Bucket List For Data Center S Design

The document outlines key considerations and a bucket list for designing data centers in the context of digital transformation. It emphasizes the importance of aligning data center services with business needs, assessing risks, and ensuring resiliency and agility in design. Additionally, it provides a flowchart for the design stages and highlights the necessity of adhering to various standards and classifications in the industry.

Uploaded by

balu_2001
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views33 pages

Bucket List For Data Center S Design

The document outlines key considerations and a bucket list for designing data centers in the context of digital transformation. It emphasizes the importance of aligning data center services with business needs, assessing risks, and ensuring resiliency and agility in design. Additionally, it provides a flowchart for the design stages and highlights the necessity of adhering to various standards and classifications in the industry.

Uploaded by

balu_2001
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 33

Bucket List for Data Center´s Design

Roberto Sánchez, PE, RCDD, Acx


PlaneRS consulting México
AGENDA
• Digital Transformation in Society & Business?
• Technology is Triggering Digital Transformation (DT)
• What does Data Centre´s Designer envisioning?
• Flowchart (proposal) for DC´s designing
• Bucket list
Digital Transformation in Society & Business
• Millenials & Gen. “Z” values, immediate response
• Smartphone devices global ubiquity
• Climate change environmental awarness
• CSR responsibility awareness
• Use instead of property (automobile, house, equipment,….)
• User “experience” QUALITY immediate solutions
Among several others
Digital Transformation in Society & Business
• What does it mean for business?

ADAPT OR DIE
TECHNOLOGY IS
TRIGGERING
DIGITAL
TRANSFORMATION (DT)
In Society & Business
But DT is not a –only- about Technology!
So what will happen in Data Centers in 2025+ ?

What must a Data Center´s Designer forsee?


What must a Data Center´s Designer forsee?

Data Center makes business´ money

DCs´ services must be aligned to organization´s business


What must a Data Center´s Designer forsee?

• Risk
• Resiliency – Availability (uptime 8760hs per year)
• Agility – Performance (adaptative to organization´s needs)
• Cost (CapEx vs. OpEx)
Which are Data Center´s Designer considerations?

• Think Big
– Best solution
– Revaluate technology always
– Outsource what you can
Which are Data Center´s Designer considerations?

• Start Small
– Opportunity cost vs. Business expansión
– Divide spaces
– Pay as you Grow
Which are Data Center´s Designer considerations?

• Move Fast
– Understand your customer´s business & needs
– Assess technology trends
– Identify core services & gaps
– Improve each time
Which are Data Center´s Designer considerations?

• Flexibility
• Agility
• Cost
• Scale
Project´s Life Time Cycle
Conceptual Basic Development Purchasing Construction System Hand over Refurbish Final
Pre Disign Design Design Testing Operation & Reconstruction Disposal
Project’s (Construction Maintenance
inception Documents)
inital OPRs (PSO)
(DB) (DD) (P) (C) (OOM) (RRA) (DF)
(PDC)

DC´s Building Construction Construction

Project´s
Design Basic Design Construction Supplier´s Project´s Testing, Operation Documents Documents
Book Documents Information Construction Adjusting Manual Refurbish, Final
1.OPRs (Proyecto Book LOG Balancing Maintenance Reconstructión Disposal
Owner´s Project Ejecutivo)

Lifetime
2. BoD Book Training
Requirements Bases of Design 1.BID 1.Supervisio 1.Pre (Bldg as system)
1. Submittals • development 2.Cross- functional
2.Approved to • process
purchase functional (per system)
2.Contracts´

Stages
3.Approved to
terms
3.Laser 3D 2. Functional
Construct docs. (full Bldg.)
3. Reception-
test-approval

Commissioning services (Checking, Reporting) to OWNER


15

Project´s Management CONSULTING services


(Planning & Programming, WBS, Control: finances, monitoring, MACs, Quality,) 15
AHJ ARChitecture
OpeMan
AUTOmation

