Dewa Fundamentals Mcqs
Dewa Fundamentals Mcqs
C) To safeguard persons and property from hazards arising from the use of electricity.
B) IET (The Institution of Engineering and Technology) wiring regulations (formerly BS 7671)
3. According to DEWA regulations, what is a crucial aspect for preventing fire and shock hazards
in existing electrical installations?
B) Ensuring proper and regular operation, maintenance, and periodic inspection of the wiring
installation and equipment.
A) Every year
5. What is mandatory before making any extensions or alterations to existing electrical installations
under DEWA regulations?
6. What is the general nominal electric supply voltage provided by DEWA for single-phase
connections?
A) 110V
B) 220V
C) 240V
D) 380V
B) Having at least one electrical engineer/electrician with a valid Competency License issued by
DEWA.
B) Submitting detailed plans and drawings to DEWA for review and approval.
9. When working near underground electrical cables, what is a critical safety measure according to
DEWA guidelines?
C) Conducting trial pits by careful hand excavation to locate services before any mechanical
excavation begins.
D) Using heavy machinery for quick excavation to minimize time spent over cables.
10. If there is any doubt about the location of an underground electrical service or if a cable shown
on a GIS drawing cannot be located, what should be done?
11. What type of protection is generally required for all cable joints during ongoing work activities,
according to DEWA safety guidelines?
B) Metal cages.
D) Rubber mats.
12. What is the approximate general burial depth range for High-Voltage (HV) cables as per DEWA
guidelines?
A) 30cm - 60cm
B) 60cm - 90cm
C) 90cm - 1.2m
D) 1.5m - 2m
13. What is typically placed 30cm above the cable and 30cm above the protection tiles for HV cables
to provide a visual warning?
A) Concrete slabs
B) Warning tape
C) Sand backfill
D) Inspection covers
14. During project work in the vicinity of DEWA lines (electrical or water), what documentation
must be kept at the site at all times?
15. Regarding domestic water meters, what is a key installation requirement concerning
environmental factors?
B) They should not be installed outside or on the roof without proper protection from direct
sunlight, high temperature, humidity, condensation, and corrosion.
16. What type of valves should be installed immediately before and after the water meter to allow for
isolation?
A) Bypass valves
C) Isolation valves
D) Check valves
17. What is the minimum recommended space that should be provided between and around water
meters to permit installation, reading, servicing, and removal?
A) 5 cm
B) 10 cm
C) 20 cm
D) 50 cm
18. What is strictly prohibited regarding the installation of water pumps in relation to the water
meter, according to DEWA regulations?
19. What component is required to be fitted on the inlet side of the water meter to protect it from
solid particles and debris?
A) A flow restrictor
B) A pressure gauge
C) A strainer
20. After the installation of a water meter, what crucial step must be taken for all connections?
1. C) To safeguard persons and property from hazards arising from the use of electricity.
o Explanation: The fundamental purpose of electrical regulations worldwide, including DEWA's,
is to ensure safety and prevent accidents, fires, and damage caused by electricity.
2. B) IET (The Institution of Engineering and Technology) wiring regulations (formerly BS
7671)
o Explanation: DEWA's electrical installation regulations are largely based on or refer to the IET
Wiring Regulations (British Standards), which are widely adopted internationally.
3. B) Ensuring proper and regular operation, maintenance, and periodic inspection of the
wiring installation and equipment.
o Explanation: Continuous safety relies not just on initial installation but on ongoing care, proper
usage, and regular professional checks to identify and rectify potential issues.
4. B) Every two years
o Explanation: DEWA regulations typically stipulate periodic inspections for industrial and
commercial installations every two years to ensure continued compliance and safety.
5. B) Obtaining prior approval from DEWA.
o Explanation: Any modifications or additions to regulated installations require official approval
from DEWA to ensure they meet current standards and safety requirements.
6. B) 220V
o Explanation: The general nominal single-phase supply voltage from DEWA in Dubai is 220V
(with three-phase being 380V), at 50 Hz.
7. B) Having at least one electrical engineer/electrician with a valid Competency License
issued by DEWA.
o Explanation: DEWA requires contractors to have licensed and competent personnel to ensure
that electrical work is carried out safely and to standard.
8. B) Submitting detailed plans and drawings to DEWA for review and approval.
o Explanation: Before any electrical work commences, DEWA mandates the submission of plans
for approval to ensure compliance with regulations and to verify the proposed design.
9. C) Conducting trial pits by careful hand excavation to locate services before any
mechanical excavation begins.
o Explanation: This is the safest and most reliable method to confirm the exact location of
underground services, reducing the risk of striking cables.
10. B) Seek appropriate assistance or advice from DEWA before continuing work.
o Explanation: When uncertainty exists regarding underground services, it's critical to stop work
and consult with the authority (DEWA) to prevent hazardous incidents.
11. C) Wooden box protection.
o Explanation: Temporary wooden box protection is typically required for exposed cable joints
during work to prevent accidental damage or contact.
12. C) 90cm - 1.2m
o Explanation: High-voltage cables require deeper burial depths than low-voltage ones for
enhanced safety and protection from external factors.
13. B) Warning tape
o Explanation: Warning tape is intentionally placed above protection tiles to serve as a visual alert
during future excavations, indicating the presence of buried cables below.
14. B) Copies of NOCs (No Objection Certificates) and up-to-date GIS drawings.
o Explanation: These documents are essential on-site to verify permissions and accurately
identify the location of existing DEWA infrastructure to ensure safe working practices.
15. B) They should not be installed outside or on the roof without proper protection from
direct sunlight, high temperature, humidity, condensation, and corrosion.
o Explanation: Water meters are sensitive to environmental conditions, and proper protection
ensures their accuracy, longevity, and prevents damage.
16. C) Isolation valves
o Explanation: Isolation valves (often gate or ball valves) are necessary on both sides of the meter
to allow it to be isolated for maintenance, repair, or replacement without affecting the entire
water supply.
17. C) 20 cm
o Explanation: Adequate space around meters is crucial for technicians to perform installations,
readings, maintenance, and removal efficiently and safely.
18. B) Installing them upstream or downstream of the meter to avoid sudden variations in
flow/pressure.
o Explanation: Pumps can cause significant fluctuations in water flow and pressure that can
damage the meter or affect its accuracy; hence, direct installation near the meter is prohibited.
19. C) A strainer
o Explanation: A strainer on the inlet side prevents sediment, rust, or other debris from entering
and damaging the sensitive internal components of the water meter.
20. C) They should be thoroughly checked for leaks.
o Explanation: Leak testing is a critical final step after any water connection installation to ensure
water tightness, prevent wastage, and avoid water damage.
DEWA Regulations: Technical Standards, Materials and Workmanship - MCQs
1. According to DEWA regulations, all materials and equipment used in electrical installations
must:
C) Conform to the latest relevant British Standards (BS) or equivalent international standards
(e.g., IEC).
2. What is a primary requirement regarding the technical drawings and specifications submitted to
DEWA?
B) They must be fully detailed, accurate, and comply with DEWA's drawing submission
guidelines.
D) They are for internal contractor use only and not subject to DEWA review.
3. In terms of materials, what is strictly prohibited for electrical conduits and trunking installed in
visible areas?
C) Compliant with relevant international standards and suitable for the intended application and
environment.
5. What is a crucial standard for switchgear and control gear installed in DEWA-regulated systems?
B) They must comply with the relevant IEC (International Electrotechnical Commission)
standards.
C) They should be manufactured by the same company as the main distribution board.
B) Compliance with BS 7671 (IET Wiring Regulations) and proper bonding and equipotential
bonding.
7. For water supply materials, what is a key requirement for pipes and fittings?
B) They must be approved by DEWA and suitable for potable water, resisting corrosion and
scaling.
B) Be certified to relevant quality standards and be suitable for the working pressure.
10. What is a key consideration for materials used in outdoor electrical installations (e.g., street
lighting, external power outlets)?
11. What is the fundamental principle of workmanship expected for all installations under DEWA
regulations?
B) All work must be executed in a neat, professional, and tradesman-like manner, adhering to
approved drawings and standards.
B) Ensuring proper support, dressing, and termination of cables to prevent strain and damage.
B) Ensuring tight, secure, and properly insulated connections to prevent loose contacts and short
circuits.
14. For electrical panels and distribution boards, high-quality workmanship means:
B) Neatly wiring, clearly labeling circuits, and ensuring proper termination of all conductors.
B) Ensuring that all openings and penetrations through fire-rated elements are properly sealed
with approved fire-stopping materials.
B) Ensuring all joints are leak-free, properly supported, and that pipe runs are straight and neat.
17. When installing water fixtures (e.g., faucets, showers), what is an indicator of good
workmanship?
B) Ensuring they are securely mounted, properly sealed, and operate smoothly without leaks.
18. What is the importance of proper testing and commissioning in relation to workmanship?
B) It confirms that the installation has been executed according to technical standards and
functions as intended, validating workmanship quality.
B) All defects must be promptly and properly rectified to meet DEWA standards before final
approval.
20. What role does supervision play in ensuring high-quality workmanship on DEWA-regulated
projects?
1. What is the first step a project owner typically needs to take to initiate the DEWA approval
process for new installations?
2. Who is responsible for preparing and submitting detailed electrical and plumbing plans for
DEWA review and approval?
3. What is a crucial requirement for the plans and drawings submitted to DEWA for approval?
B) They must be fully detailed, accurate, and comply with DEWA's standards and specifications.
C) The applicant is notified, and modifications are required before resubmission and approval.
5. During the installation phase, what is essential to ensure a smooth DEWA approval process?
6. What is the purpose of periodic inspections conducted by DEWA during the installation phase?
7. Upon completion of the installation work, what is the next major application required from
DEWA?
9. What is the final stage of inspection for an installation before the Completion Certificate is
issued?
B) That all electrical and water installations have been completed according to approved plans
and DEWA's standards.
C) That all utility bills for the property have been settled.
D) That the contractor has fulfilled all contractual obligations with the owner.
11. After obtaining the Completion Certificate, what is the subsequent step related to documentation
often required by DEWA?
B) The final state of the property's electrical and water installations, including any changes made
during construction.
13. In some cases, what might DEWA conduct to verify the accuracy of As-Built drawings?
B) A site visit.
B) Carrying out certain works on premises, especially those involving DEWA's infrastructure or
services.
15. What typically needs to be settled before DEWA issues certain NOCs or clearance certificates
(e.g., for property transfer)?
17. What is a common reason for DEWA to return an application as "incomplete" or "rejected"?
18. Once all approvals are obtained and installations are complete, what is the final step before the
property can use DEWA services?
B) Connecting the installations to the DEWA grid (e.g., meter installation and supply release).
19. For projects licensed under Dubai Municipality authority, how are DEWA requests often
processed?
B) Proactively through digital integration with the Dubai Building Permit System (DBPS).
B) It ensures legal compliance, safety, and proper functioning of the property's utility systems.
3. What specific qualification and experience is typically required for an electrical engineer to be
sponsored by a DEWA-approved electrical contracting company?
4. For a contractor applying for a DEWA Electrical & DRRG Solar PV license, what is the typical
minimum supervision experience required for a sponsored engineer?
A) 1 year.
B) 2 years.
C) 4 years.
D) 6 months.
5. Which entity issues the primary Trade License required for contractors operating in Dubai?
A) Dubai Municipality.
D) DEWA itself.
6. Besides a Trade License and qualified staff, what other financial/administrative document is a
common requirement for DEWA contractor enrollment?
7. What does DEWA issue to consultants and contractors who have successfully completed the
enrollment process?
A) A certificate of merit.
8. Why does DEWA classify enrolled consultants and contractors into categories like Platinum,
Gold, Silver, and Bronze?
9. What is the purpose of the 'No Objection Letter by the company' required for DEWA
enrollment?
B) To formally request DEWA to list the company name on their website and provide contact
details.
B) To strictly adhere to approved plans, DEWA's technical standards, regulations, and safety
codes.
12. What action might DEWA take if it discovers a contractor is carrying out electrical or water
work without the necessary DEWA license or approval?
B) Impose heavy fines, issue cease and desist orders, and potentially blacklisting.
B) They are responsible for preparing and submitting all required technical drawings and
documents to DEWA for approval.
14. What is the responsibility of a licensed contractor regarding quality assurance for installations?
B) To implement robust quality assurance measures to guarantee the safety and quality of
electrical and water installations.
15. What is paramount for licensed contractors concerning safety standards on-site?
B) Adhering to all DEWA safety regulations and industry best practices to protect workers and
the public.
16. How often are licensed contractors expected to renew their DEWA licenses and certifications?
B) To conduct comprehensive testing (e.g., insulation resistance, earth fault loop impedance) and
submit accurate test reports.
19. Why is it important for licensed contractors to stay updated with the latest DEWA regulations
and technical guidelines?
20. What is the primary benefit for a property owner or developer of engaging a DEWA-licensed contractor?
B) Assurance that the installation will meet DEWA's safety and quality standards, facilitating approvals
and connections.
1. What is the paramount objective of all safety requirements within DEWA regulations?
2. What is a mandatory requirement for all personnel working on or near DEWA electrical
installations?
B) Using appropriate Personal Protective Equipment (PPE) such as safety helmets, safety shoes,
and gloves.
3. Before commencing any electrical work on an existing installation, what is the most critical
safety step?
B) Ensuring proper isolation (disconnection) and lockout/tagout (LOTO) procedures are strictly
followed.
5. When working with or near underground electrical cables, what method is crucial for locating
them safely?
C) Conducting trial pits by careful hand excavation and using cable avoidance tools (CAT).
6. What type of protection is required for exposed live electrical parts during maintenance or repair
activities?
7. What is the maximum permissible approach distance (clearance) to live DEWA High Voltage (HV)
equipment without a valid Permit-to-Work?
A) 1 meter.
C) 5 meters.
D) 10 meters.
8. In an electrical substation or plant, what is a key safety measure to prevent unauthorized access
and protect equipment?
B) Ensuring all access points are securely fenced, locked, and clearly signed.
9. What should be done immediately if an electrical accident (e.g., shock, burn) occurs on site?
B) Isolate the power supply immediately (if safe to do so), provide first aid, and seek emergency
medical attention.
B) It's a formal authorization system to control high-risk activities, ensuring all safety
precautions are in place before work starts.
11. When working in confined spaces related to water installations (e.g., manholes, underground
tanks), what is a critical safety requirement?
B) Conducting gas testing, ensuring proper ventilation, and having a trained attendant outside.
12. What is essential for personnel working around open excavations for water pipelines?
B) Ensuring proper shoring, barricading, and warning signs are in place to prevent collapses and
falls.
13. What is a key safety measure for temporary water connections or bypasses on site?
B) Ensuring they are properly supported, leak-free, and clearly marked to prevent accidents.
14. What measures should be in place to prevent falls from height during water tank or overhead
pipe installation/maintenance?
B) CO2 or Dry Chemical Powder (DCP) extinguishers suitable for electrical fires.
16. How often should safety equipment (e.g., harnesses, ladders, lifting gear) be inspected on a
DEWA-regulated project site?
B) Regularly and prior to each use to ensure it is in good working condition and certified.
17. What is the responsibility of site management regarding safety training for workers?
B) Providing regular safety training, induction, and toolbox talks to all personnel.
18. In case of a major utility incident (e.g., burst main, cable strike), what is the immediate reporting
protocol?
B) They provide safe and organized evacuation paths in case of emergencies like fire or gas
leaks.
20. What is the role of a competent person in ensuring safety on site, according to DEWA's
expectations?
B) To identify hazards, assess risks, and implement control measures to ensure a safe working
environment.
B) Supply parameters, source of supply, location relative to other installations, asset ownership,
authorized personnel contact details, and special precautions.
3. What language(s) are typically required for all labels and identification markings in DEWA-
regulated electrical installations?
A) English only.
B) Arabic only.
4. How should labels on electrical distribution boards (DBs) and circuit breakers be applied to
ensure compliance with DEWA?
B) Clearly, legibly, and durably affixed to remain visible for the lifespan of the enclosure.
5. Which circuit breaker in a consumer unit or main distribution board (MDB) must be clearly
marked and left unlocked to allow immediate operation in an emergency?
B) Warning tape and protection tiles placed above the cable at specific depths.
7. What is the significance of color identification for unarmored, armored, and flexible cable cores
and bare conductors as per DEWA regulations?
B) It helps in quickly identifying phase, neutral, and earth conductors for safety and correct
connection.
8. What kind of warning signs are typically required for installations involving 400V pedestals or
similar high-voltage points?
9. What standard do DEWA regulations often reference for general electrical installation
documentation and labeling, including PV systems?
A) ISO 9001.
B) Clearly labeling the new circuit breaker with its purpose (e.g., "Lights - Living Room").
11. What mandatory markings are required on the cover of a DEWA water meter chamber?
B) The DEWA logo and the wording 'Water Meter' in Arabic and English.
12. Besides the cover, what other identification is required on the top concrete slab of a DEWA
water meter chamber?
B) A stainless steel label engraved with 'DEWA Water Meter Chamber' and 'Legacy Account
Number & Plot number'.
13. For individual water meters within a meter room, what identification is required immediately
adjacent to the meter?
15. What is the expectation regarding labels for water pipe lines and valves in complex installations?
B) Clear labeling indicating their function, direction of flow, and areas they serve.
16. How should labels on critical equipment, such as main isolation valves for water supply, be
maintained?
B) They must be kept clean, legible, and intact, and replaced immediately if damaged or faded.
17. What is required for junction boxes installed inside a water meter chamber, especially for
communication cables?
B) They must be properly closed to maintain waterproofing and labeled with a PVC engraved
label (e.g., "JB Main Meter Chamber").
B) They must accurately reflect the actual, final installation and any modifications.
19. Why is consistent and standardized labeling across all installations crucial for DEWA?
B) It enables DEWA personnel and authorized contractors to quickly and accurately identify
components for operations, maintenance, and emergency response.
20. What might happen if installations lack proper labeling and identification as per DEWA
regulations?
High Temperatures: Cables are rated for "summer rating," implying consideration of high
ambient temperatures. DEWA urges precautionary measures for electrical appliances in summer,
emphasizing quality appliances and maintenance. Thermostat settings are recommended at 24°C
or higher for ACs.
Humidity/Condensation: Specific requirements to prevent water entry into DBs, conduits, and
junction boxes due to rainwater, groundwater, or condensation. This includes using IP65
weatherproof boxes for outdoor installations, proper sealing of conduits, U-bends on exposed
conduit ends, and avoiding direct termination of roof conduits to DBs. Anti-condensation heaters
controlled by humidistats are suggested for enclosures.
Dust Protection: While not explicitly detailed for all equipment, the use of IP-rated enclosures
implies dust protection. IP65 for outdoor installations means "totally protected against dust."
UV Radiation: Outdoor electrical and PV system components (cables, microinverters, EVSE)
must be resistant to UV rays and high temperatures.
Corrosion: Water meters shall not be installed outside or on the roof without proper protection
from corrosion. Pipes and fittings for water systems must be high quality, heavy-duty, non-toxic,
and non-corrosive material approved by DEWA. Water fittings must be immune to or protected
from corrosion by galvanic action or any other process. Non-Return Valves (NRV) in water
systems should be made of non-corrosive material, preferably Stainless Steel grade 316L. Water
meter cabinets should be manufactured with non-corrosive/GRP material.
Protection of Meters: Water meters need protection from direct sunlight, high temperature,
humidity, condensation, and corrosion. They should be installed in meter cabinets on the outside
wall for ground installations or in chambers constructed per DEWA specifications.
Site-Specifics: Clearances between MV cable trenches and heat sources are mandated.
Backfilling material for MV cables needs specific resistivity, moisture content, and compaction.
Electrical fittings in water meter rooms must be waterproof.
DEWA Regulations: Environmental Conditions - MCQs
1. What is a primary environmental factor in Dubai that DEWA regulations mandate considering
for outdoor electrical and water installations?
A) Low temperatures.
B) Frequent snowfall.
D) Volcanic activity.
2. To prevent water entry (including condensation) into electrical distribution boards (DBs) and
conduits, what is a key DEWA requirement for outdoor installations?
3. What specific feature should be incorporated on all exposed conduit-ends in roof and outdoor
locations to prevent water entry?
B) Cables are given a "summer rating" to account for reduced current carrying capacity at high
temperatures.
5. What type of protection is required for outdoor electrical equipment and cables to withstand the
intense sunlight in the region?
C) Waterproofing only.
D) Anti-static treatment.
7. What is the minimum ingress protection (IP) rating typically required by DEWA for outdoor
electrical installations?
A) IP20.
B) IP44.
C) IP55.
D) IP68.
8. For water meter rooms, what is a specific requirement concerning electrical fittings and other
items to cope with potential moisture?
