Simcity-ETE Venture SDN BHD V Koperasi Pembangunan Kampung Tradisional Tasek Pulau Pinang BHD
Simcity-ETE Venture SDN BHD V Koperasi Pembangunan Kampung Tradisional Tasek Pulau Pinang BHD
A
Simcity-ETE Venture Sdn Bhd v Koperasi Pembangunan
Kampung Tradisional Tasek Pulau Pinang Bhd
B
COURT OF APPEAL (PUTRAJAYA) — CIVIL APPEAL
NO P-02(NCVC)(W)-1900–10 OF 2019
KAMALUDIN MD SAID, CHE MOHD RUZIMA AND AHMAD ZAIDI
IBRAHIM JJCA
29 OCTOBER 2021
C
E This was an appeal by the appellant (‘D3’) against part of the decision of the
High Court which allowed the respondent’s (‘plaintiff ’) claim for unjust
enrichment and dismissed D3’s counterclaim for the removal of the private
caveat lodged by the plaintiff and for the dismissal of the claim for damages
thereof. The plaintiff was the registered owner of a land (‘the land’). In late
F 1995, pursuant to an agreement, the plaintiff appointed Multi Track Properties
Sdn Bhd (‘MTP’), a developer to develop a housing project (‘the project’) on
the land. However, MTP failed to complete the project and the project was left
suspended. The plaintiff thereafter appointed a new developer, Elite Domain
Sdn Bhd (‘EDSB’) to revive and complete the project. EDSB also failed to do
G so and the project was again left suspended. D1 approached the plaintiff and
offered to take over and to complete the project. As a result, a joint venture was
established comprising of the plaintiff, D1 and D2 culminating in the
execution of an agreement known as the property management agreement
(‘PMA’) entered between the plaintiff and D3 which was jointly owned by the
H D1 and D2. However, D3 failed to commence works as there were charges on
the land that needed to be cleared before the project could be revived. Upon
negotiations with the financiers, the redemption sum in respect of the charges
were reduced from RM18m to RM800,000. The plaintiff had difficulty to
raise the fund and requested D3 pay the redemption sum on their behalf. To
I settle the matter, the plaintiff and D3 agreed to sign an additional agreement
(‘AA’). Pursuant to the AA, the plaintiff transferred all the development lots
(‘the 128 lots’) on part of the land to D3. As part of the promise, D3 should pay
RM100,000 to the plaintiff upon transfer of the 128 lots to D3 and to pay the
balance upon completion of the project. D3 failed to complete the whole of the
196 Malayan Law Journal [2022] 2 MLJ
project at any time. Upon request, various extensions of time were given by the A
plaintiff to D3. After nine years, the 442 units of buildings were completed.
However, the 532 units of buildings referred to in Item D of the First Schedule
to the PMA that were yet to be sold and built were never commenced at all by
D3. Alleging that D3 failed to honour its promise under the PMA and the AA,
the plaintiff decided to claim back the 128 lots and had entered a private caveat B
on the 128 lots. D3 resisted the plaintiff ’s claim on the basis that the plaintiff
had accepted D3 performance of the contract and that the 128 lots had been
transferred to D3 as consideration and not security. In the counterclaim, D3
sought to set aside the private caveats lodged by the plaintiff on the 128 lots and
to seek damages for the loss suffered consequents to the lodging of the caveats. C
The High Court allowed the plaintiff ’s claim and dismissed D3’s counterclaim.
Hence, this appeal.
A keseluruhan. Oleh itu, adalah salah bagi HMT yang bijaksana untuk
membuat penemuan dan memutuskan bahawa terdapat ketidakadilan di
pihak D3 untuk mengekalkan 128 lot itu atas sebab D3 gagal
menyiapkan projek itu sepenuhnya. Berdasarkan dapatan bahawa D3
tidak lagi bertanggungjawab untuk menyiapkan projek secara
B keseluruhan, D3 sebenarnya telah menyelesaikan tanggungjawabnya di
bawah kontrak. Oleh itu, HMT yang bijaksana telah terkhilaf dalam
penemuannya bahawa kontrak telah ditamatkan secara bersama melalui
kelakuan pihak-pihak dan prinsip kerugian terletak di mana ia terpakai
(lihat perenggan 49–50, 55 & 57–58).
C
(3) Selepas 128 lot dipindahkan secara sah kepada D3, plaintif tidak lagi
mempunyai kepentingan boleh didaftarkan ke atas tanah tersebut.
Walaupun jika HMT yang bijaksana betul dalam keputusannya
mengenai isu pengayaan yang tidak adil, hak plaintif hanya terhad
D kepada kepentingan kewangan atau hak in personam terhadap D3 dan
hak itu tidak mewujudkan sebarang kepentingan kaveat ke atas 128 lot
tersebut. Oleh itu, kaveat yang dimasukkan oleh plaintif hendaklah
dibatalkan in limine. Tiada keterangan yang dikemukakan oleh D3
untuk membuktikan bahawa ia mengalami kerugian akibat kemasukan
E kaveat plaintif. Oleh itu, D3 gagal membuktikan sebarang kerugian
akibat kemasukan kaveat plaintif yang salah pada 128 lot tersebut.
Akibatnya, mahkamah tidak dapat menerima permohonan D3 untuk
mendapatkan perintah supaya ganti rugi dinilai oleh Mahkamah Tinggi
(lihat perenggan 62 & 64–65).]
F
Cases referred to
Anjalai Ammal & Anor v Abdul Kareem [1969] 1 MLJ 22, FC (refd)
Bolton v Madden (1873) LR 9 QB 55, QBD (refd)
Chappell & Co Ltd v Nestle Co Ltd [1959] UKHL 1, HL (refd)
G Currie v Misa [1875] LR 10 Ex 153 (refd)
Dream Property Sdn Bhd v Atlas Housing Sdn Bhd [2015] 2 MLJ 441; [2015] 2
CLJ 453, FC (refd)
Fairfield Sentry Ltd (in Liquidation) v Migani and others and other cases [2014]
UKPC 9, PC (refd)
H Glamour Green Sdn Bhd v Ambank Bhd & Ors and another appeal [2006]
MLJU 649; [2007] 3 CLJ 413, CA (refd)
Mohamed Isa & Ors v Abdul Karim & Ors [1970] 2 MLJ 165 (refd)
Pembinaan SPK Sdn Bhd v Jalinan Waja Sdn Bhd [2014] 2 MLJ 322, CA (refd)
PJD Regency Sdn Bhd v Tribunal Tuntutan Pembeli Rumah & Anor and other
I appeals [2021] 2 MLJ 60; [2021] 2 CLJ 441, FC (refd)
Score Options Sdn Bhd v Mexaland Development Sdn Bhd [2012] 6 MLJ 475,
FC (refd)
Tan Tay Vui v MC Global Sdn Bhd [2020] MLJU 712; [2020] 1 LNS 21, CA
(refd)
200 Malayan Law Journal [2022] 2 MLJ
Tenaga Nasional Bhd v Ichi-Ban Plastic (M) Sdn Bhd and other appeals [2018] 3 A
MLJ 141, FC (folld)
Legislation referred to
Contracts Act 1950 s 26
Co-operative Societies Act 1993 B
Courts of Judicature Act 1964 s 64(4), (5)
Rules of Court 2012 O 15 r 2(2)
Rules of the Court of Appeal 1994 r 7(4), (5)
C
Appeal from: Civil Suit No PA-22NCVC-69–03 of 2017 (High Court, Pulau
Pinang)
Karin Lim Ai Ching (Ung Chirt Kye, Dominic Pillai s/o RK Pillai and Ooi Zie
Yiong with her) (Phee, Chen & Ung) for the appellant.
