Date 2022-09-13 Company Total Done Balance Prog.
DEMOLISHED ITEM
Quantity
Discipline NO DESCRIPTION Unit Required Qty. Demolished Qty Remaining Prog. %
1 Dike Wall Surface Removal m2 1,148.00 1,112.22 35.78 96.88%
2 Dike Wall Demolition m3 242.00 104.00 138.00 42.98% NSH 66.19 10.24 55.95 15%
3 Concrete Pavement m3 547.37 415.40 131.97 75.89% NSH 88.19 80.89 7.3 92%
4 Wall Paint (Control Room) m2 940.00 940.00 0.00 100.00%
Civil 5 Stair and Handrail m2 15.00 15.00 0.00 100.00%
6 Asphalt paving m2 9,537.58 1,337.58 8,200.00 14.02% NSH 1,635.49 1,635.49 0.00 100%
7 Steel Structure No. 19.00 19.00 0.00 100.00%
8 Parking Shed m2 78.00 78.00 0.00 100.00%
9 Roofing m2 865.80 865.80 0.00 100.00%
10 Process Pipes Lm 1,138.25 1,051.00 87.25 92.33% NSH 440.85 440.85 0 100%
Piping 11 Fire water pipes Lm 9,045.96 8,262.96 783.00 91.34% NSH 2909 2909 0 100%
12 Valves No 166.00 116.00 50.00 69.88% NSH 173 159.00 14.00 92%
13 E&I Cable Lm 110,257 110,257 0.00 100.00%
14 E&I Cable Tray Lm 203.00 203.00 0.00 100.00%
15 E&I Conduit Lm 12,367.00 12,367.00 0.00 100.00%
Electrical and 16 Instruments Nos. 72.00 72.00 0.00 100.00%
Instrumentation 17 Junction Box Nos. 34.00 34.00 0.00 100.00%
18 CP Rectifier Panel Nos. 5.00 5.00 0.00 100.00%
18 Lighting fixture Nos. 75.00 75.00 0.00 100.00%
18 High Mast and Light Pole Nos. 10.00 10.00 0.00 100.00%
19 Shell Removal Phase 1 T-105 Ton 94.39 94.39 0.00 100.00%
20 Tank Roof (T-103)- 4,214 m2 m2 4,242.00 4,242.00 0.00 100.00%
21 Rafter Nos. 312.00 312.00 0.00 100.00%
Girder and Column Removal T-
Mechanical 22 Nos. 97.00 97.00 0.00 100.00%
103
23 Tank Grit Blasting (T-108) m2 4,587.00 4,587.00 0.00 100.00%
24 Base Plate Removal m2 4,242.00 0.00 4,242.00 0.00%
25 Shell Removal T-103 m2 1,123.61 612.00 511.61 54.47%
RESTORATION ITEM
Discipline NO DESCRIPTION Unit Required Qty. Restored Qty. Remaining Prog. %
1 Wall Paint (Control Room) m2 940.00 940.00 0.00 100.00%
Stair and Handrail (Control
2 m2 15.00 15.00 0.00 100.00%
Room)
3 Parking Shed (Control Room) m2 78.00 78.00 0.00 100.00%
4 Dike Concrete Wall Restoration m3 414.18 0.00 414.18 0.00% NSH 152.8 119 33.8 78%
5 Pavement Restoration m3 547.37 161.96 385.41 29.59% NSH 307.52 238.19 69.33 77%
CIVIL
6 Dike Wall Painting m2 2,116.00 0.00 2,116.00 0.00%
7 Steel Structure No. 14.00 14.00 0.00 100.00% NSH 14 14 0.00 100%
8 Roofing m2 865.80 865.80 0.00 100.00%
9 Tank Grit Blasting (T-108) m2 4,587.00 4,587.00 0.00 100.00%
10 Tank Coating (T-108) m2 4,587.00 3,669.00 918.00 79.99%
11 Asphalt paving m2 9,537.58 0.00 9,537.58 0.00% NSH 1635.49 0 1,635.49 0%
12 Process Pipes Jump Over Lm 381.00 381.00 0.00 100.00% NSH 381 381 0.00 100%
13 Process Pipes (Other Areas) Lm 810.80 80.53 730.27 9.93% NSH 682.38 455.149 227.23 67%
PIPING 14 Fire water pipes Lm 146.00 0.43 145.57 0.29% NSH 149.5 58.43 91.07 39.08%
15 Fire Fighting Pipe Coating Lm 1,280.35 1,134.45 145.90 88.60%
16 Valves No 284.00 85.00 199.00 29.93% NSH 280 127 153.00 45%
17 Panels (Control Room) No 12.00 12.00 0.00 100.00%
18 Instrumentation Cable Lm 49,750.00 49,750.00 0.00 100.00%
19 Instruments Nos. 84.00 29.00 55.00 34.52%
ELECTRICAL & INSTRUMENTTAION
20 Instrumentation Conduits Lm 3,050.00 3,050.00 0.00 100.00%
21 Instrument Junction Box Nos. 31.00 31.00 0.00 100.00%
22 Instrumentation cable Tray Lm 130.00 130.00 130.00 100.00%
23 Electrical cable Lm 66,310.00 66,310.00 0.00 100.00%
24 Electrical Cable Tray Lm 143.00 143.00 0.00 100.00%
25 Electrical Conduit Lm 5,717.00 5,717.00 0.00 100.00%
26 Electrical Junction Box Nos. 3.00 0.00 3.00 0.00% NA
27 Lighting fixture Nos. 82.00 82.00 0.00 100.00%
28 High Mast Nos. 4.00 4.00 0.00 100.00%
ELECTRICAL 29 Light Pole Nos. 7.00 7.00 0.00 100.00%
30 CP Rectifier Panel Nos. 5.00 0.00 5.00 0.00%
31 Tank Roof (T-103)- 4,214 m2 m2 4,242.00 0.00 4,242.00 0.00%
32 Rafter Ton 41.00 0.00 41.00 0.00%
MECHANICAL 33 Girder and Column T-103 Nos. 49.00 0.00 49.00 0.00%
34 Shell Restoration T-103 m2 1,123.61 0.00 1,123.61 0.00%
35 Base Plate m2 4,242.00 0.00 4,242.00 0.00%