Barangay Ulong-Tubig Affordable Housing Project Plan
Barangay Ulong-Tubig Affordable Housing Project Plan
Name of Student
Name of Instructor
Due Date
1
Table of Contents
Introduction....................................................................................................................................3
Gantt Chart..................................................................................................................................14
Risk Register................................................................................................................................16
Impact Assessment................................................................................................................20
References.....................................................................................................................................23
2
Introduction
Like much of the world, the Philippines is experiencing rapid urbanization. This, coupled with a
growing population, has led to an increase in the demand for affordable housing (NextAsia,
2023). Even though the Philippines has made some developmental progress in the real estate
sector, it still faces a significant housing shortage. There is an estimated housing backlog of
about 6.5 million housing units in the Philippines (NextAsia, 2023). This particular challenge
offers an opportunity for developers to come up with low-cost housing since many Filipinos
(especially low to middle-income households) cannot afford to purchase houses upfront or secure
However, these developers still face various challenges in developing low-cost housing. Some of
these challenges include but are not limited to bureaucratic hurdles, limited land availability and
rising construction costs (Habitat for Humanity, 2023). In order to address the challenges and
ensure success in the initiation and completion of affordable housing units, effective project
Syndicate Group (TPEMSG) has undertaken the initiative to implement project management in
its strategic development of low-cost housing. The firm also uses innovative construction
technologies and sustainable practices. For instance, it has adopted prefabricated construction
and green building techniques. This report will contain important documents for the affordable
houses developed by The Philippine Emerging Market Syndicate Group under its subsidiary San
Pyran, specifically the Barangay Ulong-Tubig Affordable Housing Project (Carmona, Cavite).
This project targets to develop 2019 prefabricated housing units to accommodate low to middle-
income households that work in the nearby industrial zone. TPEMSG will employ structured
3
project management approach with integration of the following key components to deliver
successive projects at the set time and cost, without compromising on quality.
1. Project overview
The Barangay Ulong-Tubig Affordable Housing Project is a strategic housing initiative by The
Philippine Emerging Market Syndicate Group (TPEMSG) and San Pyran, its subsidiary. The
project aims to address the housing backlog experienced in the Philippines by constructing 2,019
prefabricated housing units in Carmona, Cavite. The development aims to provide affordable and
quality housing to low to middle-income households, overseas workers and factory workers in
2. Project purpose
Currently, the Philippines is facing a serious housing shortage that is estimated at around 6.5
million units, with low and middle-income earners being highly affected (Business Outstanders,
2024). The municipality chosen, Carmona, Cavite, is an industrial area that is rapidly growing
and is suitable for the development of affordable houses (Camella, 2025). This project is very
important as it will help reduce the housing backlog, support economic development, utilize
prefabricated construction to reduce construction cost and time, and it enhances the wellbeing of
3. Project objectives
ii. To comply with the national housing and environmental laws and regulation.
4
iv. To offer flexible financing options (to low and middle-income earners) in coaction
4. Project scope
The project will include the construction of 2019 prefabricated housing units, development of
community amenities (such as parks, children’s playground and community center), and creation
5. Project deliverables
The following are the key deliverables expected upon completion of the project;
a. Two thousand and nineteen prefabricated housing units fully completed with all utilities.
c. Essential services connection for all units (water, electricity and data).
d. Community facilities.
6. Project Milestones
2025).
Phase 1 completion: Deliver 500 fully completed housing units (December 2026)
5
7. Budget Estimate
The table below shows the estimated budget to undertake the project from initiation to
completion.
Table 1.
Barangay Ulong-Tubig Affordable Housing Project Budget Estimate
8. Stakeholders
Table 2.
Barangay Ulong-Tubig Affordable Housing Project Stakeholders and their Roles
Stakeholder Role
TPEMSG executive team Project sponsors. Decision-making.
San Pyran project team Oversee project planning and execution.
Construction team Site development and construction of housing units.
Local government units Provision of permits and regulatory approvals.
Future residents/occupants Beneficiaries of the units.
Contractors and suppliers Provision of building materials and services.
