Commercial Court Us 34 Petition UOI vs. Ms Jyoti Enterprises
Commercial Court Us 34 Petition UOI vs. Ms Jyoti Enterprises
PRESIDING OFFICER
COMMERCIAL COURT, GAUTAM BUDDH NAGAR
1. That the petitioner is filing instant objection Petition Under Section 34 of the
Arbitration and Conciliation Act 1996 being aggrieved of the AWARD
DATED 28.09.2024passed by Ld. Sole Arbitrator Sh. Niranjan Kumar Sinha
in ARB case no. NKS/ARB/JE-CPWD/22.Copy of the award is annexed
herewith as Annexure No.-1 to this arbitration application.
5. That for the aforesaid work, the agreement was executed between the
parties, wherein various terms and conditions, which were relevant for the
purpose of deciding the present dispute before this Hon’ble Court, have been
mentioned. Clause 25 says about the settlement of dispute and arbitration. A
copy of agreement, which is very material for the purposes of deciding and
for setting aside the arbitral award is annexed herewith as Annexure No.-2
to this arbitration application.
6. That it is pertinent to mention here that first time application was filed by the
respondent for appointment of arbitrator on 09.09.2022and thereafter
Arbitrator, Shri Niranjan Kumar Sinha was appointed by the competent
authority of petitioner department on 29.09.2022. Arbitration proceeding
was started by the Ld. Arbitrator on 18.10.2022.
7. That the respondent contractor had submitted Statement of claims on
05.11.2022 before the Arbitrator which was received in the office of
petitioner on 03.10.2022 Copy enclosed herewith and annexed as Annexure
No.-3 wherein the respondent contractor had claimed 16 claims before the
Arbitrator as given below:
Claim No. Description of claim Claim Amount
Amount claimed as per
referred in Rs. SOC in Rs.
Claim No.1 Reimbursement of Addl.
Bank Charges incurred
for extension of Bank
2,41,218/- 2,41,218/-
Guarantee due to
prolongation of Contract
Claim No.2 Amount illegally 37,31,634/- 45,29,420/-
withheld/recovered
Claim No.3 Wrong Computation of
22,17,064/- 5,78,659/-
rates for deviated items
Claim No.4 Wrong Computation of
rates for 26,00,572/- 26,86,569/-
Extra/Substituted items
Claim No.5 Work executed & paid in
previous bill but 20,98,648/- 21,89,765/-
subsequently recovered
Claim No.6 Delay in payment of
11,68,468/- 11,68,468/-
Final bill
Claim No.7 Watch & Ward charges
for the building after 68,64,255/- 68,63,232/-
completion
Claim No.8 Reimbursement the up to
date already made GST 36,24,758/- 30,95,879/-
on payment
Claim No.9 Reimbursement under
85,84,496 69,85,776/-
clause 10C & 10CA
Claim Reimbursement under
No.10 clause 10C on work done 3,29,427/- 1,33,031/-
but not paid.
Claim Damages towards
No.11 Additional overheads due
38,47,804/-
to prolongation of 38,47,804/-
contract.
Claim Damages towards idling / 10,26,000/- 10,26,000/-
No.12 diminution in
productivity of
machineries & T & P due
to prolongation
Claim Loss of Profit/
25,65,202/- 25,65,202/-
No.13 Profitability
Claim Declaration for payment
No.14 of GST for the above - -
claims in future.
Claim Ante-lite interest @
No.15 18o/o dale of due till date
of invocation of
arbitration i.e.
231712022, pendente lite - -
interest from date of
invocation of arbitration
to date of award & future
interest @ 2O%
Claim Cost of Arbitration &
20,00,000/- 20,00,000/-
No.16 legal Expenses
8. That Statement of Defense (SOD) was filed by the petitioner before Ld.
Arbitrator on 08.02.2023. Copy Statement of Defense (SOD) is annexed
herewith and as Annexure No.-4 to this arbitration application.
9. That the respondent filed rejoinder against SOD of the petitioner on dated
27.02.2023 Copy enclosed herewith and marked as Annexure No.-5 to this
arbitration application.
10.That having heard pleadings of both the parties during hearings held through
video conferencing on various dates and considering written submissions of
both the parties, the Ld. Arbitrator had published arbitral final award dated
28.09.2024which was received in office of the petitioner on 04.10.2024
respectively.
11.The Ld. Sole Arbitrator, awarded the amount as given below :
S.N Claim Claim Claim Amount Award
o. No. Amount as claimed as Amount
per per SOC in
reference Rs.
