73 - (J) - 03 10 2019
73 - (J) - 03 10 2019
VERSUS
UNION OF INDIA AND OTHERS …Respondents
ORDER
R. BANUMATHI, J.
Digitally signed by
MADHU BALA
Date: 2019.10.03
respondent No.6-Colonizer for the purpose of purchasing plots of
17:09:51 IST
Reason:
1
obtained seven colonization licences. In the year 1996, writ
petitions under Article 32 of the Constitution of India were filed by
the members of the petitioner-Association before the Supreme
Court contending that respondent No.6-Colonizer had not adhered
to the terms of the agreement in allotment of plots to the allottees
who had booked the plots with respondent No.6-Colonizer. In the
writ petition, number of orders came to be passed. Vide order dated
02.12.1999, the Court noted that there seems to be a dispute as to
the amount payable by each allottee to respondent No.6-Colonizer
as well as to the government. Stating that it is not possible to fix the
exact figure payable by each allottee to the government and to
respondent No.6-Colonizer, the Court directed each allottee to pay a
sum of Rs.50/- per sq. yd. towards development charges to the
Director, Town and Country Planning within four weeks. The
balance amount, if any, was to be worked out and fixed later.
2
3. The Court vide order dated 13.01.2015 appointed Mr. Raju
Ramachandran, senior advocate as amicus curiae to go into the
detailed facts of the case and prepare a report. The Supreme Court
vide order dated 27.01.2016 referred the matter to arbitration.
Justice Vikramajit Sen, former Judge of the Supreme Court was
appointed as the sole Arbitrator for resolving the terms of reference
and the dispute between the parties. The learned Arbitrator held
around twenty-two hearings in the matter to resolve the dispute
among the parties. The learned Arbitrator has completed the
mammoth task of identifying the eligible allottees. The learned
Arbitrator noted that there are three categories of allottees for the
purpose of allotment which are as under:- 1
I. General
II. Economically Weaker Sections (EWS)
III. No profit no loss (NPNL)
1 (Pg. No.44D and 55(4) of Proceedings of the Supreme Court dated 13.01.2015 and
27.01.2016 and Pg.20 of the paperbook regarding Letter dated 21.03.2018 by Arbitrator)
3
I. General … 4702
…
II. Economically … 350 (out of which
Weaker Sections … 106 applied for
(EWS) allotment)3
III. No profit, No loss … 19324
(NPNL) …
4
which portions of the land compositely held by seven licences
falls to its share?
(ii) Given that the State of Haryana has categorically stated that it
cannot take over the project and make allotments, even in view
of the fact that the Colonizer has intentionally not paid the
Licence Fee, who will undertake the development of the Project
and subsequently make allotments?
(iii) In view of the fact that around 2690 claims were received in the
NPNL category, the State of Haryana will have to devise a
policy for relaxing density norms for the Project.
(iv) The Hon’ble Supreme Court may pass appropriate directions
for converting these proceedings to that of a Special
Committee.6
5
(i) How much is the total extent of land procured by respondent
no.6-coloniser/developer, for the purpose of developing the
project in question. The details are to be furnished along with
the survey numbers/plot numbers of the land. It is also brought
to our notice, a portion of the land is encroached by the third
parties. A rough sketch is to be supplied showing the entire land
of the project and the encroached area.
(ii) Respondent No.6-coloniser, as well as the learned counsel for
the State of Haryana, shall file the approved map/layout of the
project. The map/layout shall show the position of the plots and
the actual physical features of the land as on today.
(iii) What is the total amount of money collected by the 6th
respondent-coloniser from the plot owners towards the cost of
the land and also towards development charges, for internal and
external.
(iv) What is the total amount of money actually deposited by
respondent no.6-coloniser before the competent authority, for
the purpose of internal and external development out of the
money collected from the plot owners.
(v) The total amount of money which has been paid by the plot
owners before the competent authority towards development
charges, pursuant to orders of this Court dated 07.04.1997 and
02.12.1999.