Financial institutions Provision of financing to developers and buyers
6
9. Risk management plan
Table 3.
Barangay Ulong-Tubig Affordable Housing Project Budget Risk Management
- A change request form (CRF) must be submitted for all change requests.
This project charter officially authorizes the Barangay Ulong-Tubig Affordable Housing Project
and grants the Project Manager the authority to execute the project as per the outlined scope,
Approval Signatures:
7
WBS and Dictionary
WBS
The table below represents the work breakdown structure for the project:
Below you will find on complete work package in the WBS dictionary.
8
Description: This phase involves laying the foundation and constructing the structural
framework of the housing units, including the installation of prefabricated elements, such
as beams, reinforced walls and columns.
Deliverables:
Duration: 6 weeks
Resources Required:
Dependencies:
9
Mitigation: Include buffer time in schedule and use weather-resistant
materials
The work breakdown structure and dictionary offers a proper breakdown of the project phases
and detailed description of a sample work package to allow the construction team to have a clear
manner of executing construction works and create accountability. The WBS ensures that
construction planning is detailed enough, that there is careful allocation of resources, quality
control and risk mitigation. Thus, the document is a crucial reference point for the execution of
the project, quality control and management of stakeholders. Adherence to the work breakdown
structure will help the project team to continuously monitor the progress of construction works
and allow the adjustment of strategies to ensure the successful completion of the project within
The Precedence diagram method (PDM) or the activity-on-node method a project scheduling
technique that visually represents activities in a project and their dependencies. In the Barangay
Ulong-Tubig Affordable Housing Project, PDM diagram is very crucial, as it will help in
10
mapping out the sequence of activities and ensuring that critical tasks are completed on time. By
understanding the various relationships between the different activities, project managers can
efficiently allocate resources, avoid bottlenecks, and optimize construction works to reach the set
The PDM diagram for the Barangay Ulong-Tubig Affordable Housing Project is made up of 11
activities, each with its own duration and dependencies. Note that the duration is in weeks rather
than days. The main dependencies used are Finish-to-Start relationships, which mainly means
that a task cannot be started until the preceding tasks is/are completed. Figure 1 below is the
11
Barangay Ulong-Tubig Affordable Housing Project
ID 1 Duration 2
ES 0 EF 2
Feasibility Study
LS 0 LF 2
(ID_4) FS, 0
ID 5 Duration 2
ES 9 EF 11 1 --> 2 --> 3 --> 11
Site Preparation
LS 8 LF 10
(ID_5) FS, 0
ID 6 Duration 6
ES 11 EF 17
Foundation & Structural Work
LS 10 LF 16
(ID_6) FS, +1
ID 7 Duration 3
ES 17 EF 20
Utility Installation
LS 16 LF 19
(ID_7) FS, 0
ID 8 Duration 5
ES 20 EF 25
Interior & Exterior Finishing
LS 19 LF 24
Feasibility Study (1) → Must be completed before Land Acquisition (2) and Government
12
Land Acquisition (2) and Government Permits (3) → Both must be completed before
Design Phase (4) → Leads to Site Preparation (5), which must be done before
construction.
Foundation & Structural Work (6) → Must be completed before Utility Installation (7)
Marketing & Sales (9) and Final Inspections (10) → Both must be done before Project
Handover (11).
Every activity in the PDM diagram has an assigned Early Start (ES), Early Finish (EF), Late
Start (LS), and Late Finish (LF) value. These particular values are important as they help in
determining the float or slack. Float represents the duration an activity can be delayed without
affecting the project schedule (Burke, 2021). Float can be determined by taking the late start or
late finish minus the early start or early finish of an activity, respectively. Thus,
If the float is 0, then the specific tasks is on the critical path and no delays should be present. If it
is greater than 0, then the activity is flexible and some delays can be tolerated. For example, in
the PDM diagram, it can be seen that final inspections has a float of 1 day, and thus the project
can only delay for 1 day without affecting the project schedule.