1. Claim Reimbursement of
No.1 Addl. Bank
Charges incurred
for extension of 2,41,218/- 2,41,218/- 1,71,932/-
Bank Guarantee
due to prolongation
of Contract
2. Claim Amount illegally
No.2.1 withheld/recovered 37,31,634/- 45,29,420/- 1,22,200/-
3. Claim Wrong 22,17,064/- 5,78,659/- 46,522/-
No.3 Computation of
rates for deviated
items
4. Claim Wrong
No.4 Computation of
rates for 26,00,572/- 26,86,569/-
Extra/Substituted NIL
items
5. Claim Work executed & 20,98,648/- 21,89,765/- NIL
No.5 paid in previous bill
but subsequently
recovered
6. Claim Delay in payment
11,68,468/- 11,68,468/- 1,71,231/-
No.6 of Final bill
7. Claim Watch & Ward
No.7 charges for the
68,64,255/- 68,63,232/- 9,17,643/-
building after
completion
8. Claim Reimbursement the
No.8 up to date already
36,24,758/- 30,95,879/- NIL
made GST on
payment
9. Claim Reimbursement
No.9 under clause 10C & 85,84,496 69,85,776/- 3,22,522/-
10CA
10. Claim Reimbursement
No.10 under clause 10C
3,29,427/- 1,33,031/- NIL
on work done but
not paid.
11. Claim Damages towards
No.11 Additional
overheads due to 38,47,804/- 38,47,804/- 8,36,700/-
prolongation of
contract.
12. Claim Damages towards
No.12 idling / diminution
in productivity of
10,26,000/- 10,26,000/- NIL
machineries & T &
P due to
prolongation
13. Claim Loss of Profit/
25,65,202/- 25,65,202/- NIL
No.13 Profitability
14. Claim Declaration for
No.14 payment of GST for
- - -
the above claims in
future.
15. Claim Ante-lite interest @
No.15 18o/o dale of due
till date of
invocation of
arbitration i.e.
231712022,
- - -
pendente lite
interest from date
of invocation of
arbitration to date
of award & future
interest @ 2O%
16. Claim Cost of Arbitration 2,00,000/-&
20,00,000/- 20,00,000/-
No.16 & legal Expenses 2,97,000/-
Plus GST
Total 4,08,99,546/- 3,79,11,023/- 30,85,750/-
13.That the petitioner files petition for setting aside this impugned arbitral
award published by Ld. Arbitrator in respect of Claim No. 1,3,7,11 and
interest under claim 15of the respondent under Section 34.
D. Because the Ld. Arbitrator has failed to appreciate the fact that the Ld.
Arbitrator has no discretion to exercise and has to adjudicate the disputes in
the four corners of the contract agreement.
E. Because the Ld. Arbitrator has failed to appreciate the fact that the Scope
under Section 34 has been elaborately defined in the following judgments
of the Hon’ble Supreme Court:
It has been held by the Hon’ble Supreme Court in the case of ‘Oil and
Natural Gas Corporation vs SAW pipes ltd.’2003 S.C.2629, in para no.30
inter alia held as follows:
“Hence, in our view in addition to narrower meaning given to the term
'public policy' in Renusagar's case (supra) it is required to be held that the
award could be set aside if it is patently illegal. Result would be--award
could be set aside if it is contrary to:-
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
(d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the illegality is of trivial
nature, it cannot be held that award is against the public policy. Award
could also be set aside if it is so unfair and unreasonable that it shocks the
conscience of the Court. Such award is opposed to public policy and is
required to be adjudged void.
Although the work was delayed solely due to non-mobilization of the proper
resources like submission of structural drawing, submission of labour
license, ESIC, EPFO certificates adequate machinery, materials, manpower
etc. commensurate with requirement of the work in unplanned manner and
also due to furnishing defective drawings which took a long time. Certain
defects were also notified by the Petitioner which were not make good by
the Respondent due to which Petitioner is not able to issue the completion
certificate. Hence delay was fully attributed to the Respondent but on the
basis of their earnest request and willful submission of a free consent by
Respondent on the body of application form for EOT part-I.
Petitioner showing generosity and whole heartedness, did not levied any
compensation for the delay attributed to Respondent and granted EOT
without levy of compensation under clause-2 of the contract. Therefore, this
claim again shows the fraudulent, deceitful and malicious intent of
Respondent to get undue benefit by submitting false and distorted facts to
mislead the Ld. Arbitral Tribunal.
The said clause is very specific wherein it is clearly mentioned that after
completion of work PBG will be returned without any interest.