Nicholas Tan Soon Teik (Lee Fei Wen, Phoebe Ooi Mei Wei and Chai Shi Hong D
with him) (Lim Huck Aik & Co) for the respondent.
INTRODUCTION E
A land. Based on the agreement, MTP was obliged to complete the said project
by 1 December 1999. However, MTP failed to do so and the said project was
left suspended.
[5] The plaintiff thereafter appointed a new developer, Elite Domain Sdn
B Bhd (‘EDSB’) to revive and complete the said project. EDSB also failed to do
so and the project was again left suspended.
[6] Then, D1 approached the plaintiff and offered to take over and to
C complete the said project. As a result, a joint venture was established
comprising of the plaintiff, D1 and D2 culminating in the execution of an
agreement known as the property management agreement (‘PMA’) dated
12 July 2007 entered between the plaintiff and D3 which is jointly owned by
the D1 and D2. In gist, the plaintiff had appointed D3 as its property manager,
D stepped in as a ‘white knight’ to revive the said project which had been
abandoned for about 12 years.
[9] Pursuant to the AA, the plaintiff on 1 February 2009 transferred the
I 128 lots on part of the said land to D3. As part of the promise, D3 should pay
RM100,000 to the plaintiff upon transfer of the 128 lots to D3 and to pay the
balance upon completion of the said project. However, D3 alleged that it only
received the sum of RM65,000 under the AA and later a further RM1,000
under the PMT from the plaintiff.
202 Malayan Law Journal [2022] 2 MLJ
[10] D3 failed to complete the whole of the said Project at any time. Upon A
request, various extensions of time were given by the plaintiff to D3. After nine
years, the 442 units of buildings in the renamed phases 1 to 5 were completed
with the certificate of fitness for occupation issued by the local authority
between 2009 and 2016. However, the 532 units of buildings referred to in
Item D of the First Schedule to the PMA that were yet to be sold and built were B
never commenced at all by D3. Alleging that D3 failed to honour its promise
under the PMT and the AA, the plaintiff decided to claim back the 128 lots and
had entered a private caveat on the 128 lots.
C
[11] Initially the plaintiff commenced Suit No PA-22NCVC-69–03 of 2017
(‘Suit 69’) and D3 commenced six originating summons which were on
15 March 2017 converted to a writ action and merged into Suit
No PA-22NCVC-71–03 of 2017 (‘Suit 71’). The parties thereafter merged
their claims and defences in Suit 71 into Suit 69 with the addition of D
counterclaim filed by D3.
[12] The plaintiff principally claimed for recovery of the 128 lots that was
transferred to the D3 pursuant to the PMA and the AA. The plaintiff ’s
grounded its claimed based on the reason that the 128 lots were transferred to E
D3 as security for the performance of the agreements between them. D3
resisted the plaintiff ’s claim on the basis that the plaintiff had accepted D3
performance of the contract and that the 128 lots had been transferred to D3
as consideration and not security. In the counterclaim, D3 seek to set aside the
private caveats lodge by the plaintiff on the 128 lots and to seek damages for the F
loss suffered consequents to the lodging of the said caveats.
[13] The trial of both Suit 69 and Suit 71 took six days in two tranches, to
wit, on 7–9 August 2018 for the first tranche and 14–15 March 2019 as well as G
25 April 2019 for the second tranche. This was done because, after the
conclusion of the first tranche of the trial, the learned High Court judge
(‘HCJ’) concerned that there was no evidence led by the parties on unjust
enrichment if part of the land as sought is ordered to be returned to the plaintiff
or retained by D3. Hence, on 9 November 2018, the trial was by consent H
ordered to be re-opened and the second tranche of the trial dealt only with this
aspect of unjust enrichment.
A (b) what is the purpose of the transfer of the 128 lots by the plaintiff to D3
pursuant to the AA; and
(c) what is the consequence of the transfer of the 128 lots as a result of the
mutual termination of the PMA and the AA before their entire
completion?
B
[15] On the first issue, the learned HCJ concluded that the proper parties to
the contract are the plaintiff and D3.
C [16] For the second issue, the learned HCJ found and held that upon reading
of both recital G and cl 2.4 of the AA read together with the PMA, it is plainly
expressed that the 128 lots were transferred by the plaintiff to D3 as
consideration. It is also expressed as for security not for the plaintiff, but for D3
in consideration of redeeming the reduce amount of RM800,000 loan then
D owing by MTP to the bridging financier as well as to pay the plaintiff the
consideration sum of RM500,000. In other words, the 128 lots were not
transferred as security to D3 to ensure that the D3 completed the said project
in its entirety as envisaged in the PMT and the AA, as asserted by the plaintiff.
The learned HCJ further found and held that on an objective construction of
E the AA, the arrears in quit rent in respect of the 128 lots must be borne by D3
as the new registered proprietor, not the plaintiff.
[17] As to the third issue, the learned HCJ found and held that based on the
conduct of the parties, the agreement between the plaintiff and D3 had been
F mutually terminated and that the loss lies where it falls. As to D3’s claimed that
it had incurred about RM18,225,571.16 to execute the reduced scope of the
PMA and AA, it has been challenged by the plaintiff as being excessive and
mixed up with expenditures unconnected with the said project. D3 in
undertaking the said project had also benefitted from the balance purchase
G price payment of the sold units amounted to RM8,898,806.08. The present
value of the 128 lots is RM16,420,000. They add up to RM25,318,806.08.
Mathematically as it stands, D3 hence stood to gain a profit of about 28%
without completing its originally undertaken obligation under the PMA and
AA. D3 had aiso not paid the balance of RM435,000 to the plaintiff as
H envisaged in the AA. Furthermore, the value of the undeveloped lots had
probably appreciated during the prolonged period of completion of the
renamed phases 1 to 5 of the said project.
[18] In the circumstances, the learned HCJ further found and held that D3
I had unjustly benefited at the expense of the plaintiff by simply retaining the
128 lots undeveloped. Having done so, D3 has profited at least in the sum of
RM7,093,234.90 without having to assume the contractual risk of developing
the said project in entirety. Moreover, D3 is likely to gain from the sheer
appreciation in value of the 128 lots over the period of time of the prolonged
204 Malayan Law Journal [2022] 2 MLJ
completion of the other completed parts of the said project. The 128 lots may A
instead be now put for sale as empty land by the D3 without any commercial
risks at the plaintiff experience. As such, the enrichment on the part of D3’s
retention of the 128 lots is without basis and unjust unless appropriately
restituted.
B
[19] Notwithstanding the 128 lots had been lawfully transferred to D3 as
consideration, the learned HCJ finally found and held that D3 may retain the
128 lots subject to D3 paying to the plaintiff the difference between the present
value of the 128 lots and the value of the 128 lots as at 29 October 2008, that
C
is the date the AA was executed. Upon full settlement of this positive difference
in value, the plaintiff shall cause the private caveats lodged on the 128 lots to be
removed as per the prayers in paras 7(a) to (i) of the D3’s counterclaim.
THE APPEAL
D
[20] Dissatisfied with part of the learned HCJ decision, D3 filed notice of
appeal dated 16 October 2019 confined only on the issue of unjust
enrichment. Later, D3 filed a notice of motion to this court to amend the
notice of appeal. The plaintiff did not object to D3’s application. Through a E
consent order dated 17 August 2020, the notice of appeal was amended to add
D3’s appeal against the decision the learned HCJ in dismissing its
counterclaim.
[21] It should also be noted that there is no appeal or cross appeal filed by the F
plaintiff against any part of the decision of the learned HCJ. Therefore, we find
that the plaintiff is bound by the entire findings of the learned HCJ.