(vi) The estimate of the amount which is required to complete the
project in question including internal and external development
charges.
(vii) State of Haryana to file detailed report as to actual physical
features of the land including the extent of internal development
and external development, if any, already done. The State of
Haryana shall obtain instructions and make further submissions
and/or suggestions with regard to the development and other
relevant issues for resolution of dispute in question.8
6
10. In response to the above order, all concerned parties have
filed their responses and State of Haryana filed status affidavit. So
far as the licences granted to respondent No.6-Colonizer, the DTCP,
Haryana in its counter affidavit/Status Report stated as under:-
“Details of licences and layout – Phase I and Phase II 9
That M/s Durga Builder Pvt. Ltd. and its associate companies were
granted the following licences, for a total area measuring 234.674
acres, under Section 3 of the Haryana Development and
Regulation of Urban Areas Act, 1975 (hereinafter called as Act of
1975):-
Sl. Name of the Land Owner Licence No. Area
No. Licencee (in acres)
1. M/s Durga Builders M/s Durga Builders 1/91 and 65/92 114.075
(Main Developer) 6.19
2. Ravindra Promoters Ravinder 2/91 and 66/92 0.918
Pvt. Ltd. Promoters Pvt. Ltd. 1.82
3. Sh. Ravinder Kumar Sh. Ravinder 3/91 11.731
Nanda Kumar Nanda
4. Rajdhani Housing Rajdhani Housing 67/92 84.54
Syndicate Pvt. Ltd. Syndicate Pvt. Ltd.
5. Panchsheel Co- Panchsheel Co- 68/92 15.40
operative House operative House
Building Society Building Society
Total 234.674
11. The above said licensed areas are in two pockets i.e. Okhla
Enclave Phase-I (Area 126.724 acres) and Okhla Enclave Phase-II
(Area 107.95 acres). Copy of the revised layout plan of Phase-I
and Phase-II, as revised and approved on 24.09.1997 have been
filed by the DTCP, Haryana. Out of the total extent of 234.674
acres, an extent of 46.85 acres is under encroachment and 187.825
acres land is available for planning. In the report filed by the DTCP
dated 19.08.2019, it is stated that out of the above 187.825 acres
area, 43.68 acres area was reserved for general category plots,
23.475 acres area was reserved for community-infrastructure sites.
7
Balance, 120.67 acres was planned for EWS and NPNL category
plots.10 In this regard, reference be made to layout plan of OKHLA
Enclave, Phase-I, Delhi-Haryana Border, Faridabad and Layout
plan, Phase-II, Sector-91, Faridabad, Haryana filed by the DTCP. In
the layout plans, alleged encroached areas are also shown in red
ink.
8
spent by DTCP, Haryana towards keeping watch and ward of the
licensed area and other charges.
13. Status of the Companies:- So far as the status of the above
companies, in its reply filed on 19.08.2019, the State of Haryana
stated as under:-
That Sh. Ravinder Kumar Nanda and Smt. Promila Nanda were the
Directors of M/s Durga Builder Pvt. Ltd. (as per the information
available on the website of Ministry of Corporate Affairs, the status
of the company is strike off), as per the Memorandum of Article
dated 29.01.1985. However, Sh. Divij Mehra and Sh. Saurabh
Kapoor are the present Directors since 24.03.2014 and 15.04.2015
respectively.
That Sh. Ravinder Kumar Nanda and Smt. Promila Nanda are the
Directors of M/s Ravindra Promoters Pvt. Ltd. since, 10.07.1989
(as per the information available on the website of Ministry of
Corporate Affairs, the status of the company is strike off).
That Sh. Ravinder Kumar Nanda and Smt. Promila Nanda are the
Directors of M/s Rajdhani Housing Syndicate Pvt. Ltd. since,
13.09.1989 and 22.12.1989 (as per the information available on the
website of Ministry of Corporate Affairs, the status of the company
is strike off).