A critical path can be defined as the longest sequence of dependent activities in a project that
determines the shortest possible duration to complete the project (Kerzner, 2022). Any delays in
any of the activities in the critical path can lead to significant and direct impact on the
completion date of the project. The critical path for the Barangay Ulong-Tubig Affordable
13
1 → 2 → 4 → 5 → 6 → 7 → 8 → 9 → 11
Calculations from the critical path analysis have shown that the shortest possible time to finish
The Precedence Diagram Method (PDM) is an essential project management tool for efficiently
14
Gantt Chart
Figure 2 below shows the Gantt chart for the Barangay Ulong-Tubig Affordable Housing Project.
15
A Gantt chart is a project management tool that visually represents a project's timeline, activities,
and dependencies in a manner that is structured and visually appealing. The chart is widely used
in various industries and fields across the world, such as construction, engineering, and software
development projects (Lock, 2023). In its use, the Gantt chart has proven to be of great value in
the implementation and management of complex projects, such as the Barangay Ulong-Tubig
Affordable Housing Project. In the project, multiple tasks have to be synchronized to meet
deadlines and avoid delays. By using a Gantt chart, project managers can efficiently schedule,
track progress, and allocate resources. By doing so, they ensure that there is smooth execution
The Gantt chart for the Barangay Ulong-Tubig Affordable Housing Project (Figure 1) was
created and then exported from MS Project. The chart provides details for the entire project
timeline from its scheduled commencement (May 1, 2025) to its scheduled completion
(December 10, 2025). The visual part of the Gantt chart shows each task represented by its own
horizontal bar, with the length of the bars corresponding to the duration required for completion
of the various tasks. The chart outlines essential phases, including Feasibility Study, Land
Acquisition, Design, Construction, Marketing & Sales, and Final Inspections. Notably, Land
Acquisition must be completed before Architectural & Engineering Design can commence,
ensuring a structured workflow that prevents bottlenecks in implementing the project. This
visualization is critical in identifying potential scheduling risks and ensuring that the most
important activities remain on track (Burke, 2021). The Gantt chart also shows the critical
activities that lie in the critical path as shown in the PDM diagram. It also graphically shows
activity with floats and highlights the float duration too. Moreover, the Gantt chart assists project
16
managers in carrying out proper risk management through the incorporation of buffer periods
where necessary.
Risk Register
A risk register is a very critical document that helps project managers identify, analyze, and
mitigate any risks that may tamper with a project’s timeline, cost, quality, and overall success.
The register has key risk data, such as the risks, their likelihood and impact, and mitigation
strategies to reduce potential disruptions (Project Management Institute, 2021). Potential risks
must be carefully managed in the Barangay Ulong-Tubig Affordable Housing Project to make
sure that the 2,019 housing units are fully completed at the scheduled time and within the
allocated budget.
The Barangay Ulong-Tubig Affordable Housing Project faces various risks, such as legal,
environmental, financial, and operational uncertainties. The table below shows the risk register
for the project. Each risk is classified based on the probability of its occurrence and its impact on
the project. High-probability and high-impact risks are prioritized for immediate mitigation,
while the lower-probability and low-impact risks are monitored for potential escalation (Burke,
2021).
17
Table 4. Barangay Ulong-Tubig Affordable Housing Project Risk Register
Risk Date Risk Description Probability Impact Contingency Owner Mitigation Strategy
ID Identified Amount
(PHP)
18
Change Management Plan
Change is an inevitable aspect of any project management undertaking. This is also the case for
the Barangay Ulong-Tubig Affordable Housing Project. As projects progress through their
different phases, unforeseen factors might arise and demand adjustment to the change(s). These
unforeseen factors can include but are not limited to, changes in regulatory laws and regulations,
organizations to develop change management plans that are properly structured to deal with
unforeseen changes in the future. A properly structured change management plan ensures that
modifications are systematically evaluated, approved, and implemented with minimal disruption
The main goal of this Change Management Plan is to provide a structured approach to handling
modifications in a way that maintains project integrity, while enhancing communication, and
mitigating any risks associated with uncontrolled changes. This document establishes the
1. To establish a clear and formalized process for submitting, evaluating, approving, and
implementing changes.
2. To define roles and responsibilities within the Change Control Board (CCB) to ensure
accountability in decision-making.