Consultants
COOLing
Owner
ENErgy
DESIGN
TEAM
ICT

SAFEty
PM CONSTRUCTION
TEAM
SECurity

CxA

DC´s Project´s Vendors


iNCUMBENTS´ colaboration
Flowchart for DC´s Design Stage
Project
Initiates

CONCEPTUAL
DESIGN
Common incumbents for DC´s Project
(PRE-DESIGN)
Stage  Owner
 Project management
DESIGNER´s COMMITMENT

BASIC DESIGN
Stage
 Commisioning Agent
DEVELOPMENT
 Consultants (legal, financial,
DESIGN
Stage  AHJ´s
 Designing Team (specialized designers)
PROCUREMENT
Stage  General Contractor & Subcontractors
 Manufactures & Vendors
CONSTRUCTION
Stage

DELIVERY –
HANDOVER-
OCCUPANCY
Stage
Flowchart for DC´s Design Stage
CONCEPTUAL Conceptual Design Stage
(Pre - DESIGN)
STAGE

DESIGN TEAM (DT)


INTEGRATION

NO

PROJECT OWNER´s
Bases of Design
REQUIREMENTS (OPRs), all Feasibility studies & initial
development BoD
information available Design planning (systems
Per system Vs OPRs
revision definition)
(DT & PM & CxA)

YES

NO
DEVELOPMENT
OWNER DT & PM & CxA
CONCEPTUAL DESIGN
ACCEPTS INFORMATION REVISION
INFORMATION

YES

B
(B)
Basic Design
Flowchart for DC´s Design Stage
Basic Design Stage
Stage

Design Team (DT)


develops Bases of
Design (BoD)
Document
per system

OPRs & BoD


to update

NO GO

DT define: Operational DT set equipments,


PM & CxA DT set pre-functional DT calculate the basic PM & CxA
secuences, general specs materials, tools training Revise
Check if BoD fulfill . tests and initial Check cost per solution Basic De sign
for each design
OPRs per system in compliance lists per alternative alternative Information
alternative
with OPRs
NO YES
GO
Basic De sign
Docume nt
Information
UpDate

C
Flowchart for DC´s Design Stage
C
Development
Development Design Stage
Design
Stage

DT elaborates per system:


DT, PM & CxA identify
narrative, operational Test models: (2D,3D) like DT se t technical submittals
longer delivery time PM & CxA Bill Of Materials &
se cuences, calculation, CFD, confirm best solutuin per system to fulfill all OPRs
chart, block & single line alternative & BoD
(e quipme nts/compone nts) approval
YES equipments Update
Pe r system
diagrams, models (2D & 3D)

NO

NO
DT develops
DT Confirms KPIs, set All digital & physical
construction/installation DT quote the integral &
pre-functional and DT defines training and information is set in the PM & CxA
work breakdown detailed project´s costs
functional testing SLAs requirements deliverable documentation Approval
structure (WBS), defines to get the initial budget (Constr uction Docu ments)
procedures & check lists
schedule of activities
YES

Development Design
Information deliverable
(Construction
Documents) UpDate

D
D
Procurement
&
Construction
Documents
Double check
Flowchart for DC´s project
Construction

Contractors &
Procurement & Construction Stage
Administrative:
Contracts, performance Subcontractors
bond, insurance, (security,, activities,
Administration)

Administrative: POs, Site´s Industrial


Advance payments
Security & Safety
(curses, risk
analysis,...)
Logistics Follow up
(importation, receiving NO GO
Solving equipments, manouvers,
Issues storage,…)
Components &
Spaces, pathways Cabling &
DC´s Contruction equopment Inspection
Construction/ connecting Hdw
plan & programm deployment per Start Up
installation Installation
Equipments are
System Cx
NO IMPORTED? GO
YES
NO GO
Project´s on site Prefunctional
Delivery - Reception - Testing
Acceptance

Materials & GO
equipments NO GO ICT equipment
Delivery –
Reception deployment
Functinal Reception -
Storage & Building
Testing Acceptance
Administration Operational
(manouvers, storage, (DRA)
inventory, testing)
Manual

