Jaisurya - June Monthly Report

The document outlines a schedule for remaining works at the Sector 39 site, including tasks such as drafting an agreement between the client and contractor, and completing a false ceiling for the Master Bedroom. It specifies the dates for each task and emphasizes the importance of documenting the commencement and completion dates. Additionally, it includes instructions for submitting progress reports and requires signatures from both the student and the supervising architect.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views2 pages

Jaisurya - June Monthly Report

The document outlines a schedule for remaining works at the Sector 39 site, including tasks such as drafting an agreement between the client and contractor, and completing a false ceiling for the Master Bedroom. It specifies the dates for each task and emphasizes the importance of documenting the commencement and completion dates. Additionally, it includes instructions for submitting progress reports and requires signatures from both the student and the supervising architect.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

-

(.

8. Scheduled the remaining works to be done in Sector 39 site, in 26-06-2025 27-06-2025


MS-Project after the site visit.

9. Drafted an agreement to be signed between the client and 27-06-2025 27-06-2025

I<
contractor

10. False ceiling for the Master Bedroom for the Sector 39 - 28-06-2025 30-06-2025 �
residence

11. Looping drawing for the ground floor of Sector 39 - residence 28-06-2025 01-07-2025

J---

?���
Architect: PANKAJ NAGALIA
COA No.: CA/90/12781
Signature of the Student with date Signature of the Architect/ In-Charge with Seal

Note: Name of the Architect Mr. Pankaj Nagalia


The Exact date of Commencement of work and completion of work should be clearly mentioned in the duration column
This report duly filled In should reach the Practical Training Programme Coordination not later than 10 1• of every month
This report must be signed by the senior architect of the firm/ organization/ company COA Registration Number: CA/1990/12781
Make copies of this sheet to sent the progress report for every month. Add additional sheets if needed.

You might also like