QARUN PETROLEUM CO.
DAILY DRILLING REPORT
Contractor EDC M.ELAGAWANY Rig Days Moving Drilling Test/com.
1 Well Name: HEBA-224 DRLG SUP.
Rig No. 63 MAHMOUD EL KOTB 2D+11HR 2D+6HR 5 HR
FTG Last
Average ROP 60.0
2 Operation DRLG 17 1/2" HOLE . Depth 180 FT 30 FT
Current ROP 60 24 Hrs
3 FORMATION MOGHRA SAND RKB-GL 26
4 Hours Operations No Opertaion Daily COMMU.
19.0 R/M 100% ,R/U 100 % 45 Drilling, Coring 1.5 1.5
CHECKED RIG FOR ACCEPTANCE,FUNCTION TEST TOP DRIVE,OK,P/T SURFACE 46 Surveys
LINES T/ 3000 PSI,MUD PUMPS, ROTARY TABLE, SOLID CONTROL EQUIP, OK. 47 Trips
RIG ACCEPTED @ 1:00 AM ON 5-5-2011. 48 P/U , L/D BHA 3.5 3.5
3.0 P/U & M/U 17.5'' BHA & STD BACK SAME ON DERRICK. 49 R/U & Run Casing
0.5 P/U & M/U 17.5'' RR BIT TAG @ 36 FT 50 Cement / W.O.C. / D.O.C.
SPUD IN @ 4:30 HRS ON 5-5-2011. 51 N/U &N/D test BOP & Csg
1.0 CLEAN 30" COND. F/36 FT T/ 150 FT . 52 Logging/Perf/Test
0.5 DRLG 17 1/2" HOLE F/ 150 FT T/ 180 FT . 53 Circ/Cond. Mud/lost Circ
54 Reaming/Opening Hole
55 Rig Maintenance
56 Rig Repairs
57 Fishing/Stuck Pipe/D.Time
58 W.O.Equipment/Orders/Material
59 MIRU/RD
60 P/U & M/U
61 DOWN TIME
** EDC-63 CONSUMED 4100 LITER DIESEL DURING RIG MOVE 63 MOVE 19 54
** RECEIVED 20,000 LIT. DIESEL FROM QARUN . 64 OTHER
21 24.0 61
22 Accident Report Hrs Repair this month Total Hours 24 59
Mud Properties:
Type WT Vis PV YP GELS WL FC PH PF/MF PM Chlorides Solid RM RF RC MBT
23
KCL% MUD BUILT F.LOS S.LOS Tripping Final Vol HTHP Mud Engineer
24
Added Last 24 Hrs
Bit No Size Type Serial # Jets Depth In Depth Out FTG Hrs Ft/hr WOB RPM Dull Grading
25 1 17 .5 CR1 Z823413 14 C.J.+3*18 36 SIH 30 0.5 60.0 0-2 80
26
Hydraulics Size SPM GPM Pressure P.bit AV Dp AV DC Jet vel Hhp Bit Hhp/sq in Imp/fc
27 Pump 1 6.5*12 50
250 200
28 Pump 2
Dp Size GRADE Wt lb/ft Tool Joint Length No. Dc OD ID Connection length
29
30
31 BHA Description:
32 BHA Length
33 Rot.Wt S.O.Wt P/U Wt BHA Wt in Mud Klbs Wt below Jar Klbs
34 DEPTH Deg / Az Depth Deg/az Depth Deg/az Depth Deg/az Depth
35 Dp Footage since Inspectio Dc Hr since Inspected HWDP On hand Delivered Used
36 Jar Hours Manf. & S.N: 64 Diesel (LITER) 58,500 20,000
37 Sh.Sub Hours S.N: 65 H20 (bbl)
38 Last Casing 30" WT 306 GRADE T.O.L SHOE 150 66 POT(bbl)
39 F.C.C.T. Mud Wt.: Surface Press PSI Equi. Mud Wt: ppg 67 Last BOP Test
Slow Circulating Rates (P.low) 68 Cost DAILY Cumulative
40 Pump 1 Depth spm Pressure 69 Mud $0 $0
41 Pump 2 Depth spm Pressure 70 Total $267,051 $267,051
42 AFE # Original AFE $ AFE Remaining $ Services Co 2 SPERY +1 BAKER
43 EDC-63 +CAT 15 + CASUALS 10 Qarun 2 Service 3 TOTAL 65
5-May-2011 5063
QARUN PETROLEUM CO.