That the information regarding the Directors of M/s Panchsheel
Co-operative House Building Society, is not available on the
website of MCA.12
12 (Under Point No.1 at Pg. No.3 of Reply filed by DTCP, Haryana on 19.08.2019)
9
Directors of M/s Durga Builder Pvt. Ltd. was received by the
Director, Town and Country Planning, Haryana up to 17.07.2014. 13
13 (Under Point No.1 at Pg. 3-4 of reply filed by DTCP, Haryana on 19.08.2019)
10
dated 24.08.2018 qua M/s Durga Builder Pvt. Ltd. has been kept in
abeyance.15
16. The learned amicus curiae submitted that as per the affidavit
dated 19.08.2019 filed by DTCP, Haryana and e-mail dated
18.07.2014 received by the Department from the advocate Deepak
Khosla mentioning that as per the decision of the Company Law
Board dated 11.03.2014, Mr. Arun Mehra and Divij Mehra are the
present Directors of M/s Durga Builders Pvt. Ltd. The learned
amicus submitted that when Mr. Arun Mehra is claiming to be the
Director of M/s Durga Builders Pvt. Ltd. of which he is a Director, the
claim of Mr. Arun Mehra need not be considered as it has been
15 (Under Point No.1 at Pg. No.4-5 of Reply filed by DTCP, Haryana on 19.08.2019)
11
rejected by the Court Commissioner. So far as the claim of Mr. Arun
Mehra in respect of 87 plots, liberty is granted to Mr. Arun Mehra to
work out his remedy in accordance with law by agitating the matter
before the competent court. However, it is made clear that the claim
of Mr. Arun Mehra in respect of 87 plots shall not come in the way of
the claim of the beneficiaries identified by the Scrutiny Committee.
12
19. In terms of Section 5 of the Haryana Development and
Regulation of Urban Areas Act, 1975, the Colonizer shall deposit
30% of the amount realised from time to time from the plot holders
within a period of ten days of its realisation in a separate account to
be maintained in a scheduled bank. That amount shall only be
utilised by him towards meeting the cost of internal development
works in the colony. The remaining amount shall be deemed to
have been retained by the Colonizer inter alia to meet the cost of
land and external development works. In the present case, the
Colonizer has not complied with the requirement under Section 5 of
the said Act. In the reply filed by the Director, Town and Country
Planning, Haryana (on 19.08.2019), it is stated that the licencee M/s
Durga Builder Pvt. Ltd. has not complied with Rules 24, 26(2), 27
and 28 of Haryana Development and Regulation of Urban Areas
Rules, 1976, as per which the licencee shall have to maintain
separate ledger account of each plot holder, intimate the account
number and full particulars of the scheduled bank wherein he
deposits 50% of the amount realised by him from the plot holders
for meeting the cost of internal development works. 16
13
yards to 170 sq. yards and Rs. 975/- for plots of 171 to 220 sq.
yards. As to the external development, it was worked out at Rs.
4,70,000/- per acre which was to be borne by the allottees. 17
However, it is stated only some of the allottees (according to the
Colonizer, only 143 of the allottees) have complied with the order of
the Supreme Court. But according to the petitioners that in
compliance of the order of the Supreme Court, they have paid the
amount. This has to be verified; those of them who have not
complied with the order of the Supreme Court shall be directed to
pay the amount with 6% interest on the amount payable from
01.01.1998.
21. Vide order dated 02.12.1999, the court observed that it is not
possible to fix the exact figure payable by each allottee to the
Government and to the Colonizer. All the same, the court directed
each allottee to pay a sum of Rs. 50/- per square yard within four
weeks from the date of this order to the Government of Haryana in
the account of the Colonizer. The court directed that the balance
amount if any, payable by each allottee will be worked out and fixed
up later. To avoid further complications, the court directed the
allottees to send the amount by draft by registered post to the
Director, Town and Country Planning, if personal delivery is not
feasible. The remittance of the amount was directed to be
immediately sent to respondent No.6 by the remitter. 18 However, it
is stated that only some of the allottees (according to Colonizer, only
143 of the allottees) have complied with the order of the Supreme
Court.