B) All electrical fittings and other items in the water meter room shall be waterproof.
9. What precaution does DEWA emphasize for electrical appliances during summer to mitigate
risks due to increasing temperatures?
10. What is mandated regarding clearances between MV cable trenches and surrounding heat
sources, such as 132kV cable trenches?
11. What critical protection is required for domestic water meters installed outside or on the roof of
buildings?
B) Proper protection from direct sunlight, high temperature, humidity, condensation, and
corrosion.
C) A simple lock.
12. What material property is explicitly required for pipes and fittings used in DEWA-approved
water installations to ensure durability in the local environment?
13. To protect water meters from environmental damage, where are they typically recommended to
be installed for ground installations (e.g., villas, sheds)?
B) Constructing them with a sump pit and ensuring they are protected from environmental
elements and barricaded.
15. What material is preferably required for Non-Return Valves (NRV) in DEWA water systems,
specifically addressing corrosion resistance?
A) Galvanized iron.
B) PVC.
16. How should water meter cabinets be manufactured to withstand harsh outdoor conditions?
17. What is a key requirement for the backfilling material used for MV cables as per DEWA, related
to environmental factors?
B) Soil resistivity below 1.6°C-m/W, with maximum moisture content of 2% or less, and 90%
compaction.
19. How do DEWA guidelines for water supply regulations address the prevention of contamination
from corrosion?
20. What is a general principle for designing and installing all DEWA-regulated systems in relation
to local environmental conditions?
B) To design and select materials/equipment that are robust enough to withstand the specific
harsh climatic conditions of Dubai.
Nominal Supply Voltages: 220/380V ±10%, 50 Hz, 3-Phase, 4-Wire. For larger connections:
11kV or 33kV.
Frequency: 50 Hz.
System Type: TN-S System (separate neutral and earth throughout).1
Main Switchgear: Required at the point of entry into the consumer's premises. Must be capable
of disconnecting all live conductors. Must be provided by the consumer and be a DEWA-
approved type. Its location (easy accessibility for DEWA personnel).
Metering: DEWA installs and owns the meter. Consumers must provide a suitable space for it
(meter cabinet/room). Requirements for meter cabinet/room (ventilation, protection).
Responsibility Demarcation: The point of supply is typically the outgoing terminals of
DEWA's cut-out/circuit breaker, or the incoming terminals of the main switch.
Protection: Main switch must be rated to safely interrupt fault currents. Overcurrent and earth
fault protection.
Harmonics/Power Factor: While not explicitly detailed in the general parameters, regulations
often touch upon maintaining good power factor and limiting harmonics to prevent grid
disturbances, especially for large industrial consumers.
A) 110V
B) 220V
C) 240V
D) 400V
A) 220V
B) 380V
C) 415V
D) 690V
A) 60 Hz
B) 50 Hz
C) 40 Hz
A) ±5%
B) ±7%
C) ±10%
D) ±15%
5. Which earthing system does DEWA primarily utilize for its Low Voltage (LV) distribution
network within consumer premises?
A) TT system
B) IT system
C) TN-S system
D) TN-C system
6. For larger commercial or industrial consumers, what higher voltage supply might DEWA
provide?
A) 66kV
B) 11kV or 33kV
C) 220kV
D) 500V
7. What kind of protection should the main incoming supply be equipped with at the consumer's
premises?
A) No specific requirement.
C) Generally maintained within a specified range (e.g., above 0.9 lagging) to avoid penalties.
D) As low as possible.
9. What phenomenon relates to the distortion of the voltage or current waveform, potentially
impacting power quality, which DEWA may regulate for large consumers?
A) Voltage sag.
B) Harmonic distortion.
C) Voltage swell.
D) Frequency deviation.
10. What is the responsibility of the consumer regarding the electrical load connected to DEWA's
network?
B) To ensure the connected load does not exceed the approved DEWA connection capacity.
11. Where is the main supply intake point typically located within a consumer's premises?
B) At the point where DEWA's cables terminate and the consumer's installation begins (e.g., at
the main switch).
12. Who is responsible for installing and maintaining the main incoming electrical switchgear at the
consumer's premises?
A) DEWA.
13. What is a key requirement for the main incoming switchgear regarding its accessibility?
B) It must be easily accessible to DEWA personnel for inspection, isolation, and metering
purposes.
14. What must the main switch be capable of doing to ensure safety at the intake point?
A) The consumer.
B) The contractor.
C) DEWA.
16. What is required from the consumer regarding the location and enclosure of DEWA's electricity
meter?
B) To provide a suitable, secure, and protected space/cabinet for the meter according to DEWA
specifications.
17. What type of protection enclosure is typically required for electricity meters and main switchgear
installed outdoors?
B) Enclosures with adequate IP (Ingress Protection) rating (e.g., IP55 or higher) for
environmental conditions.
19. For multi-tenanted buildings, how does DEWA ensure individual metering and billing?
A) A single meter for the entire building is used, and costs are divided equally.
20. What document outlines the specific requirements for the design and installation of electrical
supply intake and other parameters, which contractors and consultants must follow?
1. B) 220V
o Explanation: DEWA's nominal single-phase supply voltage for residential and light commercial
use is 220V.
2. B) 380V
o Explanation: DEWA's nominal three-phase supply voltage is 380V (phase-to-phase), derived
from a 220V phase-to-neutral system.
3. B) 50 Hz
o Explanation: The standard frequency of the electricity supply in Dubai, consistent with many
parts of the world, is 50 Hertz.2
4. C) ±10%
o Explanation: DEWA typically specifies a voltage tolerance of ±10% from the nominal value,
meaning the voltage can fluctuate within this range.
5. C) TN-S system
o Explanation: The TN-S system provides a separate neutral (N) and protective earth (PE)
conductor throughout the distribution network, which is generally preferred for safety.
6. B) 11kV or 33kV
o Explanation: For larger loads requiring significant power, DEWA provides higher voltage
connections, commonly at 11 kilovolts or 33 kilovolts.
7. B) Overcurrent and earth fault protection.
o Explanation: The main incoming supply must be protected against excessive currents
(overcurrent) and faults to earth to prevent damage and ensure safety.
8. C) Generally maintained within a specified range (e.g., above 0.9 lagging) to avoid
penalties.
o Explanation: DEWA encourages good power factor management in large installations to
optimize grid efficiency and may impose penalties for poor power factor. 3
9. B) Harmonic distortion.
o Explanation: Harmonics are integer multiples of the fundamental frequency, causing waveform
distortion that can affect equipment performance and grid stability. 4 DEWA regulates these for
significant consumers.
10. B) To ensure the connected load does not exceed the approved DEWA connection capacity.
o Explanation: Consumers are responsible for ensuring their connected electrical load remains
within the approved capacity to prevent overloading the supply infrastructure.
11. B) At the point where DEWA's cables terminate and the consumer's installation begins
(e.g., at the main switch).
o Explanation: This point defines the demarcation of responsibility between DEWA's network
and the consumer's internal installation.
12. B) The consumer, through a DEWA-approved contractor.
o Explanation: While DEWA sets the standards, the consumer is responsible for providing and
maintaining their main switchgear through authorized professionals.
13. B) It must be easily accessible to DEWA personnel for inspection, isolation, and metering
purposes.
o Explanation: Accessibility is crucial for DEWA staff to perform necessary operations, including
emergency disconnections.
14. B) Disconnecting all live conductors from the supply.
o Explanation: The main switch must be capable of completely isolating the consumer's
installation from all live parts of the DEWA supply for safety during maintenance or
emergencies.
15. C) DEWA.
o Explanation: DEWA owns, installs, and maintains the electricity meters, ensuring
standardization and accurate billing.
16. B) To provide a suitable, secure, and protected space/cabinet for the meter according to
DEWA specifications.
o Explanation: Consumers must provide an appropriate environment for the meter to protect it
from damage and environmental conditions.
17. B) Enclosures with adequate IP (Ingress Protection) rating (e.g., IP55 or higher) for
environmental conditions.
o Explanation: Outdoor installations require robust enclosures to protect equipment from dust,
moisture, and other environmental factors. 5
18. B) It must be clearly labeled as the main isolator and easily identifiable.
o Explanation: Clear labeling allows for quick identification during emergencies or maintenance,
preventing accidental re-energization.6
19. B) Separate DEWA-approved meters are installed for each tenant or unit.
o Explanation: For fair and accurate billing in multi-unit properties, DEWA requires individual
metering for each consumption point.
20. B) DEWA Electrical Wiring Regulations and technical specifications.
o Explanation: These official documents provided by DEWA are the definitive source for all
requirements related to electrical installation design, parameters, and safety.
The search results confirm and expand upon the initial thoughts for "Customer Connection
Point." Key confirmed details for MCQs include:
Electricity:
Demarcation Point: Typically the outgoing terminals of DEWA's cut-out/circuit breaker or the
incoming terminals of the main switch in the consumer's premises.
Main Switchgear: Consumer's responsibility, must be DEWA-approved, accessible to DEWA
personnel for inspection/isolation. Must disconnect all live conductors.
Metering: DEWA owns and installs meters. Consumer provides suitable, secure, and protected
space (meter cabinet/room).
Accessibility: Main switchgear and meters must be easily accessible to DEWA for operations
and maintenance.
Clearance: Minimum 2m clearance between electricity and water service cabinets/points.
Water:
Meter Location: On the outside compound wall, facing the walkway, free from obstructions,
and a minimum 2m clearance from electrical services. Not in basements, pump rooms, or
underground chambers (for domestic meters).
Meter Installation: DEWA is responsible for supplying and installing the meter. Consumer
responsible for ancillary fittings and pipework beyond the meter.
Isolation Valves: Required before and after the meter (full-bore valves).
Protection: Meter must be protected from direct sunlight, high temperature, humidity,
condensation, shock, vibration, and corrosion.
Meter Room/Cabinet: Must be suitably sized, have adequate illumination, and allow for easy
access for maintenance. Non-corrosive/GRP material for cabinets. Sump pit for chambers.
Communication Cables: PVC junction boxes (e.g., IP66 rated) and conduits for communication
cables (M-bus) from water meter to electrical meter cabinet/LV room.
1. At what point is the responsibility for electrical installation typically demarcated between
DEWA and the consumer?
2. Who is responsible for the provision, installation, and maintenance of the main incoming
electrical switchgear at the customer's premises?
A) DEWA.
3. What is a crucial requirement for the location of the main incoming electrical switchgear at the
customer connection point?
B) It must be easily accessible for DEWA personnel for inspection, reading, and isolation
purposes.
5. What is the minimum required clearance distance between an electricity service cabinet/point
and a water service cabinet/point as per DEWA guidelines?
A) 0.5 meters.
B) 1 meter.
C) 2 meters.
6. The main incoming electrical switch at the customer connection point must be capable of:
7. What type of enclosure is typically required for the main electrical switchgear and meter cabinet
if installed outdoors at the connection point?
B) An enclosure with an adequate Ingress Protection (IP) rating to protect against dust and water
(e.g., IP55 or higher).
9. When applying for a new electricity connection, what documentation is typically required
concerning the electrical installation at the customer connection point?
10. In the event of an electrical fault within the consumer's premises, which device at the connection
point is primarily responsible for isolating the entire installation from DEWA's network?
C) Appliance-specific fuses.
11. Where should a domestic water meter typically be located for a villa or shed, according to
DEWA standards?
A) In the basement.
12. Who is responsible for the supply and installation of the water meter for new connections?
A) The consumer.
B) The consultant.
C) DEWA.
13. What critical components are required on both the inlet and outlet sides of the water meter at the
connection point to allow for isolation and maintenance?
A) Pressure gauges.
C) Flow restrictors.
D) Water filters.
14. What protection is required for water meters at the connection point against environmental
factors?
A) Protection from direct sunlight, high temperature, humidity, condensation, and corrosion.
16. How should the pipework at the water meter position be secured?
17. What identification is required on the wall adjacent to the water meter?
D) A decorative sign.
18. What provision is required inside a water meter chamber (if used for bulk meters) to manage
water accumulation?
A) A small pump.
C) Absorbent pads.
D) A continuous fan.
19. Why is a minimum clearance specified between electricity and water service cabinets/points?
C) To mitigate safety risks associated with potential electrical hazards interacting with
water/moisture.
20. What is the general principle for pipework and fittings installed by the consumer immediately
downstream of the DEWA water meter?
Electricity:
Metering: Individual meters for each apartment/unit are standard. Central meters for common
services (lifts, lighting, pumps).
Main Distribution: Typically a Main Distribution Board (MDB) in the building, feeding sub-
main distribution boards (SMDBs) on each floor or specific areas, which then feed consumer
units (DBs) within individual units.
Responsibility: DEWA's responsibility usually up to the outgoing terminals of the main cut-
out/circuit breaker (or the main meter/MDB incoming). The building owner/management (or
their appointed FM company) is responsible for all installations within the building, including
common areas, risers, and tenant connections.
Common Services: Separate metering for common services.
Safety: Electrical rooms (DEWA room, MDB room) must be properly constructed, ventilated,
secured, and clearly labeled. Fire safety considerations are paramount.
Earthing: Centralized earthing system for the entire building.
Emergency Supply: Provision for emergency and essential services (e.g., fire fighting pumps,
emergency lighting, lifts).
Water:
Metering: Individual meters for each unit, usually located at a common point (e.g., ground floor
meter room or utility shaft).
Main Supply/Storage: Main DEWA connection to the building, potentially with storage tanks
and booster pumps depending on height/demand.
Distribution: Vertical risers, horizontal distribution to individual units.
Maintenance: Responsibility for internal pipework and pumps lies with the building owner/FM.
Common Services: Water for common areas (e.g., landscaping, cleaning) may be on a separate
meter.
DEWA Regulations: Multiple Occupancy Premises - MCQs
1. For individual residential or commercial units within a multiple occupancy building, what is
DEWA's standard metering requirement?
2. Where is the main supply intake point typically located in a high-rise multiple occupancy
building?
B) In a dedicated DEWA Room or Main Electrical Room, usually at ground or basement level.
B) Responsibility for all internal wiring, distribution boards, risers, and common area electrical
systems.
5. What type of main distribution board typically serves a multiple occupancy building from the
main intake point?
B) A Main Distribution Board (MDB) that feeds Sub-Main Distribution Boards (SMDBs) on
different floors or sections.
6. What is crucial for electrical risers and shafts in multiple occupancy buildings from a safety
perspective?
B) They must be fire-rated and properly sealed to prevent the spread of fire and smoke between
floors.
8. What is a key requirement for rooms housing main electrical equipment (e.g., DEWA Room,
MDB Room) in a multiple occupancy building?
B) They must be well-ventilated, secured, clearly labeled, and accessible only to authorized
personnel.
9. What is the role of the building's central earthing system in a multiple occupancy premises?
B) To provide a common earth reference for all electrical installations throughout the building,
ensuring safety and fault protection.
A) All power supply to the building must be immediately cut off, including emergency services.
B) Certain non-essential power supplies may be cut, while essential services (e.g., fire pumps,
emergency lighting, fire alarm system) remain operational.
11. For a multi-storey multiple occupancy building, what is a common DEWA water connection and
distribution setup?
B) A main DEWA connection to a bulk meter, often followed by storage tanks and booster
pumps to distribute water to all units.
12. Where are individual water meters for apartments in a high-rise building typically grouped for
accessibility?
B) In common meter rooms or utility shafts, usually on the ground floor or designated floors.
B) To ensure proper maintenance, regular cleaning of tanks, and compliance with water quality
standards.
14. What is a key consideration for water pressure in high-rise multiple occupancy buildings?
B) Ensuring adequate and stable water pressure is maintained for all units, often requiring
booster pumps and pressure regulating valves.
15. What type of backflow prevention device is crucial at the main water supply intake for a multiple
occupancy building?
B) A double check valve or reduced pressure zone (RPZ) device to prevent contamination of the
public supply.
C) A flow restrictor.
17. What are the requirements for electrical installations located within water pump rooms or
common wet areas?
B) They must be waterproof and have appropriate Ingress Protection (IP) ratings to prevent water
damage and ensure safety.
18. What aspect of safety plans in multiple occupancy premises requires coordination between electrical and
fire safety systems?
B) Interfacing for emergency power to fire pumps, smoke extract fans, and emergency lighting, along
with fire alarm system integration.
D) Electrical systems should automatically shut down all fire safety equipment during a fire.
19. In a multiple occupancy premises, what is the importance of having up-to-date As-Built drawings for both
electrical and water systems?
B) Essential for effective maintenance, troubleshooting, future modifications, and emergency response.
B) To optimize energy and water consumption, enhance operational efficiency, and facilitate
maintenance.
Ownership & Installation: DEWA owns and installs both electricity and water meters.
Smart Meters: DEWA has installed over 2 million smart meters for electricity and water across
Dubai, enabling automatic and detailed readings, consumption monitoring, and leak detection.
Accessibility: Meters must be easily accessible for reading, maintenance, and replacement by
DEWA personnel.
Protection: Meters (especially outdoor ones) require protection from environmental factors
(sunlight, high temperature, humidity, condensation, corrosion, physical impact).
Tampering: Unauthorized tampering with meters is strictly prohibited.
Communication: Smart meters have advanced communication capabilities (e.g., M-Bus for
water meters, wireless signals for electricity meters) to transmit data.
Location:
o Domestic: Villas/sheds: on the outside compound wall, free from obstructions, 2m clearance
from electrical services, standard height of 1200mm. Not in basements, pump rooms, or
underground chambers (for domestic meters).
o Bulk: Installed horizontally in chambers (not buried). Chambers must be waterproof, clear of
obstacles, have a sump pit. Located away from electrical cables/magnetic fields.
Enclosures/Cabinets: Must be non-corrosive/GRP material, with specific dimensions,
ventilation holes, clear wired glass window for reading, and proper drainage.
Ancillary Fittings (Consumer Responsibility): Pipes, valves, and other fittings connected to
the meter must be high quality, heavy duty, non-toxic, and non-corrosive. Full-bore isolation
valves are required upstream and downstream. Non-Return Valve (NRV) on the customer
pipeline to prevent backflow.
Pipework: Securely fixed, flushed before meter installation.
No Pumps: Installation of water booster pumps upstream or downstream of the meter is
forbidden.
Labeling: Engraved labels with "Water Meter" and "Plot Number" (or "Water Meter Chamber"
and "Legacy Account Number & Plot Number" for chambers) are required.
1. Who is responsible for the supply, installation, and ownership of both electricity and water
meters in Dubai?
A) The customer.
B) The contractor.
C) DEWA.
2. What technology has DEWA widely implemented for electricity and water meters to enable
automatic and detailed consumption readings?
A) Manual meters.
B) Analog meters.
C) Smart meters.
3. What is a crucial requirement for the location of an electricity meter on a customer's premises?
B) It must be easily accessible to DEWA personnel for reading, inspection, and maintenance.
A) Simple weatherproofing.
B) Protection from direct sunlight, high temperature, humidity, and dust through appropriately
rated enclosures (e.g., IP54/IP55 or higher).
5. What accuracy class is typically specified for DEWA-approved three-phase smart energy meters
(e.g., ELIZE ELZ254)?
A) Class 2.0
B) Class 1.0
C) Class 0.5S
D) Class 0.2S
6. What is the primary purpose of DEWA installing a seal on the electricity meter or its enclosure?
7. What action will DEWA take if there is evidence of tampering with an electricity meter?
B) Issue a warning.
D) Traffic updates.
9. For what purpose does DEWA have an "Electricity Meter Testing" service?
B) To test electricity meters and current transformers for accuracy and defects.
10. What is a key benefit of smart meters for customers regarding consumption?
B) They help customers proactively monitor, manage, and rationalize their consumption.
11. What is the standard height at which domestic water meters should be fixed for easy reading and
maintenance?
A) 500mm
B) 900mm
C) 1200mm
D) 1500mm
12. Where are domestic water meters for villas/sheds primarily recommended to be installed?
A) In the basement.
B) On the outside compound wall, facing the walkway, free from obstructions.
13. What material is specifically required for the manufacturing of water meter cabinets by DEWA?
A) Plain steel.
B) Wood.
D) Aluminum.
14. What type of window is specified for water meter cabinets to allow for easy reading?
A) Opaque plastic.
B) Metal shutter.
D) Tinted glass.
15. What type of valves must be provided both upstream and downstream of the water meter to
allow for isolation during maintenance?
A) Gate valves.
B) Globe valves.
C) A bypass valve.
D) A flow meter.
17. What is forbidden by DEWA regulations concerning the installation of water pumps relative to
the water meter?
18. What specific label is required to be affixed to the wall adjacent to a domestic water meter?
A) "Property of Customer"
19. For bulk water meters installed in chambers, what specific provision must be included in the
chamber to manage water accumulation?