OUR DECISION
G
[22] The appeal filed by the appellant is very specific. The amended notice of
appeal specifically stated that:
... merayu kepada Mahkamah Rayuan terhadap sebahagian keputusan Yang Arif
tersebut yang memutuskan bahawa perayu telah mendapat keuntungan tidak
berpatutan (unjust enrichment) dan seterusnya memutuskan bahawa keuntungan H
tidak berpatutan (unjust enrichment) yang dinikmati oleh perayu adalah
penambahan nilai tanah-tanah yang terlibat antara tempoh 15.4.2019 dan
29.10.2008 dan keputusan Yang Arif tersebut yang tidak membenarkan tuntutan
balas Perayu.
Therefore, the focus of this appeal will revolve only on two issues, that are I
whether there is any unjust enrichment received by D3 at the expense of the
plaintiff out of the said project and whether D3’s counterclaim for the removal
of the private caveats filed by the plaintiff over the 128 lots together with an
order for assessment of damages in respect of the same to be allowed.
Simcity-ETE Venture Sdn Bhd v Koperasi Pembangunan
Kampung Tradisional Tasek Pulau Pinang Bhd
[2022] 2 MLJ (Che Mohd Ruzima JCA) 205
A UNJUST ENRICHMENT
The law
H [25] The case went up to the Federal Court and the first two question posted
revolve the questions of unjust enrichment. The two question are as follows:
Question 1: Whether as a matter of law if the defendant was in breach of contract
for the purchase of the land dated 19 November 2004, whether it precludes the
defendant from being awarded restitution pursuant to the doctrine of unjust
I
enrichment in respect of the defendant’s improvement and enhancement of the
land, namely by obtaining planning permission, building plan approval and
constructing at the defendant’s own cost, effort and experience, upon the land and
a shopping mall which subsequently was tenanted with an ongoing business,
goodwill and brand name thereupon without the plaintiff (compensating the
206 Malayan Law Journal [2022] 2 MLJ
defendant for having improved the ultimate market value of the land and is the A
defendant’s remedy merely confined to compensating the defendant merely for the
cost of construction of the said shopping mall?
Question 2: What is the measure of restitution for unjust enrichment, in particular,
is the measure of restitution calculated merely restricted to the cost of construction
of a building, without reference to the enhancement of the market value of the said B
land?
[26] In discussing the law of unjust enrichment, The Federal Court made
following observation and concluded that:
C
[107] We pause here for a moment to underline the significance of the law of unjust
enrichment in relation to all the rights of the parties to a contract which has been
validly terminated. The critical issue that needs to be addressed is what constitutes
unjust enrichment and undue benefit, and in what manner should a purchaser of
vacant land be granted restitutionary relief when he has constructed a building on
D
the said piece of land pursuant to and expressly permitted by a contract between
him and the vendor. In our view, the following issues are important to determine the
outcome of this appeal. Is it fair and equitable for the purchaser upon the
termination of contract to be awarded only the cost of construction of the building,
in this case the mall, or the market value of the mall?
E
[108] This is a good place to point out that remedies for contractual disputes are
generally compensatory in nature, with damages assessed based on the loss suffered
by the claimant. Restitutionary remedies, on the other hand, focus on any unjust
enrichment to a party at the claimant’s expense. It is aimed at restoring that
enrichment to the claimant. It is clear on principle and on authority that the idea of
justice behind this aim is that no one should be made richer through loss to another. F
[109] In Goff & Jones: The Law of Unjust Enrichment, para 1–08, it is stated:
Whatever may be the underlying moral justifications for the award of restitution
all these cases, the ‘unjust’ element in ‘unjust enrichment’ is simply a
‘generalisation of all the factors which the law recognises as calling for G
restitution’. In other words, unjust enrichment is not an abstract moral principle
to which the courts must refer when deciding cases, it is an organising concept
that groups decided authorities on the basis that they share a set of common
features, namely that in all of them the defendant has been enriched by the
receipt of a benefit that is gained at the claimant’s expense in circumstances that
the law deems to be unjust. The reasons why the courts have held a defendant’s H
enrichment to be unjust vary from one set of cases to another, and in this respect
the law of unjust enrichment more closely resembles the law of torts (recognising
a variety of reasons why a defendant must compensate a claimant for harm) than
it does the law of contract (embodying the single principle that expectations
engendered by binding promises must be fulfilled). I
[110] Restitution simply means that a party who has received a benefit must restore
the benefit received by him. The theoretical foundation of the right to restitution
remedy as it is understood today is that it is founded on the law of unjust
enrichment which fall outside the domains of contract and tort. The law of
Simcity-ETE Venture Sdn Bhd v Koperasi Pembangunan
Kampung Tradisional Tasek Pulau Pinang Bhd
[2022] 2 MLJ (Che Mohd Ruzima JCA) 207
A contract/tort and the law of unjust enrichment are conceptually distinct. Unjust
enrichment describes a cause of action. On the other hand, restitution describes a
remedy. Restitution as a response to wrongdoing is therefore a different topic from
restitution as a response to unjust enrichment (see: Goff & Jones on The Law of
Unjust Enrichment para 1-04). The courts have found it necessary to make available,
B independent of the law of contract and civil wrongs, for the restoration of benefits
on the grounds of unjust enrichment.
[111] As stated by Lord Wright in Fibrosa Spolka Akcyjna Appellants; and Fairbairn
Lawson Combe Barbour, Limited Respondents [1943] AC 32 at p 61:
It is clear that any civilised system of law is bound to provide remedies for cases
C
of what has been called unjust enrichment or unjust benefit, that is to prevent a
man from retaining the money of or some benefit derive from another which it
is against conscience that he should keep. Such remedies in English law are
generically different from remedies in contract or in tort, and are now recognised
to fall within a third category of the common law which has been called
D quasi-contract or restitution.
[112] Since then English law has recognised an independent law of unjust
enrichment by recognising a claim for restitution based on unjust enrichment.
According to Goff & Jones: The Law of Unjust Enrichment (see para 105), the
highest courts have now conclusively recognised that unjust enrichment is a distinct
E source of rights and obligations in English private law that ranks alongside contract
and civil wrongs in importance and accordingly calls for discrete stand-alone
treatment. This was shown in a number of cases which were cited by learned counsel
for the defendant, namely Banque Financiere De La Cité Appellants and Parc
(Battersea) Ltd and Others Respondents [1999] 1 AC 221, R (on the application of
F Rowe) v Vale of White Horse District Council [2003] EWHC 388 (Admin), Cressman
v Coys of Kensington (Sales) Ltd [2004] EWCA Civ 47; [2004] 1 WLR 2775, Chief
Constable of the Greater Manchester Police v Wigan Athletic AFC Ltd [2008] EWCA
Civ 1449; [2009] 1 WLR 1580, Sempra Metals Ltd (formerly Metallgesellschaft Ltd)
v Inland Revenue Commissioners and another [2008] 1 AC 561 and Investment Trust
Companies (in liquidation) v Commissioners for Her Majesty’s Revenue and
G Customs [2012] EWHC 458 (Ch).
...
[118] Nearer home, there is now no longer any question that unjust enrichment iaw
is a new developing area of law which is recognised by our courts. That the principle
H of unjust enrichment is the basis to justify an award of restitutionary relief can be
seen in Sediperak Sdn Bhd v Baboo Chowdhury [1999] 5 MLJ 229; [1999] 5 CLJ 31
and in Air Express International (M) Sdn Bhd v MISC Agencies Sdn Bhd [2012] 4
MLJ 59; [2012] 4 CLJ 589. Nevertheless, it has to be said that despite the increase
in judicial reference to the expression of unjust enrichment to justify an award of
I restitutionary reliefs, the law of unjust enrichment is still in its formative stage in our
jurisdiction (see article entitled ‘An Introduction to the Law of Unjust Enrichment’
[2013] 5 MLJ 1 by Alvin WL See), in our view, the time has come for this court to
recognise the law of unjust enrichment by which justice is done in a range factual
circumstances, and that the restitutionary remedy is at all times so applied to attain
justice. (Emphasis added.)