Interest is nothing but a kind of damages. Here, the Ld. Arbitrator has
awarded the expenses incurred by the Respondent on the renewal of the BG
charged by the bank. Those expenses awarded in the form of damages are
not in consonance with the spirit of the clause. Not only this, at the time of
getting the BGs renewed till the entire currency of contract, no such
claim/letter claiming the expenses as damages was ever moved to the
Petitioner.
H. The Ld. Arbitrator has allowed bank charges @ 2% per annum on bank
guarantee extension i.e. Rs. 1,02,646/- and allowed interest @9% per
annum on the loss of interest i.e. Rs. 69,286/- and total award against this
claim is Rs. 1,71,932/- Ld. Arbitrator has failed to appreciate all the above
facts and judgments cited and argued. The impugned Award is in conflict
with basic notions of Justice as such liable to be set aside being opposed to
public policy. The Ld. arbitrator did not consider seriously the terms &
conditions of the agreement for this claim that clearly says that the
Contractor has to increase the validity of BG for extended period as per
contract. Hence, the finding of The Ld. Arbitrator is erroneous as , the
finding of Ld Arbitrator with regard to the claim no.1is absolutely erroneous
and liable to be set aside.
GROUNDS FOR CHALLENGE OF AWARD AGAINST CLAIM NO. 3.
“Certified that due to this delay in the work I have not faced any direct or
indirect loss and I undertake not to claim anything extra on this account”
From the above it is clear that time was essence of the contract which was
never refuted by the Respondent nor any objections were raised. Therefore,
time was essence of the said agreement.
The Ld. Arbitrator has allowed the claim for damages which are the subject
matter of this claim. It is revealed from the award to this claim that the ld.
arbitrator at pg. 110 of the award has mentioned that resources of the
Respondent like labor, employees, etc. remained idle, under-utilized for the
prolonged period. The ld. arbitrator has not considered the undertaking of
the Respondent on EOT proforma and at its own gave a finding that the
same was not voluntary. It is a fact that no evidence has been led by the
Respondent that this undertaking was due to financial duress or for any other
reason. A bald statement is not enough to prove that the undertaking is under
duress, coercion or financial crunches as has been dealt with by the Hon’ble
Supreme Court as has been held in the matter of Union of India Vs. Master
Construction reported in 2011 (2) ALR wherein vide para 24, the Court has
held as under:
“ In our opinion, there is no rule of the absolute kind. In a case where the
Claimant contends that a discharge voucher or no-claim certificate has
been obtained by fraud, coercion, duress or undue influence and the other
side contests the correctness thereof, the Chief Justice/his designate must
look into this aspect to find out at least, prima facie, whether or not the
dispute is bona fide and genuine. Where the dispute raised by the claimant
with regard to validity of the discharge voucher or no-claim certificate or
settlement agreement, prima facie, appears to be lacking in credibility,
there may not be necessity to refer the dispute for arbitration at all. It
cannot be overlooked that the cost of arbitration is quite huge - most of the
time, it runs in six and seven figures. It may not be proper to burden a
party, who contends that the dispute is not arbitrable on account of
discharge of contract, with huge cost of arbitration merely because plea of
fraud, coercion, duress or undue influence has been taken by the
claimant. A bald plea of fraud, coercion, duress or undue influence is not
enough and the party who sets up such plea must prima facie establish the
same by placing material before the Chief Justice/his designate. If the
Chief Justice/his designate finds some merit in the allegation of fraud,
coercion, duress or undue influence, he may decide the same or leave it to
be decided by the Arbitral Tribunal. On the other hand, if such plea is
found to be an after-thought, make-believe or lacking in credibility, the
matter must be set at rest then and there.”
Hence, the finding with respect to undertaking on EOT is against the law.
The Ld. Arbitrator has mentioned the judgment of Hon’ble Supreme Court
in the matter of Mc Dermott vs Burn Standard and other case laws that were
referred but have not been given any reasoning in not relying upon the same.
The relevant paras of McDermott case (supra) have been mentioned by the
ld. arbitrator at (xii) at pg. 105 of the award. At the same time, the judgment
of Delhi High Court in the matter of Ircon vs. DMRC. As after every
extension of time, no right was reserved by the Respondent. Hence, since the
finding for this claim is against the legal position so needs to be challenged.
The claim no. 11 is for damages only and the same have been allowed by the
ld. arbitrator on presumption not based on evidence on record & is in
violation of law, so needs to be challenged.
In view of the above, the finding of the Ld Arbitrator with regard to this
claim is erroneous and liable to be set aside.