14
22. Submissions on behalf of Respondent No.6-Colonizer:- It
has been submitted by respondent No. 6 that the rate for
development stood at Rs. 550/- per sq. yard plus the cost of land in
the year 1995. The Supreme Court revised these charges upwards
vide its orders dated 07.04.1997 and 02.12.1999. A complete
scrutiny of all the claims has revealed that out of the eligible 1708
NPNL claimants in the scrutiny committee report, only 143 have
paid development charges @ Rs. 600/-, in compliance of order
dated 02.12.1999 passed by this court; the rest 1565 have failed to
comply with the said order and have shied away from paying the
requisite development charges, thereby being no longer entitled for
allotment of a plot. Further, according to respondent No.6, many plot
claimants have also defaulted in making payment of cost of land as
stipulated by order dated 07.04.1997. According to respondent
No.6-Colonizer, the petitioners falling short on the land and
development charges have jeopardised the development of plots
allotted to them.19
15
24. The petitioners further submitted that the cost of internal
development of the land is inclusive of the land cost. As such, the
petitioners have already made the agreed payment of internal and
external development charges. It has been claimed by respondent
No. 6 that it has deposited a total amount of Rs. 18.90 crores with
the Government for external development charges out of which only
a sum of Rs. 2.30 crores has been spent by the DTCP, Haryana.
This fact has also been admitted by the Government of
Haryana/Town and Country Planning in their affidavit dated
09.09.2008. According to the petitioners, there is still a sum of Rs.
16.70 crores lying with the Government. However, it has been
stated by the petitioners that whatever amount is due and payable
to DTCP, Haryana towards internal and external development
charges, they are ready and willing to deposit the said amount as is
estimated by the Govt. of Haryana.21
21 (Point No. (V) at Pg. 15-16 of submission on behalf of petitioners filed on 13.03.2019
in terms of order dated 14.02.2019)
16
22.07.2019 stated that they have collected Rs.15,79,90,433/- from
“No Profit, No Loss” and “General Category” plot claimants and
further submitted that the DTCP, Haryana has spent
Rs.8,60,00,000/- on the internal development works and deposited
Rs.17,17,00,000/- with the State of Haryana for external
development works. The State of Haryana has also taken the stand
that in response to the show cause notice dated 23.04.2013 issued
by the Department to M/s Durga Builder Pvt. Ltd. and its associate
companies, reply dated 25.06.2013 signed by Sh. Ravinder Kumar
Nanda was filed stating that M/s Durga Builder Pvt. Ltd. has
collected Rs.28,13,91,183/- i.e. Rs.17,00,99,128/- in Phase-I and
Rs.11,12,92,055/- in Phase-II and spent Rs.21.39 crores on the
internal development works. According to the State of Haryana, the
stand of DBPL is totally contradictory to its stand taken in the written
submission filed in the court.22
17
Department against outstanding dues of external development
charges.
Sl. No. Detail of External Development Total amount
Charges deposited
(in Rs.)
1. Deposited by the licencee 17,17,72,000/-
2. Deposited by the petitioners 1,75,00,000/-
directly in the Department
Total 19,76,69,127/-
23 (Para No.2 at Pg.4-6 of Status Affidavit filed by DTCP, Haryana filed on 07.03.2019)
18
drainage and construction of roads (balance work) of Okhla
Enclave, Phase-I, Sector 91, Faridabad.
(c) Approximately Rs.20.86 crores would be required for
providing storm water drainage for Phase-I and II.
(d) Approximately Rs.3.98 crores would be required for laying
of RCC pipe and construction of disposal (sewer). This is in
addition to expenditure of Rs.1.92 crores incurred till date.
