MINUTES OF MEETING
Project: BP UCC Early Work Project No.: C0320C
Purpose: Clarification - Subcontractor/Supplier Pre- Meeting No.: 002
Qualification Assessment - PT Karunia Berca
Indonesia
Venue: Online Meeting by Microsoft Teams Date / Time: 22-Jul-2025
Attendees: PT Karunia Berca Indonesia (KBI) PT Petrosea Tbk (PTP)
1. Bpk. Tan Sin Ming 1. Bpk. Johny Vincent
2. Bpk. Billy 2. Bpk. Lukman Hakim QC
3. Bpk. Sanddy 3. Bpk. Choirul Anam
4. Bpk. Andry 4. Bpk. M Fani Indarto
5. Bpk. Leo 5. Bpk. Otniel Nevesy
6. Bpk. Duddy 6. Ibu Debby Kurnia Indah Pratiwi
7. Bpk. Bondan 7. Bpk. Ahmad Taufiq
8. Bpk. Nofite
9. Bpk. Cahyadi
10. Bpk. Anang
Distribution: All attendees
Recorded by: Ahmad Taufiq (PTP)
Item
Description Action / Date
No.
A Engineering & QC Section
1 KBI confirm duration qualification of WPS & Welder D1.8 Tubular application KBI / Info
(initiation up to approval from Migas) 1 month
2 KBI to submit CV existing QC Personnel & Candidadte CSWIP 3.1 & KBI / 24-Jul-25
Nace/bgas Level II
3 PTP informed that Blaster Painter Operator should have sufficient Info
qualification and Certified by BNSP/SLV/Ascoatindo/Indocoor
4 KBI to segregate Welding machine that will be used, calibration status, and actual Info
current condition (by photo)
5 KBI confirm perform calibration welding machine by independent parties. KBI / Info
6 KBI to provide maintenance record of compressor & painting requipment. KBI / ASAP
7 PTP advise KBI to perform Quality Awareness (Induction) to enhancing quality KBI / Info
behavior fabrication personnel prior fabrication
8 KBI to provide sample shop drawings produced by KBI’s engineering team KBI / ASAP
9 KBI to provide software lists including active licenses KBI / ASAP
Once printed this document becomes uncontrolled, Refer to Petrosea Intranet for controlled copy
FORM No.: PTP-ADM-FO-G-0006 REV No.: 0 Page 1 of 2
MINUTES OF MEETING
Once printed this document becomes uncontrolled, Refer to Petrosea Intranet for controlled copy
FORM No.: PTP-ADM-FO-G-0006 REV No.: 0 Page 2 of 2