PRAYER
In view of the above-mentioned facts and circumstances and in the interest
of justice, it is, therefore, most respectfully prayed that this Hon`ble Court
may kindly be pleased to:
This Hon’ble Court be also please to call for original arbitral record from the
I. Please to set aside the impugned Arbitral Award dated 28.09.2024 passed
by the Ld. sole Arbitrator Sh. Niranjan Kumar Sinha in the Arbitration
case between M/S JYOTI ENTERPRISES VS UNION OF INDIA.
II. Please to dismiss all the disputed claims of the Respondent /Claimant with
cost.
III. Further pass such other or further orders in favour of the petitioner and as
may be deemed appropriate in the facts and circumstances of the case.
V.K. Kaparuwan
Counsel for the Petitioner
VERIFICATION:
VERSUS
M/S JYOTI ENTERPRISES ...RESPONDENT
Affidavit of Shri Ajay Mittal (male)
aged about 36 years S/o Shri Satish
Chandra Mittal presently posted as
Executive Engineer, CPWD, Haldwani,
Nainital , Uttarakhand
I, the deponent named above hereby solemnly affirm and state on oath
as under:
1. That the deponent is duly authorized representative of the applicant
Shri Ajay Mittal
2. That the applicant filed an application before the Ld. Court alongwith
his petition. The averment made in the said application and affidavit
filed alongwith the same are true and correct and are liable to read and
understood as an integral part of this affidavit, which are not being
repeated herewith for the sake of brevity.
3. That the petition has been filed by the deponent before this Ld. Court,
seeking stay upon the effect and operations of award dated 28.09.2024
issued by the respondent before this Ld. Court, till the final
determination by the Arbitral Tribunal.
4. That the deponent has a good prima facie case in its favour and
balance of convenience also lies in favour of the deponent.
5. That no prejudice shall be caused to either of the parties in caset he
operation and effect of award dated 28.09.2024 issued by the
respondent.
6. That the arbitration application filed by the deponent is liable to be
allowed
DEPONENT
Verification:
I the above named deponents do hereby verifies that the contents
of paragraphs no. 1 to 2 are true to my knowledge , while those to
paragraphs 3 to 6 are based on legal advise and records. Nothing
material has been concealed herewith and no part of it is untrue.
SO, HELP ME GOD. Verified at Haldwani on April, 2025
………DEPONENT
BEFORE THE COURT OF LD. PRESIDING OFFICER
COMMERCIAL COURT, GAUTAM BUDDH NAGAR
1. That the full facts and circumstances of the case have been disclosed in
the accompanying Application/Petition filed U/s 34 of the Arbitration and
Conciliation Act, 1996 which shall form part of this application.
2. That the stay application is being filed on basis of the facts and grounds of
the petition and are not repeating the same for the sake of brevity and
shall be treated the averments of the stay application.
3. That it is necessary in the interest of justice that this Hon’ble court stay
the effect and operations of impugned Arbitral Award dated 28.09.2024
passed by the Ld. sole Arbitrator Sh. Niranjan Kumar Sinha in the
Arbitration case between M/S JYOTI ENTERPRISES VS UNION OF
INDIA otherwise the petitioner shall suffer irreparable loss and injury.
PRAYER
It is, therefore, Most Respectfully prayed that this court
Hon’ble stay the effect and operations of impugned Arbitral Award dated
28.09.2024 passed by the Ld. sole Arbitrator Sh. Niranjan Kumar Sinha in
the Arbitration case between M/S JYOTI ENTERPRISES VS UNION OF
INDIA otherwise the petitioner shall suffer irreparable loss and injury.
Dated: 2025
Executive Engineer-Haldwani
CPWD, Haldwani
Through its Counsel
V.K. Kaparuwan
Counsel for the Petitioner
VERIFICATION:
Verified at Haldwani this Day of April, 2025 that the contents of para no.
to of the above petition are true to my personal knowledge, no part of the
same is false and nothing material has been concealed there from, and
contents of paras to are believed to be true and correct on the
information received by me. The documents filed are true photocopies of
their respective originals/office copies.
(Ajay Mittal)
BEFORE THE COURT OF LD. ADJ/ PRESIDING OFFICER
COMMERCIAL COURT, GAUTAM BUDDH NAGAR
VERSUS
M/S JYOTI ENTERPRISES ...RESPONDENT
Affidavit of Shri Ajay Mittal(male)
aged about 36 years S/o Shri Satish
Chandra Mittalpresently posted as
Executive Engineer, CPWD, Haldwani,
Nainital , Uttarakhand
I, the deponent named above hereby solemnly affirm and state on oath
as under:
7. That the deponent is duly authorized representative of the applicant
Shri Ajay Mittal
8. That the deponent is well aware of all the facts right from the begining
9. That the petition has been filed by the deponent before this Ld. Court,
seeking stay upon the effect and operations of award dated 28.09.2024
issued by the respondent before this Ld. Court, till the final
determination by the Arbitral Tribunal.