(e) Approximately Rs.5.09 crores would be required for
providing electrification and street light.24
19
“Regarding external development it is submitted that it includes city
level infrastructure such as master plan roads, hospital, college,
public health services etc. which are executed as per the provision
of Development Plan. As per Superintendent Engineer, Haryana
Shahari Vikash Pradhikaran (HSVP), master sewer line from Durga
Builder to Palla Chowk, road from bye-pass to Okhla Enclave,
connecting sewer of Okhla Enclave disposal have already been
executed and the work of master water supply is being
undertaken.”27
20
Town and Country Planning, Haryana submitted that at least 90% of
the amount has to be deposited to enable the Department to
undertake the works. The question is as to how this amount is to be
paid to DTCP, Haryana.
21
Planning, Haryana to adjust the expenditure so far borne by DTCP
in issuing various advertisements and other such incidental
expenses. The details of such expenditure so far made by DTCP
along with necessary bills/vouchers be produced before the learned
Arbitrator and the learned Arbitrator to pass appropriate orders for
adjustment of the expenditure amount so far borne by DTCP,
Haryana.
22
pay the apportioned development charges. Since there are number
of beneficiaries, it is necessary to clarify the consequence if the
claimants do not pay the amount stipulated within the
prescribed time frame. In case the claimants express
unwillingness to pay the proportionate development charges or fail
to give an undertaking within the given time frame, the land allotted
to them will revert to the Colonizer on certain conditions viz. –
colonizer will pay the claimant the amount paid towards the cost of
land with interest from the date on which such payment was made
at a rate which may be considered appropriate by the arbitrator.
The Colonizer in addition to the above, shall also pay the
proportionate amount towards development works payable for the
said plot to the government of Haryana. On the order passed by the
arbitrator, such payment shall be made within six weeks from the
date of failure of payment by the claimant.
36. Insofar as the other categories of allottees who have not been
identified and who are yet to have the sale deed, in case if they do
not pay the development charges within the time frame, as
discussed earlier, they shall forfeit the right over the plot. The
Colonizer has undertaken to refund the amount to the allottees in
case of failure to pay the apportioned amount by the individual plot
owners. The Colonizer has also undertaken to refund the amount to
the allottees who cannot pay the due amount to DTCP, Haryana. In
case of the plot owner who cannot pay the apportioned
development charges or committed default in payment of the
apportioned amount, the colonizer shall pay the consideration
amount paid by the allottee along with the reasonable interest.
23
Additionally, the Colonizer shall also pay the apportioned amount of
the development charges qua those plots.
24
38. The exercise of deciding eligible candidates was started with
the NPNL category. The Director, Town and Country Planning,
Haryana issued a public notice on 18.08.2016 in the newspaper
inviting applications to file claims accompanied with supporting
documents regarding allotment/booking of plot in NPNL category.
The Scrutiny Committee decided that an amount of Rs. 550/- be
taken as development charge for scrutiny of claims. 29 The Scrutiny
Committee received 2690 applications for the purpose of scrutiny
before the cut-off date. However, 523 applicants did not appear
before the Committee for the purpose of scrutiny. After scrutiny of
applications, the Committee found total 1932 NPNL category
applicants, 73 general category applicants, 165 commercial
category applicants and 2 EWS category applicants. 30
39. NPNL Category were divided into five categories as under 31:-
25
40. Thereafter, scrutiny qua general and EWS category claimants
was started. Vide order No.20 dated 13.07.2018, the Arbitrator
directed the State to again give state-level advertisements inviting
representation from all parties alongwith documents supporting their
allotment in General and EWS category by 31.07.2018. The cut-off
date for submitting application/claims was four weeks from the date
of advertisement. In compliance of this order, public notice was
advertised on 04.08.2018 in Amar Ujala, Dainik Jagran (Hindi) and
Tribune (English). The last date for receipt of application was
03.09.2018 but since 03.09.2018 being a gazetted holiday, the
applications received upto 04.09.2018 were considered by the
Committee.32 Under the EWS category, draw was held on
30.07.1994 and 18.11.1995 where 350 persons were successful.