208 Malayan Law Journal [2022] 2 MLJ
[27] In consequence, the Federal Court answers to the relief questions are as A
follows:
Answer to question 1: The defendant is not precluded from being awarded
restitution pursuant to the law of unjust enrichment in respect of the defendant’s
improvement and enhancement of the land at the defendant’s own costs, effort and
experience. B
Answer to question 2: The measure of for unjust enrichment is the market value of
the mall and it is not restricted to the costs of construction of the building.
[28] Coming back to this appeal before us, it is undisputed fact that the
plaintiff had appointed D3 as its property manager and stepped in as a ‘white
knight’ to revive the said project which had been abandoned for about 12 years.
For that purpose, they voluntarily entered into the PMA dated 12 July 2007 D
and later, the AA dated 29 October 2008.
[29] Under the PMA, D3 has to pay the consideration of the sum of
RM1,000 to the plaintiff to be appointed as the project manager to rescue and
to manage the said project in whatever ways or manners deemed fit and proper E
by D3. Via a power of attorney dated on the same day as the PMA, D3 was
given full authority to act on behalf of the plaintiff to carry out the planning,
management, completion of the housing units and infrastructure of the said
project. At its own cost, D3 was required to complete the abandoned housing
units which had been sold and was also authorised to build and sell the unsold F
housing units and entitled to all monies from the sales of such unsold units in
the said project. D3 had 18 months from date of commencement which was
not later than three months from the date of the agreement to complete the said
project and entitle to an extension of time as set out in the PMA. The plaintiff
as the landowner was responsible to take all necessary steps for the discharge of G
the third party charge on the said land and in this regard settle any debts
without delay.
[30] The said project suffered a hiccup. D3 was not able to commence the
construction works as the said land was encumbered with undischarged H
bridging loan taken by D4 from two banks represented by Aseambankers.
Upon negotiations, the financiers agreed to reduce the redemption sum from
RM18m to RM800,000. The plaintiff could not raise enough fund to redeem
the said land. After negotiation, the plaintiff and D3 agreed to enter into the
AA. Inter alia, D3 agreed to bear and pay the redemption sum on behalf of the I
plaintiff to discharge the charge over the said land so that the abandoned
project can be revived and to pay additional consideration of RM500,000 to
the plaintiff. As a consideration and security to D3 in making such payments,
the plaintiff agreed to transfer the development lots of the 126 units of
Simcity-ETE Venture Sdn Bhd v Koperasi Pembangunan
Kampung Tradisional Tasek Pulau Pinang Bhd
[2022] 2 MLJ (Che Mohd Ruzima JCA) 209
A shophouses, one lot of the business complex and 1 lot of the medium cost
apartments in the said project to D3 (the 128 lots). Pursuant to the AA, the
plaintiff agreed to extend the completion date of the said project to 1 June
2011. It was also agreed that further extension of time (‘EOT’) from time to
time should be given if D3 face with difficulties from bringing financiers,
B end-financiers, purchasers, government departments, difficulties in contacting
or getting co-operation from purchasers or other problems which are not
foreseeable by D3 to which such problems will delay the revival of the said
project.
C
[31] Based on the AA, the plaintiff transferred the 128 lots to D3. The
construction works on the said project started. D3 took time to revive the said
project and after numerous EOT granted by the plaintiff, finally D3 completed
phase 5 of the said project when the certificate of practical compliance (‘CPC’)
D was issued on 16 March 2015 and the certificate of occupancy (‘CFO’) was
issued by the local authority on 9 May 2016.
E [32] Based on the undisputed facts, the learned HCJ made the following
finding:
[31] Upon my meticulous reading of both recital G and clause 2.4 of the additional
agreement read together with the Agreement, it is plainly expressed that the Lots
were transferred as consideration. It is also expressed as for security not for the
F
plaintiff, but for the third defendant in consideration of redeeming the loan then
owing by Multi Track Properties to Aseambankers (the bridging financier) as well as
to pay the plaintiff the consideration sum of RM500,000. In other words, I find and
hold that the lots were not transferred as security to the third defendant to ensure
that the third defendant completed the project in its entirety as envisaged in the
G agreement, contrary to that as asserted by the plaintiff. Hence, in principle, I find
and hold that the private lodged by the plaintiff on the lots must be removed, as it
would otherwise wrongly encumber the dealing of the lots by the third defendant as
the lawful registered proprietor. Since it was not expressly provided in the additional
agreement, I further find and hold on an objective construction of the additional
H agreement that the arrears in quit rent in respect of the transferred lots have to be
borne by the third defendant as the new registered proprietor.
[33] Of course, D3 agrees with the said finding of the learned HCJ.
However, the plaintiff did not launch any challenged against the said decision.
I What is the effect of the said finding? It clearly shows that the said 128 lots were
properly or legally transferred from the plaintiff to D3 according to the terms
and conditions of the PMA and the AA. In other words, the said 128 lots legally
belong to D3 consequence to the terms and the conditions of the contracts
entered.
210 Malayan Law Journal [2022] 2 MLJ
[34] Ironically, despite having found and held that the 128 lots were A
transferred to D3 as consideration, the learned HCJ further considered and
held that it could be unjust if the consideration does not commensurate under
such circumstances as envisaged in the contracts. At para [36] of the grounds of
judgment (‘GOJ’), the learned HCJ made the following findings:
B
That notwithstanding, the claim for compensation for breach contract is not
synonymous with restitution. They both stand on their independent footing. The
plaintiff here has also framed its case in restitution for unjust enrichment on the part of
the third defendant premised on the return of all the lots because it was transferred only
as security. It was unconscionable according to the plaintiff. I have, however, found
C
and held that the transfer of the lots was not as security but consideration based on
the agreement and additional agreement read together. Nevertheless, it could be
unjust enrichment if the consideration does not commensurate with the circumstances as
envisaged by the parties in the contract as they eventually pan out. (Emphasis added.)
D
[35] Based on the above findings, the learned HCJ referred to law of unjust
enrichment decided by the Federal Court in Dream Property’s case. Then, His
Lordship had opined and concluded that:
[41] Unjust enrichment is thus in my opinion a flexible doctrine of justice design to
ensure that no one unconscionably benefits from a commercial transection that has E
gone awry. However, it is undoubtedly fact sensitive dependant on the prevailing
circumstances of each case. Besides Dream Property Sdn Bhd , this doctrine has been
previously applied in Sediperak Sdn Bhd v Baboo Chowdhury [1999] 5 MLJ 229 and
in Air Express International (M) Sdn Bhd v MISC Agencies Sdn Bhd [2012] 4 MLJ
59; [2012] 4 CLJ 589 as and when it was reasonable and proper. F
[42] On the facts herein, the third defendant claimed that it had incurred about
RM18,225,571.16 to execute the reduced scope of the agreement and additional
agreement. I am mindful, however, that this has been challenged by the plaintiff as
being excessive and involving expenditures unconnected with the project. On the
other side of the equation, the third defendant in undertaking the project, had also G
benefitted from the purchase price payment of units in the project, payable either by
the purchasers or their end financiers, besides also the value of the transferred kots.
The total amount received or derivable by the third defendant from the purchasers
amounted to RM8,898,806.08. The present value of the lots is RM16.42m. They
add up to RM25,318,806.08. Mathematically as it stands, the third defendant H
hence stood to gain a profit of about 28% without completing its originally
undertaken obligation under the agreement and additional agreement, in both
scope and time, as alleged by the plaintiff. The third defendant had also not paid the
balance of RM435,000 to the plaintiff as envisaged in the additional agreement.