GO

E
Flowchart for DC´s project
(E)
Occupancy
Hand over & Ocuppancy Stage
Operation
Mantenance

Final Testing DCs as a


Final testing results
System
revision by PM, CxA, Warranties delivery
(Owner, PM, DT CxA,
DT, Contractors &Sub
Contractor & Sub),

Event Log UpDate PM, CxA, DT, Contractors


& Sub issues solutions

Lessons Learned
Workshop

ACCEPTANCE
D-R-A process
Final stage

Project Closing
General Designer´s bucket list

• OWNER´s Project Requirements


– Business alignment (industry, market,..)
– DC´s Type (Colo-Host-Cloud-Enterprise-Edge; public, private,…)
– Site location (Risk Analysis -climate, natural/human risks-)
– Legal (local/state´s Laws, Permits, national Standards)
– Operational (3870hs?, business impact, availability) see BICSI 002
– Day ONE (in operation)
General Designer´s bucket list

• Risk
– Risk assestment
– Business applications priority
– Industry / business Compliance (HIPAA,SOX,PCI…)
• Business Impact
– Local , Regional, National, Global
• Availability
– Uptime 8760hs per year,
– Downtime –planned / unplanned-
General Designer´s bucket list

• Designing team members


– Experience
– Updated knowledge
– Credentials (RCDD, DCDC, ATD,….)

• Resiliency – Availability
– Uptime 8760hs per year,
– Downtime –planned / unplanned-

• Agility – Performance
General Designer´s bucket list
• Decide which Standard to follow
+ International: ISO/TS 22237 Data Centers https://www.iso.org/
ISO/IEC 11801-5 Generic cabling for customer premises — Part 5: Data centres
+ Japón: JDDC FS https://www.jdcc.or.jp
+ Singapur: SS 564 Green Data Centres https://www.nccs.gov.sg/public-consultation/overview
+ México: NMX - J - C - I - 489 High Performance Data Centres https://www.onncce.org.mx
+ USA
*ANSI/TIA 942B Data Center Cabling Standard https://tiaonline.org/press-release
*ANSI/BICSI 002 Data Center Design and Implementation Best Practices https://www.bicsi.org/standards
*ANSI/ASHRAE Standard 90.4-2016, Energy Standard for Data Centers
*NFPA 75 Standard for the Fire Protection of Information Technology Equipment
General Designer´s bucket list
• Decide Classification –better than Certification- programs
WARNING: “certification” could be a legal concept in different countries
+ (GLOBAL) CEEDA (Data Center Dynamics/BCS)
+ (Europe) BREEAM
+ (Australia) NABER
+ (Japan) CASBEE
+ (México) NMX (ANCE-ONNCE_NYCE)
+ (USA) ENERGY STAR Score for Data Centers
+ (USA) LEED (USGBC)
+ (USA) TIA (EPI)
+ (USA) Uptime Institute (UTI)
General Designer´s bucket list

• Time
 Design Stages
• Conceptual – Basic – Development
• Modelling (CFD, BIM,…)
 Construction
• Equipment longest period delivery
• Building facility
• Testing (pre-functional & functional
General Designer´s bucket list
 Designing
• Commissioning (Cx) & Project Management
 Colaboration & coordination
 Conceptual – Basic – Development
 RFI & Submittals
• Technology
 Revision & Evaluation
 Calculation, Specifications
 Choosing best solution alternatives
 Documentation
General Designer´s bucket list
• Digital Plataform
 Modelling (2D & 3D)
• CFD, BIM
• Conceptual – Basic – Development
• Submittals approval
• Construction
 Meetings on site
 RFIs & Submittals (revisión & answering)
 MACs (evaluation, calculation, definitions)
 Witness Testing procedures (pre-functional & functional)
General Designer´s bucket list

• Hand Over & Occupancy Stage


 Delivery – Reception – Acceptance
 Last revisión AS BUILT documentation (as required by PM & CxA)
 Sign Acceptance document (if is included in Design´s services SOW)
GRACIAS !

QUESTIONS?