Only 106 applicants applied for allotment.33
26
deed/conveyance deed executed from
developer
Note:- The report of the general category plots was not signed by
Sh. Ashok Aggarwal, the authorised representative of Durga
General Plot Holders Welfare Association as he was not satisfied
with the scrutiny procedure/comments of the scrutiny committee. 35
27
provides for mode of carrying out the development works in the
colony. Section 8(4) of the HDRA Act enables the Director to
transfer the possession and title of the land to the plot owners.
Section 8 (4) of the HDRA Act reads as under:-
“8. Cancellation of licence –
…….
(4) Notwithstanding anything contained in this Act, after the colony
has been fully developed under sub-section (2), the Director may
with a view to enabling the colonizer, to transfer the possession of
and the title to the land to the plot-holders within a specified time,
authorise the colonizer by an order, to receive the balance amount,
if any, due from the plot-holders, after adjustment of the amount
which may have been recovered by the Director towards the cost of
the development works and also transfer the possession of or the
title to the land to the plot-holders within aforesaid time. If the
colonizer fails to do so, the Director shall on behalf of the colonizer
transfer the possession of and the title to the land to the plot-
holders on receipt of the amount which was due from them.
…….”
Once the allottees are identified and the allottees pay the
apportioned development charges, the learned Arbitrator shall direct
the Director to execute necessary documents in favour of the
allottees in terms of Section 8(4) of the HDRA Act.
28
43.68 acres area was reserved for general category plots, 23.475
acres area was reserved for community/infrastructure sites.
Balance, 120.67 acres was planned for EWS and NPNL category
plots. As per the layout plan of Phase-I and Phase-II, details of the
plots like category, plot area and the number of plots are as under:-
Phase-I
Total – 1502 plots *37
Phase-II
Total – 1424 plots*38
Sl. No. Size of the Plot Number of Plots Category Total (Category wise)
1. 200 sq. Mtrs 163 plots NPNL
2. 148.75 sq. Mtrs 176 plots NPNL 356 plots
3. 128 sq. Mtrs 17 plots NPNL
4. 101.25 sq. Mtrs 425 plots EWS
5. 50 sq. Mtrs 268 plots EWS 857 plots
6. 112 sq. Mtrs 164 plots EWS
7. 420 sq. Mtrs 96 plots General
8. 350 sq. Mtrs 24 plots General 211 plots
9. 242 sq. Mtrs 91 plots General
37 Revised lay-out plan submitted by DTCP, Haryana in its status affidavit dated
07.03.2019 at Pg. 26.
38 Revised lay-out plan submitted by the DTCP, Haryana in its status affidavit dated
07.03.2019 at Pg. 27.
29
45. On behalf of the Director, Town and Country Planning,
Haryana, it is stated that as per the revised layout plan of Phase-I
and Phase-II, the plotted area shall not exceed 55% of the net
planned area of the colony. The commercial area shall also be
included in this plotted area for calculations of the area under the
plots. In Phase-I, the total area under the scheme is 126.724 acres
out of which the area under the residential plot is 61.64 acres. In
Phase-II, the total area under the scheme is 107.95 acres out of
which 51.03 acres is the area in residential plots.* 39
30
companies for the total area measuring 234.674 acres under
Section 3 of the Haryana Development and Regulation of Urban
Areas Act, 1975 (HD&RUA Act). The above said licensed areas are
in two pockets i.e. as Okhla Enclave Phase-I (Area 126.724 acres)
and Okhla Enclave Phase-II (Area 107.95 acres). The copies of the
approved layout plans of Okhla Enclave Phase-I and Phase-II are
revised on 24.09.1997. In terms of the provisions of the Act and as
per the conditions of the licence, the Colonizer has to pay the
licence fee and the licence renewal fee. In the status affidavit filed
by the Director, Town and Country Planning, Haryana in March,
2019, it is stated that an amount of Rs.21,86,97,901/- (as on
28.02.2019) is outstanding from the Colonizer. As per the terms and
the conditions of the licence, the Colonizer/Developer is bound to
bear the expenses to carry out the internal development works in
the colony and to clear the government dues of fee for renewal of
licence and other expenses borne by the State of Haryana.
