PSU - Transactional Procurement Strategies and Procurement Planning
PSU - Transactional Procurement Strategies and Procurement Planning
1. First and foremost, any procurement activity needs to be aligned with the UNDP Strategic
Plan.
2. Based on the information gathered, potential buying strategies should be identified and
evaluated.
4. We can define significant purchases as those that are of high relative expenditure and/or for
which supply is difficult to secure.
5. The relative expenditure of goods and services is defined as their cost relative to the total
purchasing expenditure of the business unit or agency. For UNDP, a transaction of 100,000 USD
or more is considered a significant purchase.
6. The criterion “difficult to secure supply” will be based on the following factors:
The degree to which the goods or services being purchased present a risk or are critical to
the agency; as well as
The extent to which there exists a competitive market
9. Procurement strategies will seek to meet identified project goals and to mitigate existing risks.
For example, in the case of a procurement transaction where quality is critical, UNDP
procurement strategies will not only include clear specifications reflecting national and
international standards, but could also include supplier pre-qualifications, factory visit(s),
sampling and independent laboratory testing, or pre-shipment inspection, among other actions.
10. In the case of a project were delivery is critical (i.e., elections), potential strategies could include
early ordering (if proper planning has been conducted), pre-qualification of suppliers (to ensure
that with all suppliers being considered are reputable and capable), developing alternative
sources, checking manufacturing capacity, requesting performance security and including extra
assurances in the contract as liquidate damages clauses, among others.
11. Procurement is an important function to ensure that UNDP meets its organizational goals. While
Procurement is a support function for the organization, it is nevertheless a core function and
critical to enhancing programme/project delivery. UNDP does not conduct procurement in
isolation, but rather as part of the process of achieving development project outcomes.
Therefore all UNDP procurement activities are framed in the context of UNDP programmes and
projects.
12. Understanding procurement as a managerial discipline (and not an administrative one) implies
the need to acquire and enhance certain managerial skills and tools, including:
Procurement Risk Management
Procurement Strategies Development
Procurement Planning
Understanding…
What do we procure? In which markets do we operate? What are the associated risks?
(Spend Analysis) (Market Analysis) (External, internal, project risks)
We will develop…
Risk Procurement Management Procurement Strategies Procurement Plans
15. As a working principle, we always need to take into consideration all steps of Supply Chain
Management (SCM) when analyzing procurement risks, defining procurement strategies and
planning. The complexity and length of the supply chain will vary from project to project.
16. Supply Chain Management risk analysis, procurement strategies development and planning are
essential tools to ensure that procurement activities support project outcomes, are conducted
in a timely manner and at a reasonable cost. Early and accurate planning is critical to avoid last
minute procurement, which is contrary to open, efficient and effective procurement.
When does (1) procurement risk analysis (2) procurement strategies and (3) procurement
planning start?
17. SCM cycle is an integrated part of the project cycle, and therefore needs to be aligned and
synchronized with other project activities in order to contribute to achieving identified
outcomes. To this end, the SCM cycle cannot run in isolation. On the contrary, it must be
integrated into the overall project cycle.
18. This implies by definition the need for a constant interaction between operations and
programming.
19. In the project context, SCM risk assessment and procurement strategies development and
planning should start as early as the project definition stage.
What will be the implementing modality? Who will be responsible for procuring and
managing inputs?
What are the existing risks? Are there risks associated with the nature of the
products or services to be acquired? Are risks associated with the markets, the
environment or the political context?
What is the best procurement strategy for achieving the programme/project goals and to
mitigate risk?
What is the Procurement Plan and what are the associated resources?
21. Together, procurement risk assessment, procurement strategies development and procurement
planning serve as a bridge to cover the gap between programme and operations. They are also
critical to programme delivery. Benefits of this approach include:
Best value for money
Timely procurement
Avoid unnecessary and unjustifiable emergencies
Better allocation of existing resources
Sufficient time to fully explore alternative procurement approaches
Possibility to aggregate demand
Consolidated Planning
22. Based on the UNDP decentralized structure, consolidated procurement plans will be developed
at different levels, including Corporate, Business Unit and Country Office.
23. All Business Units and Country Offices shall develop Consolidated Plans . They will normally be
prepared annually, though it is a good practice to review them regularly.
24. Analysis of the consolidated Procurement Plan provides an opportunity to identify economies of
scale and better uses of resources, providing an overview of the scale of the procurement
Individual planning
25. Procurement planning will also take place at the project level or even at the activity level,
depending on the complexity of the activity and the number of interrelated procurement
actions.
26. A Requisition Plan shall be developed at the project definition stage. It must be shared with the
Procurement Unit.
27. All “Significant Purchases” of a Requisition Plan (definition is provided in Section 4.2) are subject
to the development of an Individual Procurement Plan.