19
3. To minimize risks, cost overruns, and schedule disruptions by ensuring that only
accountability.
The change management process in the Barangay Ulong-Tubig Affordable Housing Project
follows a systematic approach to ensure all modifications are carefully assessed. The key phases
of the change management process include change request initiation, impact assessment, review
Any project stakeholder can submit a change request if they identify a need for modification in
the project scope, cost, schedule, or resources. All requests from the stakeholders must be
documented in a Change Request Form (CRF), which includes the following crucial
components:
20
Once a CRF is submitted, it is forwarded to the Change Control Board (CCB) for initial
assessment.
Impact Assessment
After receiving a change request in CRF format, the project management team should carry out a
detailed impact analysis to evaluate how the proposed change will affect the project’s scope,
1. Identifying dependencies between the requested change and any ongoing tasks.
3. Evaluating the feasibility of implementing the change within the current schedule.
4. Assessing the risks associated with the change and identifying mitigation measures.
The findings of the impact assessment will then be compiled by the project management team
into a change impact report (CIR). The CIR is then submitted to the change control board (CCB)
The Change Control Board (CCB) reviews all the proposed changes and makes sure that only
essential and beneficial changes to the project are approved. The CCB for the Barangay Ulong-
Tubig Affordable Housing Project will consist of key project stakeholders, who are the Project
Manager, Lead Engineer, Financial Controller, Compliance Officer, and a representative from
During the review process, the change control board will consider the following important
elements:
21
The necessity of the change and its alignment with the project objectives.
The feasibility of integrating the change without compromising the project schedule and
budget constraints.
Based on these considerations, the CCB can approve, reject, or request modifications to the
proposed change. If the changes are approved, the implementation phase is started.
Once a change request is approved, an Implementation Plan should be developed to integrate the
The Project Manager is responsible for overseeing the implementation of changes and ensuring
After a change is implemented, there must be continuous monitoring of the change to assess its
impacts on the performance of the project. The quality assurance team should carry out regular
reviews at certain time periods to ensure that the change delivers the intended benefits without
introducing new risks. If unforeseen issues arise, corrective measures must be identified and
22
All changes, along with their approvals, impact assessments, and implementation plans, are
archived in the Project Change Log for future reference and auditing purposes.
Even though there is a structured approach to change management, it still poses various
challenges to project managers. One of the most common challenges faced during change
management is resistance from stakeholders. They may be adamant in accepting the new changes
especially if they feel as if the change will be disruptive or unnecessary to the project. To address
this, the project management team should carry out early stakeholder engagement and
transparent communication to ensure they gain the trust of stakeholders and reduce resistance.
Another challenge is that changes can have significant financial impact on the project cost. For
instance, uncontrolled modifications can lead to cost overruns. The project management team
can establish a contingency fund for unforeseen changes, which can greatly help mitigate
23
References
Burke, R. (2021). Project management: Planning and control techniques (6th Ed.). Hoboken,
NJ: John Wiley & Sons, Inc.
Business Outstanders. (2024, July 16). Lhoopa's innovative approach to affordable housing in
emerging markets. Business Outstanders:
https://businessoutstanders.com/construction/lhoopas-innovative-approach-to-affordable-
housing-in-emerging-markets
Camella. (2025, February 13). The rising tide of mid-market housing Philippines: A 2025
perspective. Camella: https://www.camella.com.ph/the-rising-tide-of-mid-market-
housing-philippines-a-2025-perspective/
Habitat for Humanity. (2023, June). Green housing solutions in the Philippines.
https://www.habitat.org/sites/default/files/documents/Green-Housing-Solutions-in-the-
Philippines.pdf
NextAsia. (2023). Building the communities of tomorrow today: The future of affordable housing
in the Philippines. NextAsia: https://nextasialand.com/news/building-the-communities-
of-tomorrow-today-the-future-of-affordable-housing-in-the-philippines/#:~:text=The
%20Philippines%20is%20experiencing%20rapid,around%206.5%20million%20housing
%20units.
Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) (7th Ed.). Newton Square: Project Management Institute.
24
25