However, with a view to move forward with the development, the
allottees of the plots have undertaken to pay the cost of the internal
and the external developments. But the Colonizer cannot be
allowed to go scot free. The sixth respondent-Colonizer is bound to
pay the licence fee of Rs. 21,86,97,901/- (as on 28.02.2019)
towards the fee for renewal of licence which is payable with interest
@ 6% per annum from 28.02.2019. If the amount is not paid by the
sixth respondent, it is for the State of Haryana to proceed against
the sixth respondent to recover the amount as if it is a land revenue.
For the said amount of 21,86,97,901/- (as on 28.02.2019), there
would be a charge on the properties of the sixth respondent-
Colonizer.
31
48. Issue of encroachment and the expenses met by the Director,
Town and Country Planning, Haryana in engaging the watch and
ward of the licensed area:- In the counter affidavit filed by the Director,
Town and Country Planning, Haryana, it is stated that an extent of 46.85
acres land was under encroachment/unauthorised construction. By the
order dated 18.07.2013, the Supreme Court has directed the
Department for watch and ward of the licenced area till the matter is
resolved. In this regard, in the affidavit filed by the Director on
19.08.2019, it is stated that:-
*The Department has hired a private security agency at the expense of
Rs.2.5 lakh per month, which has deputed twelve number of security
guards for twenty-four hours to keep a watch and ward of this licensed
area. The Department has already paid approximately Rs.1.25 crores
to the security agency. Due vigilance on the licensed area is being kept
and demolition of encroachment/unauthorised construction is being
done by the Enforcement Wing of Town and Country Planning,
Department. A whatsapp group of the officials of police department,
enforcement wing of this department and hired security guards has
been created to update the time to time status of unauthorised
constructions, if any. For the awareness of general public, the flex
boards have been displayed on prominent places of this colony clearly
mentioning that matter of this colony is subjudice and no person can
do sale, purchase of plots and raise unauthorised construction in this
colony till the matter is resolved. Whenever any new illegal
construction activity comes to the notice, the same are immediately
removed.*40
49. In the affidavit, it is further stated that there was a big
demolition drive in the colony on 11.04.2017 during which, newly
erected thirty-five residential structures and fifteen numbers of
DPC/boundary wall were removed. It is further stated that even if
any small construction activity like wire fencing, DPC, boundary
wall, etc. occurs in the colony, the same is removed by the security
guards at the initial stage and the Department has taken sincere
efforts to ensure that no new encroachment or unauthorised
construction has taken place on the licensed area. It is stated that
32
however, the already existing encroachment over an area of 46.85
acres could not be removed due to Law and Order problem.
50. In this regard, DTCP, Haryana has pointed out that an amount
of Rs.1.25 crores already spent by the Department towards the
watch and ward and the same is also payable by the sixth
respondent-Colonizer. Thus, the total amount payable by the
Colonizer to the Department is Rs.21,86,97,901/- (as on
28.02.2019) which is payable with interest @ 6% per annum from
28.02.2019 Plus Rs.1.25 crores borne by the Department to the
security agency till August, 2019-the date of filing of the affidavit
before the Supreme Court and further expenses borne by the
Department for watch and ward of the licensed area and other
incidental expenses. If the above amount is not paid by the sixth
respondent-Colonizer, it is for the State of Haryana to proceed
against the sixth respondent to recover the amount as fee which is
a land revenue.
