TECHTIPS
INSTALLING KNOCKOUT TILE IN MIAMI-DADE COUNTY
WITH APPROVED 3-COURSE FLASHING METHOD
The Miami-Dade County of Florida has
many stringent standards when it comes to
building projects, due to the hurricane-force
winds that frequent the region.
This Tech Tip will help show you how to
install Knockout Tile attachments on tile
roofs, using a sealing method compliant in
Miami-Dade and Broward Counties.
Photo Courtesy of PayOli Solar
REQUIRED COMPONENTS & MATERIALS
The following items are needed to install Knockout Tile according to the approved method:
Knockout Tile L-Foot & Hdw Knockout Tile Pedestal & Lag Knockout Tile Flashing (Varies)
GAF® FlexSeal™ Sealant GAF® HydroStop® Fabric ChemLink® M-1® Sealant
TECHTIPS
3-COURSE INSTALLATION METHOD
6
1. Remove tiles over the attachment locations.
2. Determine the orientation of Knockout Tile
Pedestal (0 or 90 deg) based on rafter location.
3. Locate and mark the attachment locations in the
“knockout” zone (see manual).
4. Drill the pilot hole and clear the hole and
surrounding area of any debris.
7
5. Fill pilot hole with M1® Sealant
6. Install KO Tile Pedestal onto underlayment.
7. Apply 12” x 12” layer of GAF® FlexSeal™ sealant
over pedestal and install over existing roof
system.
8. Cut 2” slit in center of 12”x12” piece of GAF®
HydroStop® PremiumCoat® fabric.
9. Place GAF® HydroStop® fabric slit over Knockout 9
Tile Pedestal.
10. Apply 2nd 12” x 12” layer of GAF® FlexSeal™
sealant over HydroStop® fabric and let dry.
Maintain at least 6” from the center of the lag
bolt that is anchored to the truss in all directions.
11. Install KO Replacement Flashing over Pedestal,
then L-Foot and hardware.
11
© 2022 IronRidge, Inc. All rights reserved. Visit www.ir-patents.com for patent information. Version 1.10