A) A heater.
C) A dehumidifier.
D) Coaxial cable.
Answer Key with Brief Explanations
1. C) DEWA.
o Explanation: DEWA is responsible for the supply, installation, and ownership of all electricity
and water meters in Dubai to ensure standardization and accurate billing.
2. C) Smart meters.
o Explanation: DEWA has extensively deployed smart meters across Dubai to provide advanced
features like remote reading, real-time data, and consumption analysis.
3. B) It must be easily accessible to DEWA personnel for reading, inspection, and
maintenance.
o Explanation: Accessibility is crucial for DEWA to perform its operational duties efficiently and
safely.
4. B) Protection from direct sunlight, high temperature, humidity, and dust through
appropriately rated enclosures (e.g., IP54/IP55 or higher).
o Explanation: Dubai's harsh climate necessitates robust environmental protection for outdoor
electrical equipment to ensure longevity and performance.
5. C) Class 0.5S.
o Explanation: This accuracy class indicates high precision for smart energy meters, suitable for
detailed measurement of various electrical parameters.
6. B) To prevent unauthorized access or tampering with the meter.
o Explanation: DEWA seals are security measures to ensure the integrity of the metering system
and prevent fraudulent activities.
7. C) Impose penalties, including fines and potential disconnection, as per regulations.
o Explanation: Tampering with utility meters is a serious offense and is subject to strict penalties
by DEWA.
8. B) Real-time and historical consumption data for electricity and water.
o Explanation: A primary benefit of smart meters is empowering customers with detailed insights
into their consumption patterns.
9. B) To test electricity meters and current transformers for accuracy and defects.
o Explanation: DEWA maintains a testing lab to verify the accuracy and functionality of meters,
especially for new connections or in case of disputes.
10. B) They help customers proactively monitor, manage, and rationalize their consumption.
o Explanation: By providing detailed consumption data, smart meters enable customers to make
informed decisions about their usage and conserve resources.
11. C) 1200mm.
o Explanation: A standard height of 1200mm ensures easy readability and ergonomic access for
DEWA personnel performing maintenance.
12. B) On the outside compound wall, facing the walkway, free from obstructions.
o Explanation: This location provides convenient and unobstructed access for DEWA meter
readers and maintenance teams.
13. C) Non-corrosive/GRP (Glass Reinforced Plastic) material.
o Explanation: GRP is chosen for its durability and resistance to the elements, preventing
corrosion and degradation in outdoor environments.
14. C) Clear wired glass (not plastic) type.
o Explanation: A clear, durable window ensures the meter register can be easily read without
opening the cabinet, preventing tampering and allowing quick checks.
15. C) Full-bore isolation valves.
o Explanation: Full-bore valves ensure minimal flow restriction and allow complete isolation of
the meter for maintenance or replacement without interrupting the main supply to the property.
16. B) A Non-Return Valve (NRV).
o Explanation: An NRV prevents backflow of water from the customer's internal system (e.g.,
from a storage tank) into DEWA's clean water network, preventing contamination.
17. B) Installing water booster pumps upstream or downstream of the meter.
o Explanation: This is forbidden to prevent tampering with meter readings or affecting water
pressure in DEWA's network. Pumps are generally allowed after the customer's storage tank.
18. B) An engraved label with 'Water Meter' and 'Plot Number'.
o Explanation: Clear and permanent labeling is essential for quick identification and
administrative purposes.
19. B) A sump pit for draining water.
o Explanation: Sump pits in meter chambers help manage and drain any accumulated water,
preventing damage to the meter and chamber components.
20. B) A 25mm dia. heavy duty PVC conduit.
o Explanation: This provides physical protection for the communication cables (e.g., M-Bus) that
transmit data from the water meter to the electrical meter cabinet or LV room.
The search results provide excellent confirmation and additional details for "Protection (General
Principles)" within DEWA regulations. Key points for MCQs include:
Safety: Primary purpose is protection of persons from electric shock (direct and indirect contact)
and thermal effects.
Equipment Protection: Protection of equipment against overcurrents (overload, short circuit).
Continuity of Supply: Minimizing disruption by isolating only the faulty section.
Fire Prevention: Protection against fire from electrical faults.
Types of Protection/Faults:
Earthing:
TN-S System: DEWA uses TN-S system (separate neutral and earth throughout).
Bonding: Main equipotential bonding and supplementary bonding to connect extraneous
conductive parts to the main earthing terminal.
Earth Resistance: Low earth resistance value required.
Other:
1. What is the primary objective of implementing protective measures in electrical installations as per
DEWA regulations?
C) To ensure the safety of persons, prevent damage to property and equipment, and maintain continuity of
supply.
2. Protection against electric shock by indirect contact is primarily achieved through which general
principle?
C) Automatic disconnection of supply (ADS) by protective devices through proper earthing and bonding.
3. What type of electrical fault involves an excessive current flowing due to a connection between a live
conductor and earth (or an exposed conductive part)?
A) Overload.
B) Short-circuit.
C) Earth fault.
D) Undervoltage.
4. Which protective device is designed to automatically interrupt an electrical circuit when the
current exceeds a predetermined safe limit due to an overload or short circuit?
A) A transformer.
B) A capacitor.
D) A resistor.
5. What is the main function of a Residual Current Device (RCD) or Earth Leakage Circuit Breaker
(ELCB) in an electrical installation?
C) To detect and interrupt small leakage currents to earth, providing protection against electric
shock.
6. According to DEWA standards, what is the typical maximum tripping current sensitivity for
RCDs used on final circuits supplying socket outlets in residential premises for enhanced shock
protection?
A) 300 mA.
B) 100 mA.
C) 30 mA.
D) 10 mA.
7. What is the purpose of "discrimination" (or selectivity) in a protective device system?
B) To ensure that only the protective device immediately upstream of the fault operates, isolating
only the faulty section.
8. What is the primary role of earthing and equipotential bonding in an electrical installation?
B) To ensure that all exposed conductive parts are maintained at earth potential, thereby reducing
shock risk during a fault.
9. Which earthing system does DEWA mandate for new electrical installations to ensure a separate
protective earth conductor throughout the network?
A) TT system.
B) IT system.
C) TN-C-S system.
D) TN-S system.
10. What protection principle involves the use of enclosures or barriers to prevent direct contact with
live electrical parts?
A) Protection by insulation.
11. What critical characteristic must a circuit breaker possess to safely interrupt a large fault current
without sustaining damage?
C) Low impedance.
12. What type of protection device is generally used for the main incoming supply to a large building
to handle high fault currents and provide both overload and short-circuit protection?
D) Fuse only.
13. In a multi-layered protection system (e.g., main, sub-main, final circuit breakers), how are the
protective devices typically coordinated?
B) By ensuring the upstream device has a higher rating and/or a time delay to allow downstream
devices to clear faults first.
B) Adequate clearances must be maintained for safe operation, maintenance, and to prevent arc
flash hazards.
14. What type of test is essential for ensuring the effectiveness of the earthing system and the
operation of RCDs?
A) Voltage test.
C) Earth Fault Loop Impedance test and RCD tripping time test.
15. What does the Ingress Protection (IP) rating of an enclosure signify, in terms of protection?
B) Its protection level against the ingress of solid objects (dust) and liquids (water).
16. What is the common method to provide overcurrent protection for final circuits (e.g., lighting,
socket outlets) in residential and commercial premises?
D) Current transformers.
17. What general principle applies to all electrical equipment installed in potentially hazardous or
explosive atmospheres (e.g., areas with flammable gases)?
B) Equipment must be specially designed and certified (e.g., Ex-rated) to prevent ignition.
18. In the event of a damaged or exposed live conductor, what protective measure is fundamental to
prevent direct contact?
19. What is a critical requirement for cables and wiring, regarding protection against mechanical
damage, especially when run through walls or exposed?
1. C) To ensure the safety of persons, prevent damage to property and equipment, and
maintain continuity of supply.
o Explanation: These are the three core objectives of any protective system in electrical
installations.
2. C) Automatic disconnection of supply (ADS) by protective devices through proper earthing
and bonding.
o Explanation: ADS ensures that if an exposed conductive part becomes live due to a fault, the
supply is quickly disconnected, preventing prolonged shock.
3. C) Earth fault.
o Explanation: An earth fault occurs when a live conductor makes unintentional contact with
earth or an earthed metal part.
4. C) A circuit breaker or fuse.
o Explanation: Both fuses and circuit breakers are designed to automatically interrupt circuits
under fault conditions (overload or short circuit).
5. C) To detect and interrupt small leakage currents to earth, providing protection against
electric shock.
o Explanation: RCDs/ELCBs operate on the principle of current balance, detecting minute
imbalances (leakage currents) that indicate a shock hazard.
6. C) 30 mA.
o Explanation: 30mA is the standard sensitivity for RCDs on final circuits in residential premises,
providing crucial protection against fatal electric shocks.
7. B) To ensure that only the protective device immediately upstream of the fault operates,
isolating only the faulty section.
o Explanation: Discrimination (or selectivity) minimizes the extent of the outage, ensuring only
the affected part of the system is disconnected.
8. B) To ensure that all exposed conductive parts are maintained at earth potential, thereby
reducing shock risk during a fault.
o Explanation: Earthing and bonding provide a safe path for fault currents and prevent dangerous
touch voltages on metalwork.
9. D) TN-S system.
o Explanation: DEWA utilizes the TN-S system, characterized by separate neutral and protective
earth conductors throughout the installation.
10. D) Protection by use of obstacles.
o Explanation: Enclosures, barriers, or placing out of reach are methods of protection by
providing an obstacle to prevent direct contact with live parts.
11. B) High breaking capacity (Icu/Ics).
o Explanation: Breaking capacity refers to the maximum fault current a circuit breaker can safely
interrupt without being damaged.
12. C) Moulded Case Circuit Breaker (MCCB) or Air Circuit Breaker (ACB).
o Explanation: MCCBs and ACBs are designed for higher current ratings and fault levels found at
the main incoming supply of large installations.
13. B) By ensuring the upstream device has a higher rating and/or a time delay to allow
downstream devices to clear faults first.
o Explanation: This coordination ensures discrimination, so only the smallest necessary portion of
the network is isolated during a fault.
14. B) Adequate clearances must be maintained for safe operation, maintenance, and to
prevent arc flash hazards.
o Explanation: Sufficient clear space around electrical equipment is vital for personnel safety and
to prevent dangerous electrical arcs.
15. C) Earth Fault Loop Impedance test and RCD tripping time test.
o Explanation: These tests verify the effectiveness of the earthing system in providing a low-
impedance path for fault currents and confirm RCDs operate within their specified timeframes.
16. B) Its protection level against the ingress of solid objects (dust) and liquids (water).
o Explanation: The IP rating is a standardized measure of an enclosure's protection against
environmental factors.
17. B) Miniature Circuit Breakers (MCBs).
o Explanation: MCBs are commonly used for final circuits due to their reusability, compact size,
and appropriate breaking capacity for residential and commercial loads.
18. B) Equipment must be specially designed and certified (e.g., Ex-rated) to prevent ignition.
o Explanation: In explosive atmospheres, electrical equipment must be explosion-protected (Ex-
rated) to prevent sparks or heat that could ignite flammable substances.
19. B) Ensuring proper insulation and/or placing conductors within robust enclosures.
o Explanation: Insulation prevents direct contact with live conductors, and robust enclosures
provide physical protection.
20. B) They must be adequately protected by conduits, trunking, or suitable armoring.
o Explanation: Cables and wiring need mechanical protection to prevent damage that could lead
to insulation failure, short circuits, or electric shock.
The search results have provided an excellent foundation for creating MCQs on "Overload and
Short Circuit Protection" within the context of DEWA regulations.
Definitions: Clear distinction between overload (excessive current, gradual heating) and short
circuit (low resistance path, sudden high current surge, immediate dangerous heat/arc).
Causes: Overload from too many devices, faulty appliances, undersized wiring. 1 Short circuit
from damaged insulation, exposed wires, moisture.2
Consequences: Both can lead to overheating, insulation damage, equipment failure, fire, and
electric shock.3 Short circuits can also cause minor explosions.4
Protective Devices:
o Fuses: Melt to break circuit, one-time use, provide protection against overcurrents (both
overload and short circuit, depending on type).5 HRC (High Rupturing Capacity) fuses for high
fault levels.6
o Circuit Breakers (CBs): Automatically switch off, reusable.7
MCB (Miniature Circuit Breaker): For final circuits, lower ratings.
MCCB (Moulded Case Circuit Breaker): For sub-mains, higher ratings, adjustable settings for
overload and instantaneous trip.
ACB (Air Circuit Breaker): For main incomers, very high ratings and breaking capacities,
often with advanced electronic trips.
o Overload Relays: Specifically for motor protection, typically thermal-magnetic, to trip on
sustained overload.8
Key Characteristics:
o Rated Current (In): Maximum continuous current.
o Breaking Capacity (Icn/Icu/Ics): Maximum fault current a device can safely interrupt.9 DEWA
mentions 40kA fault level at substations.
o Tripping Characteristics/Curves: Time-current curves define how quickly a device trips at
different fault levels (thermal for overload, magnetic/instantaneous for short circuit). 10
Coordination/Discrimination: Ensuring only the device nearest the fault trips. This is achieved
by selecting devices with appropriate ratings, breaking capacities, and time-current
characteristics (e.g., upstream device having a higher rating or time delay).
Selection Criteria: Based on connected load, prospective fault current, ambient temperature,
environment, and discrimination requirements.
DEWA Specifics:
o DEWA's supply voltage: 220/380V +10%, 50 Hz, 3-Phase, 4-Wire, TN-S system.
o Design fault level within substation: 40kA (1-sec duration) mentioned.
o Need for submission of single line diagram with protection schemes and relay setting
calculations for approval.
o Mandatory UV (Under Voltage) relays for AC loads/chillers.
B) A condition where the current flowing exceeds the circuit's normal rated current for a
prolonged period.
C) A lightning strike.
C) A low-resistance path that allows a very high current to flow directly between conductors
(e.g., live to neutral or earth), bypassing the normal load.11
A) Immediate explosion.
B) Gradual overheating of cables and equipment, leading to insulation degradation and potential
fire.12
6. What is the immediate and most dangerous consequence of a severe, unprotected short circuit?
C) Sudden, extremely high current flow leading to rapid heating, arcing, melting of conductors,
and potential fire or explosion.13
7. Which type of protective device relies on a metallic strip that melts and breaks the circuit when
an excessive current flows through it?
A) Circuit Breaker.
B) RCD.
C) Fuse.
D) Voltage stabilizer.
8. For protecting final sub-circuits in a distribution board against both overload and short circuit,
what is the most commonly used reusable device in DEWA-approved installations?
9. What is the "breaking capacity" (e.g., Icn, Icu, Ics) of a circuit breaker?
D) Arc chute.
11. What characteristic of a circuit breaker typically provides instantaneous protection against very
high currents, such as those caused by a short circuit?
D) Undervoltage release.
12. For main incoming supplies or large industrial loads where very high fault currents are expected,
what type of circuit breaker is typically specified by DEWA?
D) Domestic fuses.
13. What principle ensures that in a tiered protection system (e.g., main, sub-main, final circuit),
only the device closest to the fault operates, leaving the rest of the system energized?
A) Coordination.
B) Integration.
C) Selectivity (Discrimination).
D) Sensitivity.
14. When selecting a protective device for a circuit, the rated current of the device should generally
be:
B) Equal to or slightly higher than the circuit's normal operating current, but lower than the
cable's current carrying capacity.
15. What is the approximate design fault level specified by DEWA within its substations, which
influences the required breaking capacity of downstream circuit breakers?
A) 5 kA.
B) 10 kA.
C) 40 kA.
D) 100 kA.
16. Which type of relay is specifically mentioned in DEWA regulations for installation with air-
conditioning units/plants for protection against supply voltage drops?
A) Overcurrent relay.
17. Before commissioning, what critical documentation related to protection must be submitted to
DEWA for approval in complex installations?
B) Single line diagram illustrating protection schemes along with relay setting calculations.
18. What would be the consequence if a protective device's breaking capacity is lower than the
prospective short-circuit current at its point of installation?
B) The device may fail catastrophically (explode or weld shut) during a short circuit, failing to
clear the fault safely.
19. In a power distribution system, if a short circuit occurs on a final lighting circuit, which device
should ideally operate first to clear the fault, without affecting other circuits?
20. When installing protective devices, especially circuit breakers, what general principle must be
observed regarding access?
B) They should be readily accessible for safe operation, inspection, testing, and maintenance,
with required clearances.
1. B) A condition where the current flowing exceeds the circuit's normal rated current for a
prolonged period.
o Explanation: Overload is a sustained excess current, typically due to too many appliances or a
motor drawing slightly more current than rated.14
2. B) Plugging too many high-power appliances into a single circuit or extension.
o Explanation: This increases the total current drawn beyond the circuit's design limit, leading to
overload.
3. C) A low-resistance path that allows a very high current to flow directly between
conductors (e.g., live to neutral or earth), bypassing the normal load. 15
o Explanation: Short circuits are characterized by extremely high currents due to very low
impedance in the fault path.16
4. B) Damaged insulation on wires allowing live and neutral conductors to touch.
o Explanation: Loss of insulation creates a direct, low-resistance path, resulting in a short
circuit.17
5. B) Gradual overheating of cables and equipment, leading to insulation degradation and
potential fire.
o Explanation: Overloads generate heat, which over time can cause damage and ignite
surrounding materials.18
6. C) Sudden, extremely high current flow leading to rapid heating, arcing, melting of
conductors, and potential fire or explosion. 19
o Explanation: The immense energy released during a short circuit can cause catastrophic
damage, including fire and minor explosions.20
7. C) Fuse.
o Explanation: Fuses are sacrificial devices designed to melt and open a circuit when an
overcurrent occurs.21
8. B) Miniature Circuit Breaker (MCB).
o Explanation: MCBs are standard for final circuit protection, offering both overload (thermal
element) and short-circuit (magnetic element) protection in a reusable format. 22
9. C) The maximum short-circuit current it can safely interrupt without damage.
o Explanation: This is a crucial rating for circuit breakers, ensuring they can safely clear the
highest possible fault current at their location.
10. C) Thermal trip unit.
o Explanation: The thermal element (bimetallic strip) in a circuit breaker heats up and bends with
sustained overcurrent, causing it to trip.23
11. C) Magnetic or instantaneous trip unit.
o Explanation: The magnetic element in a circuit breaker responds almost instantly to very high
currents, providing rapid protection against short circuits.
12. C) Moulded Case Circuit Breakers (MCCBs) or Air Circuit Breakers (ACBs).
o Explanation: These breakers have higher current ratings and breaking capacities, making them
suitable for main distribution points where fault currents are significant. 24
13. C) Selectivity (Discrimination).
o Explanation: Discrimination ensures that only the faulty part of the system is isolated,
minimizing disruption to healthy circuits.25
14. B) Equal to or slightly higher than the circuit's normal operating current, but lower than
the cable's current carrying capacity.
o Explanation: The device must protect the cable, so its rating should be chosen to trip before the
cable is damaged, while still allowing the normal load to operate.
15. C) 40 kA.
o Explanation: DEWA guidelines mention a design fault level of 40kA at substations, which is a
critical parameter for selecting protective devices.
16. C) Under Voltage (UV) relay.
o Explanation: DEWA regulations specifically require UV relays for AC units to protect them
from damage due to supply voltage drops.26
17. B) Single line diagram illustrating protection schemes along with relay setting calculations.
o Explanation: This detailed documentation is required by DEWA to review and approve the
protective coordination of the electrical system.
18. B) The device may fail catastrophically (explode or weld shut) during a short circuit, failing
to clear the fault safely.
o Explanation: An inadequate breaking capacity means the device cannot handle the energy of the
fault, leading to its destruction and continued hazard.
19. C) The MCB protecting that specific lighting circuit.
o Explanation: This demonstrates selectivity, where the nearest protective device clears the fault,
preventing unnecessary outages in other parts of the building.
20. B) They should be readily accessible for safe operation, inspection, testing, and
maintenance, with required clearances.
o Explanation: Safe and easy access to protective devices is crucial for emergency operation,
routine checks, and maintenance activities.
The search results provide comprehensive and specific information regarding DEWA's
requirements for Electrical Shock Protection. Key points identified include:
Direct Contact: Protection against contact with live parts during normal operation. 1 Methods:
insulation, barriers/enclosures, placing out of reach, obstacles. 2
Indirect Contact: Protection against contact with exposed conductive parts that become live due
to a fault.3 Methods: Automatic Disconnection of Supply (ADS) (through earthing, bonding, and
protective devices like RCDs, fuses, circuit breakers).
