0% found this document useful (0 votes)
6 views2 pages

ES2504006 RLA Testing For UPPTCL Ghaziabad

Uploaded by

Aman Gupta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views2 pages

ES2504006 RLA Testing For UPPTCL Ghaziabad

Uploaded by

Aman Gupta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

QUOTATION

QUOTATION NO: ES2504006 QUOTATION DATE: 03.04.2025


To, MTEKPRO TECHNOLOGIES PVT. LTD.
28, Second Floor, Okhla Industrial Estate,
Uttar Pradesh Power Transmission Corporation Limited Phase-3, New Delhi-110020
Ghaziabad Quoted by: Mr. Taiyab Zia Ahmed
Founder & Director
Kind Attn: Mr. VIPIN KUMAR E: [email protected]
(Executive Engineer) M: +91 9810706882
Mob: +91-8130599629
Email: [email protected]
Sr. No. Description Qty Total Price in INR
Conducting following RLA test on 150 MVA ,220/132
01 kV Transformer at 220 kV Substation Loni.

Routine Test
 Turns Ratio test
 Megnetizing Current
1.1  Short Circuit Impendance measurement
 Winding Resistance measurement
 Insulation resistance measurment
 Polarization index test
 Magnetic Balance
Special Test
 Tan delta and Capacitance & Measurement of 01 Rs. 1,95,000/-
Bushings
1.2  Tan delta and capacitance measurement of
winding.
 Sweep frequency Response analysis
 Frequency Responses Stray Loss Measurement
Oil Test
 Routine test as per IS: 1866
1.3  Dissolve gas Analysis
 FURAN test
 DP Paper Test
Online Partial Discharge Measurement using acoustic
1.4 and HFCT
Sr.No. Description Qty Total Price in INR
Conducting following RLA test on 220 MVA , 132/33 kV
02 Transformer at 132 kV Substation Mohan Nagar
Routine Test
 Turns Ration test
 Megnetizing Current
 Short Circuit Impendance measurement
2.1
 Winding Resistance measurement
 Insulation resistance measurment
 Polarization index test
 Magnetic Balance
Special Test
 Tan delta and Capacitance & Measurement of 01 Rs. 1,75,000/-
Bushings
2.2  Tan delta and capacitance measurement of
winding.
 Sweep frequency Response analysis
Oil Test
 Routine test as per IS: 1866
2.3  Dissolve gas Analysis
 FURAN test
 DP Paper Test
2.4 Online Partial Discharge Measurement using acoustic
and HFCT
Total Rs. 3,70,000/-

GST Rs. 66,600/-

Grand Total Rs. 4,36,600/-


Commercial Terms and Conditions:
100% Advance Payment along with the Purchase order
Payment Terms
Mobilization charges Included

Lodging & Boarding for two Engineers To be arrange by UPPTCL


GST (extra) @ 18%
Offer Validity 30 Days from the date of quotation.
Note:
1. Single phase & Three Phase power supply to be arranged by UPPTCL at the point of testing free of cost.
2. Two technician for connection and disconnection of test cables to be arranged by UPPTCL free of cost.