QUOTATION FOR INTERLOCKING & KERB INSTALLATION
Scope of Work- A1
This quotation covers the supply and installation of interlocking stones and kerb stones,
including all necessary materials, labor, and equipment.
Interlocks: 75mm thick
Area of Interlocking: 936 m²
Lenght of Kerb: 72m
Number of Kerb Blocks: 120
Cost Breakdown
Total Cost
Item Quantity Unit Price (₦)
(₦)
Materials
Interlocks
(75mm Thick pre-cast 936 m² 8500 7,956,200
interlocking tiles)
Kerb
(600 x 100 x 350mm precast 120 pcs 2,500 250,000
kerb)
Cement 10 bags 9,000 90,000
Stone Dust
100 tons 13000 1,300,000
(incl. transport)
Nylon 60 kg 2,200 132,000
Roller Machine
1 140,000
(Before & After Laying)
Labor Cost
Base Preparation Work - 580,000
Laying of Kerb Stones 120 pcs 280,000
Laying of Interlocks 936 m² 1500 1,404,000
GRAND TOTAL 12,132,200
QUOTATION FOR INTERLOCKING & KERB INSTALLATION
Scope of Work- A2
This quotation covers the supply and installation of interlocking stones and kerb stones,
including all necessary materials, labor, and equipment.
Interlocks: 75mm thick
Area of Interlocking: 2,885m²
Lenght of Kerb: 582m
Number of Kerb Blocks: 970
Cost Breakdown
Total Cost
Item Quantity Unit Price (₦)
(₦)
Materials
Interlocks
(75mm Thick pre-cast interlocking 2885 m² 8500 24,522,500
tiles)
Kerb
970 pcs 2500 2,425,000
(600 x 100 x 350mm precast kerb)
Cement 60 bags 9000 540,000
Stone Dust
300 tons 13000 3,900,000
(incl. transport)
Nylon 180 kg 2200 396,000
Roller Machine
1 400,000
(Before & After Laying)
Labor Cost
Base Preparation Work - 1,480,000
Laying of Kerb Stones 970 pcs 2,163,330
Laying of Interlocks 2885m² 1500 4,327,500
GRAND TOTAL 40,154,330
QUOTATION FOR INTERLOCKING & KERB INSTALLATION
Scope of Work- A3
This quotation covers the supply and installation of interlocking stones and kerb stones,
including all necessary materials, labor, and equipment.
Interlocks: 75mm thick
Area of Interlocking: 450 m²
Lenght of Kerb: 250m
Number of Kerb Blocks: 417
Cost Breakdown
Total Cost
Item Quantity Unit Price (₦)
(₦)
Materials
Interlocks
(75mm Thick pre-cast interlocking 450 m² 8500 3,825,000
tiles)
Kerb
417 pcs 2500 1,042,500
(600 x 100 x 350mm precast kerb)
Cement 26 bags 9000 234,000
Stone Dust
50 tons 13000 650,000
(incl. transport)
Nylon 30 kg 2200 66,000
Roller Machine
1 140,000
(Before & After Laying)
Labor Cost
Base Preparation Work ` 280,000
Laying of Kerb Stones 417 pcs 973,000
Laying of Interlocks 450 m² 1500 675,000
GRAND TOTAL 7,885,500