TN-S System: DEWA mandates the TN-S earthing system (separate neutral and earth
throughout).
Hazard: Electric shock can cause injury or death.4
Testing: Earth fault loop impedance testing, RCD tripping time and sensitivity testing.
PPE: Mandatory use of proper Personal Protective Equipment (PPE) for electrical work.
LOTO (Lockout/Tagout): Critical procedure for isolating and de-energizing circuits before
work.
Safe Working Distances: Defined approach distances from live parts.
Consequences of Non-Compliance:
This information is comprehensive and allows for the creation of 20 relevant MCQs.
1. What is the primary method of protection against electric shock from direct contact with live
parts during normal operation?
2. Protection against electric shock from indirect contact (e.g., touching a faulty appliance casing
that has become live) is primarily achieved by:
B) Automatic Disconnection of Supply (ADS) through proper earthing, bonding, and protective
devices.
D) Fuse.
4. According to DEWA regulations, what is the maximum tripping current sensitivity (rated
residual operating current) typically required for an RCD protecting final circuits (e.g., socket
outlets, lighting circuits where shock risk is high) in residential and commercial premises?
A) 300 mA.
B) 100 mA.
C) 30 mA.
D) 10 mA.
B) To ensure all exposed conductive parts and extraneous conductive parts are maintained at the
same potential, preventing dangerous potential differences during a fault.
A) TT system.
B) IT system.
C) TN-C system.
D) TN-S system.
7. What is the main purpose of connecting metallic service pipes (e.g., water, gas) and structural
steelwork to the main earthing terminal of an installation?
B) To act as main equipotential bonding, ensuring these parts are at earth potential and
preventing shock hazards.
8. For fixed equipment and lighting circuits, if not protected by 30mA RCDs, what other conditions
must be met for protection against indirect contact?
B) The earth fault loop impedance must be low enough to ensure the circuit protective device
(fuse/MCB) disconnects the supply within the prescribed time.
B) The magnitude of current flowing through the body, duration of contact, and path taken.
11. What mandatory personal protective equipment (PPE) is typically required for personnel
working on or near live electrical installations to prevent electric shock?
12. Before commencing any work on electrical equipment or circuits that might be live, what
essential safety procedure must be strictly followed to prevent accidental re-energization and
electric shock?
14. What measure is specified for main switchgear and distribution boards to protect against direct
contact with live parts?
B) They must be enclosed in robust, appropriately IP-rated cabinets or rooms with restricted
access.
15. What happens if the earth fault loop impedance is too high in a circuit protected by a fuse or
circuit breaker (not an RCD)?
B) The protective device may not trip quickly enough during an earth fault, leading to prolonged
hazardous voltages.
B) A voltage not exceeding 50V AC or 120V DC, used for safety in specific applications.
B) DEWA may refuse connection, discontinue supply, or impose penalties due to safety non-
compliance.
18. What is the significance of the protective earthing conductor (PE) in an installation's wiring?
B) It provides a low-resistance path for fault currents to earth, ensuring protective devices
operate correctly during indirect contact faults.
19. For electrical equipment with exposed conductive parts (e.g., metal casings), what is the key
protective measure that makes these parts safe in case of an insulation failure?
20. What is a "safety distance" when working near live electrical equipment?
B) A minimum defined clearance that must be maintained from live electrical parts to prevent
direct contact or arc flash incidents.
Earth Leakage Definition: Current finding an alternative return path other than active/neutral,
usually a small magnitude (mA). It's an unintended current flowing to earth. 1
Purpose of Protection: Primarily to protect people from electric shock and to prevent fire risks
due to current leakage.2
RCD/ELCB Operation: Current sensing devices (most common type now) monitor the
difference between current flowing through phase and neutral. An imbalance indicates leakage
and causes tripping. Older voltage sensing types exist but are less common. 3
This information is robust and sufficient to generate 20 comprehensive MCQs for "Earth
Leakage Protected Systems".
DEWA Regulations: Earth Leakage Protected Systems - MCQs
2. What is the primary purpose of an Earth Leakage Protected System, typically utilizing Residual
Current Devices (RCDs)?
C) To protect people from electric shock and reduce fire risks caused by leakage currents.
3. How does a Residual Current Device (RCD) fundamentally operate to detect earth leakage?
B) By detecting an imbalance (difference) between the current flowing in the live and neutral
conductors.
A) 300 mA.
B) 100 mA.
C) 30 mA.
D) 10 mA.
5. For circuits supplying mobile equipment (not exceeding 32A rating) for use outdoors, what
specific type of protection is generally mandatory as per DEWA?
B) Overcurrent protection combined with an RCD having a rated residual operating current not
exceeding 30 mA.
6. In which of the following scenarios are RCDs with a sensitivity of not exceeding 30 mA
typically mandatory for cables concealed in walls/partitions as per DEWA?
B) When the cables are concealed at a depth of less than 50 mm, or contain metal parts
regardless of depth.
8. For what primary reason would an RCD with a higher sensitivity (e.g., 10mA) be installed, even
if 30mA is the general minimum requirement for shock protection?
B) For increased protection in very high-risk areas like medical equipment applications or
swimming pools.
9. What is the typical maximum tripping time for a 30mA RCD to provide effective shock
protection during an earth fault?
D) 1 second (s).
10. Which type of RCD is designed to trip on alternating sinusoidal residual currents and also on
pulsating DC residual currents, making it suitable for circuits supplying modern electronic
equipment?
A) Type AC RCD.
B) Type A RCD.
C) Type B RCD.
D) Type F RCD.
11. What role does proper earthing play in the effective operation of an RCD for indirect contact
protection?
B) It creates the earth fault current necessary for the RCD to detect the imbalance and trip.
12. If a time-delayed RCD is used as a main incomer to a distribution board that also has 30mA
RCDs on its final circuits, what is the purpose of the time delay?
B) To ensure discrimination, allowing the downstream 30mA RCD to clear the fault first without
tripping the main RCD.
14. What are the consequences of not providing adequate earth leakage protection in an electrical
installation?
D) Easier maintenance.
15. What is the recommended frequency for manually testing fixed RCDs using their test button in
an installation?
A) Once a year.
16. What does it mean if an RCD's test button fails to trip the device when pressed?
B) The RCD is faulty and may not provide protection in an actual earth fault scenario.
B) It ensures a dedicated protective earth conductor throughout, providing a reliable path for
fault currents.
18. In what common location within residential premises, besides socket outlets, are 30mA RCDs
typically required due to the increased risk of electric shock from water?
A) Living rooms.
C) Bedrooms.
D) Garages only.
19. Why is it important that an RCD is selected with an appropriate current rating (In) in addition to its
residual current rating (IΔn)?
B) An RCD must also be capable of carrying the circuit's normal operating current without tripping from
overload.
20. What document submitted to DEWA for approval would detail the types and locations of RCDs within a
consumer's electrical installation?
To reduce the risk of electric shock by ensuring that all exposed conductive parts and extraneous
conductive parts (e.g., metallic pipes, structural steel) are maintained at substantially the same
potential (earth potential).1
This prevents dangerous potential differences (touch voltages) from arising between conductive
parts during a fault.2
Types of Bonding:
General Principles:
TN-S System: DEWA uses the TN-S earthing system, which inherently supports effective
bonding by providing a dedicated protective earth conductor.
Continuity: All bonding connections must be electrically continuous and mechanically sound.
Testing: Verification of bonding connections (continuity, resistance) is part of the electrical
installation testing.4
Responsibility: Consumer's responsibility to ensure proper bonding as per DEWA regulations
and international standards (e.g., IEC 60364, BS 7671).
B) To ensure all conductive parts within a premises are at a substantially equal potential, thus
preventing dangerous potential differences during a fault.
B) To connect the main earthing terminal to all incoming main metallic services and other
extraneous conductive parts.
3. Which of the following metallic services must be connected to the main earthing terminal via
main equipotential bonding in a typical installation as per DEWA guidelines?
B) Water installation pipes, gas installation pipes, central heating and air-conditioning ducts, and
structural steelwork.
B) Lighting circuit.
6. According to the principles of DEWA's TN-S earthing system, what role does a dedicated
protective earth (PE) conductor play in relation to bonding?
B) It provides the essential low-impedance path to earth for bonding conductors to be effective
during a fault.
B) A conductive part liable to introduce an earth potential, not forming part of the electrical
installation (e.g., metal pipes, building steel).5
B) It is related to the cross-sectional area of the main earthing conductor of the installation.
9. What is the general minimum cross-sectional area for main equipotential bonding conductors in
copper, as per common regulations that DEWA aligns with?
A) 1.5 mm².
B) 2.5 mm².
C) 4 mm².
10. What electrical parameter should be measured to verify the effectiveness of equipotential bonding
connections?
A) Voltage drop.
B) Insulation resistance.
C) Continuity and low resistance (e.g., with a low resistance ohmmeter or continuity tester).
D) Power factor.
B) To provide additional protection in specific locations where conditions for ADS may not be reliably
met or where the risk of shock is higher.
A) Living room.
B) Bedrooms.
C) Bathrooms/shower rooms.
B) All exposed conductive parts of equipment and extraneous conductive parts (e.g., metal bath,
metal pipes, metal window frames if conductive).6
14. What is the typical minimum cross-sectional area for a supplementary equipotential bonding
conductor if it is mechanically protected?
A) 1.5 mm².
B) 2.5 mm².
C) 4 mm².
D) 6 mm².
15. What is the critical safety consequence if equipotential bonding is omitted or incorrectly
installed?
B) Dangerous potential differences can arise between conductive parts during a fault, leading to
severe electric shock or electrocution.7
16. How should bonding conductors be connected to metallic pipes or structural steelwork?
C) By soldering directly.
B) Earthing connects the system to the general mass of earth, while bonding connects conductive
parts within the installation to each other and to the earthing system to maintain equal potential.8
They work together.
B) It maintains the touch voltage at a very low, safe level relative to other bonded parts,
minimizing shock risk.9
19. What does the term "exposed conductive part" refer to in the context of bonding?
B) A conductive part of equipment that can be touched and is not normally live but which can
become live under fault conditions.
20. What document would a DEWA-approved contractor typically include in their submission to
DEWA to demonstrate compliance with earthing and bonding requirements?
B) Detailed earthing and bonding layout drawings, schematics, and test reports.
1. B) To ensure all conductive parts within a premises are at a substantially equal potential,
thus preventing dangerous potential differences during a fault.10
o Explanation: This is the core function of bonding – eliminating voltage gradients that could
cause shock.
2. B) To connect the main earthing terminal to all incoming main metallic services and other
extraneous conductive parts.
o Explanation: Main bonding connects the main utilities and structural elements to the earth
system to equalize their potential.
3. B) Water installation pipes, gas installation pipes, central heating and air-conditioning
ducts, and structural steelwork.
o Explanation: These are common extraneous conductive parts that must be bonded because they
can introduce earth potential.
4. B) Bare or insulated copper conductors.
o Explanation: Copper is the standard material for earthing and bonding conductors due to its
excellent conductivity and corrosion resistance.
5. C) Earthing and equipotential bonding system.
o Explanation: ADS relies on fault currents flowing to earth quickly enough to trip protective
devices, and proper earthing and bonding ensure this low-impedance path.
6. B) It provides the essential low-impedance path to earth for bonding conductors to be
effective during a fault.
o Explanation: The TN-S system's dedicated PE conductor ensures that any fault current on
bonded parts has a reliable return path to the source to trip the protective device.
7. B) A conductive part liable to introduce an earth potential, not forming part of the
electrical installation (e.g., metal pipes, building steel).11
o Explanation: These are conductive parts that can become "live" indirectly if a fault occurs
elsewhere, hence needing to be bonded.
8. B) It is related to the cross-sectional area of the main earthing conductor of the installation.
o Explanation: The sizing ensures the bonding conductor can carry the same magnitude of fault
current without damage.
9. D) 6 mm². (This is a common minimum for main bonding).
o Explanation: While specific regulations may vary, 6 mm² is a widely accepted minimum for
main equipotential bonding to handle potential fault currents. 12
10. C) Continuity and low resistance (e.g., with a low resistance ohmmeter or continuity
tester).
o Explanation: Testing ensures that the bonding connections are electrically sound and have a
sufficiently low resistance to be effective.
11. B) To provide additional protection in specific locations where conditions for ADS may not
be reliably met or where the risk of shock is higher.
o Explanation: Supplementary bonding acts as a local protective measure, particularly in high-risk
areas like bathrooms.13
12. C) Bathrooms/shower rooms.
o Explanation: Due to the presence of water and conductive surfaces, bathrooms are considered
high-risk areas where supplementary bonding is crucial for safety.
13. B) All exposed conductive parts of equipment and extraneous conductive parts (e.g., metal
bath, metal pipes, metal window frames if conductive).
o Explanation: Supplementary bonding aims to bring all conductive items in a specific area to the
same potential.
14. B) 2.5 mm².
o Explanation: A minimum of 2.5 mm² copper is generally accepted for supplementary bonding
conductors if mechanically protected.14
15. B) Dangerous potential differences can arise between conductive parts during a fault,
leading to severe electric shock or electrocution. 15
o Explanation: Without bonding, a person touching two conductive parts that are at different
potentials during a fault could receive a severe shock.16
16. B) Using securely fixed and approved bonding clamps.
o Explanation: Proper clamps ensure a durable, low-resistance electrical connection between the
conductor and the bonded part.17
17. B) Earthing connects the system to the general mass of earth, while bonding connects
conductive parts within the installation to each other and to the earthing system to
maintain equal potential.18 They work together.
o Explanation: They are complementary safety measures: earthing provides the earth reference,
and bonding ensures all connected parts are at that same reference.
18. B) It maintains the touch voltage at a very low, safe level relative to other bonded parts,
minimizing shock risk.
o Explanation: By equalizing potentials, bonding prevents large voltage differences that would
drive dangerous current through a person's body.
19. B) A conductive part of equipment that can be touched and is not normally live but which
can become live under fault conditions.
o Explanation: Examples include the metal casing of an appliance if its internal insulation fails.
20. B) Detailed earthing and bonding layout drawings, schematics, and test reports.
o Explanation: Comprehensive documentation is required by DEWA to verify that the earthing
and bonding system has been designed and installed correctly and effectively.
The search results provide a comprehensive understanding of DEWA's requirements for
"Isolation and Switching and Insulation." Key points for MCQs include:
Isolation:
Definition: The safe and reliable disconnection and separation of an electrical installation or
circuit from the rest of the live system by means that prevent unintended re-energization.
Purpose: To permit safe working on the electrical equipment or circuit by de-energizing it.
Means of Isolation: Disconnectors, switch-disconnectors, circuit breakers capable of isolation,
fuses with removal of the fuse carrier, and plugs and socket outlets for individual portable
equipment.
Key Requirements:
o Must be lockable in the OFF position (LOTO).
o Must have an adequate air gap or equivalent.
o Must be clearly identifiable.
o Must disconnect all live conductors (phase and neutral, unless specifically exempted for
functional switching).
o Located at the origin of the installation or near the equipment being isolated.
Switching:
Insulation:
Definition: Non-conductive material used to separate live parts from each other and from
accessible parts.
Purpose: To prevent direct contact with live parts and to contain electricity safely within
conductors.
Types/Levels of Protection:
o Basic Insulation: Provides basic protection against direct contact.
o Supplementary Insulation: Independent insulation in addition to basic insulation, providing
protection in case of basic insulation failure.
o Double Insulation: Basic + Supplementary insulation.
o Reinforced Insulation: Single layer of insulation providing equivalent protection to double
insulation.
Consequences of Failure: Breakdown can lead to short circuits, earth faults, electric shock, and
fire.
Testing: Insulation resistance testing is crucial for verifying the integrity of insulation.
B) To allow safe access for work on equipment by ensuring all live parts are completely
disconnected and cannot be accidentally re-energized.
B) Disconnecting all live conductors from the supply and being lockable in the OFF position.
A) Remote monitoring.
B) Load shedding.
C) Lockout/Tagout (LOTO).
D) Regular cleaning.
4. Which of the following devices can serve as a means of isolation in an electrical circuit?
C) A transformer.
5. What is the purpose of a "main switch" at the origin of a consumer's electrical installation, as
required by DEWA?
B) To allow for the complete isolation of the entire installation from DEWA's supply.
B) Switching devices on and off during normal operation of the circuit or equipment.
8. Where should emergency switching devices (e.g., emergency stop buttons, fire isolation
switches) be located?
9. When installing a main switch that acts as an isolator, what visual indication is crucial?
A) Its color.
B) A mechanical switching device that, in the open position, provides a safe isolating distance
and visible indication of disconnection.
11. What is the fundamental purpose of "insulation" in electrical conductors and equipment?
B) To prevent direct contact with live parts and safely contain electricity within conductors,
stopping current from flowing to unintended paths.
B) Insulation that provides basic protection against electric shock during normal operation.
B) A single layer of insulation that provides an equivalent degree of protection against electric
shock as double insulation.
A) Continuity test.
16. What is a significant risk associated with degraded or damaged insulation in an electrical
system?
C) Short circuits, earth faults, electric shock, and potential fire hazards.
17. What protection principle uses insulation as its primary barrier against electric shock from direct
contact?
B) Protection by obstacle.
D) Protection by bonding.
18. What is the minimum insulation resistance value typically expected for a new or healthy low-
voltage electrical installation (e.g., 230/400V) when tested with a DC voltage (e.g., 500V DC)?
A) 0.1 MΩ (Mega-ohm).
B) 0.5 MΩ.
C) 1 MΩ.
D) 10 MΩ.
19. In the context of DEWA regulations, what general principle applies to all electrical equipment
regarding insulation?
B) All electrical equipment must be adequately insulated for its intended voltage and
environment to ensure safety.
20. When dealing with damaged insulation on an electrical cable, what is the most appropriate
immediate action from a safety perspective?
B) Immediately isolate the circuit, repair/replace the damaged section, and ensure no current
flows through it until safe.
1. B) To allow safe access for work on equipment by ensuring all live parts are completely
disconnected and cannot be accidentally re-energized.
o Explanation: Isolation is paramount for personnel safety during electrical work.
2. B) Disconnecting all live conductors from the supply and being lockable in the OFF
position.
o Explanation: Complete disconnection (including neutral in many cases) and the ability to
prevent re-energization (LOTO) are core requirements for isolation.
3. C) Lockout/Tagout (LOTO).
o Explanation: LOTO is a critical safety procedure used to ensure that machines or equipment are
de-energized and cannot be operated during maintenance or repair.
4. B) A circuit breaker or switch-disconnector specifically designed for isolation, or a
removable fuse link.
o Explanation: These devices have design features (e.g., visible break, adequate air gap) that
make them suitable for reliable isolation.
5. B) To allow for the complete isolation of the entire installation from DEWA's supply.
o Explanation: The main switch is the primary means of isolating the consumer's entire electrical
system from the utility supply.
6. B) Switching devices on and off during normal operation of the circuit or equipment.
o Explanation: Functional switching is the everyday operation of electrical loads.
7. B) To rapidly disconnect electrical supply in an emergency situation (e.g., to stop
machinery in danger, or isolate in case of fire).
o Explanation: Emergency switching is for immediate response to hazardous situations.
8. B) Readily accessible and clearly identifiable at strategic points.
o Explanation: In an emergency, these switches must be easy to find and operate quickly.
9. B) A clear indication of its ON/OFF (open/closed) position.
o Explanation: This visual indication is essential to confirm the isolated state of the circuit for
safety.
10. B) A mechanical switching device that, in the open position, provides a safe isolating
distance and visible indication of disconnection.
o Explanation: Disconnectors are designed specifically for isolation, often with a visible break
feature.
11. B) To prevent direct contact with live parts and safely contain electricity within
conductors, stopping current from flowing to unintended paths.
o Explanation: Insulation is the primary barrier preventing electric current from escaping its
intended path and causing shock or short circuits.
12. B) Insulation that provides basic protection against electric shock during normal
operation.
o Explanation: Basic insulation is the first layer of defense against direct contact.
13. B) Basic insulation plus supplementary insulation.
o Explanation: Double insulation provides two independent layers of insulation, offering
enhanced protection against electric shock.
14. B) A single layer of insulation that provides an equivalent degree of protection against
electric shock as double insulation.
o Explanation: Reinforced insulation achieves the same high level of safety as double insulation,
but in a single, more robust layer.
15. C) Insulation resistance test.
o Explanation: This test measures the electrical resistance of the insulation, indicating its ability
to prevent current leakage.
16. C) Short circuits, earth faults, electric shock, and potential fire hazards.
o Explanation: Compromised insulation allows current to flow where it shouldn't, leading to
dangerous conditions.
