J 2025 SCC OnLine SC 1127 9820442110 20250811 130411 1 18
J 2025 SCC OnLine SC 1127 9820442110 20250811 130411 1 18
order 47/11
(c) Refund of panel
recovery of
steel taking 5%
of scrap
wastage in
place of 3%
wastage:—
I) Steel
difference
II) M.S. Found
Steel Rs. 1,75,
III) 12 Dia M.S. 132.00
IV) Structural Rs. 1,806.42
Steel Rs. 68,750.00
V) Steel Plates Rs. 2,513.28
VI) Scrap made Rs. 2,649.84
in labour rates Rs. 12,000.00
Total Rs. 2,62,850.70 Rs. 1,82,463.70
d) Unreasonable Rs. 3,747.75
recoveries:— Rs. 38,322.65
i) Cribes Rs. 15,776.31
ii) Shutter Rs. 64,521.00
plates Rs. 60,833.00
iii) B.F.P. Hire Rs. 10,676.00
charges for Rs. 34,701.92
shutter plates Rs. 8,000.00
iv) B.F.P. Hire Rs. 14,990.00
charges for Rs. 89,353.00
shutter plates
v) Refund of
28% overhead
supply for
metal
vi) Dozer
recovery for
work order No.
48/4
vii) Cubes
failure (never
given in writing
of any cube
failure of any
member)
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 6 Monday, August 11, 2025
Printed For: Mr. Arijit Maitra
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
viii) Chain
pulley block
(not with us)
ix) Clamps
(already
returned)
x) Pipes
(already
returned)
Total Rs. 3,40,921.63 Rs. 60,833.00
e) Work order by Rs. 84,447.00 Rs. 84,447.00
other agencies
but not in our
scope like
plastering etc.
f) Held amounts: Rs. 3,95,000.00
— Rs. 20,000.00
i) Amount held Rs. 3,09,203.14
on account of Rs. 43,000.00
grouting T.G. Rs. 51,803.00
ii) Amount held Rs. 23,000.00
on account of Rs. 3,000.00
grouting C.E.P. Rs. 10,000.00
iii) Staging held Rs. 5,000.00
amount of T.G.
iv) Work order
No. 48/4
withheld
amount
v) Work Order
No. 47/11
withheld
amount
vi) Work Order
No. 48/4
shutter plates
held
vii) Curing held
amount 48/4
viii) Work order
No. 48/4 E.S.P.
rectification
held amount
ix) Work order
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 7 Monday, August 11, 2025
Printed For: Mr. Arijit Maitra
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
ISC/Claims/1
dt. 14.10.89,
para IV
m) 2% interest Rs. 50,000.00
rate difference
on mobilization
advance.
n) Interest on Rs. 2,40,000.00
delayed release
of S.D. refer
para 9 of our
letter
ISC/Claims/1
dt. 14.10.89.
o) Mental Rs.
anguishes, 60,00,000.00
torture and loss
of social status
suffered refer
Letter No.
ISC/Claims/1
dt. 14.10.89
para II.
p) Addl. 24% Rs.
interest for 10.5 3,19,57,039.0
years w.e.f. July
1987 upto Dec.
1997.
Total Rs. Rs.
4,46,38,404.00 34,43,490.61
23. We have already extracted the nature of interest payment
provided in the award dated 28.10.2020. However, for ready reference,
interest awarded to the appellant by the arbitral tribunal may once
again be noted which is as under:
(a) Pre-reference/past period interest at the rate of 18% per annum
on the sum of Rs. 34,43,490.61 with effect from July 1987 uptill
19.01.1998.
(b) Pendente lite interest at the rate of 12% per annum with effect
from 20.01.1998 uptill 31.12.2008 on the total amount (that is,
principal amount plus the amount of interest for the pre-
reference/past period).
(c) Pendente lite interest at the rate of 12% per annum with effect
from 01.01.2017 till the date of the award on the total amount
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 9 Monday, August 11, 2025
Printed For: Mr. Arijit Maitra
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
(that is, principal amount plus the amount of interest on the pre-
reference period and for the period from 20.01.1998 till
31.12.2008).
(d) Future interest at the rate of 18% per annum from the date of
the award till the date of payment on the total amount (that is,
principal amount added to the amount of interest for the pre-
reference/past period and interest pendente lite).
23.1. While holding that appellant was entitled to award of interest
for the pre-reference period i.e. from the date on which the cause of
action arose till filing of the claim before the arbitral tribunal as well as
for the pendente lite period and also for the future period, arbitral
tribunal agreed with the respondent that no interest should be awarded
to the appellant for the period when there was absolute laches on the
part of the appellant. Arbitral tribunal held that for the period from
01.01.2009 till 31.12.2016, that is for a period of about eight years,
there was complete laches on the part of the appellant. Therefore, the
arbitral tribunal declared that appellant would not be entitled to any
interest for the aforesaid period.