Furthermore, the value of the undeveloped lots had probably appreciated during I
the prolonged period of completion of the renamed phases 1 to 5 of the project.
There is no specific express provision in the agreement or additional agreement that
the third defendant has the discretion not to develop the development in Item D of
the Final Schedule to the agreement as it deemed fit.
Simcity-ETE Venture Sdn Bhd v Koperasi Pembangunan
Kampung Tradisional Tasek Pulau Pinang Bhd
[2022] 2 MLJ (Che Mohd Ruzima JCA) 211
A [43] In the circumstances, I find and hold that the third defendant had unjustly
benefited at the expense of the plaintiff by simply retaining the transferred lots
undeveloped. Having done so, the third defendant has profited at least in the sum
of RM7,093,234.90 without having to assume the contractual risk of developing
the project in entirety based on the scope as originally envisaged in the agreement
B and additional agreement read together. Moreover, third defendant likely gained
from the sheer appreciation in value of the lots over the period of time of the
prolonged completion of the other completed parts of the project. These lots may
instead be now put for sale as empty land by the third defendant without any
commercial risks at the plaintiff experience. The plaintiff has lost out by not getting
what was bargained with the third defendant.
C
[44] It is plain that the purpose of the plaintiff in entering into this transaction is
that the third defendant would develop the project in its entirety, as originally laid
out in the agreement and supplemented by the additional agreement. However, it is
clear that the plaintiffs purpose has not been achieved since the project has not been
D completed in its entirety. As such, the enrichment on the part of the third
defendant’s retention of the lots is without basis and unjust unless appropriately
restituted. There was only part performance of the agreement and additional
agreement by the third defendant.
[45] Consequently, and notwithstanding the lots had been lawfully transferred to
E the third defendant as consideration, i find and hold that the third defendant may
retain the lots subject to the third defendant paying the plaintiff the difference
between the present value of the lots and the value of the lots as at 29 October 2008,
the date the additional agreement was executed.
[37] On the first matter, the Federal Court in the Dream Property’s case have
I found that it is necessary to make available the right to restitution of remedy as
a response to unjust enrichment, independent of the law of contract and torts.
In other words, claim for restitution based on unjust enrichment is a cause of
action by itself. Therefore, the cause of action must be established in the
statement of claim within a proper and specific plea. Material particulars that
212 Malayan Law Journal [2022] 2 MLJ
give effect to the alleged unjust enrichment must be provided in the pleadings. A
[38] The law on pleadings is well settled. Generally, parties are bound by
their pleadings and the court should not decide on the issue that was not
pleaded. Federal Court in the case of Anjalai Ammal & Anor v Abdul
Kareem [1969] 1 MLJ 22 had made the following observation and had opined B
that:
There is considerable authority in regard to the purpose and effect of particulars
filed pursuant to O 19 r 7A of the Rules of the Supreme Court at p 31 of Halsbury
(3rd Ed, Vol 3), the learned commentator has this to say: C
A party is bound by his pleadings unless he is allowed to amend them, and he is
therefore bound by his particulars, which are, in effect, part of the pleadings
under which they are delivered.
In Thomson v Birkley (1883) 47 LTR p 700 Watkin Williams J says: D
The object of particulars is to prevent surprise, and to limit and particularise
events in order that both parties should come to trial fully prepared for the issues.
In Spedding v Fitzpatrick (1888) 38 Ch D 410 at 413 Cotton LJ says:
The object of particulars is to enable the party asking for them to know what case E
he has to meet at the trial, and so to save unnecessary expense, and avoid allowing
parties to be taken by surprise.
In Thorp v Holdsworth (1876) Ch 637 at 639 Jessel Mr says:
The whole object of pleadings is to bring the parties to an issue, and the meaning F
of the rules of R XIX was to prevent the issue being enlarged, which would
prevent either party from knowing when the cause came on for trial, what the
real point to be discussed and decided was. In fact, the whole meaning of the
system is to narrow the parties to definite issues, and thereby to diminish expense
and delay, especially as regards the amount of testimony required on either side
G
at the hearing.
Finally, in Yorkshire Provident Life Assurance Co v Gilbert & Rivington [1895] 2 QB
114 at 152 Lindley LJ says:
What is the effect of these particulars? I take it the effect of these particulars is
this, that the issues to be tried are limited by these particulars in the first instance. H
I do not mean to say that leave cannot be obtained to add to the particulars —
of course it can; but the moment these particulars are delivered, and until some
further order is obtained for the delivery of further particulars, the effect of
delivering the particulars is to cut down the matters in question in the action to
the particulars. I
Therefore, in my opinion, the learned trial judge, in the instant case, had departed
from the strict rules of procedure, in deciding the case on an issue not raised in the
pleadings and on the assumption of a fact which the appellants were not obliged to
call evidence to rebut ...
Simcity-ETE Venture Sdn Bhd v Koperasi Pembangunan
Kampung Tradisional Tasek Pulau Pinang Bhd
[2022] 2 MLJ (Che Mohd Ruzima JCA) 213
A On the same principle of law related to the rule of pleadings, this court in the
case of Pembinaan SPK Sdn Bhd v Jalinan Waja Sdn Bhd [2014] 2 MLJ 322 has
made the following observation:
[23] In such a situation, a return to the basic governing principles and rules of
B pleadings in our system of civil litigation will be timely and appropriate. This was
also the route adopted by the learned judicial commissioner, but, with the utmost
respect, his conclusions resulted from a misapplication of these basic principles. The
law reports are replete with exhortations and reminders by judges on the need for
decisions to be grounded on the pleaded case of the litigants, whether plaintiff or
defendant. The need to comply with the rules on pleading are generally to be strictly
C enforced to avoid surprises at the trial and to narrow and define the issues of the
parties so that each will know the opposing party’s case, to prepare to meet it in
advance and to marshal the necessary evidence at trial to establish its claim and
answer the defence of the opposing party. The underlying rationale is not only to
prevent surprises as seemed to be the reasoning of the High Court, but is much more
D than just that.
[24] That classic, authoritative text on the rules of pleadings — Sir Jack Jacob & Ian
S Goidrein, Pleadings: Principles and Practice — provides four ‘objects’ Pleadings —
their dual object in summary. Pleadings serve a two-fold purpose:
E (a) first to inform each party what is the case of the opposite party which he
will have to meet before and at the trial; and
(b) secondly concurrently to appraise the court what are the issues. The
identity of the issues is crucial, not only for the purposes of trial, but aiso
for the purposes of all the pre-trial interlocutory proceedings.
F
The object of pleadings — in detail
(a) first to define with clarity and precision the issues or questions which are
in dispute between the parties and fall to be determined by the court ...
G (b) secondly to require each party to give fair and proper notice to his
opponent of the case he has to meet to enable him to frame and prepare his
own case for trial ...
(c) thirdly to inform the court what are the precise matters in issue between
the parties which alone the Court may determine, since they set the limits
H of the action which may not be extended without due amendment
properly made ... in Blay v Pollard and Morn’s Scrutton LJ said:
Cases must be decided on the issues on the record; and if it is desired to raise
other issues they must be placed on the record by amendment. In the present case
the issue on which the judge decided was raised by himself without amending
I the pleadings, and in my opinion he was not entitiled to take such a course ...