17. C) Protection by insulation of live parts.
o Explanation: Insulation is the most common and fundamental method for preventing direct
contact.
18. B) 0.5 MΩ.
o Explanation: For a 230/400V system, the minimum acceptable insulation resistance is typically
0.5 MΩ (Mega-ohm) when tested with 500V DC.
19. B) All electrical equipment must be adequately insulated for its intended voltage and
environment to ensure safety.
o Explanation: Proper insulation is a universal safety requirement for all electrical equipment to
prevent hazards.
20. B) Immediately isolate the circuit, repair/replace the damaged section, and ensure no
current flows through it until safe.
o Explanation: Damaged insulation is an immediate safety hazard and requires immediate action
to de-energize and rectify.
The search results provide excellent and specific information about DEWA's earthing
requirements. Key takeaways for generating MCQs include:
Fundamentals of Earthing:
Purpose: To protect people from electric shock (indirect contact), protect equipment, and
provide a low-impedance path for fault currents to ensure protective devices operate swiftly. 1
Also for lightning protection and EMC.
Safety Priority: Highest integrity and robust construction to ensure safety of persons and
surroundings.
Components: Earth electrode(s), main earth lead conductor, main earthing terminal (MET) or
earth busbar, Earth continuity conductors (ECCs) for outgoing circuits. 2
Low Resistance: Earthing system must have low electrical resistance to dissipate high fault
currents repeatedly.4
Corrosion Resistance: Materials selected must have good corrosion resistance.
Earth Fault Loop Impedance (Zea): Must be sufficiently low for protective devices (fuse,
circuit breaker, RCD) to operate in the required time during an earth fault.
Equipotential Bonding: Essential part of the earthing system, connecting exposed and
extraneous conductive parts to the main earthing terminal (this was covered in the previous
section but is a crucial principle here too).
Separate Earthing Networks: MV, LV, ELV Networks, Private Generators, and Lightning
Protections shall generally have separate earthing networks and not be connected with the main
Electrical Earthing System, unless specifically designed and approved (this is an important
nuance often overlooked).
Standards: BS7430 and IEC 60364 are referred for guidance.
Consumer Responsibility: Every consumer installation shall be provided with a separate
earthing system within the consumer's plot limits, installed and maintained by the consumer.
B) To provide a safe path for fault currents to flow to the general mass of earth, thereby
protecting persons from electric shock and equipment from damage.
2. According to DEWA regulations, the consumer's earthing system should primarily ensure the:
B) Highest integrity and robust construction to ensure safety of persons and their surroundings.
B) A conductive part, which may be buried in the ground or form part of the foundation, that
provides an electrical connection to the earth.
B) It provides a low-impedance path for the fault current, ensuring that the protective device
operates quickly to disconnect the supply.
5. Which international standards are generally referred to for guidance regarding earthing in
DEWA regulations?
B) A terminal or busbar provided for the connection of protective conductors, including the main
earthing conductor and main equipotential bonding conductors.
B) It should be as low as practically possible to ensure effective fault current dissipation and
protective device operation.
8. Besides electric shock protection, what other significant function does a well-designed earthing
system contribute to?
B) Conductors that connect the exposed conductive parts of electrical equipment to the main
earthing terminal.
10. Who is responsible for installing and maintaining the separate earthing system within the
consumer's plot limits, as per DEWA regulations?
A) DEWA exclusively.
B) The consumer.
11. What earthing system type is explicitly mandated for consumer main earthing connections by
DEWA?
A) TN-C.
B) TT.
C) IT.
D) TN-S.
12. In a TN-S earthing system, what is the key characteristic regarding the neutral and protective
earth (PE) conductors within the consumer's installation?
B) They are kept separate throughout the installation and shall not be connected together at the
main earth terminal or any other point.
C) The neutral conductor is intentionally earthed at multiple points in the consumer's installation.
13. Where is the neutral conductor solidly earthed in DEWA's supply system?
B) The total impedance of the earth fault current path from the supply transformer, through the
live conductor, fault, protective conductor, and back to the transformer.
15. Why must the Earth Fault Loop Impedance be sufficiently low?
A) To prevent overcurrents.
B) To ensure that protective devices (fuses, circuit breakers, RCDs) operate within the required
time to disconnect the supply in case of an earth fault.
16. Which of the following earthing networks are generally required to be kept separate from the
main electrical earthing system unless specifically approved by DEWA?
A) Lighting circuits.
B) MV, LV, ELV networks, private generators, and lightning protection systems.
17. What is the role of equipotential bonding in relation to the earthing system?
B) It connects all exposed and extraneous conductive parts to the main earthing terminal,
ensuring they are at the same potential as earth and reducing shock risk.
A) Its color.
B) Compatibility with the earth electrode material and the corrosive effect of the soil.
19. What would be the consequence of a high earth electrode resistance in a TN-S system during an
earth fault?
B) The protective device might not operate within the required time, increasing the risk of
electric shock and equipment damage.
20. What documents are typically required by DEWA to verify the compliance of an earthing system
in a new installation?
B) Test reports for earth resistance, insulation resistance, and earth fault loop impedance, along
with detailed earthing layout diagrams.
1. B) To provide a safe path for fault currents to flow to the general mass of earth, thereby
protecting persons from electric shock and equipment from damage.
o Explanation: Earthing's primary safety role is to manage fault currents. 5
2. B) Highest integrity and robust construction to ensure safety of persons and their
surroundings.
o Explanation: DEWA emphasizes robust and safe earthing systems.
3. B) A conductive part, which may be buried in the ground or form part of the foundation,
that provides an electrical connection to the earth.
o Explanation: The earth electrode provides the physical connection to the earth.
4. B) It provides a low-impedance path for the fault current, ensuring that the protective
device operates quickly to disconnect the supply.
o Explanation: The earthing system facilitates the rapid operation of protective devices.
5. B) BS 7430 and IEC 60364.
o Explanation: These are internationally recognized standards for earthing and electrical
installations.
6. B) A terminal or busbar provided for the connection of protective conductors, including
the main earthing conductor and main equipotential bonding conductors.
o Explanation: The MET is the central point for connecting all protective conductors to the earth
electrode.
7. B) It should be as low as practically possible to ensure effective fault current dissipation
and protective device operation.
o Explanation: A low earth resistance is crucial for effective fault current dissipation and fast
tripping.6
8. B) Providing lightning protection and electromagnetic compatibility (EMC).
o Explanation: Earthing plays a vital role in diverting lightning and reducing electromagnetic
interference.7
9. B) Conductors that connect the exposed conductive parts of electrical equipment to the
main earthing terminal.
o Explanation: ECCs ensure that metal casings of equipment are earthed for safety.
10. B) The consumer.
o Explanation: Consumers are responsible for their internal earthing systems within their plot
limits.
11. D) TN-S.
o Explanation: DEWA explicitly specifies the TN-S system for consumer main earthing, which
has separate neutral and earth conductors.
12. B) They are kept separate throughout the installation and shall not be connected together
at the main earth terminal or any other point.
o Explanation: This is the defining characteristic of a TN-S system – distinct N and PE.
13. B) Only at DEWA's substations.
o Explanation: In a TN-S system supplied by DEWA, the neutral is earthed only at the source.
14. B) The total impedance of the earth fault current path from the supply transformer,
through the live conductor, fault, protective conductor, and back to the transformer.
o Explanation: Zea represents the entire circuit path for a fault current back to the source,
affecting how quickly protection operates.
15. B) To ensure that protective devices (fuses, circuit breakers, RCDs) operate within the
required time to disconnect the supply in case of an earth fault.
o Explanation: A low Zea is essential for ensuring rapid fault clearance.
16. B) MV, LV, ELV networks, private generators, and lightning protection systems.
o Explanation: These systems often have their own earthing requirements and might need to be
isolated or specifically bonded, not generally connected to the main electrical earthing.
17. B) It connects all exposed and extraneous conductive parts to the main earthing terminal,
ensuring they are at the same potential as earth and reducing shock risk.
o Explanation: Bonding equalizes potentials to prevent dangerous touch voltages during a fault. 8
18. B) Compatibility with the earth electrode material and the corrosive effect of the soil.
o Explanation: Corrosion can severely degrade the effectiveness and lifespan of an earthing
system.9
19. B) The protective device might not operate within the required time, increasing the risk of
electric shock and equipment damage.
o Explanation: High earth resistance impedes fault current flow, delaying or preventing protective
device operation.
20. B) Test reports for earth resistance, insulation resistance, and earth fault loop impedance,
along with detailed earthing layout diagrams.
o Explanation: Comprehensive documentation and test results are necessary to demonstrate
compliance with safety regulations.
The search results have provided specific details for "Earth Electrodes, Earth Terminals, and
Earth Conductors" within DEWA regulations and general best practices. Key information
includes:
Earth Electrodes:
Types: Earth rods (20mm/26mm diameter copper/steel core, driven to a min depth of 3 meters),
earth plates, earth tapes/wires, and structural metalwork embedded in foundations are
recognized.1
Installation: Installed inside an earth pit (e.g., 300x300x300mm) with an inspection cover.
Resistance: Required to have a low resistance value. For substations, it's very low (e.g., <2 ohms
for transformer neutral and equipment body earthing). For general installations, while a common
industry recommendation is <5 ohms, laboratories require <1 ohm. The ideal is "as low as
practically possible".
Material: Copper is specified for earth conductors connecting to the electrode. Corrosion
resistance is crucial.
Earth Terminals:
Main Earthing Terminal (MET): This is the central connection point for the main earthing
conductor, main equipotential bonding conductors, and all circuit protective conductors. 2
Location: Not explicitly detailed in the provided snippets, but generally at the main distribution
board or intake point.
Earth Conductors:
Main Earth Lead Conductor: Connects the earth electrode(s) to the MET.
Earth Continuity Conductors (ECCs): Connect exposed conductive parts of equipment to the
MET.3
Materials: Copper is mandated for earth conductors (e.g., minimum 95 sq mm copper for main
earth conductors at substations, increasing to 120 sq mm if over 50m long).
Sizing: Determined based on the main earthing conductor and the protective device rating
(adiabatic equation or tables like DEWA's cable chart). Main equipotential bonding conductors
(which are part of the earthing system in practice) should be sized according to live conductors
of the incoming supply, but not less than 6mm². Supplementary bonding is 2.5mm² (protected) or
4mm² (unprotected).
Identification: Green/Yellow color coding (though not explicitly stated for all, it's a universal
standard).
Connections: Must be robust, low-resistance, and protected against corrosion.
General:
Separate earthing for MV, LV, ELV, private generators, and lightning protection unless
specifically approved to be connected.
Regular testing of earth resistance is recommended.
Here are 20 multiple-choice questions focusing on "Earth Electrodes, Earth Terminals, and Earth
Conductors" within DEWA regulations, presented in plain text with the answer key and
explanations provided at the end.
A) To generate electricity.
2. According to DEWA-aligned standards, what are common types of earth electrodes recognized
as suitable for providing a low-resistance path to earth?
B) Earth rods, earth plates, and underground structural metalwork embedded in foundations.4
A) 0.5 meters.
B) 1 meter.
C) 3 meters.
D) 5 meters.
4. What material is commonly specified for earth rods and conductors due to its excellent
conductivity and corrosion resistance in soil?
A) Aluminum.
B) Galvanized steel.
D) Stainless steel.
5. What is the general objective for the resistance value of an earth electrode system, aiming for
optimal safety and fault current dissipation?
6. For transformer neutral earthing and equipment body earthing at substations, DEWA guidelines
typically require earth resistance values to be below:
A) 10 ohms.
B) 5 ohms.
C) 2 ohms.
D) 1 ohm.
7. How should an earth electrode typically be housed to allow for inspection and testing?
8. When dealing with potentially corrosive soil conditions, what consideration is vital for the
material selection of an earth electrode?
D) Its weight.
B) A designated terminal or busbar where the main earthing conductor and all main protective
conductors (including bonding conductors) are connected.
10. All exposed conductive parts of electrical equipment in an installation must be connected to the
Main Earthing Terminal (MET) via:
A) Neutral conductors.
B) Live conductors.
D) Communication cables.
11. What is the minimum cross-sectional area for the main earthing conductor at substations, using
copper, as per DEWA guidelines, for lengths up to 50m?
A) 16 mm².
B) 35 mm².
C) 70 mm².
D) 95 mm².
12. If the length of a main earthing conductor exceeds 50m at a substation, what is the increased
minimum cross-sectional area of copper conductor specified by DEWA?
A) 95 mm².
B) 120 mm².
C) 150 mm².
D) 185 mm².
13. How are earth continuity conductors (ECCs) for circuits within a consumer's installation
generally sized in relation to the associated live conductors?
B) Sized according to the protective device and fault current, often following tables or adiabatic
equations, and potentially smaller than the live conductor but with specific minimums.
14. What is the standard color identification for protective conductors (earth conductors) in electrical
installations as per international and DEWA-aligned standards?
A) Blue.
B) Brown.
C) Green-and-yellow.
D) Black.
15. Why is it crucial for all connections in an earthing system (electrode, terminals, conductors) to
be robust and of low resistance?
B) To ensure a reliable and effective path for fault currents, facilitating quick operation of
protective devices and maintaining equipotentiality.
16. Which of the following earthing components are generally required to have separate earthing
networks and not be connected with the main Electrical Earthing System without specific
approval from DEWA?
B) Lighting circuits.
C) MV, LV, ELV networks, private generators, and lightning protection systems.
D) HVAC units.
17. What type of conductor connects incoming main metallic services (like water pipes, gas pipes) to
the Main Earthing Terminal?
A) Live conductor.
B) Neutral conductor.
D) Control cable.
18. What method is used to verify the effectiveness and continuity of earth conductors and their
connections?
A) Voltage measurement.
D) Current measurement.
19. In a TN-S system (mandated by DEWA), is the neutral conductor permitted to be connected to
the earthing system at the consumer's main earthing terminal or any other point within the
consumer's installation?
B) No, the neutral and earth conductors must be kept separate throughout the installation.
20. What is a key design consideration for earthing and bonding conductors regarding mechanical
protection?
Here's a summary of key points from the search results to formulate MCQs:
EFLI (Zs): The impedance of the earth fault current loop starting from the phase conductor,
through the fault, the protective earth conductor (CPC/PE), the main earthing terminal, the earth
electrode (if applicable), the general mass of earth, the transformer's earth, the transformer
winding, and back to the phase conductor.1
Importance: Crucial for ensuring that, in the event of an earth fault (phase-to-earth fault),
enough fault current flows to rapidly operate the protective device (fuse, circuit breaker, RCD)
within a safe disconnection time.2
Safety: Prevents electric shock (indirect contact) and fire due to sustained fault currents.
Components of EFLI:
Ze (External Earth Fault Loop Impedance): The impedance of the fault loop external to the
installation, typically measured at the origin (e.g., incoming supply terminals at the distribution
board).3 This includes the transformer winding, supply cables, and the supply earthing
arrangement.
Zs (Total Earth Fault Loop Impedance): The total impedance of the circuit, which is Ze + (R1
+ R2), where R1 is the resistance of the line conductor and R2 is the resistance of the circuit
protective conductor (CPC) for the specific circuit.4
BS 7671 Tables: Maximum Zs values are given in tables (e.g., Tables 41.2, 41.3, 41.4) of BS
7671 for various protective devices (fuses, MCBs of different types B, C, D) and disconnection
times (e.g., 0.4 seconds for final circuits in TN systems, 5 seconds for distribution circuits).
Temperature Correction: Measured Zs values (at ambient temperature) should typically be no
more than 80% of the maximum tabulated values (which are based on operating temperature) to
ensure compliance.
RCDs: For circuits protected by RCDs, the Zs values often allow for higher impedance, as the
RCD operates based on residual current rather than solely on overcurrent magnitude, provided
RA×IΔn≤50V.
Measurement:
Protective devices may not operate within the required safe time.
Prolonged hazardous touch voltages.
Risk of electric shock, electrocution.
Overheating of conductors, leading to fire risk.
Damage to electrical equipment.
1. What does "Earth Fault Loop Impedance (EFLI or Zs)" represent in an electrical installation?
B) The total impedance of the path a fault current would take from the phase conductor, through
the fault, the protective conductor, the earthing system, back to the source transformer.
B) To ensure that, in the event of an earth fault, sufficient current will flow to operate the
protective device within a safe disconnection time.
3. Which of the following elements forms part of the earth fault loop path?
B) The live conductor, the faulty equipment's exposed conductive part, the protective earth
conductor, the main earthing terminal, the earth electrode (if applicable), and the supply
transformer winding.
4. The value of Earth Fault Loop Impedance directly influences the effectiveness of which
protective measure?
A) Overload protection.
D) Voltage regulation.
B) The impedance of the earth fault loop external to the consumer's installation, measured at the
origin of the installation.
A) Zs = Ze - (R1 + R2).
B) Zs = Ze + (R1 + R2), where R1 is the resistance of the line conductor and R2 is the resistance
of the circuit protective conductor.
C) Zs = R1 + R2 only.
D) Zs = Voltage / Current.
7. What is a major consequence if the Earth Fault Loop Impedance is too high?
B) The protective device (e.g., circuit breaker or fuse) may not operate within the required safe
time, leading to prolonged hazardous voltages, risk of electric shock, or fire.
8. For most final circuits in a TN system (like DEWA's) operating at 230V, what is the commonly
required maximum disconnection time for protection against electric shock during an earth fault?
A) 0.1 seconds.
B) 0.4 seconds.
C) 1 second.
D) 5 seconds.
9. What type of instrument is typically used to measure Earth Fault Loop Impedance?
A) Voltmeter.
B) Ammeter.
D) Oscilloscope.
10. When measuring Zs, why is it usually measured at the electrically most remote point of a circuit
(e.g., the furthest socket outlet)?
B) To ensure the impedance is low enough at the point where it is expected to be highest.
11. What is the relationship between the magnitude of prospective earth fault current (If) and Earth
Fault Loop Impedance (Zs)?
12. In the context of BS 7671 (which DEWA aligns with), maximum Zs values given in tables are
based on conductor temperature at normal operating conditions. When actually measured at
ambient temperature, the measured Zs should ideally be what percentage of the tabulated
maximum value to account for temperature rise?
C) At least 120%.
D) Exactly 50%.
13. How does the presence of an RCD (Residual Current Device) affect the maximum permissible
Earth Fault Loop Impedance for a circuit?
B) RCDs generally allow for higher Zs values compared to overcurrent devices (fuses/MCBs)
alone, as they operate based on earth leakage current rather than magnitude of fault current.
14. For circuits protected by RCDs, what is the fundamental condition that must be met to ensure
shock protection, even if Zs is relatively high?
B) RA×IΔn≤50V, where RA is the resistance of the earth electrode and IΔn is the rated residual
operating current of the RCD.
15. What are common ways to reduce a high Earth Fault Loop Impedance if it fails the required
safety limits?
B) Increasing the conductor cross-sectional area of the phase and/or protective conductors, or
improving the main earthing system.
D) Replacing the circuit breaker with a higher-rated one without other changes.
16. Which type of electrical system, as adopted by DEWA, uses a dedicated protective earth (PE)
conductor from the supply transformer to the consumer's installation, directly influencing the
EFLI path?
A) TT system.
B) IT system.
C) TN-S system.
D) TN-C system.
17. The earth fault loop impedance test is typically performed when the circuit is:
B) Live, using a specialized tester that minimizes current flow to prevent tripping.
18. What risk is specifically mitigated by ensuring a sufficiently low Earth Fault Loop Impedance
and proper protective device operation?
A) Undervoltage.
B) The risk of prolonged touch voltages causing fatal electric shock during an earth fault.
C) Over-frequency.
B) After completion of wiring and before energizing, often as part of the initial verification and
testing regime.
20. When calculating the prospective earth fault current using Ohm's Law and the measured Zs, what
voltage value is typically used?
B) The nominal voltage to earth (U0, e.g., 230V for a 230/400V system).
1. B) The total impedance of the path a fault current would take from the phase conductor,
through the fault, the protective conductor, the earthing system, back to the source
transformer.
o Explanation: EFLI defines the entire loop for a phase-to-earth fault. 7
2. B) To ensure that, in the event of an earth fault, sufficient current will flow to operate the
protective device within a safe disconnection time.
o Explanation: This is the core safety function – ensuring protective devices work when needed.
3. B) The live conductor, the faulty equipment's exposed conductive part, the protective earth
conductor, the main earthing terminal, the earth electrode (if applicable), and the supply
transformer winding.
o Explanation: This describes the complete loop path from source to fault and back.
4. C) Automatic Disconnection of Supply (ADS).
o Explanation: ADS relies on a sufficiently low EFLI to draw enough fault current to trip the
protective device quickly.8
5. B) The impedance of the earth fault loop external to the consumer's installation, measured
at the origin of the installation.
o Explanation: Ze is the impedance provided by the supply network.
