Project No: 96973
Project Title: Polio Emergency Operation Center Construction Project - New Water Well
Location: Kabul, Afghanistan
Component: Drillign a new water well,
Original Issue: March 15, 2017
Currency: US Dollars
Revision No.: N/A
Revised Date: N/A
Pos. Description of Work/Items Sections of Specs Unit Quantity Unit Cost Total Cost
General Notes:
1 - The cost for all items in this BOQ, in general, includes deploying of any machineries, manpower, carrying out of any
relocations/ removal/ salvage/ disposal /reinstating tasks. However, particular issues to the costs of items mentioned
under each section in this BOQ.
2 - Details of work method & equipment/machinery for different types of work shall be brought to the attention of Engineer
to get approval of Engineer before commencing the jobs.
3 - Read given all project document before pricing the job. Changes of market prices during project period for any item is
to the responsibility of the Contractor without any extra payment.
Given Docs:
The term "given docs" or "Given Docs", mentioned anywhere in this BOQ, covers all project documents such as
given drawings, BOQ, specifications, any technical schedules, manufacturer's data sheets etc. issued along the
contract (or issued during the work).
Drillign a new water well,
1.0 General
1.1 - 1.5 Preliminaries/General Requirements/Contractor Quality Control/Health and Safety/Environmental Impacts
1 Pre-construction work relevant to all sub sections of 1.0 General mentioned in the
All of Section "1.0
given docs including all site mobilization activities and paper/ documentation tasks.
General" and as well
NOTE: This amount is NOT payable in the case of failure/withdraw from the
as all issues
Contractor side, in which the project is not going to be completed 100%.
emphasized at pre-bid
meetings.
LS 1.00 -
2 Post construction works, clean up and hand over, along with any details may require
All of Section "1.0
to the full satisfaction of Engineer.
General" and as well
as all issues
emphasized at pre-bid
meetings.
LS 1.00 -
Subtotal 1.0 General -
8.0 Water Services
8.1 Water Services
Items related to water well
NOTE:
Cost for water well in this section includes all types of works, efforts, machineries, materials, manpower,
transportations, installation, concrete works, water services works to complete a functioning well to the full approval
of Engineer.
1 Arrangement of water drainage temporary channel in the site. This item is to
divert/connect the well-capacity-water-flow toward a safe place within/outside the
compound. The temporary drainage system could be consist of pipes/conduits, and
some surface channel excavation/preparation. The temporary water channel will be Engineer's approval
removed after well-capacity-test is done. The cost for this item includes all materials,
excavation, diversion, connection and also removal of them back. -
Lin M 100.00
2 Drilling a well (using rotary-type drilling method/ machinery) with 300mm (12")
diameter in any type strata to a depth of 80 meters.
The cost includes execution of any surveying required to investigate proper under-
ground water-source for the well (if required).
(NOTE: Actual well depth will depend to the site/strata condition water discharge and
status, and therefore will be re-adjusted by UNOPS engineer during the work for a
"successful well".
Specifications for
Water Well
Cost for this item includes all process of well-capacity tests required to proof the well
is "Successful well". Successful well means that well capacity to be (>60
liters/minutes for at least 48 hours continuous pumping) of potable water.
The cost includes preparation of reports and diagrams at the end of work about
geological condition of the well, yield of well, ground water level etc. Consult
Engineer for details of this item. -
Lin M 140.00
Original
Issue
Project No: 96973
Project Title: Polio Emergency Operation Center Construction Project - New Water Well
Location: Kabul, Afghanistan
Component: Drillign a new water well,
Original Issue: March 15, 2017
Currency: US Dollars
Revision No.: N/A
Revised Date: N/A
Pos. Description of Work/Items Sections of Specs Unit Quantity Unit Cost Total Cost
3 250mm (8") diameter PVC pipe, schedule 80, for casing/filter. The actual pipe length
will be adjusted according to the actual well depth in the site. Also see drawings for
the length of filter and length of casing. The cost includes successful installation of Specifications for
filters/casings into the well and the condition is ready for backfills. Cost for backfills Water Well
not included in this item.
Lin M 140.00 -
4 Backfilling around the casing/filter using river type 4-10mm gravel and as well as the
soil backfill as per given drawings. See drawing or consult Engineer for details of Specifications for
work method. Water Well
Cu.m 4.00 -
5 PCC grouting (M-200) seal to borehole. The cost includes all work and materials to
Specifications for
prepare the rated grout to full satisfaction of UNOPS Engineer.
Water Well Cu.m 2.00 -
6 Water wash and cleansing of well, and as well as chemical and bacteriological
analysis/tests of water samples (at least 2 samples) including provision of all Specifications for
certificates and results documents. Water Well
LS 1.00
-
7 Water pump, Italian 'Pedrollo' brand, 4SR6m/31-PD, 4kW, 3-phase (or equivalent),
submersible D=50mm, with >75 L\min discharge capacity, up to 170m head, 5.5HP.
The cost includes electrical cable, switchboard, connection, water pipe connections,
fittings, accessories, auxiliary materials, to the complete and functioning pump Engineer's approval
installation.
No 1.00
-
8 PCC M-150 apron structure
This is 6 sq.m concrete apron around the water well. The structure includes base
compaction, 100mm thick gravel layer and 100mm thick PCC apron as per given
Engineer's approval
size/shape to the complete job. See drawings for details. The cost includes all work
and materials to full satisfaction of UNOPS Engineer.
LS 1.00
-
Subtotal 8.0 Water Services -
TOTAL FOR {Drillign a new water well, } -