(d) fourthly to provide a brief summary of the case of each party, which is
readily available for reference, and from which the nature of the claim and
defence may be easily apprehended, and to constitute a permanent record
of the issues and questions raised in the action and decided thereon so as
214 Malayan Law Journal [2022] 2 MLJ
F
[39] Specifically, the party pursuing relief on unjust enrichment must
provide the material particulars that can shows the elements of unjust
enrichment in the pleadings. Federal Court in the case of Tenaga Nasional Bhd
v Ichi-Ban Plastic (M) Sdn Bhd and other appeals [2018] 3 MLJ 141 refuse to
answer the question framed by TNB on unjust enrichment because it was never G
pleaded. The strict approach by the Federal Court can be seen in the judgment
as follows:
[96] Coming back to the present appeals, as an alternative or in addition to the
statutory cause of action under s 38(3) of the Act for recovery for loss of revenue,
TNB is similarly entitled to legally pursue the claim based on a cause of action in H
unjust enrichment. If TNB elects to pursue relief for unjust enrichment then, as is a
matter of settled law, there must be a proper and specific plea in the statement of claim
that its cause of action is so founded. Further, material particulars that give rise to unjust
enrichment must be provided in the pleadings. In this regard, it is a well-settled legal
principle that the court should not decide on an issue that was not pleaded by the
I
parties. Parties are required to set out the factual bases of their respective cases in the
pleadings. The most important purpose of pleadings is to plead reasonable cause of
action, define the issues of fact and questions of law to be determined by the court
(see Salman bin Umar v Lembaga Pertubuhan Peladang and another appeal [2015] 6
MLJ 492). Pleadings enable both parties to know in advance the averments being
Simcity-ETE Venture Sdn Bhd v Koperasi Pembangunan
Kampung Tradisional Tasek Pulau Pinang Bhd
[2022] 2 MLJ (Che Mohd Ruzima JCA) 215
A made against them so that they will not be taken by surprise during the trial.
Tellingly, in the present appeals TNB did not plead that its cause of action was founded
on the law of unjust enrichment. Unjust benefit was not a pleaded issue. With respect,
the submission on the benefit/unjust enrichment question by learned counsel for
TNB is, therefore, misconceived. (Emphasis added.)
B
[40] Guided by the said settled principle of law, we perused the plaintiff ’s
pleadings, which include the plaintiff ’s statement of claim and the plaintiff ’s
reply to D3’s statement of defence and plaintiff ’s defence to D3’s counterclaim.
Upon reading the plaintiffs pleadings as a whole, we found that the basis of the
C plaintiff ’s claim against D3 was for the return of the 128 lots which had been
transferred to D3. The plaintiff at all material time referred the 128 lots as
security lots held by D3 on behalf of the plaintiffs to secure the performance of
the contracts. Nowhere, especially in the statement of claim did the plaintiff
plead restitution for unjust enrichment or at least lay down material facts or
D
material particulars that give rise to unjust enrichment. Besides that, the
plaintiff also did not plead that its cause of action was founded on the law of
unjust enrichment. Therefore, it is crystal clear that the issue of unjust
enrichment or unjust benefit was never pleaded by the plaintiff.
E
[41] To round off on the pleadings point, we are off the opinion that the
learned HCJ’s had erred in his finding when he found out that the plaintiff had
framed its case on restitution for unjust enrichment based on plaintiff ’s
pleadings.
F
[42] Then, on the second matter, the learned HCJ had considered and held
that it is an unjust enrichment if the consideration paid to the plaintiff under
the PMA and the AA does not commensurate the benefit obtained by D3. On
this issue, the law on the adequacy of consideration in a contract is well settle.
G Explanation 2 of s 26 of the Contracts Act 1950 clearly stated that:
An agreement to which the consent of the promisor is freely given is not void merely
because the consideration is inadequate; but the inadequacy of the consideration
may be taken into account by the court in determining the question whether the
consent of the promisor was freely given.
H
The adequacy of consideration further illustrated under Illustrations (f ) of the
same section as follows:
A agrees to sell a horse worth RM1,000 for RM10. A’s consent to the agreement was
I freely given. The agreement is a contract notwithstanding the inadequacy of the
consideration.
The general rule is, that an executory agreement, by which the plaintiff agrees to do A
something on the terms that the defendant agrees to do something else, may be
enforced, if what the plaintiff has agreed to do is ‘either for the benefit of the
defendant or to the trouble or prejudice of the plaintiff ’. If it be either, the adequacy
of the consideration is for the parties to consider at the time of making the
agreement, not for the court when it is sought to be enforced. B
House of Lords in the case of Chappell & Co Ltd v Nestle Co Ltd [1959] UKHL
1 confirmed the traditional doctrine that consideration must be sufficient but
need not be adequate and consideration also need not have economic value.
Lord Somervell of Harrow in his finding had made a simple analogy as follows: C
F
[44] Back home, this court in the case of Tan Tay Vui v MC Global Sdn
Bhd [2020] MLJU 712; [2020] 1 LNS 21 had decided that the adequacy of
consideration is never a basis to invalidate any contract. Thus, if we go back to
basic, a legally binding contract is formed when there is an offer, acceptance of
that offer, consideration and an intention to be legally bound by the terms G
agreed by the contracting parties. As for consideration, it must be sufficient but
need not be adequate. The contractual promise will only be enforced if the
person benefiting from it has provided something in return. The courts are not
concerned with the adequacy of consideration provided, but it must have some
sufficient value. A valuable consideration, in the sense of the law, may consist H
either in some right, interest, profit, or benefit accruing to the one party, or
some forbearance, detriment, loss, or responsibility, given, suffered, or
undertaken by the other. See Currie v Misa [1875] LR 10 Ex 153.
[46] At paras [43]–[44] of the GOJ, the learned HCJ had found and held
that D3 is unjustly benefited at the expense of the plaintiff by simply retaining
the 128 lots undeveloped and D3 is likely gained from the sheer appreciation
B in value of the 128 lots over the period of time of the prolonged completion of
the other completed parts of the said project. As to the purpose of the contracts,
the plaintiff had expected that D3 would develop the said project in its entirety
as originally laid out in the PMA and the AA. However, the plaintiff can’t
achieve its purpose since D3 failed to complete the said project in its entirety.
C
Therefore, it is unjust on the part of the D3’s to retain the 128 lots unless
appropriately restituted.
[47] Before going into the issue of unjust enrichment, let be reminded that
D the learned HCJ in his decision had found out that the 128 lots were
transferred to D3 as a consideration and not as a security under the PMA and
the AA. There is no appeal failed by the plaintiff against the said finding. If
means that the 128 lots were legally transferred according to the contracts
entered by the plaintiff and D3.
E
[48] Federal Court in Dream Property’s case had adopted ‘the absence of
basis’ approach and held that the plaintiff can escape restitutionary liability by
showing that there was a legal ground for receiving such enormously benefits.
In PJD Regency Sdn Bhd v Tribunal Tuntutan Pembeli Rumah & Anor and other
F
appeals [2021] 2 MLJ 60; [2021] 2 CLJ 441 the Federal Court rejected a plea
for unjust enrichment on the basis that liquidated ascertain damages is
statutorily provided pursuant to the sale and purchase agreement. Whereas,
Lord Sumption in the Privy Council decision in Fairfield Sentry Ltd (in
G
Liquidation) v Migani and others and other cases [2014] UKPC 9 had made
following observation:
18 The basic principle is not in dispute. The payee of money ‘cannot be said to have
been unjustly enriched if he was entitled to receive the sum paid to him’: Kleinwort
Benson Ltd v Lincoln City Council [1999] 2 AC 349 at 408B (Lord Hope) or, as
H Professor Burrows has put it in his Restatement of the English Law of Unjust Enrichment
(2012) at §3(6), ‘in general, an enrichment is not unjust if the benefit was owed to the
defendant by the claimant under a valid contractual, statutory or other legal
obligation’.Therefore, to the extent that a payment made under a mistake discharges
a contractual debt of the payee, it cannot be recovered, unless (which is not
I suggested) the mistake is such as to avoid the contract: Barclays Bank Ltd v WJ
Simms Son & Cooke (southern) Ltd and Another [1980] QB 677, 695. So far as the
payment exceeds the debt properly due, then the payer is in principle entitled to
recover the excess. (Emphasis added.)