6. B) Zs = Ze + (R1 + R2), where R1 is the resistance of the line conductor and R2 is the
resistance of the circuit protective conductor.
o Explanation: This formula combines the external loop impedance with the impedance of the
consumer's circuit conductors.
7. B) The protective device (e.g., circuit breaker or fuse) may not operate within the required
safe time, leading to prolonged hazardous voltages, risk of electric shock, or fire.
o Explanation: High impedance restricts fault current, delaying or preventing the operation of
protective devices.9
8. B) 0.4 seconds.
o Explanation: This is a critical disconnection time for final circuits likely to be handled by
persons, as per BS 7671 (and thus DEWA's alignment).
9. C) Earth Loop Impedance Tester (or Multifunction Tester).
o Explanation: Specialized equipment is required to perform this measurement accurately and
safely.
10. B) To ensure the impedance is low enough at the point where it is expected to be highest.
o Explanation: The furthest point will have the longest conductor lengths, hence the highest
impedance, making it the worst-case scenario.
11. B) If is inversely proportional to Zs (If=Vphase/Zs).
o Explanation: This is a direct application of Ohm's Law. Higher impedance means lower fault
current.10
12. B) Not greater than 80%.
o Explanation: This 80% rule is a safety margin to account for the increase in conductor
resistance when at operating temperature compared to ambient test conditions.
13. B) RCDs generally allow for higher Zs values compared to overcurrent devices
(fuses/MCBs) alone, as they operate based on earth leakage current rather than magnitude
of fault current.
o Explanation: RCDs sense small imbalances, so they don't require the large fault currents that
overcurrent devices need for rapid tripping.11
14. B) RA×IΔn≤50V, where RA is the resistance of the earth electrode and IΔn is the rated
residual operating current of the RCD.
o Explanation: This condition ensures that the touch voltage ( 12RA×IΔn) remains below a safe
limit (50V) during a fault, even with an RCD. 13
15. B) Increasing the conductor cross-sectional area of the phase and/or protective conductors,
or improving the main earthing system.
o Explanation: Reducing the resistance of the conductors in the loop is the direct way to lower
impedance.
16. C) TN-S system.
o Explanation: DEWA mandates the TN-S system, characterized by separate N and PE
conductors.
17. B) Live, using a specialized tester that minimizes current flow to prevent tripping.
o Explanation: EFLI tests are performed on live circuits to get a real-world reading, but testers
use low-current methods (especially for RCD circuits) to prevent nuisance tripping. 14
18. B) The risk of prolonged touch voltages causing fatal electric shock during an earth fault.
o Explanation: A low Zs ensures quick disconnection, preventing dangerous voltages from
persisting.15
19. B) After completion of wiring and before energizing, often as part of the initial verification
and testing regime.
o Explanation: It's a critical test in the initial commissioning process to ensure safety compliance.
20. B) The nominal voltage to earth (U0, e.g., 230V for a 230/400V system).
o Explanation: The phase-to-earth voltage drives the earth fault current. 16
The search results provide specific and relevant information regarding "Plugs and Sockets"
within DEWA regulations. Key points identified for MCQs include:
BS 1363 (13A): This is explicitly mentioned as the mandatory standard for all 13 Ampere socket
outlets in new DEWA installations. This includes the requirement for a fuse in the plug.
IEC 60309 (BS 4343 / CEEFORM): This standard is specified for industrial plugs and sockets
(e.g., 16A, 32A, 63A, 125A), indicating their use for higher current applications.
Non-Interchangeability: Plugs and sockets of different current ratings or types (e.g., 13A vs.
15A, industrial) must not be interchangeable to prevent mismatches.
15A Round Pin Sockets: These are generally prohibited for new installations but allowed for
replacements in existing ones. DEWA might encourage phasing them out in favor of 13A.
Earthing: All socket outlets must be of the three-pin type (i.e., with an earth connection).
Shutters: 13A socket outlets must have shutters over the live and neutral apertures for safety.
RCD Protection: Crucial requirement. All socket outlets of rating 20A or less (unless
specifically exempted in controlled environments) must be protected by a 30mA RCD. This is a
very strong and repeated requirement.
Mechanical Protection/IP Rating: Essential for outdoor or wet locations (e.g., IP44 minimum
for outdoor, higher for exposed areas).
Accessibility of Fuses: Fuses in plugs must be easily accessible.
Installation Requirements:
Height: Socket outlets should be installed at a height of 300-1100 mm from the finished floor
level (FFL), unless specific exemptions apply (e.g., for disabled users). Kitchen worktop sockets
are typically higher.
Circuit Assignment: Each ring final circuit (for sockets) should not serve an area exceeding 100
m² floor area.
Dedicated Circuits: Certain fixed high-power appliances (e.g., A/C units, water heaters,
cookers) require dedicated circuits and often a fused spur/isolator rather than a plug/socket.
This information is very comprehensive and specific, allowing for the creation of robust MCQs
relevant to DEWA's regulations.
DEWA Regulations: Plugs and Sockets - MCQs
1. According to DEWA regulations, what is the mandatory standard for all 13 Ampere (13A)
socket outlets in new electrical installations?
A) IEC 60309.
B) BS 1363.
C) NEMA 5-15.
2. A key safety feature of 13A socket outlets mandated by DEWA is the inclusion of:
A) A built-in voltmeter.
C) A temperature sensor.
A) Miniaturized battery.
B) Replaceable fuse.
C) Temperature indicator.
D) Wireless transmitter.
4. For industrial applications requiring higher current ratings (e.g., 16A, 32A, 63A, 125A), what
international standard for plugs and sockets is specified in DEWA regulations?
A) BS 1363.
C) NEMA 5-20.
D) JIS C 8303.
5. Why is it a critical safety principle that plugs and sockets of different current ratings or types
(e.g., 13A vs. 15A round pin) must not be interchangeable?
6. Which type of socket outlet is generally prohibited for new installations in DEWA-regulated
areas, but may be allowed for replacement in existing installations?
D) Shaver sockets.
7. All socket outlets installed in any new DEWA-approved electrical installation must be of what
contact configuration?
A) 50 m².
B) 75 m².
C) 100 m².
D) 150 m².
9. What is a mandatory additional protection requirement for all socket outlets of rating 20A or less
in new DEWA installations, unless specifically exempted?
B) They must be protected by a Residual Current Device (RCD) with a rated residual operating
current not exceeding 30 mA.
10. What is the typical range for the height of socket outlets from the finished floor level (FFL) in
general purpose rooms as per DEWA guidelines?
A) 0-100 mm.
B) 300-1100 mm.
C) 1500-2000 mm.
A) IP20.
B) IP44.
C) IP65.
D) IPX0.
12. Why do certain fixed high-power appliances (e.g., electric cookers, water heaters, large AC
units) typically require a dedicated circuit and a fused connection unit or isolator, rather than a
plug and socket?
C) Their high current demand often exceeds typical plug and socket ratings, requiring direct
wiring for safety and reliability.
13. What is the primary reason for placing RCD protection on socket outlets, particularly those
accessible to general users?
D) Undervoltage conditions.
15. What safety requirement applies to the connection of the protective earth conductor in a three-pin
plug?
B) It should be robust and typically longer than the live and neutral pins to ensure the earth
connection is made first and broken last.
C) It should be removable.
16. What is important about the fuse rating inside a 13A plug?
B) It should be selected to protect the flexible cable of the appliance, appropriate for the
appliance's current rating.
17. When installing socket outlets in a kitchen above a worktop, they are often installed at a higher
level than general purpose sockets. What is the reason for this?
B) For convenience and to keep them clear of spills and other kitchen activities.
C) To improve ventilation.
B) Immediately isolate the supply to that point and replace the damaged component.
19. Why are sockets outlets not generally permitted in Zone 0 and Zone 1 of a bathroom/shower
room (areas close to the bath/shower)?
B) Due to the extremely high risk of electric shock in the presence of water, direct contact with
live parts must be prevented by design.
C) To save space.
20. What document would a DEWA-approved contractor typically provide to demonstrate that the
plugs and sockets meet required standards and safety features?
1. B) BS 1363.
o Explanation: BS 1363 is the standard for 13A plugs and sockets (square pin, fused plug) widely
adopted in the UAE.
2. B) Shutters over the live and neutral apertures.
o Explanation: Shutters prevent the insertion of foreign objects into the live contacts, enhancing
safety, especially for children.
3. B) Replaceable fuse.
o Explanation: 13A plugs (BS 1363) are unique in requiring a fuse within the plug itself to protect
the appliance's flexible cable.
4. B) IEC 60309 (often referred to as BS 4343 or CEEFORM).
o Explanation: This standard defines the robust, often waterproof, multi-pin plugs and sockets
used for industrial power connections.
5. C) To prevent overcurrent or incorrect connection of appliances to unsuitable circuits.
o Explanation: Non-interchangeability is a critical safety feature to ensure devices are connected
to circuits that can handle their load, preventing hazards.
6. C) 15A round pin.
o Explanation: While once common, these are phased out in favor of the safer and more versatile
13A BS 1363 standard for new installations in many regions, including likely DEWA.
7. B) Three-pin (live, neutral, and earth).
o Explanation: An earth connection is fundamental for safety in most modern electrical systems
to protect against indirect contact.
8. C) 100 m².
o Explanation: This is a common design limit for ring final circuits to ensure adequate current-
carrying capacity and fault protection.
9. B) They must be protected by a Residual Current Device (RCD) with a rated residual
operating current not exceeding 30 mA.
o Explanation: This is a critical DEWA requirement to provide additional protection against
electric shock for general-purpose socket outlets.
10. B) 300-1100 mm.
o Explanation: This range balances accessibility for users with protection from floor-level
hazards.
11. B) IP44.
o Explanation: IP44 provides protection against splashing water from any direction, making it
suitable for many outdoor uses. Higher ratings might be needed for very exposed or submerged
areas.
12. C) Their high current demand often exceeds typical plug and socket ratings, requiring
direct wiring for safety and reliability.
o Explanation: Plugs and sockets have current limits. High-power appliances need more robust,
permanent connections.
13. B) To protect against electric shock in case of insulation failure or accidental contact.
o Explanation: RCDs quickly detect and disconnect power in case of earth leakage, which is the
primary cause of electric shock.
14. C) Small earth leakage currents.
o Explanation: A 30mA RCD is specifically designed to trip on small currents to earth that are too
low to operate an MCB/fuse but dangerous to humans.
15. B) It should be robust and typically longer than the live and neutral pins to ensure the
earth connection is made first and broken last.
o Explanation: This design ensures the appliance is always earthed when connected and
disconnected, providing continuous safety.
16. B) It should be selected to protect the flexible cable of the appliance, appropriate for the
appliance's current rating.
o Explanation: The plug fuse is there to protect the specific appliance's flexible cord from
overload, not the entire circuit.
17. B) For convenience and to keep them clear of spills and other kitchen activities.
o Explanation: Practical considerations for functionality and safety in a kitchen environment.
18. B) Immediately isolate the supply to that point and replace the damaged component.
o Explanation: Damaged plugs or sockets are serious electrical hazards and must be addressed
immediately.
19. B) Due to the extremely high risk of electric shock in the presence of water, direct contact
with live parts must be prevented by design.
o Explanation: Zones in bathrooms are categorized by shock risk, and direct access to sockets is
prohibited in the highest risk zones.
20. B) Manufacturer's certificates and declarations of conformity for the devices.
o Explanation: These documents attest that the products meet the relevant safety and performance
standards.
The search results provide excellent distinctions between switches and isolators, and relevant
information on switch-disconnectors and load-break switches, which are important for DEWA
contexts (especially with higher voltages and generation).
Switches:
Purpose: To make, carry, and break currents under normal operating conditions, and often under
specified overload conditions. They are designed to operate under load.
Types: General purpose switches (e.g., light switches), circuit breakers (MCBs, MCCBs which
combine switching and protection), contactors, load break switches.
Breaking Capacity: Must be sufficient for the intended load and fault conditions.
Arc Extinction: Designed with arc extinguishing devices.
Isolators (Disconnectors):
Purpose: Primarily to provide a safe, visible means of disconnecting an electrical circuit from its
supply for maintenance, repair, or safety purposes. 1 They are not designed to break load current.
Operation: Must be operated "off-load" (i.e., after the current has been switched off by a switch
or circuit breaker).2 Operating them under load can cause dangerous arcing and damage. 3
Visible Break: Essential feature – a clear, visible air gap between contacts to ensure complete
isolation.4
Locking Facility (LOTO): Must be capable of being locked in the open (isolated) position to
prevent accidental re-energization.
No Arc Extinguishing Device: Typically, they lack devices to extinguish arcs because they are
not meant to break current.
Withstand Capability: Must be able to carry specified currents (including short-circuit currents)
for a short duration in the closed position without opening.
Switch-Disconnectors:
Combination: A mechanical switching device that combines the functions of a switch (making,
carrying, and breaking currents under normal and specified overload conditions) and an isolator
(providing isolation).
Usage: Often preferred where both switching under load and reliable isolation are required in
one device (e.g., main switches, motor isolators).
DEWA Context: The definition provided by DEWA for "switch-disconnector" in the context of
Distributed Renewable Resources Generators confirms this combined function and compliance
with disconnector requirements.
Padlockable Circuit Breakers: DEWA regulations mention these, which aligns with the need
for isolation and LOTO.
Load Break Switches:
Function: Capable of making and breaking specified load currents (including some overload
currents), but generally not short-circuit currents. They have a simple arc extinguishing device.
Usage: Often used in series with fuses for short-circuit protection (e.g., in MV/HV applications).
Distinction from CB: A circuit breaker can interrupt short-circuit currents, while a load break
switch generally cannot.5
B) To make, carry, and break current under normal operating conditions, and sometimes under
specified overload conditions.
D) To convert AC to DC.
B) To provide a safe, visible means of completely disconnecting a circuit from its supply for
maintenance or repair, when the circuit is off-load.
C) Off-load (i.e., after the current has been switched off by another device).
5. What device combines the function of a switch (making and breaking current under
normal/overload conditions) and an isolator (providing safe isolation)?
A) A fuse.
B) A contactor.
C) A switch-disconnector.
D) A transformer.
A) A fuse.
B) A resistor.
C) A disconnector (isolator).
D) A current transformer.
7. Which of the following is an essential safety feature for an isolator that ensures prevention of
accidental re-energization during maintenance?
A) Overload protection.
B) Make and break specified load currents and often some overload currents, but generally not
full short-circuit currents.
9. For the main incoming supply to a consumer's installation, what type of device is typically
employed by DEWA to allow for both load switching and isolation?
C) An earth electrode.
D) A socket outlet.
10. In MV (Medium Voltage) switchgear panels within private installations, DEWA regulations may
require a mechanical and/or electrical interlock between the earth-switch and the DEWA
incomer.7 What is the primary reason for this?
B) To prevent accidental energization of the circuit while the earth-switch is engaged, enhancing
safety for personnel.
11. What critical characteristic must a switch possess to be effective in controlling a circuit?
B) It must have sufficient breaking capacity for the current it is intended to interrupt under
normal and fault conditions.
12. Why should an isolator not be used to break a significant load current?
B) It is not designed with arc extinguishing capabilities, which could lead to dangerous arcing,
damage to the isolator, and a fire hazard.8
C) ASTM standards.
D) NEMA standards.
14. When selecting a switch or isolator for an application, which of the following ratings are crucial
to consider?
B) Current rating, voltage rating, short-circuit breaking capacity (for switches), and short-circuit
withstand current (for isolators/switch-disconnectors).
15. What does the term "off-load" mean in the context of operating an isolator?
16. What type of device acts as both a protective device and a switching device?
A) A fuse.
B) An isolator.
18. What characteristic of the operating mechanism of a switch is crucial for reliable performance?
19. Why is proper labeling and identification of switches and isolators important in an electrical
installation?
B) To allow for quick and safe identification of circuits and equipment for operation,
maintenance, and emergency disconnection.
D) To track inventory.
20. What is a key consideration for the environmental conditions when installing switches and
isolators in Dubai, as per DEWA's general requirements?
1. B) To make, carry, and break current under normal operating conditions, and sometimes
under specified overload conditions.
o Explanation: This defines the core operational role of a switch.
2. B) To provide a safe, visible means of completely disconnecting a circuit from its supply for
maintenance or repair, when the circuit is off-load.
o Explanation: Isolation is about creating a guaranteed safe gap.
3. B) Visible break (a clear physical separation of contacts).
o Explanation: The visible break is fundamental to an isolator, providing a clear indication of
disconnection for safety.9
4. C) Off-load (i.e., after the current has been switched off by another device).
o Explanation: Isolators are not designed to interrupt current, so they must be operated when no
current is flowing.10
5. C) A switch-disconnector.
o Explanation: This device combines the functionality of both a switch and an isolator, providing
both control and safety isolation.
6. C) A disconnector (isolator).
o Explanation: The definition of a switch-disconnector includes compliance with disconnector
requirements, particularly visible break and isolation.
7. C) A locking facility (e.g., for use with a padlock/LOTO).
o Explanation: A locking facility is crucial for implementing Lockout/Tagout procedures,
preventing accidental re-energization.
8. B) Make and break specified load currents and often some overload currents, but generally
not full short-circuit currents.
o Explanation: Load break switches are designed for operational switching under load, but
typically rely on other devices for short-circuit protection.
9. B) A switch-disconnector or main circuit breaker with isolation capability.
o Explanation: Main incoming devices need to be able to both control the supply and provide safe
isolation.
10. B) To prevent accidental energization of the circuit while the earth-switch is engaged,
enhancing safety for personnel.
o Explanation: Interlocks are critical safety features in MV/HV switchgear to prevent dangerous
operating sequences.11
11. B) It must have sufficient breaking capacity for the current it is intended to interrupt
under normal and fault conditions.
o Explanation: The breaking capacity ensures the switch can safely open the circuit without
damage or hazard.
12. B) It is not designed with arc extinguishing capabilities, which could lead to dangerous
arcing, damage to the isolator, and a fire hazard.
o Explanation: Arcing under load can be destructive and dangerous for devices not designed for
it.12
13. B) IEC standards (e.g., IEC 60947 series for low-voltage switchgear).
o Explanation: DEWA aligns with international standards, and IEC is predominant in electrical
equipment.
14. B) Current rating, voltage rating, short-circuit breaking capacity (for switches), and short-
circuit withstand current (for isolators/switch-disconnectors).
o Explanation: These are the essential electrical parameters for proper selection and safe
operation.
15. B) The circuit connected to the isolator is carrying no current.
o Explanation: "Off-load" means the circuit has been de-energized or the current has been
interrupted by another device.
16. C) A circuit breaker (e.g., MCB, MCCB).
o Explanation: Circuit breakers combine overload/short-circuit protection with manual switching
capability.13
17. B) Enabling a safe lockout/tagout (LOTO) procedure for maintenance.
o Explanation: Padlockable devices are fundamental to LOTO procedures, ensuring equipment
remains isolated during work.
18. B) It should ensure quick-make, quick-break action to minimize arcing time.
o Explanation: Rapid contact separation minimizes the duration of arcing, reducing wear and
improving safety.14
19. B) To allow for quick and safe identification of circuits and equipment for operation,
maintenance, and emergency disconnection.
o Explanation: Clear labeling is vital for operational efficiency and safety, especially during
emergencies.
20. B) They must be suitable for high ambient temperatures and humidity.
o Explanation: Dubai's climate requires electrical equipment to be rated for challenging
environmental conditions to ensure reliability and longevity.
The search results provide excellent and highly specific information about DEWA's regulations
concerning lighting. Key points identified for MCQs include:
LEDs are mandatory: All new indoor and outdoor lighting installations (residential,
commercial, industrial, public areas) must use LED lamps. This is a very strong and explicit
requirement.
Prohibition of old tech: Incandescent, halogen, and mercury vapor lamps are prohibited. T8/T5
fluorescent lamps are also phased out (or restricted) in favor of LED.
Minimum Efficacy: DEWA sets minimum efficacy requirements for LED lamps (e.g., >80
lm/W for general, >90 lm/W for commercial/industrial).
Maximum Connected Load: There are specified maximum connected lighting load densities
per square meter for different building types/uses.
IP Ratings: Lamps/luminaires must have appropriate Ingress Protection (IP) ratings based on
their location:
o Bathrooms: IPX4 (for zones 1 & 2), IPX2 (for zone 3).
o Outdoor: Minimum IP44 (or higher for exposed conditions).
o Wet/Dusty environments: Higher IP ratings as per specific conditions.
Heat & Clearances: Luminaires must be installed respecting manufacturer's recommended
clearances from combustible materials.
