The construction project for the WVSU College of Law faced delays due to heavy rain, resulting in saturated site conditions and halted activities. Key issues include the need for timely delivery of MEPF materials, formworks, and manpower, as well as the transfer of rebars for ongoing work. Recommendations include fast-tracking embankment work and ensuring site supervision to mitigate further delays.

Uploaded by

God
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views1 page

Wvsu-Bldg 1 I&c Daily - 11

The construction project for the WVSU College of Law faced delays due to heavy rain, resulting in saturated site conditions and halted activities. Key issues include the need for timely delivery of MEPF materials, formworks, and manpower, as well as the transfer of rebars for ongoing work. Recommendations include fast-tracking embankment work and ensuring site supervision to mitigate further delays.

Uploaded by

God
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Project : CONSTRUCTION OF WVSU COLLEGE OF LAW PACKAGE 2, ID# 24GO0042

Location: WVSU MAIN CAMPUS, LUNA ST., LAPAZ, ILOILO CITY


Date: JULY 25, 2025 - FRIDAY

Direct Manpower:
BIGPAT-BCC Admin - 24, Subcon - 9
MARGAR-MCS 0
No. ACTIVITIES:
1 BCC - No activities due to Heavy Rain

2 MCS - Saturated site

No. ISSUES/CONCERNS ACTIONS TAKEN/RECOMMENDATIONS


1 BCC- MEPF materials & MANPOWER - Must be deliver on-site specially GF & tradecon manpower should be on-
board.

2 BCC- Formworks/accessories - Formworks & accessories must be deliver 1 or 2 floors ahead to prevent
delay.
3 BCC- Stockpile of rebars - Need manpower & equipments to transfer the remaining rebars for
the completion of 2units bored pile along GL M' at Bldg 2.
- NDC issued a letter dated June 11, 2025 to transfer rebars fronting
building 2 to new staging area, to give space for the drilling/survey works
of BP by KDC.
- As per weekly coordination meeting and agreed they will transfer but as
of this moment no action taken. As per verbal communication, they will
rent dumptruck of skyconnect to transfer the said rebars.
4 BCC- RFA/RFI for CSA & MEPF - Submission of RFA/RFI lead time is 1 month for
review/comments/approval of designer.
- To prevent delays on purchase, delivery & execution of work.
- Submit physical sample (attached on sample board if possible) before
purchasing on all MEPF materials for DPWH reference and approval.

5 MCS - Embankment - Need to fast track embankment work due to unpredictable rain at site.
- Should coordinate always at site for access prior to schedule of
embankment due to on-going works of BP at Bldg. 2.

6 MCS - Supervisor at site - Should always be present at site.

7 Zone 1 & 2 - Embankment, compaction by layer as per DPWH standard procedure.


- MCS should prepare stockpile materials for embankment & gravel fill.
- MCS- prepare additional manpower, compaction equipments & for
spreading of embankment/gravel fill at Zone 1.

8 Heavy rain causes saturated site - Scope of works affected:


1. Embankment materials
2. Hauiling of embankment materials
3. Compaction of embankment
4. Access road at site
5. Schedule of FDT for embankmet at zone 2 was cancelled