As SCM (and procurement in general) is a sub-process of the project cycle, different actions will need to
be taken at each stage of this cycle.
Development of a TRANSACTIONAL
Initiating a PROCUREMENT PLAN TRANSACTIONAL PROCUREMENT
project PLAN
Develop Specifications/ TOR/SOW
Close project
Closing a
Dispose/transfer assets .
project
Identify procurement lessons learned
29. Procurement Risk Assessment, Procurement Strategies Definition and Planning shall be
integrated at the programming stage and not as a back-end process.
30. UNDP needs to proactively and systematically monitor and manage risks (defined as both
threats and opportunities). Among other risks, UNDP must identify and manage any risks
associated with the conduct of its procurement activities. UNDP must not only be aware of and
monitor the procurement risks it faces, but it must also proactively anticipate and assess those
risks. This chapter deals exclusively with “transactional” procurement risks. Therefore it does
not elaborate on Corporate Procurement risks, which are part of UNDP Corporate Procurement
Strategies.
33. A number of procurement risks must be taken into consideration when defining procurement
strategies. These can be clustered in three main groups:
Environmental risk, including the political environment, natural environment or delivery
infrastructure environment, among others
Programme risk, including but not limited to the risk of operating in the market, the
complexity of the Supply Chain Management, or the risk associated with the nature of the
service or goods to be acquired, among others
Implementation risk, or risk associated with the implementation unit capacity
34. In the table below you will find some examples of potential risks and mitigation activities. Please
note that this list is for reference purposes only and is not exhaustive.
Critical procurement
activity
Plan in advanced
PROCUREMENT PLANNING
REQUISTION PLAN
36. During the definition stage of the project cycle, all relevant activities will need to be identified
and budgeted. Among these activities, considerations must be taken for the acquisition of
goods, services and works in order to achieve the project objectives. Required services identified
should also include any individual consultant services necessary for the successful
implementation of the project (including services for complex/highly technical specifications
development, if applicable). This information will be the groundwork for the establishment of
the Requisition Plan.
37. The Requisition Plan shall be developed at the project definition stage and recorded in Quantum
as part of project activities. The plan will be updated regularly as required.
38. The requisitioner is responsible for developing the Requisition Plan, including the following
minimum information:
Description of goods, services or works
Quantities
Estimated budget
Expected completion date of activity
39. Low-priority procurement categories can be quantified and budgeted in the Requisition Plan as a
lump sum. For example, “stationary lot” (pens, pencils, pad, other) – QTY 1 – Budget 2,000 USD
40. High/medium priority procurement categories should be carefully quantified and accurately
budgeted.
41. The Requisition Plan is based on estimates of procurement operations to be carried out. While
some procurement needs cannot be anticipated, a Requisition Plan based on estimates is always
better than no planning at all.
42. At the planning stage, it is always necessary to take into consideration the entire SCM, including
the project requirements and UNDP’s roles and responsibilities in terms of the SCM.
43. However, it is only under certain circumstances, and normally due to the extension and
complexity of the SCM, that the Country Office or Business Unit will need to develop a SCM Plan
in writing.
44. For some projects with an extended and complex SCM, we recommend the development of a
SCM Plan before moving into the development of the transactional Procurement Plan. An
45. In these cases, it is important to analyze each step of the SCM, identify roles, responsibilities,
existing infrastructures, potential bottlenecks and actions to be taken.
Inventory management
o Is sufficient storage space available at all level of the distribution chain
(central/regional/ district)?
o Provide estimates of the total storage space that exist. If there is no sufficient space
indicate alternative solution.
o Are there any items that require special storage conditions?
o What are the security conditions? How would sensitive items be treated?
o Who is responsible for coverage against theft, damage, etc.?
o Does any inventory management system exist?
o Does there exist a clear process and procedure for the receipt of goods?
Distribution
o To approximately how many points are products distributed? Distinguish between
distribution points; for example, central storage, regional, and site storage.
o Are there any significant challenges in distributing to the sites (e.g. lack of roads, conflict
zones, very long distances, seasonal rains, etc.)?
o What are the estimated distribution lead times from central to regional locations (each)
and from regional locations to sites (each)?
o Will a pull or push system be used?
o Who is responsible for the risks encountered during distribution? If UNDP, does
insurance exist?
47. Based on the received Requisition Plan and after taking into consideration the market situation
and associated risks, the project and procurement personnel willproceed to develop a
Procurement Plan in Quantum.
48. All Requisition Plans for significant procurement shall be converted to a Procurement Plan.
49. When developing Consolidated or Individual Procurement Plans, it is important to take into
consideration any existing long-term or other arrangements. The minimum information
included in the Procurement Plan should be:
Type of goods/services/works to be provided
Method of procurement
Estimated cost (unitary and total)
Expected date for specification/TOR/SOW to be finalized
Sourcing period