24. Respondent filed a petition under Section 34 of the 1996 Act
before the High Court impugning the arbitral award dated 28.10.2020.
Vide the judgment and order dated 02.08.2021, learned Single Judge
upheld the claims awarded by the arbitral tribunal. On the question of
interest, learned Single Judge framed the question as to whether
interest awarded by the arbitral tribunal was exorbitant and
unsustainable. Learned Single Judge held that arbitral tribunal's
decision to award pre-reference interest at the rate of 18 percent per
annum did not warrant any interference. As regards pendente lite
interest, learned Single Judge while noting that arbitral tribunal had
awarded 12 percent interest per annum for the period from 20.01.1998
till 31.12.2008 and again from 01.01.2017 till 28.10.2020, justified the
decision of the arbitral tribunal not to award interest for the period from
01.01.2009 to 31.12.2016 as during this period the appellant was
remiss and did not pursue its claim before the arbitral tribunal
diligently. On the rate of interest, learned Single Judge held that
interest at the rate of 12 percent per annum could not by any stretch
be considered to be exorbitant or unreasonable but held that 18
percent future interest from the date of the award till the date of
payment granted by the arbitral tribunal was ex facie erroneous as
according to learned Single Judge the interest rate should have been 2
percent higher than the current rate of interest prevalent on the date of
the award. Therefore, this portion of the award was set aside by the
learned Single Judge; instead learned Single Judge awarded future
interest holding that it could not have been in excess of 9 percent per
annum. Therefore, learned Single Judge partly allowed the petition
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 10 Monday, August 11, 2025
Printed For: Mr. Arijit Maitra
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
under Section 34 of the 1996 Act to the extent of setting aside the
award of future interest at a rate exceeding 9 percent per annum from
the date of the award till the date of payment.
25. This brings us to the impugned judgment and order dated
01.08.2023. We have already noted about the limited nature of
challenge made by the respondent during the hearing of the appeal
filed under Section 37 of the 1996 Act. Learned senior counsel
appearing for the respondent clarified that the challenge to the award
stood restricted to the directions issued by the arbitral tribunal insofar
the issue of interest was concerned. He clarified that the challenge was
not with respect to either the rate at which interest was awarded or the
grant of interest for the pre-reference/past period. The grievance was
confined to the directions contained in paragraph 58(b)(i) of the award
and the similar nature of interest in paragraph 58(b)(ii) inasmuch as
the arbitral tribunal proceeded to award interest on identical terms : on
the principal amount plus the amount of interest for the pre-
reference/past period. Division Bench referred to Section 31(7)(a) and
(b) of the 1996 Act as well as placed reliance on the decision of this
1
Court in Sayeed Ahmed and Company v. State of Uttar Pradesh and
came to the following two conclusions:
i) Section 31(7) recognizes only two periods for which interest may
be awarded. The two periods are, firstly from the date on which
the cause of action arose till passing of the award and secondly
from the date of the award till actual payment. Therefore, the
distinction between pre-reference/past period and pendente lite
period no longer existed. The period from the date of cause of
action i.e. July, 1987 till the date of the award dated 28.10.2020
would constitute the period contemplated under Section 31(7)(a)
of the 1996 Act. The period commencing from the date of award
till payment would be the second period within the meaning of
Section 31(7)(b) of the 1996 Act. Therefore, the arbitral tribunal
committed an illegality in awarding interest for three periods : pre
-reference/past periods, pendente lite and for the future period.
ii) Arbitral tribunal committed further illegality in forging the
principal amount with interest as would be evident from
paragraph 58(b) of the award. Interest awarded for the pre-
reference period as well as for the pendente lite period have been
subjected to further levy of interest for the said periods by adding
the interest amount with the principal amount awarded. This
amounted to levying compound interest which is impermissible.
Accordingly, the directions contained in paragraph 58(b) were set
aside by the Division Bench.
26. In our considered view, the reasonings given by the Division
Bench are fallacious. We say so for the reasons mentioned hereunder.