DRILLING & COMPLETION AFE COST SHEET
COST SHEET NO. 1 5-May-2011
WELL : HEBA-224
T.D. : 6900 FT
AFE No :
71 REQUIREMENTS:
72 RECEIVED:
73 COST DESCRIPTION :
AFE : DRY PREVIOUS DAILY CUM
AFE FEATURE EXPLORATORY DRILLING HOLE COST COST COST
150510 MOBILIZATION & DEMOBILIZATION $125,000 125,000 $125,000.0
150511 CONTRACTOR DAYWORK / ST'BY RATE $162,500 12500*13D $2,600 $2,600.0
150520 ROCK & DSIAMOND BITS $20,000 $0.0
150521 MUD MATERIAL & SERVICES $60,000 $0.0
150522 RENTAL TOOLS & EQUIPMENT $17,000 $1,000 $1,000.0
150525 Water & Vac Trucks $25,000 $5,000 $5,000.0
150526 FUEL,LUBRICANT,POWER $50,000 $0 $0.0
150530 CEMENT MATERIAL & SERVICES $75,000 $0.0
150531 ELEC. LOGGING WIRELINE SERVICES $75,000 $0.0
150532 MUD LOGGING $10,350 850*13D $0.0 $850 $850.0
150533 FORMATION TESTING $0 $0.0 $0.0
150534 CORING EQUIPMENT & SERVICES $0 169/FT $0.0 $0.0
150535 FISHING TOOL SERVICES $0 $0.0 $0.0
150536 ACID , FRAC , STIM. SERVICES $0 $0.0 $0.0
150537 PERFORATING $0 $0.0 $0.0
150538 DIRECTIONAL DRILLING & SURVEYS $10,000 MMS $0.0
150550 CATERING $6,500 500*13D $500 $500.0
150551 TRANSPORTATION $5,000 $100 $100.0
150552 TUBULAR INSPECTION TREATMENT $2,000 $0.0
150553 COMMUNICATIONS $1,600 $100 $100.0
150554 CUSTOMS $0 $0.0
150555 COMPANY LABOUR EXPENSES $6,500 500*13D $500 $500.0
150556 CONTRACT SUPERVISION, SERVICES $8,125 625*13D $625 $625.0
150557 WELL CONTROL INSURANCE $14,000 LUMPSUM $14,000 $14,000.0
150560 SITE WORK , LOCATION, ROADS $60,000 LUMPSUM $60,000 $60,000.0
150561 RATHOLE, CELLAR, COND CSG $15,000 $0.0
150562 LOCATION RESTORATION $0 $0.0
150570 ABONDONED EQUIP.(CSG, TBG, W.H ) $0 $0.0
150590 DRILLING FABRICATIONS $0 $0.0
150591 DRILLING INSTALLATION $0 $0.0
150592 CSG/TBG RUNNING SERVICE/EQUIP.&PERS. $7,500 $0.0
150593 USAGE CHARGES(MIS.CONT.)(10%OF ALL COST) $80,233 10% $21,028 $21,027.5
TANGIBLES $0.0 $0.0
151501 CASING: 30" COND $23,832 100FT*238.32 $0.0 $35,748 $35,748.0
20" CSG $0 $0.0
13 3/8" CSG $54,520 1450*37.6 $0.0
9 5/8" CSG $79,971 3450*23.18 $0.0
7" & 5"LINER $51,110 3800*13.45 $0.0
151502 TUBING $0 $0.0
151503 WELL HEAD EQUIPMENT $14,000 $0.0
151504 PRODUCTION PACKER,NIPPLE $0 $0.0
151505 LINER HGRS, PKRS,NIPPLES, ETC. $35,000 $0.0
151506 ESP & CABLE $0 $0.0 $0.0
151507 GENERATOR, S.BOARD, TRANSFORMER $0 $0.0 $0.0
151508 CHEMICAL SKID $0 $0.0 $0.0
TOTAL DRY & CASED $949,571 $0 $267,051 $267,050.5
LINER & CEMENT 151035
TOTAL TEST & COMPLETION $900,678
TOTAL AFE ESTIMATE 2,001,284 remaining $1,734,234