218 Malayan Law Journal [2022] 2 MLJ
[49] Based on those authorities and the decision of the learned HCJ that the A
128 lots were transferred to D3 as a consideration under the PMA and the AA
read together, obviously D3 is contractually entitled to own the 128 lots. With
that, D3 is also entitle to develop or to sell the 128 lots and retain or to keep
whatever proceeds therefrom. In other words, D3 had received the 128 lots
under a valid contractual transaction and therefore, no element of unjust B
enrichment can arise from that transaction.
[51] Next, the learned HCJ also found and held that D3 failed to develop the
said project in entirety which is against the purpose of the contracts and the
expectation of the plaintiff. On this issue, we have to look at the entire evidence E
including the contemporaneous document involve. The law on documented
evidence is clear. Where documents formed part of the same transaction, they
should be read together. See: this court decision in the case of Glamour Green
Sdn Bhd v Ambank Bhd & Ors and another appeal [2006] MLJU 649; [2007] 3
CLJ 413 and High Court decision in the case of Mohamed Isa & Ors v Abdul F
Karim & Ors [1970] 2 MLJ 165.
[52] No doubt that the most relevant document to look at should be the
PMA and the AA. Looking at both contract document in entirety, D3 is
G
responsible to complete the development of the said project and the said
project refer to the whole project known as ‘Taman Pekatra Indah’. It is
undisputed fact that as the said project progress, D3 had faced a few obstacles
and problems to construct and to complete the said project which needed
plaintiff ’s assistance in term of granting EOT. This can be seen from the series H
of correspondences exchange between D3 and the plaintiff.
A Tuan
Perjanjian Pengurusan Projek Tambahan bertarikh 29.10.2008
Dengan segala hormatnya kami merujuk kepada surat tuan bertarikh 9.5.2012
mengenai perkara di atas dan kami mewakili “Koperasi Pembangunan Kampung
B Tradisional Tasek Berhad (selepas ini dirujuk sebagai “klien kami”).
2. Dimaklumkan bahawa anak quam kami bersetuju dengan isi kandungan surat tuan
bertarikh 9.5.2012 vang dikemukakan melalui kami.
3. Oleh yang demikian, sila tuan uruskan supaya klien tuan memulangkan semua
hakmilik bagi 321 unit banglo yang berkenaan kepada pejabat kami dengan kadar
C yang segera. (Rujuk para 3 surat tuan bertarikh 9.5.2012).
Sekian, terima kasih,
Yang benar,
Zulhaimi & Co
D
(Emphasis added.)
[54] From the said correspondences, it is clear that the plaintiff is asking for
the returned of the 321 bungalow lots and 336 low-cost units from D3 as a
E consideration for the EOT. D3 agreed to the plaintiff ’s request subject to a few
conditions which was later agreed by the plaintiff. The relevant condition was
at para 5 of D3’s letter dated 9 May 2012. D3 in agreeing to return the
bungalow lots and the low-cost units to the plaintiff had demanded that it will
no longer be bound by the obligation as set out in cl 2, 5 (a), (b), (c) of the
F PMA. Furthermore, D3 had requested that the contents of the said letter dated
9 May 2012 will be taken as addition to the contracts entered between the
plaintiff and D3. Without hesitation, the plaintiff agrees to D3’s request in
toto.
G
[55] Obviously, the plaintiff ’s acceptance to D3’s request through the letter
dated 21 June 2012 had amended or modified the terms and conditions of the
PMA. For easy reference, cl 2, 5 (a), (b), (c) of the PMA are as follows:
2. CONFERMENT OF FULL AUTHORITY TO THE PROJECT MANAGER
H The Landowner hereby confers upon the Project Managers full authority to act on
the Landowner’s behalf and a Power of Attorney shall be granted by the Landowner
to Project Manager to carry out its planning, management, completion of the housing
units and infrastructure for the said Project and the development of the said Land. The
Power of Attorney shall be revoked in the event the Project Manager fails to
I complete the said Project together within the stipulated completion period.
...
5. THE PROJECT MANAGER’S OBLIGATION
(a) The Project Manager hereby covenants to construct and complete the
222 Malayan Law Journal [2022] 2 MLJ
buildings, driveways, drains, electricity and water supply and water and A
sewerage lines and all other related installation in a good and workmanlike
manner and in accordance with approved plans and specifications.
(b) The Project Manager shall conform to all Provisions, Acts and any
Regulation or By-Laws for the time being in force and affecting the
housing units and will give all necessary notices to and obtain all requisite B
sanctions from the local authorities and or other authorities in respect of
the construction of the said Project.
(c) The Project Manager undertakes to complete the abandoned housing
units or buildings within eighteen (18) months from the date of work C
commenced on the project site whereby the time shall run subject to
clause 4(b) above. The Project Manager shall be entitled to an automatic
extension of time not exceeding twelve (12) months in the event the
Project Manager is unable to complete the housing units due to any force
majeure event as stated in Clause 8(a) or as a result of the failure of the
Landowner to observe any of its obligations set forth in this Agreement or D
when there is any delay which is not within the control of the Project
Manager to obtain any approval required by Majlis Perbandaran Seberang
Perai or any other authorities, any letters, appeals and forms required by
any statutory bodies or government departments related to the
development of the said Project. (Emphasis added.) E
With the modification to cl 2 and 5(a) of the PMA as agreed by the plaintiff, we
find that D3 is no longer under obligation to complete the said project in
entirety. Therefore, it is wrong for the learned HCJ to make a finding and hold F
that there is unjust on the part of the D3’s to retain the 128 lots on the reason
that D3 failed to complete the said project in entirety.
[56] Related to the same issue, the learned HCJ at para [32] of the GOJ held
that the parties by their conduct had mutually terminated the PMA and the AA G
after prolonged non-completion of the said project in its entirety as required in
the contracts. His Lordship further held that:
[33] The reduced scope of the project was not completed on 1 April 2014 but only
around 2016. The certificate of fitness of the final portion of the renamed Phase 5
was only issued on 9 May 2016. Moreover, the third defendant only paid the H
plaintiff RM66,000 pursuant to clause 1 of the agreement and clause 2.2 of the
additional agreement leaving the balance of RM435,000 unpaid thereunder.
[34] There is no documentary evidence that the parties have mutually terminated
the agreement and the additional agreement in accord and satisfaction. There is,
I
however, also no claim and cross claim for compensation in damages for breach of
contract particularly for late completion of the project. The parties here,
nevertheless, had, by their conduct, treated the agreement and the additional
agreement as discharged by the time these suits were instituted. At this point, it is
evident that the 70 units of buildings referred to in Item C phase 4 and the
Simcity-ETE Venture Sdn Bhd v Koperasi Pembangunan
Kampung Tradisional Tasek Pulau Pinang Bhd
[2022] 2 MLJ (Che Mohd Ruzima JCA) 223
A development in Item D of the First Schedule to the agreement were not even carried
out yet. Put simply, the agreement was not fully performed by the third defendant.
[35] Generally, in the absence of any specific agreed provision, the principle is that
loss lies where it falls in mutually terminated part performed contract by conduct;
see SPM Membrane Switch Sdn Bhd v Kerajaan Negeri Selangor [2016] 1 MLJ
B 464; [2016] 1 CLJ 177 at para [49]. In other words, save for claims made pursuant
to accrued rights, neither party can claim against the other. Thus, the plaintiff ’s
claim for RM435,000 allegedly based on breach of contract is unsustainable
because it was not yet due thereunder as an accrued right in the absence of
completion of the project in its entirety as provided in cl 2.2. read with cl 2.4 of the
C additional agreement.
