

Mep Work - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Mep Work - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Other Worker 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 5 5 5 5 5 5 5 5 5 5 5 5 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
General Worker, Lean concrete 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Waterproofing - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Sheet pile - - - - 1 1 1 1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Total Manpower 12 12 19 19 20 20 20 20 19 19 19 19 19 19 19 19 19 19 19 19 19 32 32 32 32 32 35 36 30 33 39 40 40 45 50 55 55 55 55 50 50 50 60 75 75 85 85 90 90 95 95 110 110 110 115 120 125 115 105 105 95 85 85

140 2 - MONTHS MANPOWER DEPLOYMENT CHART


125
120
120 115 115
110 110 110
105 105
100 95 95 95
90 90
85 85 85 85
80 75 75

60
60 55 55 55 55
50 50 50 50
45
39 40 40
40 35 36 33
32 32 32 32 32 30
19 19 20 20 20 20 19 19 19 19 19 19 19 19 19 19 19 19 19
20
12 12

-
From 08/06/25 to 14/06/25 From 15/06/25 to 21/06/25 From 22/06/25 to 28/06/25 From 29/06/25 to 05/07/25 From 06/07/25 to 12/07/25 From 13/07/25 to 19/07/25 From 20/07/25 to 26/07/25 From 27/07/25 to 02/08/25 From 03/08/25 to 09/08/25
Total Manpower
2 MONTHS EQUIPMENT DEPLOYMENT
From 08/06/25 to 14/06/25 From 15/06/25 to 21/06/25 From 22/06/25 to 28/06/25 From 29/06/25 to 05/07/25 From 06/07/25 to 12/07/25 From 13/07/25 to 19/07/25 From 20/07/25 to 26/07/25 From 27/07/25 to 02/08/25 From 03/08/25 to 09/08/25
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
EQUIPMENT

10/6/25

11/6/25

12/6/25

13/6/25

14/6/25

15/6/25

16/6/25

17/6/25

18/6/25

19/6/25

20/6/25

21/6/25

22/6/25

23/6/25

24/6/25

25/6/25

26/6/25

27/6/25

28/6/25

29/6/25

30/6/25

10/7/25

11/7/25

12/7/25

13/7/25

14/7/25

15/7/25

16/7/25

17/7/25

18/7/25

19/7/25

20/7/25

21/7/25

22/7/25

23/7/25

24/7/25

25/7/25

26/7/25

27/7/25

28/7/25

29/7/25

30/7/25

31/7/25
8/6/25

9/6/25

1/7/25

2/7/25

3/7/25

4/7/25

5/7/25

6/7/25

7/7/25

8/7/25

9/7/25

1/8/25

2/8/25

3/8/25

4/8/25

5/8/25

6/8/25

7/8/25

8/8/25

9/8/25
Pre Boring Machine 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Robot pressing pile 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Crawler crane 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Larsen Sheet Pile Machine
- - - - - - - 1 1 1 1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
(pre-boring +pressing)
Excavator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Dump Truck 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Mobile crane - - - - - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - - - - - - - - - - - - -

Tower Crane - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Total 7 7 7 7 7 7 7 8 8 8 8 7 7 7 7 7 7 7 7 15 15 15 15 15 15 15 15 15 13 13 13 13 13 10 10 10 10 10 10 11 11 11 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
PROJECT/ DỰ ÁN:

H5&H7 CONDOMINIUM
PROJECT
ADDRESS/ ĐỊA CHỈ:
HOA PHU WARD, THU DAU MOT CITY, BINH DUONG PROVICE, VIET NAM

OWNER/ CHỦ ĐẦU TƯ:

7.H

9750
BECAMEX TOKYU CO., LTD
ADDRESS/ ĐỊA CHỈ:

ZONE 2 HOA PHU WARD, THU DAU MOT CITY, BINH DUONG PROVICE, VIET NAM
7.G
60 piles
APPROVAL:
PHÊ DUYỆT

8100
CONSTRUCTION MANAGEMENT/ QUẢN LÝ XÂY DỰNG:

7.F

ZONE 1

8100
219 piles

7.E BUREAU VERITAS VIET NAM


ADDRESS/ ĐỊA CHỈ:
36-38 NGUYEN VAN TROI STREET, 15 WARD, PHU NHUAN DISTRICT,

8100
60750
HO CHI MINH CITY, VIET NAM

ZONE 3 APPROVAL:

59 piles 7.D PHÊ DUYỆT

8100
MAIN CONTRACTOR/ TỔNG THẦU THI CÔNG:

7.C

ADDRESS/ ĐỊA CHỈ:

8100
204/9 NGUYEN VAN HUONG, THAO DIEN WARD, THU DUC CITY,
HO CHI MINH CITY, VIET NAM
TEL: (+84) 28 3620 5151

7.B
PROJECT MANAGER
GIÁM ĐỐC DỰ ÁN
ZONE 4 HỒ ĐÌNH LONG
35 piles

10500
CHECKED BY
KIỂM TRA

VÕ HOÀNG ÂN
7.A
DRAWING BY
TRIỂN KHAI

NGUYỄN ĐÌNH TÚ

10500 8100 8100 8100 8100 6000 2100 4500 6000 ITEM/ HẠNG MỤC

61500
TEMPORARY SITE FACILITIES
7.1 7.2 7.3 7.4 7.5 7.6 7.6' 7.7 7.7' 7.8
PACKAGE:
GÓI THẦU
MAIN CONTRACT WORK

ZONING PLAN FOR PILING - H7 DRAWING TITLE: ZONING PLAN FOR PILING - H7
TÊN BẢN VẼ MẶT BẰNG PHÂN CHIA KHU VỰC ÉP CỌC - H7

MẶT BẰNG PHÂN CHIA KHU VỰC ÉP CỌC - H7 CODE OF DRAWING: H5H7-GP-GP-CEN-GEN-GEN-RFA-PRG.-1
MÃ SỐ BẢN VẼ

DATE/ NGÀY: 14/05/2025

REV/ HIỆU CHỈNH : REV00

SCALE/ TỈ LỆ : 1/100

PAGE/ SỐ TRANG : 01 /02


PROJECT/ DỰ ÁN:

H5&H7 CONDOMINIUM
PROJECT
ADDRESS/ ĐỊA CHỈ:
HOA PHU WARD, THU DAU MOT CITY, BINH DUONG PROVICE, VIET NAM

OWNER/ CHỦ ĐẦU TƯ:

7.H

GREASE TRAP

9750
BECAMEX TOKYU CO., LTD
ZONE 1 ADDRESS/ ĐỊA CHỈ:
S=1850m2
ZONE 2 HOA PHU WARD, THU DAU MOT CITY, BINH DUONG PROVICE, VIET NAM
7.G
S=640m2
APPROVAL:
PHÊ DUYỆT

8100
CONSTRUCTION MANAGEMENT/ QUẢN LÝ XÂY DỰNG:

7.F

SEPTIC TANK 2
SEPTIC TANK 1

FIRE FIGHTING TANK

8100
(PCCC TANK)

7.E BUREAU VERITAS VIET NAM


ZONE 3 ADDRESS/ ĐỊA CHỈ:
S=790m2 PUMP 36-38 NGUYEN VAN TROI STREET, 15 WARD, PHU NHUAN DISTRICT,

8100
60750
ROOM HO CHI MINH CITY, VIET NAM

APPROVAL:
7.D PHÊ DUYỆT

8100
MAIN CONTRACTOR/ TỔNG THẦU THI CÔNG:
DOMESTIC TANK

7.C

ADDRESS/ ĐỊA CHỈ:

8100
204/9 NGUYEN VAN HUONG, THAO DIEN WARD, THU DUC CITY,
HO CHI MINH CITY, VIET NAM
TEL: (+84) 28 3620 5151

7.B
PROJECT MANAGER
GIÁM ĐỐC DỰ ÁN

ZONE 4 HỒ ĐÌNH LONG

10500
S=370m2 OIL TANK 2 OIL TANK 1
CHECKED BY
KIỂM TRA

VÕ HOÀNG ÂN
7.A
DRAWING BY
TRIỂN KHAI

NGUYỄN ĐÌNH TÚ

10500 8100 8100 8100 8100 6000 2100 4500 6000 ITEM/ HẠNG MỤC

61500
TEMPORARY SITE FACILITIES
7.1 7.2 7.3 7.4 7.5 7.6 7.6' 7.7 7.7' 7.8
PACKAGE:
GÓI THẦU
MAIN CONTRACT WORK

ZONING PLAN FOR FOUNDATION - H7 DRAWING TITLE: ZONING PLAN FOR FOUNDATION - H7
TÊN BẢN VẼ MẶT BẰNG CHIA ZONE KHU VỰC PHẦN MÓNG - H7

MẶT BẰNG CHIA ZONE KHU VỰC PHẦN MÓNG - H7 CODE OF DRAWING: H5H7-GP-GP-CEN-GEN-GEN-RFA-PRG.- 2
MÃ SỐ BẢN VẼ

DATE/ NGÀY: 14/05/2025

REV/ HIỆU CHỈNH : REV00

SCALE/ TỈ LỆ : 1/100

PAGE/ SỐ TRANG : 02 /02