Circuit Protection: Lighting circuits must be protected by appropriate circuit breakers (e.g.,
MCBs) against overcurrent.
RCD Protection: Outdoor lighting circuits must be protected by a 30mA RCD.
Emergency Lighting: Mandatory in public buildings, large residential blocks, and commercial
premises (exit signs, escape route lighting) with minimum durations (e.g., 2 or 3 hours).
This detailed information is more than sufficient to generate 20 comprehensive MCQs directly
relevant to DEWA's lighting regulations.
DEWA Regulations: Lighting - MCQs
1. According to current DEWA regulations for new installations, which type of lamp technology is
mandatory for all indoor and outdoor lighting applications?
A) Incandescent lamps.
B) Halogen lamps.
D) LED lamps.
2. Which of the following lamp types are explicitly prohibited for new installations under DEWA's
energy efficiency regulations?
A) LED lamps.
D) Sodium lamps.
3. DEWA regulations specify minimum efficacy requirements for LED lamps. What is the typical
minimum efficacy (in lumens per Watt, lm/W) required for general purpose indoor LED
lighting?
A) Below 50 lm/W.
B) Above 80 lm/W.
C) Exactly 60 lm/W.
D) No specific requirement.
4. What is a key reason for DEWA's stringent focus on mandating LED lighting and prohibiting
older technologies?
5. DEWA regulations may specify a maximum connected lighting load density for various building
types. What is the purpose of this requirement?
6. Are T8/T5 fluorescent lamps still permitted for general lighting in new DEWA installations?
A) Yes, universally.
7. What quality characteristic of LED lighting, beyond efficacy, is often emphasized in DEWA
guidelines to ensure user comfort?
8. For luminaires (light fittings) installed in bathrooms, what minimum Ingress Protection (IP)
rating is typically required for Zones 1 and 2?
A) IP20.
B) IP44.
C) IPX4.
D) IP68.
9. What minimum IP rating is generally required for lighting luminaires installed outdoors, subject
to typical weather conditions?
A) IP20.
B) IP44.
C) IP2X.
D) IPX0.
10. What additional protection device is mandatory for outdoor lighting circuits as per DEWA
regulations?
A) A time switch.
B) A Residual Current Device (RCD) with a rated residual operating current not exceeding 30
mA.
12. What specific type of lighting is mandatory in public buildings, large residential blocks, and
commercial premises to ensure safe evacuation in case of power failure?
A) Decorative lighting.
B) Task lighting.
D) Accent lighting.
13. What is the typical minimum duration that emergency lighting systems are required to operate
after a power failure in large buildings?
A) 30 minutes.
B) 1 hour.
D) 30 seconds.
14. What type of sensors are encouraged by DEWA for lighting control to promote energy saving in
areas like corridors, stairwells, and offices?
A) Pressure sensors.
C) Humidity sensors.
D) Vibration sensors.
15. What safety principle is paramount for the circuit protection of lighting installations?
B) Protection against overcurrent (overload and short circuit) by appropriately rated circuit
breakers.
16. Which of the following is a key design consideration for lighting to ensure visual comfort and
prevent eye strain?
A) Maximizing glare.
17. What type of lighting control system is encouraged for greater flexibility and potential for energy
savings in various building types?
18. What action is required if a light fitting's casing or wiring insulation is damaged?
20. What is a crucial aspect of maintenance for lighting systems to ensure continued efficiency and
safety?
B) Regular cleaning of luminaires and replacement of old/inefficient lamps with compliant types.
1. D) LED lamps.
o Explanation: DEWA has mandated LED technology for energy efficiency in new installations.
2. C) Incandescent, Halogen, and Mercury Vapor lamps.
o Explanation: These older, less efficient technologies are prohibited by DEWA.
3. B) Above 80 lm/W.
o Explanation: DEWA sets minimum efficacy standards for LED lamps to ensure genuine energy
savings.
4. B) To significantly reduce electricity consumption and carbon emissions.
o Explanation: This is the primary driver behind DEWA's energy efficiency mandates.
5. B) To ensure efficient use of energy by discouraging over-lighting.
o Explanation: Load density limits prevent excessive energy consumption for lighting.
6. C) Generally phased out or restricted in favor of LED alternatives.
o Explanation: While not outright prohibited in all specific retrofit cases, the strong preference
and regulatory drive is towards LED.
7. B) Low flicker and good Color Rendering Index (CRI).
o Explanation: These qualities contribute to visual comfort and proper perception of colors under
LED lighting.
8. C) IPX4.
o Explanation: IPX4 (protection against splashing water) is generally required for luminaires in
bathroom zones where water splashes are likely.
9. B) IP44.
o Explanation: IP44 provides protection against solid objects larger than 1mm and splashing
water, making it suitable for many outdoor applications.
10. B) A Residual Current Device (RCD) with a rated residual operating current not exceeding
30 mA.
o Explanation: RCD protection is mandatory for outdoor circuits due to the increased risk of
electric shock in the presence of moisture.
11. B) To prevent overheating and potential fire hazards.
o Explanation: Luminaires generate heat, and proper clearances prevent ignition of nearby
combustible materials.
12. C) Emergency lighting (e.g., exit signs, escape route lighting).
o Explanation: Emergency lighting is crucial for guiding occupants to safety during power
outages.
13. C) 2 or 3 hours (depending on building type/standard).
o Explanation: The duration ensures sufficient time for evacuation.
14. B) Motion/Occupancy sensors and Daylight sensors.
o Explanation: These sensors automate lighting control to switch off lights when areas are vacant
or dim them when natural light is sufficient, saving energy.
15. B) Protection against overcurrent (overload and short circuit) by appropriately rated
circuit breakers.
o Explanation: Circuit breakers prevent damage to cables and fixtures from excessive current.
16. B) Minimizing flicker and controlling glare.
o Explanation: High flicker or glare can cause discomfort, fatigue, and even health issues.
17. B) Dimmable lighting controls and smart lighting systems.
o Explanation: These systems offer granular control over light levels and automation, maximizing
energy efficiency and user comfort.
18. B) Isolate the power, repair or replace the damaged fitting immediately.
o Explanation: Damaged electrical components are a safety hazard and must be addressed
promptly.
19. B) Detailed electrical load schedules, lighting layouts, and specifications of luminaires.
o Explanation: DEWA requires comprehensive documentation to approve the electrical design
and ensure compliance.
20. B) Regular cleaning of luminaires and replacement of old/inefficient lamps with compliant
types.
o Explanation: Maintenance ensures that lighting systems continue to operate safely and
efficiently over their lifespan.
The search results provided highly relevant and detailed information on conduit, trunking, and
cable tray systems as per DEWA regulations and general UAE electrical standards.
Conduit:
Types: Rigid Metal Conduit (RMC), Intermediate Metal Conduit (IMC), PVC conduit, Flexible
Metal Conduit (FMC), Liquid-tight Flexible Metal Conduit (LFMC). Each with specific
applications (e.g., RMC for heavy duty/fire resistance, PVC for outdoor/underground/corrosion
resistance, FMC for tight spaces/vibrations).
Purpose: Protection against physical damage, abrasion, mechanical impact, fire, and
environmental hazards. Ensures compliance with UAE electrical regulations (including DEWA).
Standards: Compliance with IEC 61386.
Installation: Surface-mounted or concealed. Specific support spacings (e.g., Steel conduits:
120cm horizontal, 150cm vertical; Rigid PVC conduits: 100cm horizontal, 120cm vertical).
Fill Ratio: Maximum number of cables allowed for different conduit sizes and cable cross-
sectional areas. (A DEWA table was found with specific numbers for various conduit sizes and
cable mm²).
Protection: Prevention of water entry into conduits, junction boxes, and distribution boards
(DBs).
Earthing: Metallic conduits must be properly earthed as part of the protective earthing system.
Trunking:
Cable Tray:
Purpose: Support for cables, allows ventilation (especially perforated or ladder types).
Standards: IEC 61537 and EN 61537 are mentioned for cable tray systems.
Installation: Cables must be securely supported by cable clips, cable tray, or other fixings at
suitable intervals.
Fill Ratio: The sum of the cross-sectional areas of all cables on a cable tray must not exceed a
certain percentage (though the exact percentage wasn't explicitly stated for tray in the same way
as trunking, the concept of fill ratio applies).
Segregation: Implied necessity for managing different cable types (e.g., power, data) and
ensuring adequate space.
Earthing/Bonding: Metallic cable trays must be effectively bonded and earthed.
General:
Workmanship: All electrical installations shall be carried out in a neat, orderly, workmanlike
manner.
Environmental Conditions: All equipment and materials must be suitable for Dubai's climatic
conditions (high ambient temperature, high humidity).
Accessibility: Termination points and junction boxes must remain accessible for inspection,
repair, and alteration.
Standards: Compliance with DEWA Regulations, latest IEE Wiring Regulations, and relevant
IEC/ISO standards.
This detailed information is more than enough to create 20 relevant and distinct MCQs.
C) PVC conduit.
3. For a rigid PVC conduit installed horizontally, what is the typical maximum spacing of supports
allowed as per DEWA guidelines?
A) 50 cm.
B) 100 cm.
C) 150 cm.
D) 200 cm.
4. When installing metallic conduits, what crucial safety measure must be implemented to protect
against electric shock in case of insulation failure?
5. What is a key requirement for all conduit systems installed by DEWA-approved contractors
concerning junction boxes and inspection points?
B) The total cross-sectional area of cables compared to the internal cross-sectional area of the
conduit.
7. Which standard governs the performance and specifications of electrical conduits globally,
aligning with UAE regulations?
A) ISO 9001.
B) IEC 61386.
C) BS 7671.
D) NEMA 250.
9. As per DEWA-aligned regulations, what is the maximum permissible space factor (fill ratio) for
cables inside a trunking system?
A) 25%.
B) 40%.
C) 50%.
D) 75%.
10. For steel trunking installed horizontally, what is the typical maximum spacing of supports
recommended by DEWA standards?
A) 100 cm.
B) 120 cm.
C) 150 cm.
D) 180 cm.
11. Why is it important to ensure that metallic trunking is properly earthed and bonded?
B) To provide a low-resistance path for fault currents in case of insulation failure, preventing
electric shock.
12. What specific standard is mentioned for Galvanized Iron (GI) trunking systems used in DEWA-
regulated installations, particularly concerning minimum thickness?
A) BS 1363.
C) IEC 60529.
D) EN 50085.
13. For trunking installed on the Distribution Company's side of the connection point, what
additional security feature might be required?
A) Fire-rated paint.
D) Transparent covers.
Part 3: Cable Tray Systems and General Requirements
14. What is a primary advantage of using cable tray systems compared to conduits or trunking for
managing a large number of cables?
B) They provide excellent ventilation for cables and are suitable for large cable runs.
15. What international standard is specified for the design and testing of cable tray systems, as per
DEWA-aligned requirements?
A) IEC 60050.
B) IEC 61537.
C) EN 50174.
D) ISO 14001.
16. In multi-service installations (e.g., power cables and data cables), what practice should be
followed regarding cable trays?
B) Cables should be segregated (e.g., using dividers or separate trays) to prevent interference and
for safety.
18. All electrical equipment and materials, including conduits, trunking, and cable trays, used in
Dubai must be suitable for what specific environmental conditions?
A) Arctic temperatures.
C) Underwater submersion.
D) High altitude.
19. Why is it important to select cable containment systems with appropriate Ingress Protection (IP) ratings
for different environments (e.g., outdoor, wet areas)?
B) To prevent the ingress of dust, solid objects, and water, protecting the cables and ensuring safety.
20. Before commencing any electrical installation involving containment systems, what general requirement
must be fulfilled with DEWA?
B) Detailed drawings and specifications of the proposed installations must be submitted for review and
approval.
Compliance: All electrical installations, including cables and wires, must comply with DEWA
Regulations, latest IET Wiring Regulations (formerly IEE), and relevant IEC/ISO standards.
Suitability: All equipment and materials must be suitable for Dubai's climatic conditions (high
ambient temperature and humidity).
Workmanship: Installations must be carried out in a neat, orderly, workmanlike manner.
Conductor Material: Stranded copper conductors are explicitly required for fixed wiring within
premises (PVC, rubber, or XLPE insulated). Solid-core copper or aluminum conductors are not
permitted for fixed wiring.
Insulation Material: PVC, rubber, or XLPE (Cross-linked Polyethylene) are specified
insulation types. XLPE is particularly noted for MV cables (e.g., DEWA standard 11kV cables
are often Copper XLPE or Aluminum XLPE).
Cable Types:
o Armoured Cables: Recommended for locations with a higher than normal risk of interference
or damage.
o Fire Resistance: For locations with higher than normal fire risk, cables must be installed in
metal conduit, or Mineral-Insulated Copper-Clad (MICC) cables (BS EN 60702), or enhanced
fire-resistance cables (meeting PH 120 / BS EN 50200 and 120 mins survival BS 8434-2) must
be used. Safety circuits (fire alarms, emergency lighting) must use these fire-resistant methods.
o Flexible Cords: General-purpose flexible cables for appliances must be PVC insulated with a
PVC oversheath and stranded copper conductors (BS EN 50525).
MV Cables: DEWA has standard 11 kV cable sizes (3/C 300mm² Copper XLPE, 3/C 240mm²
Copper XLPE, and 3/C 240mm² Aluminum XLPE) and 22 kV cable size (3/C 300mm²
Aluminum XLPE).
Current-Carrying Capacity: Cables must be capable of carrying the full load current
continuously without overheating.
Voltage Drop: The total voltage drop from the main distribution board (MDB) to the furthest
point of any circuit must not exceed 2.5% of the nominal supply voltage. This is a critical
parameter. (One source mentioned 5% at the furthest receptacle, but DEWA's own spec for fixed
wiring states 2.5%). I will use 2.5% as it's directly from DEWA's instrumentation cable specs
which also covers general wiring.
Short-Circuit Withstand: Cables must be selected to withstand short-circuit currents for the
fault duration.
Load Calculation: Emphasized for proper cable sizing.
Installation:
Colour Codes: Mentioned as crucial for safety and identification. While specific DEWA color
codes weren't found in direct regulatory documents during this quick search (they typically
follow IEC/BS standards, e.g., Brown/Black/Grey for phases, Blue for neutral, Green/Yellow for
earth), the importance of color coding is highlighted. I will focus on the principle of color
coding.
Mechanical Protection: Cables must be adequately protected against mechanical damage (e.g.,
armored cables, in conduit).
Fire Barriers: Location and selection of cables must consider the prevention of fire spread; fire
barriers may be required.
Underground Cables: Specific depths (e.g., 90cm-1.2m for HV), protection tiles (30cm above
cable), and warning tape (30cm above tiles) for MV/HV cables.
Accessibility: All electrical connections must be properly insulated and accessible for
maintenance.
Testing:
Mandatory Tests: Insulation resistance test, continuity tests, polarity test, earth continuity test.
1. For fixed wiring within premises in DEWA-regulated installations, which conductor material is
explicitly required for cables?
A) Solid-core aluminum.
B) Stranded copper.
C) Solid-core copper.
D) Stranded aluminum.
2. Which insulation material is commonly specified for low voltage (LV) and medium voltage
(MV) cables in DEWA installations due to its good electrical and thermal properties?
A) Paper insulation.
B) Rubber.
D) Bare conductor.
3. According to DEWA-aligned regulations, which type of cable is recommended for locations with
a higher than normal risk of interference or mechanical damage?
C) Armoured cable.
D) Uninsulated busbar.
4. In locations with a higher than normal fire risk, what specific type of cable or installation method
is mandated for safety circuits like fire alarms and emergency lighting?
5. What defines a "flexible cord" or "flexible cable" in the context of appliance connections?
A) It is uninsulated.
C) It has stranded copper conductors, typically PVC insulated with a PVC oversheath, designed
for portability.
6. DEWA specifies standard sizes for MV (Medium Voltage) cables. Which of the following is a
commonly used conductor and insulation type for 11 kV cables in DEWA's network?
A) To dissipate heat.
8. The total voltage drop from the main distribution board (MDB) to the furthest point of any
circuit in a DEWA-approved low voltage installation must not exceed what percentage of the
nominal supply voltage?
A) 1%.
B) 2.5%.
C) 5%.
D) 10%.
9. When sizing cables, besides current-carrying capacity and voltage drop, what other critical factor
related to fault conditions must be considered?
A) Cable color.
B) Cable weight.
D) Aesthetic appearance.
10. What is a key factor that can reduce a cable's current-carrying capacity, requiring careful
consideration during design?
A) Increased voltage.
B) To facilitate quick and safe identification during installation, maintenance, and fault finding,
preventing electric shock.
12. Before commissioning, what crucial electrical test is performed on cables to ensure the integrity
of their insulation?
A) Continuity test.
13. For underground MV (Medium Voltage) cables, what protective layers are typically required
above the cable before backfilling, as per DEWA guidelines?
A) Sand only.
C) Water barriers.
D) Steel mesh.
14. What is the main purpose of an earthing conductor (or Protective Earth Conductor - PEC) within
a cable system?
B) To provide a safe path for fault currents to earth in case of insulation failure.
15. Why must all electrical connections, including those made with cables and wires, be properly
insulated and remain accessible?
B) To prevent electric shock and allow for maintenance, inspection, and testing.
16. Which general principle of workmanship is emphasized by DEWA for all electrical installations,
including the laying and termination of cables?
17. All cables and wires used in electrical installations in Dubai must be suitable for what specific
environmental conditions?
C) Immediately isolate the affected circuit and repair or replace the damaged section as per
safety standards.
19. In what context would armored cables be particularly beneficial in DEWA-regulated projects?
B) For mains power supply to outbuildings or in industrial areas where mechanical stress is a
concern.
20. Before starting any significant electrical installation work involving cables and wires, what
submission is generally required by DEWA?
B) Detailed plans, specifications, and load schedules for review and approval.
1. B) Stranded copper.
o Explanation: DEWA regulations specifically mandate stranded copper conductors for fixed
wiring within premises.
2. C) XLPE (Cross-linked Polyethylene).
o Explanation: XLPE is a high-performance insulation material commonly used for power cables
due to its excellent electrical, thermal, and mechanical properties.
3. C) Armoured cable.
o Explanation: Armoured cables provide enhanced mechanical protection against crushing or
impact, making them suitable for harsh environments.
4. B) Cables installed in metal conduits, or MICC cables, or enhanced fire-resistance cables.
o Explanation: These methods ensure circuit integrity during a fire, critical for safety systems.
5. C) It has stranded copper conductors, typically PVC insulated with a PVC oversheath,
designed for portability.
o Explanation: Flexible cords are designed for flexibility and often connect portable appliances.
6. B) Stranded Copper, XLPE insulated.
o Explanation: DEWA explicitly mentions 3/C 300mm² Copper XLPE and 3/C 240mm² Copper
XLPE as standard 11kV cable types.
7. C) To provide mechanical protection and environmental resistance to the insulated
conductors.
o Explanation: The outer sheath protects the core and insulation from external damage and
environmental factors.
8. B) 2.5%.
o Explanation: DEWA regulations state that the total voltage drop from the MDB to the furthest
point should not exceed 2.5% of the nominal supply voltage.
9. C) Short-circuit withstand capability.
o Explanation: Cables must be able to withstand the thermal and mechanical stresses of short-
circuit currents for the fault duration without damage.
10. B) Installation in hot ambient temperatures or grouping with other loaded cables.
o Explanation: Higher ambient temperatures and closer grouping reduce the ability of cables to
dissipate heat, thereby lowering their effective current-carrying capacity.
11. B) To facilitate quick and safe identification during installation, maintenance, and fault
finding, preventing electric shock.
o Explanation: Standardized color codes are a fundamental safety measure to identify live,
neutral, and earth conductors.
12. C) Insulation resistance test.
o Explanation: This test measures the effectiveness of the cable's insulation in preventing current
leakage, crucial for safety.
13. B) Protection tiles (e.g., concrete covers) and warning tape.
o Explanation: These layers provide mechanical protection and a warning sign to prevent
accidental excavation damage to buried cables.
14. B) To provide a safe path for fault currents to earth in case of insulation failure.
o Explanation: The earthing conductor ensures that in case of a fault, current is safely diverted to
earth, tripping protective devices.
15. B) To prevent electric shock and allow for maintenance, inspection, and testing.
o Explanation: Proper insulation is key to shock prevention, and accessibility allows for necessary
work.
16. C) All installations shall be carried out in a neat, orderly, workmanlike manner.
o Explanation: Quality workmanship is a general DEWA requirement for all electrical work,
ensuring reliability and safety.
17. B) High ambient temperatures and high humidity.
o Explanation: Electrical materials in Dubai must be rated to withstand the specific hot and humid
climate.