10.That further the deponent is competent to swear and sign the present
affidavit.
11.That the deponent may also be read of part of this affidavit.
DEPONENT
Verification:
I the above named deponents do hereby verifies at Haldwani on
April, 2025
That the contents of Para no 1 to 4 are true to my knowledge and
belief.
………DEPONENT
BEFORE THE COURT OF PRESIDING OFFICER COMMERCIAL
COURT, GAUTAM BUDDH NAGAR
1. That the above Arbitration case has been filed challenging the
impugned award dated 28.09.2024 passed by Ld. Sole arbitrator in the
matter of Arbitration Case. M/s Jyoti Enterprises Vs. Union of India.
2. That against the impugned award dated 28.09.2024 earlier the
applicant/petitioner filed an Arbitration Petition before Commercial
Court/ Firstt Additional District Judge, Haldwani which was registered
on 24.12.2024 Misc. Case No. 115 of 2024” Union of India Vs. Jyoti
Enterprises.
3. That on 17.01.2025 the said Misc. Case was decided by the Ld.
Commercial Court/ Ist Additional District Judge, Haldwani whereby
returned the plaint of petitioner to file the same before the competent
court having jurisdiction. The certified copy of the order dated
17.01.2025 is being filed as Annexure No.1 to this delay condonation
application.
4. That thereafter the order dated 17.01.2025 passed in Misc. Case No.
115 of 2024 was challenged before Hon’ble High Court of Uttarakhand
at Nainital, in WPMS No. 894 of 2025 “Union of India Vs. M/s Jyoti
Enterprises”.
5. That the said writ petition was dismissed by Hon’ble High Court of
Uttarakhand at Nainital vide its judgment dated 01.04.2025 whereby
confirmed the order dated 17.01.2025 passed by Ld. Commercial Court
Haldwani in Misc. Case No. 115 of 2024, The certified copy of the
order dated 01.04.2025 is being filed as Annexure No.2 to this delay
condonation application.
6. That after the judgment passed by Hon’ble High Court of Uttarakhand
at Nainital, further legal opinion was sought from Standing Counsel,
Govt. of India who in his opinion suggested to filed the Arbitration
Case before Hon’ble court
7. That thereafter the applicant prepared the instant Arbitration Case to
file the same before Hon’ble Court challenging the impugned award
passed by Ld. Sole Arbitrator.
8. That the delay occasioned in filing the petition / Arbitration Case is not
deliberate but the same is due to the reason of legal process initiated by
the petitioner and therefore the petitioner/ applicant is entitled to get the
benefit of Sec. 14 of the Limitation Act, 1963 and delay is liable to be
condoned.
9. That there is delay of…….. days in filing the above arbitration case/
petition before Hon’ble court which is not deliberate and intentional
but the same is due to bonafide in the part of applicant / petitioner and
delay in filing above Arbitration Case/ petition is liable to be condoned.
10. That it is necessary in the interest of justice that this Hon’ble court may
graciously be pleased to allow the delay condonation application and
condone the delay of days and please to hear the Arbitration
Case/ Petition on merits, against the impugned award dated 28.09.2024
passed by Ld. Sole Arbitrator in the matter of M/s Jyoti Enterprises vs.
Union of India.
PRAYER
11. It is, therefore, Most Respectfully prayed that this Hon’ble court may
graciously be pleased to allow the delay condonation application and
condone the delay of days and please to hear the Arbitration
Case/ Petition on merits, against the impugned award dated 28.09.2024
passed by Ld. Sole Arbitrator in the matter of M/s Jyoti Enterprises vs.
Union of India., otherwise the applicant shall suffer irreparable loss and
injury.
Dated : / /2025
(V.K.Kaparuwan)
Advocate
Counsel for the Appellant
BEFORE THE COURT OF LD. PRESIDING OFFICER
COMMERCIAL COURT, GAUTAM BUDDH NAGAR
VERSUS
M/S JYOTI ENTERPRISES ...RESPONDENT
I, the deponent named above hereby solemnly affirm and state on oath
as under:
DEPONENT
Verification:
I the above named deponents do hereby verifies at Haldwani on
of April 2025
That the contents of Para no 1 to 4 are true to my knowledge and
belief.
………DEPONENT