[58] Therefore, we are off the view that the learned HCJ had erred in his
finding that the contracts had been mutually terminated by conduct of the
F parties and the principle of loss lies where it falls apply. As D3 had performed
his duties and obligations under the contracts, the plaintiff is entitled to the
consideration of RM500,000 as set out in recital (F) of the AA. It is not
disputed that D3 had paid a total sum of RM65,000 to the plaintiff to comply
with the terms set out, leaving the balance of RM435,000 unpaid to the
G plaintiff. In fact, the learned counsel for D3 had acknowledged the balance
amount as stated in para 55 of her written submission. Even though the learned
counsel for D3 had submitted that the balance amount should deduct the quit
rent paid by D3 on behalf of the plaintiff, the learned HCJ had decided that the
quit rent should be borne by D3 as the new owner of the 128 lots. Therefore,
H
the learned HCJ should have allowed the whole balance amount owed to the
plaintiff as prayed in subpara 23(iii) statement of claim.
COUNTERCLAIM
I
[59] Next, we move to the second issue raised in D3’s appeal, that is on the
counterclaim. This second issue consist of two parts. First, the removal of the
caveats lodged by the plaintiff on the 128 lots and secondly, the damages for
wrongful entry of caveats to be paid by the plaintiff to D3.
224 Malayan Law Journal [2022] 2 MLJ
[60] On the first part, even though the learned HCJ had decided that the A
128 lots were legally transferred to D3 under the contracts and the private
caveats lodged wrongfully encumbered the 128 lots, His Lordship instead of
ordering the private caveats to be removed as prayed for by D3 its counterclaim
had otherwise ordered that the caveats to remain pending D3 paying the
judgment sum on unjust enrichment once it is ascertained. B
[61] The law on caveatable interest is well settle. Federal Court in the case of
Score Options Sdn Bhd v Mexaland Development Sdn Bhd [2012] 6 MLJ 475
had held that: C
[35] It is our considered view, therefore, that based on the provisions of the NLC
and the authorities cited above, the only parties who are authorised to lodge a
private caveat are those who may effect dealings in the particular interests in the
land. Those parties may either have a claim to the title to the land or a claim to a
registrable interest in the land or a claim to any right to such title or registrable D
interest.
[36] Emphasis should be given to the words ‘registrable interest’ in s 323(1)(a) of
the NLC. To be caveatable, the interest must be an interest in the land and that
interest must be capable of registration. In short, it must represent a transaction that
can ultimately lead to its registration on the register. E
[62] It is clear that, after the 128 lots being legally transferred to D3, the
plaintiff has no longer registrable interest on those lands. Even if the learned
HCJ is correct in his decision on the issue on unjust enrichment, the plaintiff ’s
right is only confine to the monetary interest or a right in personam against D3 F
and that right did not create any caveatable interest on the 128 lots. Therefore,
those caveats entered by the plaintiff should be removed in limine.
[63] For the second part, D3 in the memorandum of appeal gave one liner G
ground of appeal as can be seen at para 20 as follows:
20. The learned Judge had erred in law and in fact in failing to allow the Appellant’s
counterclaim.
In the pleadings, D3 did not plead any facts as to the losses suffered due to
caveats entered. In the statement of defence, the only relevant pleaded fact is at H
para 18 as follows:
18. Kaveat yang dimasukkan oleh Plaintif tersebut telah menyebabkan kebenaran
merancang atas tanah tersebut tidak dapat diluluskan oleh Majlis Perbandaran
Seberang Perai atas status kaveat tersebut.
I
In the counterclaim, D3 repeat and adopt the facts in the statement of defence
without stating any further facts as to the losses suffered as a result of the
wrongful entry of the caveats. As to the relief or remedy sought, D3 prayed at
subpara 7(j) of the counterclaim as follows:
Simcity-ETE Venture Sdn Bhd v Koperasi Pembangunan
Kampung Tradisional Tasek Pulau Pinang Bhd
[2022] 2 MLJ (Che Mohd Ruzima JCA) 225
A j) bahawa ganti rugi dibayar oleh plaintif kepada D3 Simcity-ETE untuk kerugian
yang dialami oleh D3 Simcity-ETE akibat kemasukan kaveat yang tidak sah ke atas
128 lot tersebut;
There is also no prayer in the counterclaim that D3 is seeking for the relief on
B general damages and that damages to be assessed by the court.
CONCLUSION
[66] Based on the reason adumbrated above, we unanimously find and held
G that there are merits in the D3 appeal which warrant appellate intervention.
We allow D3’s appeal in part and also make a further order which ought to be
given by the learned HCJ to the plaintiff based on the evidence tendered and
more so agreed by D3.
H [67] As to the issue of unjust enrichment, we find that the matter was not
properly pleaded by the plaintiff and since the learned HCJ had decided that
the transfer of the 128 lots to D3 were for consideration under the PMA and
the AA read together, there should be no element of unjust enrichment arise.
We find that the learned HCJ had misdirected himself as to the law and the
I facts, had failed to appreciate or to evaluate the evidence, had misunderstood
the relevant evidence and had failed to consider relevant evidence in arriving at
his decision on unjust enrichment issue. Therefore, we allowed D3’s appeal on
this issue and set aside the learned HCJ decision.
226 Malayan Law Journal [2022] 2 MLJ
[68] As to the counterclaim, we allow D3’s appeal in part. For the first part, A
we allow the D3’s appeal and set aside the learned HCJ decision to retained all
the caveats entered by the plaintiff pending D3’s payment of the judgment sum
on unjust enrichment. For the second part, we find that the losses due to the
wrongful entry of caveats were not properly pleaded and the damages incur
were not proved. We dismiss D3’s appeal on the damages and there is no just B
cause for us to make any order for assessment of damages before the High
Court.
[69] Next, based on the specific facts of the case, our finding at para [58]
above and pleaded relief as prayed in subpara 23(iii) statement of claim, we are C
of the opinion that we should exercise our discretionary powers under
sub-s 64(4) and (5) of the Courts of Judicature Act 1964 (the CJA 1964) and
sub-r 7(4) and (5) of the Rules of the Court of Appeal 1994, PU(A) 524/1994.
For easy reference, we produce the law and the rule which had a same provision
as follows: D
(4) The Court of Appeal may draw inferences of fact, and give any judgment, and
make any order which ought to have been given or made, and make such further or other
orders as the case requires.
(5) The powers aforesaid may be exercised not with standing that the notice of
E
appeal relates only to part of the decision, and the powers may also be exercised in
favour of all or any of the respondents or parties although the respondents or parties have
not appealed from or complained of the decision. (Emphasis added.)
The fact is that, D3 had performed its obligation under the contracts.
Therefore, the learned HCJ ought to have given an order to D3 to pay the F
balance consideration as stipulated under the contracts. It is not fair for D3 to
keep the 128 Lots without paying the agreed consideration to the plaintiff. For
the sake of justice, the consideration should be paid to the plaintiff even though
the plaintiff failed to file any appeal or cross appeal against the learned HCJ’s
decision. By using the power under sub-s 64(5) of the CJA 1964, we order that G
D3 to pay RM435,000 unpaid consideration to the plaintiff together with the
interest at the rate of 5%pa from the date D3 completed the development of
phase 5, that is when CPC was issued on 16 March 2015.
[70] Finally, on cost of this appeal, we are of considered view that there H
should be no order as to cost based on the peculiar facts of the case. Each party
had to bear their own cost.