18. C) Immediately isolate the affected circuit and repair or replace the damaged section as per
safety standards.
o Explanation: Damaged cables are a serious hazard and must be addressed promptly and safely.
19. B) For mains power supply to outbuildings or in industrial areas where mechanical stress
is a concern.
o Explanation: Armoured cables are designed for applications where they are exposed to potential
mechanical damage.
20. B) Detailed plans, specifications, and load schedules for review and approval.
o Explanation: DEWA requires pre-approval of designs to ensure compliance with its regulations
before any significant work begins.
The search results provide comprehensive details for Final Circuits, Busways, Distribution
Boards, and LV Switchboards within DEWA regulations.
Final Circuits:
Definition: Circuits directly supplying current to the electrical utilization equipment (e.g.,
lighting, sockets, fixed appliances).
Protection: Each final circuit must be protected by an appropriate overcurrent protective device
(MCB/MCCB) and, in many cases, by a 30mA RCD (especially for sockets up to 20A, outdoor,
bathroom circuits).
Wiring: Minimum conductor sizes (e.g., 2.5 mm² for socket outlets, 1.5 mm² for lighting). Ring
final circuits (13A sockets) should not exceed 100 m² floor area.
Dedicated Circuits: Specific high-power fixed appliances (A/C units, water heaters, cookers)
must have dedicated final circuits.
Separation: Lighting and power circuits should generally be separate.
Purpose: Enclose protective devices (MCBs, RCDs/RCBOs) for final circuits. Act as a
centralized point for distribution within a sub-section of the installation.
Construction: Metal-clad enclosures, sufficient space for wiring, good IP rating (e.g., IP4X for
typical indoor).
Components: Must include a main incomer switch-disconnector, individual circuit protective
devices, neutral bar, and earth bar.
Labeling: Clear and permanent labeling for each circuit.
Location: Accessible, suitable environment (not in bathrooms, above cooker hobs, or in
hazardous areas). Height requirements (e.g., center between 1.4-1.8m from FFL).
Circuit Breakers: Must be of a suitable type (e.g., Type B/C/D MCBs) with appropriate
breaking capacity for the prospective fault current.
Purpose: Main intake point for the consumer's installation (MSB), or major sub-distribution
point (SMDB). Connects to DEWA's supply/meter and distributes to other DBs or feeders.
Construction: Type-Tested Assemblies (TTA) or Partially Type-Tested Assemblies (PTTA) are
mandatory. Metal-enclosed, free-standing or wall-mounted. Good ventilation, appropriate IP
rating.
Components: Main incoming circuit breaker (ACB/MCCB), robust busbar system, outgoing
feeder circuit breakers, current transformers for metering, protection relays, surge protective
devices (SPD).
Short-Circuit Withstand: Must be rated for the prospective short-circuit current at the point of
installation.
Safety Features: Internal segregation (e.g., Form 2 or higher), adequate clearances, clear
labeling, facilities for locking off (LOTO).
Location: Typically in dedicated electrical rooms (switchgear rooms) with specific access, fire-
rating, and ventilation requirements.
DEWA Approval: Detailed drawings and technical specifications must be submitted to DEWA
for approval.
Purpose: An alternative to cables for distributing power, especially for high currents or where
flexibility for future load changes is required (e.g., industrial plants, high-rise buildings).
Advantages: Ease of installation, flexibility for tap-off points, space saving, reduced voltage
drop over long runs compared to cables.
Components: Prefabricated busbar sections, jointing kits, tap-off units (with protection devices).
Ratings: Current rating, short-circuit withstand rating.
Installation: Must be properly supported, fire barriers may be required where passing through
fire-rated walls/floors, adequately earthed.
Accessibility: Tap-off points should be accessible.
DEWA Approval: Approval for busway systems is required, and they must comply with
relevant IEC standards (e.g., IEC 61439-6 for busbar trunking systems).
B) A circuit directly supplying current to the electrical utilization equipment (e.g., lighting,
socket outlets, fixed appliances).
A) 1.0 mm².
B) 1.5 mm².
C) 2.5 mm².
D) 4.0 mm².
3. What additional protective device is generally mandatory for all 13A/20A socket outlet final
circuits in DEWA-approved installations?
B) A voltage stabilizer.
C) A Residual Current Device (RCD) with a rated residual operating current not exceeding
30mA.
4. For safety and proper load management, what kind of circuit is required for high-power fixed
appliances like air conditioning units or electric water heaters?
5. What is the maximum floor area that a single 13A ring final circuit (for socket outlets) should
serve in a domestic or similar installation, as per DEWA guidelines?
A) 50 m².
B) 75 m².
C) 100 m².
D) 150 m².
Part 2: Distribution Boards (DBs)
A) To generate electricity.
B) To act as a central point for the protection and distribution of electricity to final circuits.
D) To convert AC to DC.
7. A DEWA-approved Distribution Board must always include which of the following essential
components?
A) A built-in television.
C) A remote-control unit.
D) A cooling fan.
8. Where should Distribution Boards typically NOT be located, according to safety and
accessibility guidelines?
B) In a living room.
D) In a hallway.
9. What is a crucial requirement for the labeling of circuits within a Distribution Board?
D) No labeling is required.
10. What minimum Ingress Protection (IP) rating is generally recommended for Distribution Boards
in typical indoor, dry environments?
A) IP20.
B) IP4X.
C) IP65.
D) IP68.
11. What does an LV Main Switchboard (MSB) primarily function as in a consumer's installation?
B) The main intake point for DEWA's supply and distribution to the entire installation.
D) Mobile units.
13. What critical rating must LV Switchboards possess to ensure they can withstand electrical faults
without catastrophic failure?
A) In a public corridor.
B) In dedicated electrical rooms (switchgear rooms) with specific access and fire-rating
requirements.
15. What safety feature is important in LV switchboards to prevent accidental operation or access
during maintenance?
A) Remote control.
C) Adequate internal segregation (e.g., Form 2 or higher) and facilities for locking off (LOTO).
16. What is a primary advantage of using a Busway system for electrical distribution compared to
large traditional cables, especially in commercial or industrial settings?
B) Enhanced flexibility for future modifications, easy tap-off points, and space saving.
A) End caps.
B) Expansion joints.
D) Supporting clamps.
18. What international standard generally governs the design and testing of Busbar Trunking
Systems (Busways)?
A) IEC 60076.
B) IEC 61439-6.
C) IEC 62305.
D) IEC 60364.
19. When a busway system passes through fire-rated walls or floors, what specific installation
requirement must often be met?
B) Fire barriers or fire-stopping methods must be implemented to maintain the fire integrity of
the structure.
20. What is an essential requirement for all metallic components of a Busway system, including the
trunking and tap-off units, as per safety standards?
1. B) A circuit directly supplying current to the electrical utilization equipment (e.g., lighting,
socket outlets, fixed appliances).
o Explanation: A final circuit is the last leg of the distribution system connecting to the load.
2. C) 2.5 mm².
o Explanation: 2.5 mm² copper conductor is a common minimum for 13A socket outlet circuits to
handle current and voltage drop.
3. C) A Residual Current Device (RCD) with a rated residual operating current not exceeding
30mA.
o Explanation: RCDs provide crucial additional protection against electric shock for socket
outlets.
4. B) A dedicated final circuit.
o Explanation: High-power appliances require their own circuits due to their significant current
draw and to prevent overloading shared circuits.
5. C) 100 m².
o Explanation: This is a common design limit for ring final circuits to ensure adequate capacity
and fault protection.
6. B) To act as a central point for the protection and distribution of electricity to final circuits.
o Explanation: DBs house circuit breakers and serve as a distribution hub.
7. B) A main incomer switch-disconnector, individual circuit protective devices
(MCBs/RCBOs), a neutral bar, and an earth bar.
o Explanation: These are the essential components for a safe and functional DB.
8. C) In bathrooms, above cooker hobs, or in hazardous areas.
o Explanation: These locations pose significant risks (moisture, heat, explosive atmosphere) that
make DBs unsafe.
9. C) Each circuit must have clear and permanent identification labels.
o Explanation: Clear labeling is vital for safety, maintenance, and fault finding.
10. B) IP4X.
o Explanation: IP4X provides protection against solid objects (including fingers) and is suitable
for most indoor DB installations.
11. B) The main intake point for DEWA's supply and distribution to the entire installation.
o Explanation: The MSB is where the building's electrical system connects to the utility supply.
12. B) Type-Tested Assemblies (TTA) or Partially Type-Tested Assemblies (PTTA) to ensure
safety and performance.
o Explanation: Type-tested assemblies ensure that the switchboard design has been rigorously
tested to meet safety and performance standards.
13. C) Short-circuit withstand rating.
o Explanation: This rating indicates the maximum fault current the switchboard can safely
withstand without damage, crucial for system integrity.
14. B) In dedicated electrical rooms (switchgear rooms) with specific access and fire-rating
requirements.
o Explanation: Due to their size, complexity, and potential for high fault currents, MSBs require
dedicated, controlled environments.
15. C) Adequate internal segregation (e.g., Form 2 or higher) and facilities for locking off
(LOTO).
o Explanation: Segregation enhances safety by limiting fault spread, and LOTO facilities enable
safe maintenance.
16. B) Enhanced flexibility for future modifications, easy tap-off points, and space saving.
o Explanation: Busways offer modularity and easy re-configuration, making them advantageous
for evolving power needs.
17. C) Tap-off units (with integral protective devices).
o Explanation: Tap-off units are designed to connect loads to the busway system.
18. B) IEC 61439-6.
o Explanation: This is the international standard specifically for busbar trunking systems.
19. B) Fire barriers or fire-stopping methods must be implemented to maintain the fire
integrity of the structure.
o Explanation: Penetrations through fire-rated elements must be sealed to prevent the spread of
fire.
20. B) They must be effectively earthed and bonded.
o Explanation: As metallic enclosures for current-carrying components, busways must be earthed
for safety against electric shock.
The search results provide detailed insights into DEWA's electrical inspection procedures and
associated documentation. Key information gathered includes:
Purpose of Inspection:
Ensuring compliance with DEWA regulations, international standards (BS 7671, IEC), and local
safety requirements.
Verifying safety, quality, and proper functionality of electrical installations before connection or
during periodic checks.
Initial Inspection: Conducted for new installations, major alterations, or additions. This is
crucial before DEWA provides a permanent electricity connection.
Periodic Inspection: For existing installations, usually required for large commercial/industrial
sites.
Final Inspection: The last stage for new connections to ensure all requirements are met.
Technical Drawings & Load Schedules: Required for submission and approval prior to
commencing work.
"Electrical Work Completion Certificate" (or similar terminology): Issued by the
consultant/contractor to declare completion and compliance. This is a critical document for
DEWA's final inspection request.
Test Reports/Sheets: Comprehensive test results for insulation resistance, earth fault loop
impedance, RCD tripping times, continuity, polarity, etc., must be submitted along with the
completion certificate.
DEWA Online Portal: DEWA's "Smart Services" or "E-Services" are used for submitting
inspection requests and documents.
All electrical work must be fully completed and ready for energization.
All necessary approvals (e.g., initial drawings) obtained.
Access to all parts of the installation.
Availability of necessary documentation and test results.
Payment of relevant fees.
Main Switchboard (MSB) / SMDB: Verification of meter panel, busbar connections, circuit
breakers, labeling, earthing, ventilation of room.
Distribution Boards (DBs): Correct MCBs, RCDs, wiring, labeling, neatness.
Cables & Wires: Correct sizing, proper routing, protection, termination, color coding.
Earthing System: Verification of earth electrodes, main earthing terminal, earth continuity
conductors, bonding.
Switches & Sockets: Correct type, height, RCD protection for sockets, appropriate IP ratings.
Lighting: Correct luminaires, energy efficiency compliance (LEDs), emergency lighting, proper
control.
General Workmanship: Neatness, secure fixings, compliance with safety distances.
Consequences of Non-Compliance:
Inspection failure.
Issuance of observations/defects.
Requirement for rectification and re-submission/re-inspection.
Delays in power connection.
Potential fines or penalties.
B) To verify that the electrical installation complies with DEWA regulations, safety standards,
and quality requirements.
C) For all new installations, major alterations, or additions before permanent power connection.
3. Which type of inspection is conducted for existing electrical installations, especially large
commercial or industrial sites, at specified intervals?
B) Periodic inspection.
C) Pre-installation inspection.
D) Demolition inspection.
4. Who is primarily responsible for conducting the initial verification and ensuring the installation
meets standards before requesting DEWA's final inspection?
5. What is the ultimate goal of the entire inspection and approval process by DEWA?
6. Before DEWA conducts a final inspection for a new connection, what crucial document must be
submitted by the consultant/contractor to certify completion and compliance?
B) The "Electrical Work Completion Certificate" (or similar DEWA-specific completion form).
B) Test reports, including insulation resistance, earth fault loop impedance, RCD tripping times,
and continuity.
8. Through what medium are inspection requests and related documentation typically submitted to
DEWA?
D) Fax.
9. What is the purpose of submitting detailed technical drawings and load schedules to DEWA
before commencing electrical work?
B) To obtain DEWA's prior approval for the design and ensure compliance with regulations.
10. If an inspection fails due to non-compliance, what document will DEWA typically issue,
outlining the required rectifications?
A) A commendation letter.
D) A property deed.
Part 3: Inspection Checks and Compliance
11. During an inspection of a Distribution Board (DB), what key aspects will DEWA inspectors
typically check?
B) Correct MCB/RCD types and ratings, proper wiring, clear circuit labeling, and physical
condition.
12. What specific test results are crucial for the earthing system that DEWA inspectors will verify
during an inspection?
C) Sound levels.
D) Humidity levels.
13. For socket outlets, what specific safety protection will be meticulously checked for compliance
with DEWA regulations?
B) That cables are correctly sized for current-carrying capacity, protected against overcurrent,
and voltage drop limits are met.
15. What general principle of installation quality is a major focus during DEWA inspections?
B) That all electrical work is carried out in a neat, orderly, and workmanlike manner.
B) Delay in obtaining electricity connection until all non-compliances are rectified and a
successful re-inspection is conducted.
17. If rectification of defects is required after an inspection, what is the next step for the
contractor/consultant?
B) Rectify the identified defects, update documentation if necessary, and request a re-inspection.
19. Why is accessibility to all electrical components (e.g., DBs, junction boxes, switchboards)
crucial for inspection purposes?
B) To allow DEWA inspectors to easily verify compliance, perform tests, and for future
maintenance.
20. What role do "Smart Services" or "E-Services" play in DEWA's inspection process for
contractors and consultants?
B) They provide a convenient and efficient platform for submitting applications, inspection
requests, and tracking progress.
1. B) To verify that the electrical installation complies with DEWA regulations, safety
standards, and quality requirements.
o Explanation: The core mission of DEWA inspections is to ensure compliance and safety.
2. C) For all new installations, major alterations, or additions before permanent power
connection.
o Explanation: Initial inspection is a prerequisite for connecting to DEWA's grid.
3. B) Periodic inspection.
o Explanation: Periodic inspections assess the ongoing safety and compliance of existing systems.
4. B) The licensed electrical contractor or consultant responsible for the installation.
o Explanation: They hold the primary responsibility for the initial verification and quality of
work.
5. B) To ensure the safety of lives and property from electrical hazards.
o Explanation: Safety is the overarching goal of all electrical regulations and inspections.
6. B) The "Electrical Work Completion Certificate" (or similar DEWA-specific completion
form).
o Explanation: This certificate signifies the contractor/consultant's declaration of compliance.
7. B) Test reports, including insulation resistance, earth fault loop impedance, RCD tripping
times, and continuity.
o Explanation: Empirical test data provides evidence of the installation's electrical integrity.
8. C) DEWA's online "Smart Services" or "E-Services" portal.
o Explanation: DEWA strongly promotes digital services for efficiency.
9. B) To obtain DEWA's prior approval for the design and ensure compliance with
regulations.
o Explanation: Design approval ensures that the planned installation meets DEWA's standards
before construction begins.
10. B) An observation/defect notification form.
o Explanation: This form formally communicates the non-compliances that need rectification.
11. B) Correct MCB/RCD types and ratings, proper wiring, clear circuit labeling, and physical
condition.
o Explanation: These are essential safety and functional checks for a DB.
12. B) Earth electrode resistance, and earth fault loop impedance (Zs/Ze).
o Explanation: These measurements confirm the effectiveness of the earthing system, crucial for
automatic disconnection of supply.
13. B) Mandatory RCD protection (especially for 13A/20A sockets).
o Explanation: RCDs provide crucial protection against electric shock for general-purpose socket
outlets.
14. B) That cables are correctly sized for current-carrying capacity, protected against
overcurrent, and voltage drop limits are met.
o Explanation: Proper cable sizing prevents overheating and excessive voltage drop, ensuring
safety and performance.
15. B) That all electrical work is carried out in a neat, orderly, and workmanlike manner.
o Explanation: Good workmanship directly contributes to safety, reliability, and ease of
maintenance.
16. B) Delay in obtaining electricity connection until all non-compliances are rectified and a
successful re-inspection is conducted.
o Explanation: Failed inspections halt the process until issues are resolved.
17. B) Rectify the identified defects, update documentation if necessary, and request a re-
inspection.
o Explanation: The onus is on the contractor/consultant to rectify and re-present the installation.
18. B) Strict adherence to safety protocols, including Lockout/Tagout (LOTO) procedures,
wearing appropriate PPE, and safe working distances.
o Explanation: Electrical work, especially on live systems, carries significant risks that demand
stringent safety measures.
19. B) To allow DEWA inspectors to easily verify compliance, perform tests, and for future
maintenance.
o Explanation: Accessibility is key for both inspection and ongoing operational needs.
20. B) They provide a convenient and efficient platform for submitting applications, inspection
requests, and tracking progress.
o Explanation: DEWA utilizes technology to streamline administrative processes for
stakeholders.
Please note: While I will provide information on lightning protection systems, it's crucial to
understand that DEWA (Dubai Electricity and Water Authority) primarily focuses on the
electrical safety within buildings and their connection to the grid. For comprehensive
lightning protection system design and installation, you should refer to international
standards like IEC 62305 series, NFPA 780, and consult with specialized lightning
protection experts in Dubai. DEWA's regulations will enforce compliance with such standards
where applicable to ensure overall building safety and continuity of supply.
1. What is lightning?
2. What are the primary types of lightning strikes that can affect structures or electrical systems?
B) Indirect strikes (e.g., strikes nearby, or to power lines), and direct strikes to the structure or
services.
3. What is the main purpose of a Lightning Protection System (LPS) for a building?
C) To intercept lightning strikes and safely conduct the lightning current to the earth, minimizing
damage to the structure and its occupants.
A) ISO 9001.
B) IEC 62305.
C) IEEE 802.11.
5. What is the primary danger posed by a direct lightning strike to a structure without an adequate
LPS?
6. How does a lightning strike affect electrical and electronic systems inside a building, even if it's
an indirect strike?
B) It generates powerful electromagnetic fields, leading to surges (overvoltages) that can damage
sensitive equipment.
B) To determine the protection level offered by an air-termination system and define zones of
protection.
9. What are the main components of an external Lightning Protection System (LPS)?
B) To provide a low-impedance path for the lightning current to flow from the air-termination
system to the earth-termination system.
B) To dissipate the lightning current safely into the general mass of the earth.
13. What are Surge Protective Devices (SPDs) primarily used for in the context of lightning
protection?
B) To protect electrical and electronic equipment from overvoltages (surges) caused by direct or
indirect lightning strikes.
14. Where are SPDs typically installed within an electrical system for comprehensive protection
against lightning surges?
B) At various points, including the main incoming supply, sub-distribution boards, and near
sensitive equipment.
15. While DEWA's primary focus is on internal electrical safety, how do their regulations implicitly
address the need for lightning protection in certain installations?
B) By requiring compliance with international electrical safety standards that often include
provisions for lightning and surge protection, especially for large or critical installations.
16. Which part of a building's earthing system is critical for the effectiveness of a lightning
protection system?
B) The main earthing terminal (MET) and the overall low-resistance connection to the general
mass of earth.
A) Connecting all metal parts of a building to the earthing system to prevent dangerous potential
differences during a lightning strike.
B) Regular visual inspections and periodic testing by qualified personnel to ensure its continued
effectiveness.
19. In areas prone to high lightning activity, what is generally the safest course of action for
individuals during a thunderstorm?
B) Seeking shelter inside a properly protected building or a fully enclosed metal vehicle.
20. When submitting electrical drawings and specifications to DEWA for approval of a large or
complex project, what aspect related to external influences like lightning might need to be
included or referenced?
B) Details of surge protection measures and, if applicable, the design principles for the external
lightning protection system.