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 11 Monday, August 11, 2025
Printed For: Mr. Arijit Maitra
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
of the 1996 Act. A careful and minute reading of this provision will
make it clear that the arbitral tribunal has the discretion to include in
the sum awarded interest at such rate as it deems reasonable on the
whole or any part of the money awarded for the whole or any part of
the period from the date on which the cause of action arose till the date
on which the award is made. We may exclude that part of the sentence
‘on the whole or any part of the money’ from our analysis since this is
not relevant to the controversy. If we exclude this portion, what then
becomes discernible is that the arbitral tribunal has the discretion to
include in the sum awarded : firstly, interest at such rate as it deems
reasonable; and secondly, for the whole or any part of the period
between the date on which the cause of action arose and the date on
which the award is made. This would mean that the arbitral tribunal
can exclude a period from the date on which the cause of action arose
till the date on which the award is made for the purpose of grant of
interest, as has been done in the present case. It would also mean that
the arbitral tribunal can grant interest for the whole or any part of the
period between the date on which the cause of action arose and the
date on which the award is made. It can be a composite period or the
said period can be further sub-divided, as done in the present case i.e.
from the date of cause of action to filing of the claim and from the date
of filing of the claim till the date of the award excluding the period
when the appellant was found to be remiss. It would also mean that
there can be one rate of interest for the whole period or one or more
rates of interest for the sub-divided periods as has been done in the
instant case. In our opinion, this would be the correct approach to
interpret Section 31(7)(a), given the scheme of the 1996 Act.
36. That being the position, we are of the view that the Division
Bench had fallen in error by holding that the arbitral tribunal had no
jurisdiction to award interest for two periods i.e. pre-reference and
pendente lite when the statute provides for only one period viz. from
the date when the cause of action arose till the date of the award. The
view expressed by the High Court is not the correct interpretation of
Section 37(1)(a) of the 1996 Act as explained by us supra as well as in
Pam Developments Private Limited (supra) and S.A. Builders Ltd.
(supra).
37. This brings us to the second issue on which the High Court set
aside the directions of the arbitral tribunal contained in paragraph 58
(b) of the award. According to the Division Bench, the arbitral tribunal
had committed an illegality in forging the principal amount with
interest while computing the awarded amount on which future interest
is to be paid. Interest awarded for the past period could not have been
subjected to further levy of interest during the pendente lite or post
award period on merger with the principal amount as this would
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 16 Monday, August 11, 2025
Printed For: Mr. Arijit Maitra
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
Industries Limited8).
43. Finally, in S.A. Builders (supra), this Bench after a thorough
analysis of Section 31(7)(a) and Section 31(7)(b) of the 1996 Act came
to the following conclusion:
38. Natural corollary to the above analysis would be that the ‘sum’
so awarded by the arbitral tribunal which may include interest from
the date when the cause of action arose to the date of the award,
would carry further interest of 18 percent from the date of the award
to the date of payment unless the arbitral award otherwise directs
(referring to the pre 23.10.2015 position). Thus, the legislative
intent is that the awarded sum whether inclusive of interest or not,
in case included, then from the date of cause of action to the date of
award, would carry further interest from the date of the award to the
date of payment.
44. It has been held that the sum awarded would mean the principal
amount plus the interest awarded from the date of cause of action upto
the date of the award. The sum awarded in Section 31(7)(a) would
mean principal amount plus the interest awarded. Thereafter, as per
Section 31(7)(b) of the 1996 Act, the sum (principal amount +
interest) would carry further interest at the rate of 2 per cent higher
than the current rate of interest prevalent on the date of the award to
the date of payment.
45. Therefore, in view of the clear legal position delineated as above,
impugned judgment of the Division Bench dated 01.08.2023 cannot be
sustained.
46. Thus, having regard to the discussions made above, impugned
judgment and order dated 01.08.2023 passed by the Division Bench of
the High Court is hereby set aside. Civil appeal is accordingly allowed.
However, there shall be no order as to cost.
———
1
(2009) 12 SCC 26
2
(2024) 10 SCC 715
3
2024 SCC OnLine SC 3768
4
(2010) 3 SCC 690
5
(2015) 2 SCC 189
6
(2022) 4 SCC 116
7
(2022) 9 SCC 286
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 18 Monday, August 11, 2025
Printed For: Mr. Arijit Maitra
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
8
(2023) 1 SCC 602
Disclaimer: While every effort is made to avoid any mistake or omission, this casenote/ headnote/ judgment/ act/ rule/
regulation/ circular/ notification is being circulated on the condition and understanding that the publisher would not be
liable in any manner by reason of any mistake or omission or for any action taken or omitted to be taken or advice
rendered or accepted on the basis of this casenote/ headnote/ judgment/ act/ rule/ regulation/ circular/ notification. All
disputes will be subject exclusively to jurisdiction of courts, tribunals and forums at Lucknow only. The authenticity of
this text must be verified from the original source.