ASSIGNMENT
Semester 1, 2025
Module name Project Management II
Module code POM200/POMD262
Due date 22 April 2025
Total Marks 75
This assignment is compulsory and must be submitted through CANVAS,
inside the corresponding Module Course site on or before
22 April 2025 by 24:00.
STEP 1: COMPLETING YOUR ASSIGNMENT
Your assignment answer must include the following sections:
COVER PAGE
Please include the following information on the first page of the assignment:
Name, Surname, Student Number and Module Code.
BODY
1. The assignment answers must be typed in MS Word format and saved as a PDF
document (File > Save As > Save as Type: PDF).
2. Save your file (MS Word or PDF) with the following naming convention:
[STUDENTNUMBER] [MODULECODE] [SURNAME].pdf
E.g. 21111234 BCU101 Surname.pdf
LIST OF REFERENCES
Refer to the STADIO Referencing guide HERE for guidance.
©STADIO [Project Management II - POM200/POMD262] [Assignment -
Semester 1, 2025] Page 1 of 5
Once you have completed your assignment and saved it, you must log into Canvas to submit
your assignment by the due date.
IMPORTANT: Ensure that you submit your assignment answers on or before the due date
and time.
STEP 2: SUBMITTING YOUR ASSIGNMENT ON CANVAS
Once you have completed your assignment, log in to Canvas as follows:
1. Log in to CANVAS using your MySTADIO details:
(Username:
[email protected] and Password: ID number)
2. A specific course inside of CANVAS for each of your modules has been created for you
to submit your Assignment to. Select the desired module from the dashboard.
3. Submit your assignment before the end of the due date.
PLEASE ENSURE THAT THE ANSWER THAT YOU SUBMIT IS IN MS WORD OR PDF FORMAT.
NO SCANNED DOCUMENT WILL BE MARKED.
• The process detailed above is the same on a personal computer and mobile device. You
will, however, need to ensure that you have saved your completed assignment on the
mobile device and have downloaded the Canvas Student Application before attempting
to submit.
• You do not require a Canvas class ID and enrolment key to access your registered module
class, as you have been allocated to the class based on your registration. If you do not
see your module class appear, please contact the office for assistance.
• If you experience any difficulties during the submission process – after reading through
the guide and attempting the prescribed steps – please do not hesitate to contact the
office for assistance.
©STADIO [Project Management II - POM200/POMD262] [Assignment -
Semester 1, 2025] Page 2 of 5
ARTIFICIAL INTELLIGENCE TRAFFIC LIGHT MATRIX (AIMat)
Question / Part RED AMBER GREEN
Part May NOT May MUST use AI Detail of AI use
use AI use AI
All questions in You may use CHATGTP or any
this assignment other relevant and suitable AI
tools. Refer to the STADIO
Referencing Guide to
acknowledge the AI-generated
content.
You may only use AI to correct
your grammar. If you decide to
use AI for this purpose, capture
your text before and after fixing
the grammar and spelling and
explain which tool/s you used.
NOTE:
• STADIO employs AI writing detection tools to monitor AI use.
• Presenting work produced by AI as your own contravenes the STADIO Plagiarism policy.
• Refer to the STADIO Referencing Guide for guidance.
©STADIO [Project Management II - POM200/POMD262] [Assignment -
Semester 1, 2025] Page 3 of 5
Question 1 (25 marks)
You must manage a project with activities and their respective durations as listed in Table 1.
Review Table 1 below to complete the questions that follow.
Table 1: The Project Activity/Dependency sequence
Activity Predecessor Duration
A - 5
B A 3
C A 2
D B, C 4
E D 6
F D 5
1.1. Prepare a network diagram from the information in Table 1. (12)
1.2. Determine the Critical Path (CP). (1)
1.3. Complete the slack for each activity. Please ensure to show your working out for each
activity. (12)
Question 2 (25 marks)
Read the case study below and answer the question that follows.
AstraZeneca Case
Under intense pressure during the global pandemic, AstraZeneca met the global need for
Covid-19 vaccines by leveraging PMI standards. AstraZeneca partnered with the University
of Oxford to address the vaccine problem; this work included managing clinical trials while
simultaneously ramping up manufacturing capacity. As customers were mainly governments
seeking to immunize their populations, each government brought its own regulatory
requirements and compliance framework challenges.
At the outset, AstraZeneca’s initial focus was on establishing the necessary collaborations,
defining objectives and setting the groundwork for large-scale vaccine production, while also
addressing key risks. Careful planning ensured that clinical trials could proceed swiftly, with
detailed strategies for scaling manufacturing and securing global regulatory approvals.
Execution became a major focus as AstraZeneca ramped up production alongside clinical
trials. This included not only managing trial data but also setting up the internal government
contracting organisation to streamline negotiations and distribution logistics with
governments across the world. Continuous adjustments were made based on trial outcomes,
regulatory changes and the evolving nature of the pandemic.
©STADIO [Project Management II - POM200/POMD262] [Assignment -
Semester 1, 2025] Page 4 of 5
AstraZeneca Case
AstraZeneca’s team established an internal project management infrastructure to address
these challenges, including the rapid setup of the R&D division’s first PMO office, which
provided oversight and ensured that all project elements—from clinical results to
manufacturing output—were closely monitored and controlled. Throughout the process,
they adapted their strategies in response to ongoing data and stakeholder feedback.
By July 2021, AstraZeneca had successfully delivered 1 billion doses to 170 countries, having
navigated the complexities of a global, multi-faceted project in record time, with key lessons
learned informing future initiatives.
Source: Adapted from https://www.pmi.org/business-solutions/case-studies/astrazeneca-case-study
Using the AstraZeneca case study as an example, describe how the team may have experienced
each of these stages throughout the vaccine development project. For each stage, explain the
typical activities or challenges faced by team members and provide specific examples from the
AstraZeneca project to illustrate how the team navigated these phases to meet their project
goals.
Question 3 (25 marks)
3.1 Using the AstraZeneca case study, develop a Work Breakdown Structure (WBS) for the
Covid-19 vaccine development project. The WBS should include three levels of detail,
breaking down the project into its key deliverables and sub-deliverables. (15)
3.2
In a project to develop a new pharmaceutical product, the Planned Value (PV) for the
work scheduled to be completed by a certain date is R500,000. However, the Earned
Value (EV) for the work actually completed by the same date is R450,000.
Calculate the Schedule Performance Index (SPI) and explain what this value indicates
about the project's schedule performance. (5)
3.3
In the same project, the Earned Value (EV) for the work completed is R450,000, but
the Actual Cost (AC) incurred to complete this work is R480,000.
Calculate the Cost Performance Index (CPI) and explain what this value indicates about
the project's cost efficiency. (5)
ASSIGNMENT TOTAL: 75 MARKS