33
encroached land, they would not be entitled from claiming any
further allotment in their favour.
34
direct the sixth respondent-Colonizer to compensate the allottee of
the plot by directing the sixth respondent-Colonizer to pay adequate
compensation in lieu of the claim for the plot falling vacant. In order
to make a claim for such plots falling vacant, the sixth respondent-
Colonizer is to pay:- (i) the compensation to allottee as directed by
the learned arbitrator; and (ii) to pay the apportioned amount of
internal and external development charges.
56. In his letter dated 23.01.2018, the Arbitrator has also observed
that “these proceedings are not in the nature of arbitration and
35
essentially, in the nature of a Special Committee of the Hon’ble
Supreme Court of India.” We fully agree with the views expressed
by Justice Vikramjit Sen. It is made clear that the present
proceedings are not in the nature of arbitration within the meaning
of the Arbitration and Conciliation Act, 1996; but essentially, in the
nature of a Special Committee constituted by the Hon’ble Supreme
Court of India.
Once the allottees are identified and the allottees pay the
apportioned development charges, the learned Arbitrator
shall direct the Director to execute necessary documents in
favour of the allottees in terms of Section 8(4) of the HDRA
Act.
36
Question No.1:
Members of the petitioner association/allottees purchased the plots
from the Colonizer who held the above seven licences and
therefore, they are entitled to the entire extent of land as per the
layout without going into the question of which is the portion of the
land M/s Durga Builder Pvt. Ltd. is claiming succession.
37
the matter before the competent court. However, it is made clear
that the claim of Mr. Arun Mehra in respect of 87 plots shall not
come in the way of the claim of the beneficiaries.
Question No.2:
The Town and Country Planning Department has stated that only
after payment of at least 90% of the total amount, they will
undertake the work.
38
allottees) have complied with the order of the Supreme Court. But
according to the petitioners that in compliance of the order of the
Supreme Court, they have paid the amount. This has to be
verified; those of them who have not complied with the order of
the Supreme Court shall be directed to pay the amount with 6%
interest on the amount payable from 01.01.1998.
The Arbitrator shall determine the cost for the square meter and
proportionately apportion the total cost amongst the eligible plot
owners depending on their respective plot size.
In case the claimants who have not so far got the sale deed
executed express unwillingness to pay the
proportionate/apportioned development charges or fail to give an
undertaking within the given time frame, the land allotted to them
will revert to the Colonizer on certain conditions viz. – (i) colonizer
will pay the claimant the amount paid towards the cost of land with
interest from the date on which such payment was made at a rate
39
which may be considered appropriate by the arbitrator; and(ii) in
addition to the above, the Colonizer shall also pay the proportionate
amount towards development works payable for the said plot to the
government of Haryana.
Question No.3:-
Insofar as the question raised by the learned Arbitrator that
whether the present density norms can be relaxed for the project,
Mr. Maninder Singh, learned Senior counsel appearing for the
State of Haryana has submitted that the density norms like the
area reserved for roads, common purposes, etc. cannot be
reduced.
Insofar as the density of the plots, the learned Arbitrator if need be,
shall make appropriate adjustments of the plots in conformity with
the existing rules. The adjustments of the plot area will have to be
done from amongst the plot owners. The State of Haryana shall
render its co-operation in adjustment of the plot sizes in the
approved layout of course, subject to the conformity with the
existing rules and governing sanction of the scheme.
Question No.4:-
40
It is made clear that the present proceedings are not in the nature
of arbitration within the meaning of the Arbitration and
Conciliation Act, 1996; but essentially, in the nature of a Special
Committee constituted by the Hon’ble Supreme Court of India.
41
On payment of licence fee and other dues, the Colonizer would
be entitled to make a claim for the surplus plots, if any, left over.
………………………..J.
[R. BANUMATHI]
………………………..J.
[A.S. BOPANNA]
New Delhi;
October 03, 2019
42