Potential Planner Check List
Date Description Complaint
01-10-2024 ss1 transformer 1,2 health check up
02-10-2024 ss1 operating work done
03-10-2024 rmu and vcb panel health check up
04-10-2024 capacitor bank 1,2 health check up
05-10-2024 ss1 LT panel health check up
06-10-2024 ss1 and 2 operating work done
07-10-2024 generator 1,2 health check up
08-10-2024 ug tank 1 health check up
09-10-2024 ss1 operating work done
10-10-2024 ss2 transformer health check up
11-10-2024 ss2 vcb panel health check up
12-10-2024 ss1 operating work done
13-10-2024 ss1 and 2 operating work done
14-10-2024 ug tank 2,3 health check up
15-10-2024 type 3 lighting feeder panel health check up
16-10-2024 ss1 operating work done
17-10-2024 ss2 capacitor bank health check up
18-10-2024 ss1 transformer 1,2 grass clean work done
19-10-2024 ss2 LT panel health check up
20-10-2024 ss1 and 2 operating work done
21-10-2024 ss2 generator health check up
22-10-2024 generator 1,2 battery and oil level check work done
23-10-2024 ss1 operating work done
24-10-2024 ug tank 2,3 health check up
25-10-2024 ss1 transformer silica gel change work done
26-10-2024 Electrical work work done
27-10-2024 Electrical work work done
28-10-2024 Electrical work work done
29-10-2024 Electrical work work done
30-10-2024 ss1 operating and eletrical work work done
31-10-2024 ss1 and 2 operating work done
Customer Remark
Check by Customer Signature